You are on page 1of 10

OTC 16555

Ormen Lange - Flow assurance challenges


Arild Wilson, Sverre J Overaa, Henning Holm / Norsk Hydro ASA, Norway

Copyright 2004, Offshore Technology Conference


to the city of Molde. The gas will be produced from up to 24
This paper was prepared for presentation at the Offshore Technology Conference held in subsea wells. The well fluid will be transported to the land
Houston, Texas, U.S.A., 3–6 May 2004.
terminal through two 30” multiphase lines. After processing,
This paper was selected for presentation by an OTC Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as
the dry gas will be transported from the land terminal through
presented, have not been reviewed by the Offshore Technology Conference and are subject to a new 42”pipeline to Sleipner and from there through a new
correction by the author(s). The material, as presented, does not necessarily reflect any posi-
tion of the Offshore Technology Conference or its officers. Electronic reproduction, distribution, 44” pipeline to receiving facilities in Easington, UK.
or storage of any part of this paper for commercial purposes without the written consent of the The annual gas export plateau will be approximately
Offshore Technology Conference is prohibited. Permission to reproduce in print is restricted to
an abstract of not more than 300 words; illustrations may not be copied. The abstract must 21 billion Sm3 and the daily export capacity up to 70 mil-
contain conspicuous acknowledgment of where and by whom the paper was presented.
lion Sm3.
To maintain production when reservoir pressure declines,
Abstract an offshore compression facility is planned for installation in
Ormen Lange is a gas field located 100 km off the Norwegian the field with a planned start-up date in 2016. However, a sub-
coast in water depths varying between 850 and 1,100 meters. sea compression solution will be evaluated, in parallel, as a
The selected development scenario for Ormen Lange is a sub- cost-effective alternative to a compression platform.
sea tie-back to an onshore processing facility at Nyhamna.
The field is located in a prehistoric slide area with varying Field development and subsea system architecture
water depths, from 250 to 1,100 meters. The result of this sub- Due to the wide geographical extent of the Ormen Lange field,
sea slide is an extremely uneven sea bottom with local sum- the risk of experiencing a segmented reservoir and, in addi-
mits 60 to 80 m high. The back wall of the slide is steep, up to tion, limitations with respect to long reach well/high deviated
26 degrees. Environmental conditions are also challenging. wells, the subsea architecture requires a high degree of flexi-
This paper describes the flow assurance challenges and bility. A phased development scheme has been selected for the
technical solutions selected due to the harsh environmental field. The completion of subsea wells will be timed to main-
conditions specific to the Ormen Lange development, includ- tain plateau production as the field depletes.
ing:
• Rough seabed combined with long tie-back distance. Initial development. The initial subsea development will con-
• Sub-zero temperatures (-1 oC). sist of two 8-slot production templates (A & B), located ap-
All together, this makes the Ormen Lange project one of proximately 4 km apart in the main production area as shown
the most challenging field developments worldwide with re- in Fig. 2. There will be dual 20” production headers on each
spect to flow assurance. template that will be tied into the two 30” multiphase pipelines
by means of rigid spools. The two 30” lines will be connected
Introduction via a pipeline end termination system (PLET). Two main con-
The Ormen Lange field, discovered in 1997, is located off- trol umbilicals will link the onshore plant to the subsea pro-
shore Norway approximately 130 km west-northwest of Kris- duction system; one will be connected to template A, and the
tiansund. The field covers an area approximately 10 km by other to template B. A crossover control umbilical will inter-
44 km. The reservoir is located at a depth ranging from connect the two production templates, providing redundant
2,650 m to 2,915 m below mean sea level. Recoverable re- control of all the subsea wells. The capability for round-trip
serves are estimated to be approximately 375 billion Sm3 gas pigging of the 30” multiphase pipeliens is provided by instal-
and 22 million m3 condensate. The intitial reservoir pressure is lation of a pigging loop.
290 bara, and the reservoir temperature ranges from 86 to For prevention of hydrate formation, all wells are continu-
93 oC. ously dosed with monoethylene glycol (MEG) supplied via
The field is located within a prehistoric slide area, the Sto- two 6” pipelines from the shore terminal. One line will be
regga slide, with water depths varying from 850 to 1,100 m in connected to template A, and the other to template B. A 6”
the planned development area. The seabed in the Storegga crossover MEG line will interconnect the two production tem-
slide is extremely irregular with soil conditions varying from plates providing redundant supply of MEG to the templates.
very stiff clay with boulders to soft clay. Each 6” MEG line has sufficient capacity to supply the MEG
The selected development concept for Ormen Lange con- requirements of all the wells in the field.
sists of a subsea tie-back to a shore terminal as shown in
Fig. 1. The shore terminal will be located at Nyhamna, close
2 OTC 16555

