Professional Documents
Culture Documents
Prepared for
Ministry of Transport
Prepared by
University of Moratuwa
October 2009
TABLE OF CONTENT
1 INTRODUCTION ................................................................................................................. 1
2.4.3 Existing Habitats / Vegetations and Flora of the Project Area ..................... 22
INTRODUCTION Page 3
LIST OF TABLES
Table 1-1: Divisional Secretariat Divisions in the Project Area of Trace-A ...................... 4
Table 1-3: Divisional Secretariat Divisions in the Project Area of Trace-B ...................... 5
Table 1-5: Divisional Secretariat Divisions in the Project Area of Trace-C ...................... 6
Table 2-2: Noise sensitive areas: 500 m buffer on either side of proposed alternatives .. 15
Table 2-3: Key references used for identification, nomenclature and taxonomic status of
species ................................................................................................................................ 22
Table 2-5: Summary of the flora species recorded during the field visit ........................... 25
Table 2-6: Summary of the faunal species recorded during the field visit ........................ 26
Table 2-7: The details of the Social Impact Assessment (SIA) ............................................ 28
Table 2-8: The methods intend to employ for information generation of SIA .................. 28
Table 2-9: Likelihood negative impacts along Trace A Panadura – Horana ....................... 29
Table 2-10: Likelihood negative impacts along Trace B: Ratmalana - Horana ................... 30
Table 2-11: Likelihood negative impacts along Trace C: Kottawa - Horana ....................... 32
Ministry of Transport, New Rail Road Development Project has requested the services of
the Transportation Engineering Division of the Department of Civil Engineering,
University of Moratuwa to undertake an Economic Feasibility study and Environmental
Impact Assessment for possible rail line connection to Horana. Discussion for this study
was initiated in July 2007 and the study team was mobilized in April 2008 after signing
the agreements. However, Terms of Reference for the EIA was received in July 2008.
Main objective of this project is to provide a railway link to Horana such that Horana &
surrounding area will have better access to Colombo and other parts of the country.
Systematic development of the railway network in Sri Lanka and help minimizing road
based transport demand in the project area are considered as secondary objectives.
As set out in the terms of reference (TOR) issued by the Central Environment Authority
(CEA), this study will assume a single track line designed for operating speed of 100 to
120 kilometers per hour. Design life is to be taken as 100 years for all structures.
Reservation will take into account future widening to double track and the shunting
facilities, station expansion where considered appropriate. Rail/road crossing control will
be grade separated except for selected locations where at grade signal controlled gates
with provision for grade separation in the future if necessary.
The aim of the economic feasibility is to determine the economic feasibility of the
project, by comparing the estimated benefits to the costs of different options of
implementation expressed in terms of economic benefit-cost indicators. The following
steps are to be followed in carrying out the study:
Select the most preferred alternative based on the findings from the economic,
social and environmental studies.
INTRODUCTION Page 1
To estimate the potential traffic demand for the proposed railway operation
under existing conditions.
To estimate the overall economic benefits for each of the above scenarios.
The aim of the Environmental Impact Assessment (EIA) is to investigate environmental
and social implications associated with the proposed railway extension especially in
selecting the most suitable alternative for the said proposal. Suitable mitigatory
measures are to be proposed along with a monitoring mechanism to minimize any
adverse impacts and to enhance any positive impacts. EIA study will be carried out in
accordance with the Terms of Reference given by the Central Environmental Authority.
Based on the information given by the Ministry of Transport, New Rail Road
Development Project (MOT/NRDP) a study area was defined to cover all possible
alternatives. Relevant land use maps, 1:50,000 topo sheets and in addition, some digital
maps of the area to scale 1:10,000, 1:2,000 and some satellite images were collected.
Tentative traces were identifies on 1:50,000 maps such a way that they avoid populated
areas. These preliminary alternate traces will be fine tuned after field visits to avoid any
environmentally sensitive areas. The sensitivity of a particular geographical location
could be defined in numerous ways. However, the Gazette Notification dated 24 th June
1993 on the declaration of environmentally sensitive areas based on the National
Environmental Act No 47 of 1980 will be based for the entire study in order to avoid such
lands as practical as possible. After fine-tuned the preliminary alternative traces for the
railway extension with due considerations to environmental sensitivity, different
technical, social, economical & environmental elements and compartments were studied
in detail.
