Professional Documents
Culture Documents
Raymund Mariano1
Timely detection, evaluation and classification of emergencies are in place in the San
Roque Dam to insure the safety of the Dam.
The San Roque Dam is a multipurpose, zoned earth and rock-fill dam with a central core
across the Lower Agno River in the Province of Pangasinan, Luzon, Philippines (Figure
1). It has a height of 200 m above the existing river valley floor with a compacted fill
volume totaling nearly 40 million cubic meters. At its nominal crest of El. 295.0 m, the
Dam length is 1,130 m.
The construction of the Dam started in March of 1998 and the first filling of the reservoir
started in August of 2002.
The Dam is owned by the Government of the Philippines under National Power
Corporation (NPC) and is being operated and maintained by the San Roque Power
Corporation (SRPC) over a 25 year Built-Operate-Transfer arrangement that commenced
on May 1, 2003.
The design, review, and construction of the Dam were undertaken by multiple and
recognized dam experts, namely:
• United Engineers International/Washington Group Incorporated (Designer)
• Raytheon Ebasco Overseas Ltd. (Constructor)
• Harza Engineering (SRPC’s Engineer)
• Panel of Consultants (Independent Review)
• R.W. Beck (NPC/Lenders’ Independent Engineer)
• Sembenelli Consulting (Original Dam Designer)
Currently, the Consultant for SRPC, the Operator of the Dam, in assessing the
performance of the Dam is Kansai Power International Corporation (KPIC).
1
Facilities Engineer, San Roque Power Corporation
1 of 15 9/17/2009
San Roque Dam
Ambuklao Dam/1956
CA = 617km2
Volume = 125.5 MCM
Binga Dam/1960
CA = 860km2
Volume = 22 MCM
Structural Safety
The San Roque Dam and its appurtenant structures were designed to withstand the
Maximum Credible Earthquake (MCE) having an acceleration of 0.60 g or a magnitude
of 7.8. Should an MCE occur, the Dam may be subject to limited settlement and minor
cracking, but will remain secure and intact.
The Dam was also designed so that high reservoir inflow conditions alone cannot cause
the dam to overtop or otherwise fail, because the Dam spillway is capable of passing in
excess of the Probable Maximum Flood (PMF) – a flow greater than a flood event that
has a return interval of 10,000 years.
The Dam consists of combined earth/gravel fill and rockfill shell zones, filter, drain and
transition zones. The impermeable core is a clay gravel blend. Three grouting/drainage
galleries are provided for inspection and maintenance purposes which are located in the
dam foundation. The majority of the 1,200 meters of gallery length are 3 m wide by 4.5
m high with a shotcrete lining. The section located at the lowest level of the foundation is
reinforced with a formed concrete lining to accommodate potentially higher ground water
pressures. Access to the galleries is provided by four adits, two on each side of the
downstream abutments.
Prior to the placement of the dam materials, the dam foundation received extensive
treatment including the stripping of unsuitable base materials, careful cleaning,
2 of 15 9/17/2009
investigation and geotechnical mapping and other surface preparation procedures.
Surface and subsurface grouting (from within the galleries) form a grout curtain that
extends more than 80 meters below the foundation. This curtain consolidates the rock
structures below the dam to form an effective barrier to seepage.
The functions of the various zones of the dam are presented in Table 1 and Figure 2.
Safety Monitoring
The San Roque Dam Safety Program focuses on preparedness actions taken both prior to
and following development of emergency conditions. Preparedness actions involve the
installation of warning systems or establishment of procedures for:
Dam Instrumentation
During construction, first reservoir filling, and subsequent operations, the performance of
the Dam and its foundation has been continually monitored to verify that the as-
constructed dam is performing according to design.