Future development. A further development of the Ormen has been intensive discussion on the risk of hydrate/ice plugs,
Lange field may take place in the future depending on the pro- physical characteristics of the plugs, methods for prevention
duction experience from the initial phase. The scenario fore- and remediation of potential hydrate/ice plugs.
seen for the future extension of the field is shown in Fig. 3 and The low hydrate equilibrium pressure at seabed tempera-
is comprised of two additional 6-slot production templates (C ture, combined with the rough seabed topography, challenges
& D). The future 6-slot templates will each include two spare depressurization as a means for hydrate remediation, as the
well slots that may be used for additional wells. Each of these hydrates may convert to ice during depressurization.
production templates will produce gas through dual 12” mani- All together, this makes the Ormen Lange development
fold headers and infield flowlines tied back to the 30” PLET one of the most challenging field developments worldwide
(valid for template C) and hot-tap tees in the 30” lines (valid with respect to flow assurance.
for template D). A new infield 6” MEG line will be connected
to each of the two future templates (C and D) as extensions Hydrate management
from the initial templates A & B. Similarly, new infield con-
trol umbilicals will be connected to each of the two templates Hydrate and ice formation. Due to the low seabed tempera-
(C and D) as extensions from the templates A & B. See /2/ for ture, both hydrates and ice may form, unless the fluid is suffi-
further details. ciently inhibited. Experiments have shown that the uninhibited
Ormen Lange well fluid has a high potential for hydrate for-
Well completions. The initial development will include 8 of mation in continuous flow mode as well as during shut-in, and
9-5/8” hybrid well completions with 7”downhole safety valves the hydrates have a high tendency to deposit on the pipe walls.
(DHSV) and horizontal Xmas trees. The remaining well com- The hydrates appear to be sticky and the plugging potential
pletions are assumed to be 7” completions with identical Xmas seems to be high. Therefore a basic assumption is that the un-
trees as for the initial wells. See /3/ for further details. inhibited Ormen Lange well fluid very easily forms hydrates
and ice and that the plugging potential is high.
Future compression. The concept will allow for tie-in to a
future pre-compression platform or a subsea compression unit. Primary hydrate prevention strategy. Prevention of hy-
The system will include subsea tie-in points applicable for drate/ice formation is given high priority, as removal of hy-
both a platform and a subsea gas compression solution. How- drate/-ice plugs may be complicated.
ever, the initial subsea control system and control umbilicals The overall Ormen Lange hydrate prevention strategy is to
will not include any facilities for signal or power for a future minimize the risk of operation within the hydrate region.
subsea compression facility. See /4/ for further details. This is achieved by continuous MEG injection at the indi-
vidual wellheads. Each well will be equipped with a dosage
Ormen Lange specific flow assurance challenges system. The MEG distribution system will be designed with a
The key Ormen Lange specific environmental conditions chal- capacity to inhibit the maximum expected condensed water
lenging flow assurance are: plus formation water/gas production from individual wells.
• Rough seabed. MEG delivery requirements for each well will be individually
• Sub-zero temperatures (-1 oC). determined based on water production predictions from each
well. Measurements of water production using wet gas meter-
Rough seabed. The gas field is situated in 850 m water depth ing technology will be used as a backup to water production
in an area of a prehistoric subsea slide, the largest known to predictions. A safety factor will be used to ensure adequate
date. The result of this slide is an extremely uneven sea bot- MEG injection, taking into account the water prediction and
tom with local peaks, 60 to 80 m high. The back wall of the measurement accuracy.
slide area is very step, up to 26 degrees. The rough seabed The MEG injection/distribution system will be designed
topography combined with the 120 km tie-back distance to the with respect to high availability/reliability/redundancy to
onshore processing facilities stretch the limits of current mul- minimize the risk and consequences of failure of individual
tiphase flow technology. system components, and to minimize the risk of hydrate for-
Correct modelling of the detailed seabed and pipeline to- mation and the need for hydrate remediation.
pography and reliable multiphase flow models are imperative Dual 6” MEG supply lines from shore, each with 100%
for the Ormen Lange development, and will be discussed be- overcapacity, will be installed to increase availabil-
low. ity/reliability/redundancy and to provide capacity for overdos-
Correct calculation of pressure drop is a requirement for ing to reduce the hydrate risk due to MEG injection system
hydraulic capacity and line-sizing/liquid holdup manage- failure (uncertainty, mechanical, operator error).
ment/compression requirements.
Correct prediction of liquid holdup is important for pres- MEG injection requirements. The hydrate suppression re-
sure drop calculations, operational flexibility and slugcatcher quirement is a hydrate temperature of –5 oC at maximum po-
design. tential pipeline shutin pressure (255 bara). This corresponds to
60 wt% MEG in the aqueous phase.
Sub-zero temperatures. The other Ormen Lange specificen- The MEG injection and regeneration system will be de-
vironmental challenge is the sea water temperature of minus signed for saturation water only, combined with up to 50
one (-1) degree Celsius, which creates the risk of ice formation Sm3/sd of formation water (maximum). The total MEG injec-
in addition to the risk of hydrate formation. As a result, there tion capacity is 1,500 Sm3/sd.
OTC 16555 3