Each team member of the study team has given terms of reference for specific studies in
their areas of specialties. Individual consultants carried out their investigations after a
group field visit. Based on the individual investigations impacts related to environment
were identified and evaluated. After a scoping exercise a simple matrix will was
developed to identify the types of impacts on specific environmental parameters that
might occur from individual project activities. This matrix was used to compare the
alternatives with respect environment considerations.
Simultaneously, based on the ground profiles identified based on the survey map,
approximate cost for each alternative was prepared. Earth work cost, cost of rail track,
signals, bridges and other drainage structures, land acquisition cost, cost of overpasses
INTRODUCTION Page 2
and underpasses, cost of road crossings have been taken into account in the estimation
of approximate project cost. In addition cost of necessary improvements to the existing
KV line from Makumbura (Kottawa) to Fort is also taken in to account.
Discussions were then held among members of the economic and environmental study
groups to determine the preferred alternative based on economic and environmental
aspects.
The project area falls within Colombo & Kalutara districts in the Western Province. Based
on the client’s requirements and taking into account the objectives considered three
alternate traces were selected for the study (Annexure A; Map 1). Description of the
three identified traces, Trace-A – Panadura to Horana, Trace-B – Ratmalana to Horana,
Trace-C – Makumbura to Horana are as follows:
This trace connects Horana to Coastal railway line at Pinwatta, South of Panadura via
Bandaragama. Approximate length of the trace up to Coastal railway line is 17.4 km
(Annexure A; Map 2). The total length from Horana to Colombo Fort through this trace
will be approximately 47 km.
Trace-A goes through following three Divisional Secretariat Divisions (DSD) shows in
INTRODUCTION Page 3
Table 1-1. A statistical synopsis of the three Divisional Secretariat Divisions demography
through which the Trace-A passes is given in the
INTRODUCTION Page 4
Table 1-1 below:
INTRODUCTION Page 5
Table 1-1: Divisional Secretariat Divisions in the Project Area of Trace-A
Total Population
Project area DS Land Area
District Number of Population Density
Divisions (km2)
GN Divisions (persons/ km2)
Panadura 74 46.42 162,979 3,511
Kalutara Bandaragama 102 137.02 86,409 631
Horana 83 204.13 90,526 443
Total/Average 259 387.57 339,914 877
All Grama Niladhari Divisions (GN Divisions) fully or partly falls within the 1 km (500 m
either side) wide corridor is considered as the project impact area and it approximately
covers 18 km2. There are altogether 46 GN Divisions in the project impact area. The
estimated population living in these GN Divisions is about 73,380.
Approximate land use distribution along the area of impact (500 m wide corridor) shows
that traces mainly traverse through Home gardens and Paddy areas. Percentage
distribution of land use is given in the Table 1-2.
Table 1-2: Percentage distribution of Land Use along Trace-A
INTRODUCTION Page 6
1.3.2 Trace-B – Ratmalana to Horana
This trace connects Horana to Coastal railway line at Ratmalana via Kesbewa.
Approximate length of the trace up to Coastal railway line is 27 km (Annexure A; Map 3).
The total length from Horana to Colombo Fort through this trace will be approximately
38 km.
Trace-B goes through following five Divisional Secretariat Divisions (DSD) shows in Table
1-3. A statistical synopsis of the five Divisional Secretariat Divisions demography through
which the Trace-B passes is given in the Table 1-3 below:
Total Population
Project area Number of Land Area Density
District Population
DS Divisions GN (km2) (persons/
Divisions km2)
Dehiwala –
13 13.00 209,787 16,137
Mt. Lavinia
All Grama Niladhari Divisions (GN Divisions) fully or partly falls within the 1 km (500 m
either side) wide corridor is considered as the project impact area and it approximately
covers 27 km2. There are altogether 62 GN Divisions in the project impact area. The
estimated population living in these GN Divisions is about 192,940.
Preliminary investigations reveal that the proposed rail corridor predominantly pass
through Home gardens and Paddy lands (approximately 80%) and then through Coconut
and Rubber.
INTRODUCTION Page 7
Table 1-4 gives the percentage share of land use along the tentative corridor.
