ABC PTE LTD

ACTIVITY-BASED RISK ASSESSMENT FORM


Project: ABC PTE LTD Conducted By : Mr.Toh En Rui – Safety Coordinator
(Names, Designations, Date) Mr.Alam- Safety Coordinator
Mr.Raj- Safety Supervisor (01-12-2010)
Process/Location Operation & Maintenance of Welding Machine Approved By : Mr.Ong Kim Kee – Director ( 01-12-2010)
: (BT-RA-01) (Name, Designation, Date)
No. Of Pages : 4 Last Review Date: 02-12-2010 Next Review Date: 01-12-2013

1. Hazard Identification 2. Risk Evaluation 3. Risk Control


1a. 1b. 1c. 1d. 2a. 2b. 2c. 2d. 3a. 3b. 3c. 3d. 3e.
No Activities Hazard Possible Existing Risk S L R Additional Risk Control Residual Risk Index Action Officer,
Accident / Control Measures Designation
Ill Health S L R (Follow-up date)
&
Persons-
at-Risk

1 Operation & Live Electric Appoint Ma O H Measures made for workers to Ma R M Mr.Badal- Safety
maintenanc electrical shock to qualified report the Worn out and Damaged supervisor
Wires and will be immediately
e of Welding cable personnel personnel, replaced./ Proper maintenance (01-05-2011)
Machine provision of
training before
commence the
work, refer
SWP-02
Sharp Cut injury Wear the Mi R L - Mi R L Mr.Badal- Safety
object to working necessary PPE ( supervisor
personnel Hand gloves) (01-05-2011)
refer SWP-02/
SWP-11

Likelihood Remote Occasional Frequent


Severity (R) (O) (F)
Major (Ma) M H H
Moderate (Mo) L M H
Minor (Mi) L L M
H = High Risk, M = Medium Risk, L = Low Risk
(Page 1 of 6)
ABC PTE LTD
ACTIVITY-BASED RISK ASSESSMENT FORM
Project: ABC PTE LTD Conducted By : Mr.Toh En Rui – Safety Coordinator
(Names, Designations, Date) Mr.Alam- Safety Coordinator
Mr.Raj- Safety Supervisor (01-12-2010)
Process/Location Operation & Maintenance of Welding Machine Approved By : Mr.Ong Kim Kee – Director ( 01-12-2010)
: (BT-RA-01) (Name, Designation, Date)
No. Of Pages : 4 Last Review Date: 02-12-2010 Next Review Date: 01-12-2013

1. Hazard Identification 2. Risk Evaluation 3. Risk Control


1a. 1b. 1c. 1d. 2a. 2b. 2c. 2d. 3a. 3b. 3c. 3d. 3e.
No Activities Hazard Possible Existing Risk S L R Additional Risk Control Residual Risk Index Action Officer,
Accident / Control Measures Designation
Ill Health S L R (Follow-up date)
&
Persons-
at-Risk

1 Operation & Fumes Ill health to Provision of the Mi R L - Mi R L Mr.Badal- Safety


maintenanc generati working nose mask , supervisor
e of Welding on personnel refer SWP-02 / (01-05-2011)
Machine SWP 11

Fire Fatal injury Tool box Ma O H Personnel need to train on Ma R M Mr.Badal- Safety
Accident meeting emergency response supervisor
– due to conduct (01-05-2011)
spark regularly &
discussed on
fire
prevention /
Fire
extinguisher
PROVISION

Likelihood Remote Occasional Frequent


Severity (R) (O) (F)
Major (Ma) M H H
Moderate (Mo) L M H
Minor (Mi) L L M
H = High Risk, M = Medium Risk, L = Low Risk
(Page 2 of 6)
ABC PTE LTD
ACTIVITY-BASED RISK ASSESSMENT FORM
Project: ABC PTE LTD Conducted By : Mr.Toh En Rui – Safety Coordinator
(Names, Designations, Date) Mr.Alam- Safety Coordinator
Mr.Raj- Safety Supervisor (01-12-2010)
Process/Location Operation & Maintenance of Welding Machine Approved By : Mr.Ong Kim Kee – Director ( 01-12-2010)
: (BT-RA-01) (Name, Designation, Date)
No. Of Pages : 4 Last Review Date: 02-12-2010 Next Review Date: 01-12-2013

1. Hazard Identification 2. Risk Evaluation 3. Risk Control


1a. 1b. 1c. 1d. 2a. 2b. 2c. 2d. 3a. 3b. 3c. 3d. 3e.
No Activities Hazard Possible Existing Risk S L R Additional Risk Control Residual Risk Index Action Officer,
Accident / Control Measures Designation
Ill Health S L R (Follow-up date)
&
Persons-
at-Risk

1 Operation & Flying Eye injury Wear safety Mo O M Provision of glass / face Mo R L Mr.Badal- Safety
maintenanc Particles to working glass – refer shield / Need to provide supervisor
e of Welding personnel SWP 11 / SWP training on importance of (01-05-2011)
Machine 02 PPE
Skin Wear safety Mi O L - Mi O L Mr.Badal- Safety
Spark &
Burning to glass / safety supervisor
Heat
personnel gloves – refer (01-05-2011)
SWP 11 / SWP
02

