Example - Value Engineering Study/Workshop Proposal

The Thomas Consulting Group LLC.

Financier

Operator

Designer

Owner
User

V.E.
Architectural

Mechanical

Electrical

Structural

Civil

Process
Table of Contents

Proposed Value Engineering Study Includes study title, proposal date, study type, project type,
project location, and project estimate information.
Construction Cost Data Conceptual building costs and ve target costs.
Proposed 5 Day VE Study Fee Pre-Workshop, Workshop, Post Workshop Fees, and ROI
Client's Potential Return On Investment (USD)
Cost/Worth Model Example
Hotel in Riyadh, Saudi Arabia (Example)
Recent Value Engineering Study Proposal Example

Study Title : Jakarta Office Building


Proposal Date : April 2, 2005
Study Type : Facilitate A 5 Day VE Study/Workshop
Project Type : Multi Story Office Building
Project Location : Jakarta, Indonesia
Project Estimate : 150 Billion (IDR) = $15,831,051 (USD)
Submitted To :

Submitted By : The Thomas Consulting Group LLC.


Richard D. Ridgeway
VE Program Manager
thomasconsultgroup@sbcglobal.net
CONSTRUCTION COSTS FOR JAKARTA, INDONESIA - Indonesia Rupiahs
Multi Story Offices Buildings - (Excluding tenancy works)

Type of Quantity Unit Rp/m2 Original Design Estimated VE Estimated


Building Estimated Cost Target Cost Potential VE
Savings
Central
Business
District;
Prestigious 25,821 SQM Rp5,809,011 Rp149,994,473,031 Rp140,994,804,649 Rp8,999,668,382
Central
Business
District;
Investment 31,560 SQM Rp4,752,827 Rp149,999,220,120 Rp140,999,266,913 Rp8,999,953,207
Suburban
District;
Investment 37,872 SQM Rp3,960,689 Rp149,999,213,808 Rp140,999,260,980 Rp8,999,952,828

Estimated Potential VE Savings in dollars = $949,858


Note: 1 USD = 9,475.05 IDR
*Proposed 5 Day VE Study Fee - United States Dollars
Jakarta, Indonesia
Note: *This client was the design firm for the project’s owner, and provided his employees as VE Team Members.
VE Team Members - Quantity Unit Mat'l Total Man *Labor Total Total Cost
Cost/Unit Mat'l Hours Rate Labor
Pre-Workshop Phase Cost Cost

CVS Study Facilitator (Our


employee) 1 Each 0 0 20 $200 $4,000 $4,000
Architect (Your employee) 1 Each 0 0 15 NA NA
Electrical Engineer (Your
employee) 1 Each 0 0 15 NA NA
Civil Engineer (Your employee) 1 Each 0 0 15 NA NA
Mechanical Engineer (Client
employee) 1 Each 0 0 15 NA NA
Estimator (Client employee) 1 Each 0 0 15 NA NA
Sub-Total $4,000
In-Direct Costs
Telephone 1 Allow $200 $200 $200
Mailing 1 Allow $100 $100 $100
Sub-Total $300
Pre-Workshop Phase Total $4,300
VE Team Members -
Workshop Phase
CVS Study Facilitator (Our
employee) 1 Each 0 0 40 $200 $8,000 $8,000
CVS Study Facilitator (Travel
time to Jakarta and return) 4 Days $1600 $3,200 $6,400
Architect (Client employee) 1 Each 0 0 40 NA NA
Electrical Engineer (Client
employee) 1 Each 0 0 40 NA NA
Civil Engineer (Client
employee) 1 Each 0 0 40 NA NA
Mechanical Engineer (Client
employee) 1 Each 0 0 40 NA NA
Estimator (Client employee) 1 Each 0 0 40 NA NA
Sub-Total $14,400
In-Direct Costs
Air Travel (Round trip) 1 Allow $2,000 $2,000 $2,000
Hotel Accommodations & Per
Diem 6 Day $200 $1,200 $1,200
Sub-Total $3,200
Workshop Phase Total $17,600

Post-Workshop Phase
CVS Study Facilitator (Our
employee) 1 Each 0 0 20 $200 $4,000 $4,000
Telephone 1 Allow $200 $200 $200
VE Report Printing 12 Each $20 $240 $240
Mailing 1 Allow $200 $200 $200
Post-Workshop Phase Total $4,640

VE Study Fee Grand Total $26,540


Note: *Our labor rate is actually
lower

Client's Potential Return On Investment (USD)


For
VE Study
Potential VE Savings VE Study Fee Return On Investment

$949,858
/ $26,540
= 36:1
NOTE: Return on investment of 60:1 is possible using VE methodology