The following assumptions have been made in prediction 8) Provisions shall be made to prevent backflow of wellfluid
of the condensed water: from the production bore into the MEG injection system.
• The produced gas will always be saturated with water at 9) The dosage unit will as far as practically possible be de-
in situ reservoir conditions (P&T). signed to minimize the risk of particle accumulation result-
• The gas water saturation is expected to increase during ing in clogging of the dosage unit (smooth geometry with
the lifetime of the field due to the reservoir depletion. no abrupt geometry changes, no cavities, etc.). The l/d ra-
tio of the hole sizes should be maximized to achieve as big
MEG injection and distribution system. The subsea MEG hole sizes as possible, and in-situ flushing/cleaning of the
injection and distribution system is designed with high focus MEG dosage unit will be possible.
on availability/ reliability/ redundancy to minimize the risk 10) The subsea system will be protected from over pressuriza-
and consequences of a hydrate prevention failure, and conse- tion by the MEG injection pumps in the event of a pump-
quently the risk of hydrate formation and the need for hydrate trip or a shutdown of the MEG system.
remedial actions. 11) It will be possible to use the MEG dosage unit as a com-
MEG delivery requirements for each well will be individu- bined flow control and backup flow measurement device
ally determined based on predictions of water production from with accuracy better than ±10%, i.e., a position indicator is
each well. A safety factor will be used to ensure adequate provided.
MEG injection, taking into account the water measurement 12) A dedicated computerized “MEG monitoring” system will
accuracy (+35% has been applied for design purposes), and be developed to monitor the integrity (e.g., leak-
uncertainties in the MEG distribution and control (+20% has age/blocking) and performance of the subsea MEG distri-
been applied for design purposes). bution system, and ensure that sufficient MEG is injected
The following requirements have been defined for de- at all times to inhibit the production templates and 30"
sign/operation of the subsea MEG distribution system from a multiphase export pipelines to shore.
flow assurance perspective:
1) Line pressure in MEG distribution system will be at asuffi- Risk of hydrate and ice formation. The risk of hydrate pre-
cient margin above maximum wellhead shut-in pressure to vention failure and the risk of getting a hydrate plug have been
prevent backflow of wellfluid into the MEG system and to evaluated through both availability analysis and fault-tree
ensure MEG injection into the well(s) with the highest analysis. The work has focused on normal operation of the two
wellhead pressure at any flowrate including no-flow condi- 30” multiphase production pipelines. The model has been used
tions. to identify critical contributors, and to improve system design
2) The line pressure and pressure drop across the subsea and operational strategies to reduce the risk of hydrate forma-
MEG dosage system will be sufficient to minimize impact tion.
of pressure transients and interaction between wells. A simplified schematic of the fault tree analysis is illus-
3) Frictional pressure drop in the MEG supply lines will be trated in Fig. 7.
minimized to avoid transients and significant interaction The main contributor to the risk of forming a hydrate plug
between wells during operation of either the production or is MEG injection failure/ insufficient MEG inhibition. The
the MEG injection system. fault-tree analysis indicates that a hydrate prevention failure
4) The Xmas tree system will be equipped with two MEG resulting in insufficient MEG inhibition in one of the two 30”
injection points: multiphase production pipelines may exist approximately
i. During normal production MEG will be injected every 250 years given formation water breakthrough will oc-
downstream PWV / upstream the choke to ensure cur, and every 450 years given water break through will not
good mixing. occur. However, given insufficient MEG inhibition, develop-
ii. During valve integrity testing, pressure equalization ment of a critical hydrate plug that cannot be removed by de-
prior to start-up, bull heading and well treatment fol- pressurization requires the following additional conditions to
lowing shut-in, MEG will be injected between the be in place (see Fig. 7):
PMV and PWV. 1) Continued operation in hydrate conditions (e.g. pressure
5) Each well will be equipped with a distribution system/logic and temperature).
that ensures that sufficient MEG is injected into each indi- 2) Conditions for forming sufficient hydrates to plug the line
vidual well. (e.g. water and time).
6) Due to the varying reservoir depth and corresponding 3) Inability to remove the plug by depressurization.
change in the reservoir temperature and water saturation, Hence, critical hydrate plugging would occur at frequen-
the required MEG injection rate to inhibit the water satu- cies less than indicated since the probability that these other
rated well fluid needs to be calculated individually for all conditions required for hydrate plug formation to occur will
wells based on individual well bottom hole pressure and also be considered. It should be noted that the subsea produc-
temperature. tion system and the deepwater part of the multiphase produc-
7) The control of the MEG dosage unit will, as a minimum, tion pipelines still may operate outside hydrate conditions dur-
have 5 positions to control the MEG injection rates. The ing flowing conditions, even with an uninhibited wellstream.
size/flow performance of the 5 positions will be optimized Table 1 shows the risk of forming a hydrate or ice plug in
during detailed design and verified by experimental flow one of the two multiphase production pipelines for different
tests. combinations of “high”, ”medium” and “low” conditional
probabilities. It is stressed that values of the “high”,” medium”
4 OTC 16555

