Professional Documents
Culture Documents
>
M-SAT-M-63-11
AUGUST 1 5 , 1 9 6 3
b "66 81238
(ACCESSIO? NUWBERI ITHRU)
f
>
- 9/
(PAGES)
ICODEI
CCATEGORY)
c
I
P r e p a r e d by:
S a t u r n Systems O f f i c e A
National Aeronautics and Space Administration
-
a
4
Satuhn
.*
QQQusthated CbhonoQogy
To s e c u r e t h i s amount of t h r u s t , ABMA f i r s t c o n s i d e r e d c l u s t e r i n g
f o u r 380,000 pound t h r u s t Rocketdyne E - 1 e n g i n e s , t h e n i n a n e a r l y s t a g e
of development. T h i s i n i t i a l concept w a s n o t c a r r i e d f u r t h e r , because
of t h e e s t i m a t e d l e n g t h of t i m e r e q u i r e d t o develop t h e e n g i n e . However,
s t u d i e s c o n t i n u e d t o d e t e r m i n e i f o t h e r e n g i n e s c o u l d be used i n a s i m i -
lar a p p l i c a t i o n .
*-
Then, i n J u l y 1958, r e p r e s e n t a t i v e s o f t h e Advanced Research Pro-
j e c t s Agency (ARE'A) e x p r e s s e d i n t e r e s t i n a c l u s t e r e d b o o s t e r of
. 1,500,000 pounds t h r u s t t h a t would u s e r o c k e t e n g i n e s a l r e a d y t e s t e d
and of proven r e l i a b i l i t y . On August 1 5 , 1958, ARPA Order 14-59 f o r -
m a l l y i n i t i a t e d what was t o become t h e SATURN p r o j e c t . The o r d e r au-
t h o r i z e d a r e s e a r c h and development program f o r a l a r g e , s p a c e v e h i c l e
b o o s t e r . To s e c u r e t h e d e s i r e d t h r u s t of one-and-a-half m i l l i o n pounds,
1
August 1958
Previous studies had shown that the liquid oxygen (LOX) and fuel
tanks developed for the REDSTONE and JUPITER missiles could, with some
modification, be used for the tanks of the proposed booster. It was
also determined that an existing engine, the S-3D, used on both the
THOR and JUPITER missiles (Fig. 2), could be modified to produce an in-
creased thrust of 188,000 pounds. Certain of the tools and fixturcs
developed,for the REDSTONE and JUPITER programs could also be used with
comparafiively little modification (Fig. 3). Thus, it was possible to
begin booster development with certain well-tested hardware of proven
reliability. As a result, the time for design and development of some
important booster components and tooling was significantly shortened, 8
2
September - October 1958
/-
- - . - -
L
I
-\
-
3
December 1958 - January 1959
4
January - March 1959
1
In response to ARPA Order 47-59 of the previous month, construction
of the ABMA static test stand for large boosters began January 10, 1959.
At the same time, Army representatives of the ARPA board visited AMR to
discuss selection of a site for large vehicle launch facilities at Cape
Canaveral. By February 1959, a contract had been awarded for construc-
tion of the blockhouse at the site (Launch Complex 3 4 ) , and a design
contract was also awarded for a movable service structure, which would
. be used to assemble and service the vehicle on the launch pedestal.
d On February 3 , an ARPA memorandum officially renamed the project
SATURN, cancelling the former identification of JUNO V.
--r
120"
011 -
F
I I
a a
it
I
i
I
t
200'
I
i
i
I
I-'
f
i,
256-
_..
.
.
