Professional Documents
Culture Documents
Abstract—The procedure to fully coordinate the relays and 1. More efficient and economic means of performing
test their performance, in an interconnected power system, is routine engineering calculations required in the
not an easy task for the electrical engineer, if not impossible at planning, design and operation of an electrical
all. This is further complicated if all contingencies are to be power system.
considered. This publication describes a computer program
2. A better utilisation of engineering talent, i.e. the
which has been developed to calculate overcurrent relay
settings, modify them automatically for the proper time engineer has been released from tedious an
coordination of the relays, on an interconnected and large repetitive calculations, and therefore, allowing him
system. This program eliminates the need for searching pre- to concentrate on more creative work.
calculated system fault data; in fact it selects and calculates the 3. More effective engineering studies has been made
necessary fault current when and where it is needed. possible to be performed, i.e. different calculation
procedures have been made applied to obtain a
Index Terms—Overcurrent protection, Protection systems, number of alternative solutions for a particular
Electrical Engineering, Fault, Relays. problem and therefore, providing a wider base for
engineering decision.
I. INTRODUCTION 4. Many tedious and time-consuming tasks has been
lifted from the relay engineer, such as:
I N recent years, major transformations have been
introduced into the structure of electrical power utilities to
improve efficiency in the operation of the power system
a. Review the system under current
conditions for proper coordination of the
networks by deregulating the industries and opening it to relays.
their private competitors. b. Determination of relay coordination
The net effect of such adjustments will mean that the requirements for possible permanent
generation, transmission and distribution systems must now changes in the network.
adapt to a new set of rules dictated by open markets. In c. Review of relay operation as part of post-
particular for the transmission sector of power utilities, this fault analysis.
adaptation may require the construction or modification of To sum up, the development of computer technology
inter-connections between regions and countries. (i.e. the declining cost and development of efficient
Furthermore, the adaptation to new generation patterns will computational techniques) relieved the power system
also necessitate changes and require increased flexibility and engineer from the tedious- and time consuming tasks that
availability of the transmission system, as well as improved have to be performed frequently [7].
reliability. The following sections will be devoted to the theoretical
The size and the complexity of modern power review of overcurrent protection and relays, the description
transmission and distribution systems, as well as the recent of the overcurrent relay setting, coordination and logic of
advances in digital computing, and protection relays assessment of the performance of the predicted settings.
technologies have made the manual calculation of relay Then, identification of the data required follows. Finally, the
settings impractical [1, 2, 3, 4]. Although the setting of one results obtained from a test system are presented.
relay at a time can be made, the coordination required for
overcurrent protection relays dictates that a system approach II. RELAYS COORDINATION APPROACH
must be used. Despite the increase of the size and When radial systems are involved, the procedure for
complexity of power systems, the development of digital grading the relays is very simple and so it is for simple ring
computer technology has provided many advantages [5, 6]: systems using directional overcurrent relays. In the case of
interconnected power systems, the procedure to fully
coordinate the protection and to consider all contingencies is
not an easy task [8]. The analytical method is based on the
work of J. P. Whiting and D. Lidgate [9].
1
Faculty of Engineering, Sohar University, Oman, P.O. Box 44, PC 311,
Sohar, Sultanate of Oman, Tel: +968 9722805, Fax: +968 267280102,
E-mail: a.tami@soharuni.edu.om
AB Compute AR settings
AR
F2
next
LB
LR All adjacent subs
considered?
N
Y
FB
FR Compute RR settings
F1
next
time [s]
1 3 600 125 0.92
4
2 0 600 200 0.40
2 3 600 125 0.88 3
2 5 600 75 0.99 2
3 1 600 50 0.85 1
3 2 600 50 0.66 0
3 4 600 50 0.63
3 6 400 125 0.33 13 25 23 32
4 3 600 50 0.14 Feeder
4 5 400 50 0.20
4 7 400 125 0.32
5 2 600 50 0.24 Fig. 5 – Fault at busbar 3 on feeder 2-3
5 4 600 50 0.54
5 8 400 75 0.40 Again, Figure 5 illustrates the operating times of the
6 3 400 125 0.33 relays when a fault is initiated at busbar 3 on feeder 2-3.
6 10 600 125 0.40 Clearly the fault is isolated by tripping the relay at bus 3
7 4 400 125 0.32 then the relay at bus 2.
7 10 600 125 0.40
VI. CONCLUSION
8 5 400 75 0.40
8 10 600 125 0.40 The idea behind this work was to transfer the tedious and
time-consuming relay setting protection and time
Table 3: Line protection data
coordination checks from the relay engineer to the
Once the settings have been determined, they can be computer. It is believed that this has been achieved through
used to check the performance of these relays when a fault the development of a program that predicts the overcurrent
occurs on the system. The following graphs show the relay settings along with another one that checks the
operating time of the relays with a fault at different performance of the predicted settings.
locations. The programs described provide a basic framework of an
automatic directional overcurrent relay setting logic.
Although these programs have been developed for a
Fault at busbar 1 on feeder 1‐3 particular system, which has resulted in specific features, it
is believed to be general. It is the addition of the assessment
10 program, however, which enables the relay performance of
9 the system to be checked thoroughly under all operating
8 conditions.
7 It is obvious, that the digital computer has proven its
6 value in the electric power industry. For some time it was
time [s]
Figure 4 shows the discrimination time of the relays [3] IEEE Committee Report, “Application of Protective
when a fault occurs at busbar 1 on feeder 1-3. Relays and Devices to Distribution Circuits”, IEEE Western
It is very clear from Figure 4 that when a fault occurs at Appliance Technical Conference, Los Angeles, California,
busbar 1 on feeder 1-3, the relay at bus 1 trips first, then May 1964.
relay at bus 3 trips next, and consequently clearing the fault.
[4] IEEE Committee Report, “Computer representation of
Overcurrent Relay Characteristics”, IEEE Trans. On Power
Delivery, Vol.4, No.3, pp. 1656 – 1667, July 1989.
© SQU-2009 ISSN: 1813-419X 303
INTERNATIONAL CONFERENCE ON COMMUNICATION, COMPUTER AND POWER (ICCCP'09) MUSCAT, FEBRUARY 15-18, 2009