and “low” conditional probabilities are only for illustration Hydrate remediation. Should hydrates form in sufficient
purposes. The results are based on normal production during quantity, and subsequently cause a blockage, the primary hy-
30 years production time. drate remediation strategy for the subsea production system,
in-field flow lines and two 30” multiphase production pipe-
Table 1. Risk og forming a hydrate or ice plug lines is depressurization to melt the hydrates. Depressurization
MTTF Conditional Conditional Risk of hydrate Risk of ice plug is the strategy normally selected for hydrate remediation in
(MEG<60wt%) probability probability plug subsea pipelines, and has a proven track record.
of getting of forming P(MEG<60wt%) P(MEG<10wt%)
into hy- a plug
The specific challenges related to depressurization in the
drate con- deepwater part of Ormen Lange (sub zero temperature/ice
(yrs) dition (%) (%) formation and low hydrate equilibrium pressure at seabed
(P&T) temperature) have been addressed and several solutions identi-
450 1 1 13,33 0,667 fied to achieve low enough pressure reduction to melt hydrates
450 1 0,5 6,67 0,333 in all cases.
450 1 0,2 2,67 0,133 The following key questions related to depressurization
450 0,5 1 6,67 0,333 were raised during execution of the project:
450 0,2 1 2,67 0,133 • What is the most likely plug location? Why and where do
450 0,5 0,5 3,33 0,167 hydrate plugs form?
450 0,2 0,2 0,53 0,027 • What is hydrate equilibrium /-dissociation pressure at the
plug location as function of seabed temperature and in-situ
The key conclusion from the fault-tree analysis is that a MEG concentration?
certain degree of MEG overdosing (approximately 25%) sig- o What is the local MEG concentration in the hydrate
nificantly reduces the risk of hydrate prevention failure result- plug / vicinity of plug when a hydrate plug dissociates
ing in insufficient MEG inhibition. during depressurization?
See Fig. 6 for illustration of water-development, MEG in- o What is the plug characteristic of the hydrate plug
jection requirement and available MEG over-capacity during formed in the presence of MEG (porosity, permeability
lifetime of the field. In addition, based on production experi- and MEG concentration in the free aqueous phase
ence, some of the “design uncertainties” with respect to con- within the plug)?
densed water calculation (35%) and MEG distribution and o What pressure is required to dissociate a hydrate plug
control (20%) may be utilized as over capacity/overdosing. in a “partly inhibited” system?
The fault tree analysis indicates that the main contributors • What is the risk of ice formation?
to hydrate prevention failure are: o Sea water temperature.
1) Operator overrides shutdown function. o In situ MEG concentration.
2) Automatic shutdown failure due to MEG injection failure. o What is the risk of getting into an uninhibited situation?
3) Regulation failure of MEG dosage valve after detection of o What happens to the MEG during hydrate formation in
formation water breakthrough. an under-inhibited system?
4) Undetected failures. o Is the MEG concentration in the aqueous phase suffi-
The main contribution to production unavailability due to cient to prevent hydrates to convert into ice, even at
hydrate prevention failure is unavailability of the MEG injec- depressurization to pressure close to atmospheric pres-
tion system. However, in most cases hydrate formation will sure?
not occur due to mitigating actions (shutdown of relevant parts • Depressurization strategy – how should depressurization
of the system, MEG overdosing, etc.). Hence, the contribution be performed?
to gas unavailability from hydrate/ice plugging and remedia- o How to achieve the pressure required to melt hydrates
tion in the subsea production system or in the two 30” multi- (less than 8-10 bara in an uninhibited system) from all
phase production pipelines is small, due to the low probability pipeline conditions/ operational modes (shutdown from
of a hydrate plug forming. low turndown/high hold-ups)?
o Is it possible to control the pressure during depressuri-
Hydrate formation detection. Malfunction of the MEG in- zation to prevent too low pressure resulting in very low
jection system resulting in insufficient hydrate inhibition could temperatures due to the hydrate/ice equilibrium tem-
result in hydrate formation somewhere in the production sys- perature at very low pressures?
tem. • What are the criteria for successful hydrate remediation by
The indications of hydrate formation in the multiphase depressurization?
pipelines will be increased pressure drop and pressure fluctua-
tions. The pressure drop in the different parts of the production Most likely plug locations. Fig. 4 shows the minimum, maxi-
system will be monitored by a real-time pipeline monitoring mum and average seabed temperatures as function of depth
system. Any abnormal pressure and flow condition will be and along the pipeline profile.
detected by a hydrate detection module implemented in the From the upper part of the escarpment to shore, the mini-
pipeline monitoring system. mum seabed temperature is always above zero degrees Cel-
The mitigation action will be to increase the MEG injec- sius, i.e. there is nothing unique for Ormen Lange in the shal-
tion rate into the relevant part of the system and, if possible, low water part with respect to hydrate/ice formation and/or
increase production rate to increase the flowing temperature.
OTC 16555 5