Likelihood Remote Occasional Frequent


Severity (R) (O) (F)
Major (Ma) M H H
Moderate (Mo) L M H
Minor (Mi) L L M
H = High Risk, M = Medium Risk, L = Low Risk
(Page 3 of 6)
ABC PTE LTD
ACTIVITY-BASED RISK ASSESSMENT FORM
Project: ABC PTE LTD Conducted By : Mr.Toh En Rui – Safety Coordinator
(Names, Designations, Date) Mr.Alam- Safety Coordinator
Mr.Raj- Safety Supervisor (01-12-2010)
Process/Location Operation & Maintenance of Welding Machine Approved By : Mr.Ong Kim Kee – Director ( 01-12-2010)
: (BT-RA-01) (Name, Designation, Date)
No. Of Pages : 4 Last Review Date: 02-12-2010 Next Review Date: 01-12-2013

1. Hazard Identification 2. Risk Evaluation 3. Risk Control


1a. 1b. 1c. 1d. 2a. 2b. 2c. 2d. 3a. 3b. 3c. 3d. 3e.
No Activities Hazard Possible Existing Risk S L R Additional Risk Control Residual Risk Index Action Officer,
Accident / Control Measures Designation
Ill Health S L R (Follow-up date)
&
Persons-
at-Risk

Continue Fatigue to Work with Mi O L - Mi O L Mr.Badal-


s work the worker group of people Safety supervisor
Provision of
sufficient rest /
shift
management

Likelihood Remote Occasional Frequent


Severity (R) (O) (F)
Major (Ma) M H H
Moderate (Mo) L M H
Minor (Mi) L L M
H = High Risk, M = Medium Risk, L = Low Risk
(Page 4 of 6)
ABC PTE LTD
ACTIVITY-BASED RISK ASSESSMENT FORM
Project: ABC PTE LTD Conducted By : Mr.Toh En Rui – Safety Coordinator
(Names, Designations, Date) Mr.Alam- Safety Coordinator
Mr.Raj- Safety Supervisor (01-12-2010)
Process/Location Operation & Maintenance of Welding Machine Approved By : Mr.Ong Kim Kee – Director ( 01-12-2010)
: (BT-RA-01) (Name, Designation, Date)
No. Of Pages : 4 Last Review Date: 02-12-2010 Next Review Date: 01-12-2013

1. Hazard Identification 2. Risk Evaluation 3. Risk Control


1a. 1b. 1c. 1d. 2a. 2b. 2c. 2d. 3a. 3b. 3c. 3d. 3e.
No Activities Hazard Possible Existing Risk S L R Additional Risk Control Residual Risk Index Action Officer,
Accident / Control Measures Designation
Ill Health S L R (Follow-up date)
&
Persons-
at-Risk

1 Operation & Heat Dehydratio Provision of Mi O L - Mi O L Mr.Badal-


maintenanc Stress n / ill sufficient rest Safety supervisor
e of Welding health to Provision of
Machine worker
water bottle &
wear hand
gloves & body
protector
Generati hearing Worker must Mo O M Regular tool box meeting Mo R L Mr.Badal- Safety
on of discomfort wear the ear & discussed on importance supervisor
Noise plug SWP 04/11 of Hear Protection (01/05/2011)
/ Personal
protective
equipment
provided

Likelihood Remote Occasional Frequent


Severity (R) (O) (F)
Major (Ma) M H H
Moderate (Mo) L M H
Minor (Mi) L L M
H = High Risk, M = Medium Risk, L = Low Risk
(Page 5 of 6)
ABC PTE LTD
ACTIVITY-BASED RISK ASSESSMENT FORM
Project: ABC PTE LTD Conducted By : Mr.Toh En Rui – Safety Coordinator
(Names, Designations, Date) Mr.Alam- Safety Coordinator
Mr.Raj- Safety Supervisor (01-12-2010)
Process/Location Operation & Maintenance of Welding Machine Approved By : Mr.Ong Kim Kee – Director ( 01-12-2010)
: (BT-RA-01) (Name, Designation, Date)
No. Of Pages : 4 Last Review Date: 02-12-2010 Next Review Date: 01-12-2013

1. Hazard Identification 2. Risk Evaluation 3. Risk Control


1a. 1b. 1c. 1d. 2a. 2b. 2c. 2d. 3a. 3b. 3c. 3d. 3e.
No Activities Hazard Possible Existing Risk S L R Additional Risk Control Residual Risk Index Action Officer,
Accident / Control Measures Designation
Ill Health S L R (Follow-up date)
&
Persons-
at-Risk

Likelihood Remote Occasional Frequent


Severity (R) (O) (F)
Major (Ma) M H H
Moderate (Mo) L M H
Minor (Mi) L L M
H = High Risk, M = Medium Risk, L = Low Risk
(Page 6 of 6)