INTRODUCTION Page 8
Table 1-4: Percentage distribution of Land Use along Trace-B
This trace connects Horana to Kelani Velly railway line at Makumbura (Kottawa) via
Diyagama. Approximate length of the trace up to Coastal railway line is 18 km (Annexure
A; Map 4). The total length from Horana to Colombo Fort through this trace will be
approximately 35 km.
Trace-C goes through following three Divisional Secretariat Divisions (DSD) shows in Table
1-5. A statistical synopsis of the three Divisional Secretariat Divisions demography
through which the Trace-C passes is given in the Table 1-5 below:
Table 1-5: Divisional Secretariat Divisions in the Project Area of Trace-C
Population
Number of
Project area DS Land Area Density
District GN Population
Divisions (km2) (persons/
Divisions
km2)
Maharagama 41 37.00 180,112 4,868
Colombo
Homagama 81 119.00 183,782 1,544
Kalutara Horana 83 204.13 90,526 443
INTRODUCTION Page 9
Total/Average 205 360.13 454,420 1,261
All Grama Niladhari Divisions (GN Divisions) fully or partly falls within the 1 km (500 m
either side) wide corridor is considered as the project impact area and it approximately
covers 18.2 km2. There are altogether 39 GN Divisions in the project impact area. The
estimated population living in these GN Divisions is about 74,240.
Approximate land use distribution along the Trace C of impact (500 m wide corridor)
shows that traces mainly traverse through Home gardens and Paddy areas. Percentage
distribution of land use is given in the Table 1-6.
Table 1-6: Percentage distribution of Land Use along Trace-C
The following information and documents have been identified as relevant for this study
and some of them have been already collected and reviewed. The Engineers who will be
assigned to this project by the Ministry would be requested to assist in collecting some of
the balance documents:
Feasibility Study for the Matara Kataragama Railway Extension, Korean Consultants
International, 1991.
Environment Impact Assessment for the Matara Kataragama Railway Extension, Dept.
of Civil Engineering, University of Moratuwa, 2008.
Any study or project report relating to planned Coastal railway line improvements.
INTRODUCTION Page 10
Traffic counts made by the RDA on A2 - Galle Road up to Kalutara, A8 -Panadura-
Horana Road, and on any other A and B class roads and bridges thereon in Colombo
and Kalutara Districts.
Information on Road safety on A2, A8 and B84 and on any other A and B class roads
in Colombo and Kalutara District.
Feasibility studies for the proposed Horana Export Processing Zone, International
Stadium at Diyagama.
All reports, designs, cost estimates pertaining to the STDP (Southern Expressway) and
any other road projects carried out in project area.
Development studies and plans for the districts of Colombo and Kalutara that are
available with other agencies such as the Ministry of Industrial Development, Board
of Investment, Urban Development Authority, Tourist Board etc.
INTRODUCTION Page 11
2 ENVIRONMENTAL IMPACT ASSESSEMENT
The EIA study team comprises of an EIA specialist, Environmental Engineer, Socio-
Economist, Ecologist, Hydrologist, Geologist, Infrastructure Design Engineer, Air, Water
and Noise Quality Specialists, Transport Planner, Urban Planner and Traffic Engineer.
The intention of the Environmental and Social Impact Assessment study is to identify the
primary environmental and social issues associated with the proposed traces for
connection to Horana in collaboration of technical and economic studies and identify the
most preferred alternative. Three alternatives are already identified as reasonable
alternatives and studies were conducted for all three alternatives and compared with the
no project scenario.
Project overview, background information on the project and trace details have been
obtained from relevant authorities. Relevant land use maps have also been obtained.
A scoping exercise was conducted to identify the main environmental and social issues
that may be of concern. All the alternatives were visited by the entire team with officials
of the MOT/NRDP. In this exercise a simple matrix was used to identify the types of
impacts on specific environmental parameters that might occur from individual project
activities. After the scoping exercise each team member conducted specific studies on
the areas of impacts identified.
The selection of the preferred alternative was done based on a quantified and graded
matrix. For this environmental parameters were given an importance value based on
multi criteria ranking technique. The importance is based on the significance to the
environment due to an effect on the particular environment parameter. The importance
values were assigned on local, regional and global context. Information for this exercise
was gathered from the field visits, interviews with locals and experts. Finalization of
significance values was done by the entire team.