FIGURE 6. FIGURE 7. FIGURE 8 . VEHICLES USING
SATURN B SATURN C TITAN AND ATLAS STAGES
5
April - July 1959
By April 28, the first production H-1 engine (H-1001) had been de-
livered on schedule to ABMA (Fig. 10). The first firing test of this
engine, later used in the first test booster, was performed successfully
on May 26, 1959. Shortly after, on July 5, 1959, construction began of .
the SATURN blockhouse for Launch Complex 3 4 , at Cape Canaveral (Fig. 11). \
On July 27, 1959, the date that the last JUPITER airframe was com-
pleted at Redstone Arsenal, the Arsenal shops began retooling to support
the SATURN project. On the same day, the Director of Defense Research
..
and Ecgineering sent the Secretary of the Air Force and the Director of
ARPA a memorandum stating that as the requirements for the second stage
of SATURN and the booster for the proposed DYNA SOAR vehicle were quite
similar,ARPA and the Air Force should consider a common development of
these projects. Until completion of this review, neither agency was to
make firm commitments for the redesign of existing boosters or develop-
ment of new ones. Immediately after issuing this memorandum, July 29,
1959, ARPA ordered that all AOMC inhouse and contract work, and other
expenditures relating to the TITAN second stage, cease immediately. How-
ever, permission was granted to continue preliminary work not directly
connected with the stage diameter.
.
.
FIGURE 9. ATLAS CENTAUR VEHICLE FIGURE 10. H-1 ENGINE IN ALIGNMENT
(CENTAUR SECOND STAGE) FIXTURE
6
August - October 1959
7
October - December 1959
i
70"-
REDSTONE JUPITER-C 2:
835
LI
?Y
NE
185'
XL'
105'
t
i
JUPITER JUNO II
- -
S
December 1959
9
January - February 1960
and producing a t o t a l of 80,000
pounds of t h r u s t . The S-V s t a g e
( F i g . 16) used two of t h e same en-
g i n e s as t h e s-IV s t a g e , p r o d u c i n g
a t o t a l o f 40,000 pounds of t h r u s t .
A s a r e s u l t of t h e December de-
c i s i o n s , a c t i o n w a s taken t o procure
t h e S-IV s t a g e . A b i d d e r ' s confer-
ence c o n c e r n i n g t h e s t a g e w a s h e l d
a t H u n t s v i l l e , J a n u a r y 26 and 2 7 ,
1960, a n d , by F e b r u a r y 29, 1960,
twelve companies had s u b m i t t e d con-
FIGURE 16. THIRD STAGE (S-V) tract proposals.
10
January - A p r i l 1960
On F e b r u a r y 1 9 , 1960, w h i l e p r e p a r a t i o n s f o r t h e f i r s t series o f
.-
FIGURE 18. BOOSTER I N TEST STAND FIGURE 19. BOOSTER STATIC FIRING
11
April - May 1960
-.
12
May 1960
13
June - July 1960
high-thrust 5-2 engine (Fig.24).
This engine, of the type defined by
the Silverstein Committee in December
1959, would burn liquid hydrogen-
liquid oxygen, and would be used in
an advanced upper stage for the
SATURN vehicle.
14
July - August 1960
Formal procurement of the SlIV stage was initiated July 26, i 9 6 0 ,
when NAS7-1 Supplemental Agreement was signed with Douglas Aircraft
Corporation (DAC). This contract required that DAC design, develop,
and fabricate the four-engine S-IV stage (Fig. 25) for the SATURN C-1
configuration. Contracts were also let on August 10, 1960, with Pratt
and Whitney (PGXJ) to develop and produce LR-119 engines; the government
would furnish these engines to the contractors responsible for building
the S-IV and S-V stages of the C - 1 vehicle. The LR-119 engine, an up-
rated LR-115, was planned to generate 17,500 pounds of thrust.
.-
15
September - October 1960
On September 8, 1960, the
facilities o f the National Aero-
nautics and Space Administration
at Huntsville, Alabama, were de-
dicated and designated as the George
C. Marshall Space Flight Center.
Attended by President Eisenhower,
Mrs. G. C. Marshall, NASA Administra-
tor T. Keith Glennan, and many other
National, State, and local dignitar-
ies, this dedication, (Figs. 27, 28,
and 29) was the culmination of events
originating in the Presidential EX-
ecutive Order, dated March 15, 1960.