The main objectives of the instrumentation monitoring and visual inspections are:
• Analytical assessment
o Verify design assumptions and construction techniques
3 of 15 9/17/2009
o Analyze adverse events; and
o Verify satisfactory performance of the dam
The parameters that are monitored are: water levels and pore-water pressure within the
dam and its foundation; quantity, sources and turbidity levels of seepage; total and
differential movements and overall dam movement. Dam instrumentation includes
piezometers, settlement survey monuments, internal settlement cells, flow measuring
weirs, and rainfall and turbidity measurement devices (Table 2 and Figures 3 - 7).
4 of 15 9/17/2009
Table 3 –San Roque Dam Monitoring Schedule
Emergency Preparedness
The Emergency Action Plan (EAP) is a plan of action to be taken to reduce the potential
for property damage and loss of life in an area affected by a dam failure or large flood. It
provides the Operator (SRPC) with a systematic procedure to notify:
1. The Government of the Philippines (GOP) agencies responsible for emergency
responses to “dam related” emergencies;
2. The five nearby municipalities located immediately downstream of the Dam.
A Dam Break Scenario is now part of the Disaster Preparedness Plan of the Province of
Pangasinan. Public Information Drives and Tabletop Emergency Situation Drills using
the Notification Procedure are conducted regularly with the emergency response
agencies.
Based on the seven years of data collected to date, there are no concerns on the
performance and safety of the Dam and its foundation. The Dam’s performance is
actually exceeding the expectations of the Designer. Figures 9 shows the San Roque
Reservoir’s Operation Status. Figure 10 shows the San Roque Dam’s Total Seepage
Trend.
5 of 15 9/17/2009
Over the seven year life of the dam, some instruments have already stopped functioning
but this is no problem due to the redundancies of the instruments installed.
The dam itself is now in the period of transition to the long-term stable condition and the
frequency of monitoring will eventually be revised at longer intervals.
The Emergency Action Plan (EAP) for San Roque Dam is the first of its kind in the
Philippines. EAPs are now being formulated for the older dams in the country.
References
1. San Roque Dam Emergency Action Plan, Version 1.5. January 2007
2. San Roque Multipurpose Project Instrumentation Monitoring and Inspection Manual.
2006.
3. KPIC’s Annual Report for Civil Works. 2006.
4. San Roque Dam Emergency Management Contingency Plan. 2003.
5. San Roque Multipurpose Project. SRPC Consulting Panel Meeting No. 14. 2003.
6 of 15 9/17/2009
Figure 2 - Cross Section of the Dam
7 of 15 9/17/2009
Figure 3 – Plan view of instrument locations
8 of 15 9/17/2009
Figure 4 – Instrumentation Section - Sta. 9+25
9 of 15 9/17/2009
Figure 5 – Flow Measurement Stations in Galleries
10 of 15 9/17/2009
Figure 6 – Detail of Gauge and Vibrating Wire Piezometers in Galleries
11 of 15 9/17/2009
Figure 7 – Movement Survey Monuments over the Dam
12 of 15 9/17/2009
STATION TYPE LOCATION
Master Station Hub O&M Office
Station 1 Micro Seismic Abandoned NPC/Old Repeater Station
Station 2 Micro Seismic Daynet
Station 3 Micro Seismic Island Station (in the Reservoir)
MicroSeismic
Strong Station 4 Micro Seismic Abandoned NPC Station
MabuhaySat
Station 5 Strong Motion Left Abutment of Dam
2 Station 6 Strong Motion Toe of Dam
Station 7 Strong Motion Left Dam Crest
Station 8 Strong Motion Center Dam Crest
Station 9 Strong Motion Right Abutment of Dam
3
Dam Axis
9
8
1
6 7 4
5
Master Station at
Administration Building
13 of 15 9/17/2009
Reservoir Elevation (m) .
.