hydrate remediation. This area is analogue to most other long drate prevention failure resulting in an uninhibited system,
distance, gas/condensate tiebacks. which is low. This conclusion is from an uncertainty analysis
The Ormen Lange specific challenges with respect to hy- of the MEG injection rate that was performed, based on the
drate/ice plug formation/prevention/remediation are in the fault tree already discussed. A typical result from this analysis
lower part of the escarpment, located in deepwater and sub- is illustrated in Fig. 8. Hence it can be concluded that the risk
zero temperatures. of getting a hydrate plug that cannot be removed by depres-
surization, is low.
Plug location. Potential hydrate/ice plugs may form either
during flowing or no-flowing conditions: Depressurization strategy. The primary depressurization
Flowing condition. During flowing conditions, plugs that strategy is depressurization via the dual two 30” multiphase
form are most likely due to: export lines. The key to a successful hydrate remediation by
MEG injection failure / operator failure. depressurization is the dual pipeline system.
Undetected formation water breakthrough. Simulation indicates that in many cases (depending on
The most likely plug location is the upper part of escarp- pipeline topography and operational conditions prior to plug-
ment where the flowing temperature drops below the in-situ ging occurred) it may be difficult to reach the low pressure
hydrate temperature of the under-inhibited wellfluid. The hy- required (due to holdup effects) to melt hydrates in an unin-
drate temperature and the corresponding most likely plug loca- hibited system (less than 8-10 bara) by depressurization
tion is thus a function of the in-situ MEG concentration, and through the plugged pipeline. As a result, depressurization will
the production rate/temperature profile as illustrated in Fig. 5. take place through the un-plugged line as well.
It should be noted that the seabed temperature in this area Potential liquid holdup in the un-plugged pipeline may be
is above the ice formation temperature, and that the risk of swept out from the un-plugged pipeline by maximizing the
getting an ice plug that cannot be removed by depressurization production in that line (dynamic pigging) prior to depressuri-
is low. zation. The plugged pipeline may then be depressurized from
No-flowing conditions. During no-flowing conditions, both ends after connecting the two pipelines either via the pig-
plugs that form are most likely due to: ging loop, or via one of the manifolds by opening the diverter
• Commissioning/tie-in of new in-field flow lines. valves between the two manifold headers.
• Water ingress (cold sea water or “commissioning fluids”) After depressurization the two lines may be disconnected
into no-flowing conditions. and production can be resumed in the un-plugged line. De-
• MEG injection failure during start-up. tailed procedures will be established to avoid gas leak-
The most likely plugging location is in the areas age/freezing across the valves exposed to high differential
within/close to subsea production systems, i.e. in the area ex- pressure.
posed to sub-zero temperatures. However, in this situation it Depressurization simulations have been performed to ver-
can be assumed that the fluid in the multiphase production ify the depressurization strategy. The study included the fol-
pipelines is sufficiently inhibited. lowing scenarios:
• 50 and 100% flow rate prior to shutdown.
Risk of ice formation. Experiments with uninhibited gas have • 14 days liquid accumulation at 50% turndown.
shown that hydrates convert to ice during depressurization at • Steady state aqueous phase liquid holdup.
sub-zero temperatures. The depressurization was controlled with a fixed flow rate
One of the key project findings is that the presence of down to 60 bara via the normal production facilities, and with
MEG, even at a fraction of the required injection rate, will a fixed orifice to the flare system down to atmospheric pres-
prevent ice formation and facilitate hydrate melting even at the sure.
worst case expected pressures. Studies showed that depres- The key conclusions from the simulation study are:
surization may be used in deepwater with sub-zero tempera- • Depressurization to atmospheric pressure takes approxi-
tures if the fluid is “partly” inhibited with MEG. The presence mately 3-5 days.
of MEG, even at a fraction (<10wt%) of the concentration • Low temperature in the multiphase production pipelines
required to prevent hydrates, will prevent ice formation. In the due to JT cooling is not expected (slow depressurization).
presence of MEG also the hydrate equilibrium pressure at sea- • Depressurization (from one side) to pressure less than
bed temperature (-1 oC) increases significantly, which makes 10 bara from all operating conditions may be difficult due
depressurization more applicable for “partly inhibited” system to liquid holdup effects, but may be solved by proper de-
compared to an uninhibited system. pressurization strategy (depressurization from both sides
Depressurization is thus feasible if the fluid in the subsea via unplugged pipeline).
system is sufficiently inhibited to prevent ice formation at in-
situ flow line conditions during depressurization. Secondary hydrate remediation strategy. The engineering
Experimental studies show that the MEG remains within studies indicate that the risk of forming a hydrate/risk plug
the hydrate masses during hydrate formation in underinhibited that cannot be removed by depressurization is quite small.
systems, and hence prevents ice formation during hydrate dis- There is some cause for caution, however. Ice will not form if
sociation during depressurization. the water contains 10% of MEG, but hydrates may. The hy-
The risk of not being able to remove a hydrate plug by de- drates will convert into ice during depressurization, but the ice
pressurization is thus strongly linked to the risk of getting hy- will melt if it remains in steady contact with water containing
6 OTC 16555