- b
FIGURE 28. DR. VON BRAUN AND FIGURE 29. MR. GLENNAN, PRESIDENT
PRESIDENT EISENHOWER EISENHOWER, AND DR. VON BRAUN
16
November 1960 -. January 1961
was delivered to MSFC, November 22,
1960.
17
January - F e b r u a r y 1961
Rogallo p a r a g l i d e r ( F i g . 3 2 ) . A
d e s i g n c o n t r a c t w a s awarded f o r e q u i p -
ment which would be u s e d a t MSFC t o
check o u t t h e S-1 s t a g e a u t o m a t i c a l l y .
-
and moved t o checkout ( F i g . 3 4 ) .
On J a n u a r y 31, a n eight-engine
T h i s w a s a t e s t of 113 s e c o n d s ' d u r a -
tion.
A dummy S-V s t a g e , b u i l t f o r u s e
on SA-1, w a s r e c e i v e d from Convair on
F e b r u a r y 8 , and mated t o t h e dummy
S - I V s t a g e . The f i r s t h o r i z o n t a l as-
sembly of t h e complete C - 1 v e h i c l e
w a s accomplished d u r i n g t h i s month
(Fig. 35).
I n F e b r u a r y , a s e r i e s of m e e t -
i n g s were h e l d a t NASA H e a d q u a r t e r s
and MSFC t o d i s c u s s d i f f i c u l t i e s m e t
I I
d u r i n g LR-119 e n g i n e development.
A s a r e s u l t of t h e s e m e e t i n g s , s t u -
FIGURE 33. c-2 SECOND STAGE CONCEPT d i e s began e a r l y i n March t o d e t e r m i n e
18
.-i
I --
I -
I
19
March 1961
.
.
A l s o , on March 2 , 1961, a s a
p a r t of t h e b o o s t e r r e c o v e r y studies,
t e s t s began a t Cape C a n a v e r a l t o de-
t e r m i n e t h e f e a s i b i l i t y of r e u s i n g
H-1 engines a f t e r exposure t o s a l t
water ( F i g . 3 7 ) . C o n s t r u c t i o n work
a t Launch Complex 34 c o n t i n u e d t o
progress s a t i s f a c t o r i l y , with the
service s t r u c t u r e , b l o c k h o u s e , and
FIGURE 37. SALT WATER TEST OF gas f a c i l i t i e s , n e a r i n g completion
H-1 ENGINE (Fig. 3 8 ) .
20
March 1961
21
March - A p r i l 1961
a l s o made t o use s i x LR-115 e n g i n e s on t h e S-IV s t a g e i n s t e a d of f o u r
, LR-119 e n g i n e s . P r a t t and Whitney would s t i l l b e t h e s u p p l y i n g c o n t r a c -
t o r . Also proposed were c e r t a i n d e s i g n changes of t h e S - I s t a g e , i n c l u d -
i n g i n c r e a s e d p r o p e l l a n t c a p a c i t y , f i n s ( F i g . 4 0 ) , and i n c r e a s e d s t r u c -
t u r a l s t i f f e n i n g f o r l a t e r v e r s i o n s of t h e b o o s t e r .
22
April 1961
23
April 1961
On April 17, the Palaemon began its first trial run to Cape
Canaveral. The barge carried a water-ballasted tank simulating the
size and weight of the S-I booster (Fig. 4 4 ) , plus a dummy S-V stage
for the SA-1. The barge reached Cape Canaveral on April 30 (Fig. 4 5 ) .
After rehearsing movement of the booster along roads at the Cape, the
simulator was reloaded aboard the Palaemon. The d m y S-V stage remain-
ed at the Cape. On May 3, the barge began its return trip, arriving
at the Redstone Arsenal dock, May 15 (Fig. 4 6 ) .