0
25
50
75
100
125
150
175
200
225
250
275
300
325
350
375
400
1-Jan-03
31-Jan-03
2-Mar-03
1-Apr-03
1-May-03
31-May-03
TO
30-Jun-03
8-AUG-02
15-0CT-03
PERIOD 1
30-Jul-03
29-Aug-03
PERIOD 1
28-Sep-03
28-Oct-03
27-Nov-03
27-Dec-03
26-Jan-04
25-Feb-04
26-Mar-04
TO
25-Apr-04
30-JUN-04
PERIOD 2
16-OCT-03
25-May-04
PERIOD 2
24-Jun-04
24-Jul-04
23-Aug-04
22-Sep-04
22-Oct-04
14 of 15
TO
21-Nov-04
1-JUL-04
28-DEC-04
PERIOD 3
21-Dec-04
20-Jan-05
19-Feb-05
PERIOD 3
21-Mar-05
20-Apr-05
20-May-05
TO
19-Jun-05
26-JUL-05
19-Jul-05
29-DEC-04
PERIOD 4
18-Aug-05
17-Sep-05
17-Oct-05
16-Nov-05
PERIOD 4
16-Dec-05
15-Jan-06
TO
14-Feb-06
16-Mar-06
5-JUL-06
27-JUL-05
PERIOD 5
15-Apr-06
15-May-06
14-Jun-06
14-Jul-06
13-Aug-06
PERIOD 5
12-Sep-06
RESERVOIR ELEVATION
12-Oct-06
11-Nov-06
11-Dec-06
9/17/2009
10-Jan-07
TO
9-Feb-07
Figure 9 – Reservoir Operation Status
11-Mar-07
7-AUG-07
6-JULY-06
PERIOD 6
10-Apr-07
10-May-07
9-Jun-07
PERIOD 6
9-Jul-07
8-Aug-07
7-Sep-07
7-Oct-07
6-Nov-07
6-Dec-07
5-Jan-08
4-Feb-08
TO
5-Mar-08
PERIOD 7
4-Apr-08
8-AUG-07
16-JUL-08
PERIOD 7
4-May-08
3-Jun-08
3-Jul-08
2-Aug-08
1-Sep-08
1-Oct-08
31-Oct-08
30-Nov-08
PERIOD 8
30-Dec-08
TO
29-Jan-09
17-JUL-08
16-APR-09
PERIOD 8
28-Feb-09
30-Mar-09
29-Apr-09
29-May-09
28-Jun-09
TO
28-Jul-09
DATE
27-Aug-09
PERIOD 9
17-APR-09
PERIOD 9
26-Sep-09
Seepage, l/s .
0
20
40
60
80
100
120
140
160
180
200
220
240
260
280
300
320
340
1-Aug-02
1-Oct-02
1-Dec-02
1-Feb-03
1-Apr-03
RAINFALL
1-Jun-03
1-Aug-03
1-Oct-03
1-Dec-03
1-Feb-04
1-Apr-04
1-Jun-04
1-Aug-04
15 of 15
1-Oct-04
1-Dec-04
1-Feb-05
1-Apr-05
RESERVOIR ELEVATION (m)
1-Jun-05
1-Aug-05
1-Oct-05
1-Dec-05
1-Feb-06
1-Apr-06
1-Jun-06
1-Aug-06
TOTAL SEEPAGE
TOTAL SEEPAGE
1-Oct-06
TOE DRAIN & GALLERIES
1-Dec-06
9/17/2009
1-Feb-07
1-Apr-07
1-Jun-07
Figure 10 – San Roque Dam Total Seepage Trend
1-Aug-07
1-Oct-07
1-Dec-07
1-Feb-08
TOE DRAIN FLOW
1-Apr-08
1-Jun-08
1-Aug-08
1-Oct-08
1-Dec-08
1-Feb-09
1-Apr-09
1-Jun-09
1-Aug-09
GALLERY SEEPAGE
1-Oct-09
0
20
40
60
80
100
120
140
160
180
200
220
240
260
280
300
320
340
Spillway
¾ Type : Open Chute - gated
¾ Crest Level : 270 m.a.s.l.
¾ Design Capacity : 12,800 m3/sec