the MEG. However, if the hydrate plug resides in a gas-filled line downstream from the templates. To reduce this phenome-
section of the flow line, the ice will not melt. Such a situation non, the external pipeline coating (FBE + PP) will be in-
could occur if a hydrate plug forms in an upward bend (re- creased to 8 mm to reduce the condensation rate on the inter-
versed dip), and the liquids drain away from the plug immedi- nal pipe wall and thus reduce the top of the line corrosion rate
ately after the blockage occurs. Probably, the risk for this hap- to an acceptable level (about 0.1 mm/y). Hence, a corrosion
pening is not too large, but it cannot be fully excluded. As a allowance of 10 mm for the warm part of the pipeline and
result, the Ormen Lange project has investigated several op- 7.5 mm for the cold part of the pipeline is specified to obtain
tions for secondary hydrate remediation. the 50 years design lifetime for the multiphase pipeline. This
The secondary hydrate remediation strategy selected for also includes a safety margin of 0.1 mm/y.
the Ormen Lange multiphase production lines is flow- Since no signs of H2S have been detected in the well
line/pipeline replacement. analyses, sour service has not been specified for the pipeline
material.
Restart after hydrate remediation. Prior to restart after a
hydrate plug has been remediated, the uninhibited fluid in the Multiphase flow
plugged pipeline will be either replaced or inhibited. This can
be done in two ways: Linesizing strategy. Two 30” pipelines have been selected to
• Roundtrip pigging at “low pressure” may be carried out to utilize a total hydraulic capacity of 60 to 70 MSm3/sd at “a
remove under-inhibited liquid. A “huge” batch of MEG is reasonable” pressure drop, to minimize compression require-
inserted in front of the pig. Dry gas inhibited with MEG ments and postpone compression requirements as much as
will be used as the driving medium. possible.
• Circulating dry gas combined with MEG injection to In addition, one of the key line-sizing criteria has been to
sweep out uninhibited fluid. MEG is injected both onshore achieve a large degree of operational flexibility, i.e. turndown
and subsea. First the rate is adjusted to sweep out uninhibi- flexibility in each of the two multiphase export pipelines with-
ted fluid. Afterwards the rate is decreased to establish a out mitigation actions such as dynamic pigging or gas circula-
sufficient MEG holdup in the system. tion.
Gas is provided by back-flowing dry gas from the export sys- A dual pipeline system is selected compared to one single,
tem from the onshore plant. large pipe diameter pipeline both for in-field flowlines and
multiphase export pipelines to:
Hydrate prevention prior to initial start-up. All subsea • Increase flexibility with respect to liquid holdup manage-
equipment will be filled with MEG inhibited water prior to or ment and turndown capability to facilitate sufficient turn-
just after installation to avoid hydrate formation due to gas down, ramp-up and swing flexibility according to com-
leaking valves. MEG supply lines will be filled with MEG mercial/operational requirements.
prior to or just after installation to avoid hydrate formation and • Enable production through only one line at low production
to eliminate concequences of erroneous injection of uninhibi- rates.
ted water into well fluid due to design, procedure or operator • Allow “dynamic pigging” by periodically increasing the
errors. MEG will be distributed along the flow path from the production rate through one line at a time to sweep out liq-
wells to the onshore plant, prior to initial well start-up. uid.
• Reduce slug volumes/liquid surge volumes during transient
Corrosion management operations (start-up after shutdown, increasing production
rates) and minimize required slugcatcher size.
Corrosion protection and material selection multiphase • Enable circulation of dry gas to increase flow velocities
pipelines. The reservoir fluid of the Ormen Lange field con- during low turndown (“subsea gas lift”).
tains mainly gas. Due to a relatively high CO2 content and the • Increase flexibility to remove potential hydrate plugs (de-
presence of condensed water inside the pipeline, the corrosiv- pressurization from two sides or increased availability due
ity is relatively high. In order to accept carbon steel as pipeline to production through one line if the other line is blocked
material, the injection of chemicals is necessary to reduce the by hydrate plug).
corrosion rate to an acceptable level. In the first phase of pro- • Increase regularity/production availability in case hydrates
duction, before any formation water is present in the well blockage /failure in one line.
fluid, injection of a pH stabilizer (NaHCO3 or possibly • Simplify pipeline installation in deepwater (smaller diame-
KHCO3) is planned. This will increase the pH in the well fluid ter). Maximum pipeline / riser dimension is limited by in-
and thus reduce the corrosion rate down to about 0.1 mm/year. stallation in deepwater (30” nom).
After the appearance of formation water, the method of corro- Fig. 9 illustrates the typical performance of the 30” multiphase
sion control must be changed. The pH of the MEG must be production lines at typical plant arrival pressures.
reduced to avoid scale formation. Corrosion will then be con-
trolled by the injection of a film-forming corrosion inhibitor at Liquid holdup management. The minimum turndown / op-
the X-mas trees to reduce the corrosion rate to below erational envelope is defined by the declination point of the
0.1 mm/y. A qualification program is underway to qualify a flow characteristic (friction dominated) pressure drop, but may
suitable corrosion inhibitor. be extended by use of dynamic pigging to manage liquid
Due to the low sea temperature in the Ormen Lange area, (condensate and aqueous phases) holdup. However, it should
top-of-line corrosion is expected in the first part of the pipe-
OTC 16555 7