24
May 1961
._ -___--- ---
, . . .^ * . .. _1
25
VtVILLt
L N 6 T H 17 BLOCK I BLOCK II
165
I60 - 51 I ' $ .,"
I50
140
Ix)
I20
110
S-E
SE
100
90
JUMW - 7
I
80 I
70
, '1
60
50 $ 1
40
30
20 ~
10
0
I F I G W 49. CONFIGURATIONS O F SATURN FIGURE 50. SEPARATION OF UPPER
FLIGHT VEHICLES STAGES FROM BOOSTER
t w o - s t a g e manned m i s s i o n ( F i g s . 49 and 5 0 )
T h i s change e l i m i n a t e d t h e immediate need
f o r a n S-V stage w i t h t h e C - 1 , e x c e p t f o r
p o s s i b l e s p e c i a l missions. Also, during
May 1961, MSFC began r e e x a m i n a t i o n of t h e
c a p a b i l i t i e s of t h e SATURN C-2 c o n f i g u r a -
t i o n t o support l u n a r circumnavigation
missions. R e s u l t s of t h i s examination
i n d i c a t e d t h a t , as lunar mission r e q u i r e -
ments had i n c r e a s e d , a SATURN v e h i c l e of
even g r e a t e r performance would be de-
sirable.
26
May - J u n e 1961
During J u n e , c o n s t r u c t i o n of t h e l i q u i d - h y d r o g e n t e s t s i t e ( F i g . 5 3 )
27
May - June 1961
I
I
.
Engine gimbal tests performed at MSFC during April and May had indi-
cated the advisability of increasing the stiffness of the engine control
support structure in the booster. To investigate this matter further,
the control engine support structure of the S-I stage of the dynamic test
vehicle was modified and a series of single-engine gimbal tests began on
May 29, 1961. As test results were of marginal satisfaction, a new t y p e -.
of actuator s e m o valve was then installed. Further test results were
satisfactory. On completion of these tests, the dummy booster was moved
to the dynamic test stand early in June, and, for the first time, verti-
cally mated with dummy S-IV and S-V stages. The assembled vehicle was
then readied f o r dynamic testing (Fig. 5 4 ) .
During May and June 1961, Douglas Aircraft had continued fabrication
of full-scale mockups of S-IV stage sections (Figs. 55 and 56). These
28
J u n e 1961
FIGURE 55. TAIL AREA MOCKUP FIGURE 56. FORWARD INERRSllAGE MOCKUP
29
J u n e 1961
i
*.
--t
F i n a l a c c e p t a n c e t e s t i n g of t h e S - I s t a g e f o r t h e f i r s t f l i g h t
b o o s t e r began a t MSFC, June 1 2 , 1961, t h e f i r s t o p e r a t i o n accomplished
-.
30
June 1961
I .-
On June 2 1 , Phase I1 procure-
ment of the s-I1 stage began. Four
companies were invited to attend
the Phase I1 meeting at MSFC and
proposals were requested.
FIGURE GO. INSTRUMENT UNIT MOCKW
A t another meeting held in
June with DAC, MSPC made the de-
cision that the S-IV stage would be
redesigned to incorporate chill-
down venting through which accumulated hydrogen gas would be disposed.
31
J u n e 1961
( F i g . 6 2 ) . I n v e s t i g a t i o n s were s p e c i f i c a l l y d i r e c t e d toward d e t e r m i n i n g
c a p a b i l i t i e s of t h e proposed C-3 c o n f i g u r a t i o n i n s u p p o r t i n g t h e APOLLO
mission (Fig. 6 3 ) .
-.
32
June - July 1961
FIGURE: 64. INSTALLATION OF SA-T2 FIGURE 65. DR. VON BRALTN, JAMES E.
ON STATIC TEST STAND WEBB, AND MAJ. GEN. OS-ER
On June 27, the first static test of the SA-T2 booster (the SA-T1
booster modified to the configuration of the SA-2 booster stage) was
successfully accomplished at MSPC (Fig. 64). This was an eight-engine
test (SAT-14) of 30 seconds' duration to confirm effectiveness of the
new actuator servo valve and the stiffening of the control engine
support structure.
33
July 1961
testing proceeded at MSFC,
Rocketdyne, in California,
began static firing tests
of a complete F-1 engine,
(Fig. 66). In the course
of these tests, the engine
would build up to 1.5 mil-
lion pounds of'thrust (Fig.
67).
34
a-
.-
35
July 1961
On July 18, 1961, the third static firing of the SA-T2 booster was
successfully completed in an eight-engine static test (SAT-16) of 110
seconds' duration. During this test, the in-flight engine cut-off se-
quence (shutdown of the inboard engines six seconds before shutdown of
the outboard engines) was simulated for the first time. The test also
continued investigation of heat shield and engine curtain materials; and
testing was performed t o support studies of the SA-D1 test vehicle.
36
July - August 1961
NUCLEAR STAGE
SATURN C - 2
FIGURE 71. ARTIST'S CONCEPT OF MOLL3 STANnARD CHEMICAL
SEPARATION FROM SEC9XI.I STAGE 2 N D STAGE
by MSFC to General Dynamics-Astronautics,
Douglas Aircraft Company, Lockheed Air-
craft Company, the Martin Company, for
a six-month RIFT (Reactor in Flight) de-
sign analysis for a nuclear-powered SATURN BOOSTER
SATURN upper stage (Fig. 72).
-
Assembly of the booster stage for
the SA-3 vehicle began on July 31, 1961. FIGURE 72. CONCEPT OF SATURN
The following day, August 1, 1961, the WITH NUCLEAR POWER STAGE
SA-2 booster was transferred from the
assembly area to checkout. On August 3 , a planned 114-second static test
(SAT-17) of the SA-T2 booster was terminated after 1.2 seconds, when
instrumentation indicated an unacceptably high temperature of the LOX
pump inlet on engine No. 1. The test was therefore rescheduled for the
ful:owing ~ e e k , Test SAT-18 was performed on August 7, to accomplish
objectives established for SAT-17. Tne SA-T2 5 c z s t e r was successfully
fired in a test of 124 seconds' duration.
37
August 1961
38
August 1961
39
August 19 61
-*XI_(" A
Compromise arrived at the Cape, unloaded her cargo (Fig. 77), and assem-
bly of the first flight vehicle on the launch pedestal began (Figs.78-8)).
40
FIGURE 79. S-IV ERECTION AT CAPE CANAVERAL
41
August 1961
--* .-
-- “ I
-”
i x x
-
FIGURE 81. ASSEMBLED SA-1 LAUNCH PEDESTAL
A f t e r t h e v e h i c l e was c o m p l e t e l y assembled on t h e l a u n c h p e d e s t a l
( F i g . 81), f i n a l p r e p a r a t i o n s f o r t h e launch began.
42
FIGURE 8 2 . SATURN LAUNCH COMPLEX 37, CAPE W W R L U ,
43
September 1961
On September 15, 1961, the SA-1 vehicle had been completely assem-
bled on the launch pedestal at LC 3 4 . For the first time, the service
structure was moved back, leaving the SATURN standing as it would at
launch (Fig. 8 5 ) .
.
FIGURE 8 4 . MICHOUD PLANT AT NEW ORLEANS
44
September - October 1961
hydrogen are studied. The SA-2 flight booster was inscaiied tii E h 2 YSFC
static test tower early in October. On October 10, a successful eight-
engine test of 33 seconds duration ( S A - 0 4 ) was performed to check
reliability and performance of booster and gimbal systems. Test SA-05
was successfully conducted on October 24 for a duration of 112 seconds.
Test objectives included evaluation of the flight cutoff sequence.