be noted that dynamic pigging to control the total liquid • A campaign with gas-condensate-fresh water including
holdup is applicable only at low turndown rates or late life 50 wt% MEG.
when the condensate to gas ratio has decreased. At higher • A campaign with gas-condensate-fresh water including
rates/early field life, the liquid holdup buildup rate is too high 42 wt% MeOH.
requiring unrealistic dynamic pigging frequencies. Fig. 10 Based on the results from the experimental campaigns, the
shows the liquid holdup as a function of flowrate and the typi- OLGA2000 model was modified for better representation of
cal operational envelope of the multiphase production lines. the data. Norsk Hydro Research Centre, IFE and Scandpower
An alternative to dynamic pigging during production at were all involved in this work The following parameters were
low turndown rates (utilizing only one production pipeline) is modified:
to circulate dry gas from the onshore plant via the un-used • The apparent wall roughness in the gas core.
production pipeline and co-mingle it with the wellstream sub- • The transition from laminar to turbulent flow.
sea, to increase the flowrate in the producing production line. • The gas-liquid and oil-water interfacial friction.
A computerized liquid holdup management system to keep • The mixing of water into condensate in the slugs.
track of the liquid holdup in the multiphase export pipeline The results from the experiments and model comparisons
will be developed and installed in the central control room are given in detail in /5/ and /6/. The main conclusions are:
(CCR). • The OLGA2000 model overestimates the slug flow region
Slug flow is not expected to occur during normal produc-
compared to the experiments. The observed annular/mist
tion, but only as consequence of pipeline operations (ramp-up
pattern is not recognized by the model.
and start-up after shutdown), or low turndown.
• The frictional pressure drop is overestimated at high super-
Slug catcher size is defined by steady state differential liq-
ficial gas velocities while underestimated at low superficial
uid holdup and ramp-up modelling.
gas velocities and positive inclination angles.
• In general, the total liquid hold-up (Hl) is estimated with a
Turndown and ramp-up. Liquid holdup in the multiphase
high degree of confidence for all conditions.
production pipelines will increase dramatically at low flow
rates. Ramp-up from turndown conditions need to be carefully • The results from the experiments using three different wa-
controlled so as to keep the liquid delivery rates within the ter phases indicate no major differences in flow behaviour
liquid handling capacity of the onshore receiving and process- between them.
ing facilities. The results from the model modifications indicated that the
The results from multiphase flow simulations indicate that experiments were better represented both for water hold-up
the multiphase production pipelines have good flexibility for and pressure drop. The revised model was then used to simu-
turndown and ramp-up from approximately 50% of design late the Ormen Lange field conditions. However, the key con-
flowrate. At turndown below 50%, the steady state liquid clusion was that the model modifications only gave minor
holdup increases significantly. Ramp-up from these conditions changes for simulating the Ormen Lange conditions (see Fig.
will have to be extensively managed – especially after pro- 11).
longed turndown periods which have enabled steady state liq-
uid holdup conditions to be reached. Sensitivity of model parameters. In order to investigate the
low impact of the modifications performed and to visualize the
Multiphase flow modelling and verification. Correct model- uncertainty of the revised OLGA model with respect to Ormen
ling of the detailed seabed and pipeline topography and reli- Lange conditions, a sensitivity analysis was carried out. The
able multiphase flow models have been imperative for the model parameters subject to changes were tested individually
Ormen Lange development. to obtain a measure of the uncertainty.
Several studies have been carried out to verify the model- The estimated uncertainty in each of the five selected
ling of multiphase flow in rough seabed topography: model parameters were conveniently expressed as a multiplier
for the parameter. The selected variations for each parameter
• Small scale experiments at high inclinations (3” ID, real
are given in Table 2 below.
hydrocarbon fluids).
• Evaluation of scaling of small diameter/lab data to large
diameter/high inclinations conditions.
• Field experiments with tracers to “measure” liquid holdups
(condensate and water) – data analysis, model comparison
and model verification is currently ongoing.
An extensive experimental campaign was carried out at
Norsk Hydro Research Centre in Porsgrunn. The OLGA2000
model was modified according to the findings from the ex-
perimental campaign.
Four different campaigns were conducted during the
course of this work:
• A campaign with gas-condensate.
• A campaign with gas-condensate-fresh water.
8 OTC 16555

Table 2. Model parameter sensitivity


Parameter Low Default High
Apparent roughness multiplier 0 1 5
Interfacial friction factor multiplier 0.3 1 3.5
for steep angles
Oil-water interfacial friction multi- 0.25 1 4
plier, stratified
Oil-water interfacial friction multi- 0.5 1 2
plier, slug
Multiplier for onset point for mixing 0 1 ∞
in slug
NOTES:
1) From the field data and the Porsgrunn high-pressure data, it is concluded that the
apparent roughness is most probably too high and not too low. The high value of the
apparent roughness multiplier is, therefore, regarded only as an illustration of the
sensitivity with respect to this parameter, without any implications that the high
value could be a reasonable value of the parameter.
2) The “infinite” value of the onset point for oil-water mixing in the slug body is
equivalent to setting the mixing to zero independent of velocity.

The results are summarized in Fig. 11, and they indicate


that further improvements of the OLGA model seems to re-
quire significant effort in the fundamental modelling, and that
tuning of the correlation parameters alone is not sufficient.