45
Octo5er - Novennber 1961
L a t e i n October, NASA s e l e c t e d a 1 3 , 5 5 0 - a c r e s i t e i n M i s s i s s i p p i
on which t o b u i l d a f a c i l i t y f o r s t a t i c t e s t i n g of t h e Advanced
SATURN, and NOVA f i r s t s t a g e s . The s i t e , which w i l l become t h e
M i s s i s s i p p i T e s t F a c i l i t y , i s o n l y 35 m i l e s from t h e Michoud P l a n t
where i n d u s t r y w i l l manufacture t h e S - I and S-IC S t a g e s .
On November 6 ,
1961, MSFC d i r e c t e d
NAA t o r e d e s i g n t h e
S-I1 S t a g e t o i n c o r -
porate five 5-2
engines, providing a
t o t a l of 1,000,000
pounds s t a g e t h r u s t
(Fig. 87).
Work a t t h e new
large booster S t a t i c
T e s t S t a n d a t MSFC
was interrupted i n
November f o r re-
d e s i g n of the s t a n d
t o accept thrust
l e v e l s of m o r e t h a n
7.5 m i l l i o n pounds.
On November 1 0 ,
1961, NASA r e c e i v e d .\
p r o p o s a l s from f i v e
f i r m s f o r the
development and
p r o d u c t i o n of t h e 4
advanced SATURN
booster.
NASA announced
s e l e c t i o n of C h r y s l e r
t
C o r p o r a t i o n on
November 1 7 , t o FIGURE 8 6 . LAUNCH OF SAT-LJRS SA-1 FLIGHT VEHICLE
46
I
November 1951
47
November - December 1961
The SA-T3 test stage was installed in.the test stand and, on
November 30, 1961, Test SAT-20 was conducted to investigate flight
cut off sequencing, to perform an "engine out" test, and to study
fuel and LOX tank levels. The test was prematurely cut off at 95
seconds by the automatic fire detection system. No hardware damage
occurred. This was the first of a series of tests to verify SA-3
design improvements.
A preproposal confer-
ence was held on December 7,
at Huntsville, Alabama, to
select a prime contractor
for the reactor-in-flight
test (RIFT) stage launch
vehicle. On January 29,
1962, NASA selected three % *
49
December 1961 - January 1962
will be 33 feet in diameter and about 140 feet high (Fig. 91). The
manufacturing program at Michoud was planned to consist of 24 flight
stages and one for ground test.
50
January 1962
51
J a n u a r y 1962
FIGURE 9 3 . SATURN C - 5
52
February - March 1962
/
,/
S t a g e s o f t h e SATURN SA-2 f l i g h t v e h i c l e d e p a r t e d H u n t s v i l l e on
F e b r u a r y 1 6 , f o r Cape Canaveral. The v e h i c l e a r r i v e d a t Cape Canaveral
on F e b r u a r y 27, 1962 and, by March 1, t h e v e h i c l e was e r e c t e d on t h e
-- l a u n c h pad of LC 34 (Fig. 94).
53
March - April 1962
The SA-T3 t e s t b o o s t e r
was removed from t h e MSFC
s t a t i c t e s t s t a n d on March 15,
f o r i n s p e c t i o n , r e p a i r and
m o d i f i c a t i o n . On March 19,
t h e b o o s t e r f o r t h e SA-3 f l i g h t
v e h i c l e was i n s t a l l e d i n t h e
t e s t tower, and p r e p a r a t i o n s
begun f o r t h e f i r s t f l i g h t
qualification test.
L a t e i n March, a c o n s t r u c t i o n c o n t r a c t w a s awarded f o r c o n s t r u c t i o n
of a second launch area a t t h e SATURN Launch Complex 37, Cape C a n a v e r a l .
C o n s t r u c t i o n began e a r l y i n A p r i l (Fig. 97).
54
A p r i l 1962
NASA H e a d q u a r t e r s announced
on A p r i l 18 t h a t t h e h i g h e s t
n a t i o n a l p r i o r i t y (DX) had been
approved f o r t h e AFOLLO, SATURN
C-1, and SATURN C-5. The p r i o r i t y
includes a l l stages, engines,
f a c i l i t i e s , and r e l a t e d c o n s t r u c -
.- t i o n f o r p r o d u c t i o n , t e s t , re-
s e a r c h , launch, and i n s t r u m e n t a -
tion.
The second f l i g h t v e h i c l e ,
t h e SA-2, w a s s u c c e s s f u l l y
launched-from Cape Canaveral on
A p r i l 1 5 ( F i g . 98). A s w i t h t h e FIGURE 98. LAUNCH OF SATURN SA-2
SA-1, t h e v e h i c l e was launched FLIGHT VEHICLE
55
April 1962
56
I n mid-May, MSFC d i r e c -
t e d DAC t o u s e a 260-inch
d i a m e t e r f o r t h e S-IVB (an
i n c r e a s e o f 40 i n c h e s from
t h e i n i t i a l diameter) per-
m i t t i n g development o f a
more optimum s i z e d s t a g e .
A l s o d u r i n g May, t h e S - I 1
Stage length was increased
from 75 f e e t t o 81.5 f e e t ,
and t h e S-IC S t a g e w a s
d e c r e a s e d i n l e n g t h from
I --
141 f e e t t o 138 f e e t .
A c o n t r a c t w a s awarded
I t o Greenhut C o n s t r u c t i o n
Company on June 5 , t o mod-
i f y t h e SATURN C - 1 b o o s t e r
I s t a t i c t e s t s t a n d a t MSFC.
The s t a n d , o r i g i n a l l y b u i l t
t o t e s t t h e REDSTONE and
I JUPITER m i s s i l e s and l a t e r
m o d i f i e d f o r SATURN t e s t i n g ,
w i l l provide test positions
f o r two C - 1 f i r s t s t a g e s
( F i g . 100).
On J u n e 9 , P r a t t and
-- . .
WriLuitsy c"i;li;:ZZZ2 Frclhi-
I n a r y f 1i g h t r a t i n g t e s t s FIGURE 100. C - 1 FIRST STAGE TEST STAND
o f t h e RLlOA-3 e n g i n e w i t h
a l l t e s t o b j e c t i v e s suc-
cessfully met.
During J u n e , b i d s w e r e r e q u e s t e d f o r c o n s t r u c t i o n of a s t a t i c t e s t
s t a n d t o c a p t i v e f i r e t h e SATURN C-5 b o o s t e r . The s t a n d , t o be l o c a t e d
.- a t MSFC, w i l l p r o v i d e h a n d l i n g equipment and t h r u s t r e s t r a i n t f o r b o o s t -
ers up t o 178 f e e t i n l e n g t h , 48 f e e t i n d i a m e t e r , and w i t h t h r u s t o f up
t o 7 . 5 m i l l i o n pounds. I n c l u d i n g a c r a n e a t the cop, L'ne Lower w i l l
s t a n d 405 f e e t h i g h , more t h a n twice a s t a l l a s t h e p r e s e n t SATURN C - 1
booster test stand.
57
J u l y 1962
On J u l y 2 1 , NASA H e a d q u a r t e r s announced c o n s t r u c t i o n p l a n s f o r
Complex 3 9 , SATURN C-5 launch f a c i l i t i e s ( F i g . 1 0 2 ) . The 350-foot h i g h
v e h i c l e w i l l be e r e c t e d and checked o u t v e r t i c a l l y i n a s p e c i a l 48-stOry
assembly b u i l d i n g . Following c h e c k o u t , t h e SATURN w i l l be moved t o a 4
58
FIGURE 103. SATURX C - 5 LAUNCH PAD
59
July - August 1962
booster.
60
August 1962
61
August - September 1962
62