References
/1/ A. Henriksson, A. Wilhelmsen, T. Karlsen, ” Pipelines in harsh
environment,” OTC 16557, 2004.
/2/ T. Bernt, “Subsea Facilities,” OTC 16553, 2004.
/3/ R. Hartmann, “Production Drilling,” OTC 16554, 2004.
/4/ B. Bjerkreim, ”Subsea Compression,”OTC 16561, 2004.
/5/ G. Elseth, H.Holm, H.Kvandal, S.Munaweera, P.Duchet-
Suchaux, G.Coffe, W. Vandersippe, "High-Pressure Recom-
bined Gas-Condensate-Water Flow at Inclined Conditions,"
BHR 11th International Conference on Multiphase 03, San
Remo, Italy 2003.
/6/ H.Kvandal, S.Munaweera, G.Elseth, H.Holm, "Two-Phase Gas-
Condensate Flow in Inclined Pipes at High Pressure," SPE
77505, SPE Annual Tech. Conf. and Exhibition, 2002.
OTC 16555 9

100 18

0 A nalogue to any other gas/condensate tie-backs (Troll A to 16


Kollsnes, Midgard, Snøhvit, Goldeneye, Malampaya etc)
-100 14

-200 12

Sea water temperature (C)


-300 10

Elevation (m)
-400 8
200

0
-500 6
-200

Depth (m)
Ormen Lange specific challenge!
-400
-600 4
-600
Max
-700 -800 Avg 2
Min
-1000
-800 -5 0 5 10 15 0
Temperature (C)
-900 -2
0 20000 40000 60000 80000 100000 120000
Horizontal distance (m)

Fig. 1. Field development overview. Fig. 4. Ormen Lange specific challenges.

80 100

0
70

-100
60

-200

50
Most likely hydrate plug during
flowing conditions: -300
• MEG injection failure / Qg=10 MSm3/d
Temperature (C)

40 operator failure Qg=14 MSm3/d -400


• Undetected formation water Qg=20 MSm3/d
breakthrough
Qg=24 MSm3/d -500
30
Qg=30 MSm3/d
Most likely hydrate plug during no-flowing
Pileline profile -600
20 conditions:
• Commissioning/tie-in new in-field flow lines
• Water ingress (cold sea water or -700

10 “commissioning fluids”) into no-flowing


conditions
-800

0
-900

-10 -1000
0 10000 20000 30000 40000 50000 60000 70000 80000 90000 100000 110000 120000
Distance (m)

Fig. 5. Expected hydrate plug location during flowing / no-flowing


Fig. 2. Initial subsea development. conditions.
1000
Formation water, unconstrained (P50) (Sm3/sd)
900 Condensed water (P50) (Sm3/sd)
MEG+20% uncertainty, 60wt% (Sm3/sd)
MEG wo uncertainties, 60wt% (Sm3/sd)
800

700
Flowrate (Sm3/sd)

600

500

400

300

200

100

0
08

10

12

14

16

18

20

22

24

26

28

30

32

34
20

20

20

20

20

20

20

20

20

20

20

20

20

20

Fig. 6. Water production and MEG injection requirements during


Fig. 3. Future subsea development. lifetime of the field.
10 OTC 16555

Risk of hydrate blockage in 30" pipeline that


can not be removed
(i.e. pipeline replacement) 10000
60 bara
9000
75 bara
Hydrate blockage Plug can not be removed by
8000 90 bara
in 30" pipeline primary hydrate remediation
strategy

Total liquid holdup (m³)


7000
Operational envelope
6000

5000
Conditional probability of Conditional probability of Hydrate prevention Depressurization Chemical
getting a hydrate/ ice plug getting into hydrate failure Remediation
(MEG wt%, water & time) condition (P&T, MEG wt%) (MEG wt% < 60%)
4000

Unplanned shutdown T (flowing) < T(hydrate) 3000

2000

1000

MEG injection
0
Excessive water Poor MEG quality Operator error MEG Transients
system failure
(x of n wells)
production
(Qw >Qmax) (Cleanliness<88%) 0 5 10 15 20 25 30 35 40
Gas flow rate (MSm3/sd)
Fig. 10. Liquid holdup vs. flowrate @ 60, 75 and 90 bara arrival
Fig. 7. Simplified hydrate risk fault tree model. pressure at Nyhamna.

12000 90
Liquid content
0,05 1,0
Water content
0,9 10000 80
0,04 Pressure loss
0,8
Liquid & Water content (m3)

0,04
8000 70
0,7

Pressure loss (bar)


0,03
0,6
0,03 6000 60
p()

p()

0,5
0,02
0,4
0,02 4000 50
0,3
0,01 0,2
2000 40
0,01 0,1
0,00 0,0
0 30
0 10 20 30 40 50 60 70 80 90 100
50 100 150 200 250 300
% of injected MEG rate left in one 30" pipeline Production rate (kg/s)

Fig. 8. MEG concentration uncertainty. Fig. 11. Results from model correlation parameter sensitivities.

190
180
170
Pipeline inlet pressure (bara)

160
150
140
130
120
60 bara
110
75 bara
100
90 bara
90
0 5 10 15 20 25 30 35 40
Gas flow rate (MSm3/sd)
Fig. 9. Pipeline inlet pressure vs. flow rate @ 60, 75 and 90 bara
arrival pressure at Nyhamna.

You might also like