Based on the individual investigations the team prioritized the alternatives with regard
the overall environmental and social impacts each would have. Each expert assigned a
value to represent the magnitude of impacts each project activity would have on the
respective environmental parameters on a scale of 1-3. Multiplication of the magnitude
of the impact a project activity has on a particular parameter by the significance of an
impact on that parameter gives a representative value of the impact an activity would
have on an environmental parameter. A value to represent the overall impact of an
alternative of the project was obtained by totaling the impact values. This exercise was
conducted for each of the alternatives and the completed matrices and the calculations
are given in Annexure B.
The proposed project is located within the Western Province of Sri Lanka and the traces
run through mainly flat terrain with isolated hillocks. During the study following
geotechnical concerns will be considered:
1. Assessing the existing environment pertaining to the geology and soil with the main
focus on:
i. Geology of the area within the corridor;
ii. Geological formations and the subsurface soil characterization; and
iii. Mineral resources found within the trace and the present utilization of such
resources.
2. Identification of the critical areas along the traces related to the following
geotechnical/geological problems:
i. Embankment construction on soft grounds and tunnel construction through
elevated terrain;
ii. Soil erosion during and after construction;
iii. Change in the land form due to the construction activities within and outside
the project corridor due to borrowing of construction material;
iv. Stability of slopes and earth retaining structures; and
v. Disposal of the construction waste.
The identification of the critical areas along the traces and investigation of the impacts of
the construction of the rail track at the critical locations to be carried out using data
obtained from the following sources:
i. Maps and desk study considering topological maps, geological maps, land use
maps to identify probable geotechnical problematic areas for embankment
construction, soil erosion, tunnels and other structures, and slope stability;
ii. Data from other sources such as: ADB and JBIC sections of the Southern
Expressway project, Colombo – Kandy Expressway project, Outer Circular
Highway (OCH), other data available with RDA, Irrigation Department, GSMB;
The land area that falls in the proposed traces studied with the available 1:50,000 scale
topographic maps and other maps that are available with the Survey Department.
Alternative traces which have been identified studied in detail, with a clear demarcation
of the watersheds that are draining across the proposed center lines. Available contours,
land use/cover maps, will be used to prepare the drainage direction maps. All proposed
traces intercept surface water which is naturally draining in to the Bolgoda Lake. The
general nature of topography indicates that the interception of Bolgoda catchment and
its flood plain may tend to create constraints to surface water movement. These were
verified through field work.
Traces are crossing three branches of a major drain with the same common name which
is the Maha Oya. All watersheds crossing the traces will be studied for drainage and
hydrological concerns. The study will identify the flood detention or retention area that
would be affected due to the rail track. Preliminary investigations indicate the presence
of paddy fields along, upstream and down stream of the traces. Irrigation waterways
along with associated infrastructure will be studied to identify the impacts due to each of
the traces through field visits and desk analysis. Paddy area and other area affected
would be also studied for the comparison of the traces. Field visits will be carried out to
identify the flooding area and the other concerns related to hydrology. Physical
infrastructure such as irrigation and flood control structures in the proposed trace area
will be identified and studied for effects due to the proposed infrastructure.
Once the reconnaissance survey is done, sensitive areas to the air pollution will be
identified. Available maps are also made use in order to identify the sensitive areas that
fall within 1 km wide corridor of all three proposed alternatives. Based on the number of
trains planned in each of the alternative, likely air pollutant emissions will be estimated.
The alternative that brings about the minimum air pollutants will be selected as the best
alternative in terms of air pollution. Mitigation measures will then be proposed so as to
minimize the likely air pollution caused by the movement of trains.
Particulate Matter
Land clearing during the pre-construction phase could emanate particulate matter once
the vegetative material is dried. It is usual that setting fire to vegetative piles after
uprooting be done and it may cause emission of particulate matter into atmosphere. This
phenomenon is common for all three alternatives hence there is no different bearing on
each alternative.
Demolition of existing building with a view to clearing site could also cause particulate
material to be air borne unless proper mitigations are taken. However this activity is also
found to be not significant and but common to all three alternatives.
Blasting and drilling may be inevitable once the proposed trace runs through rock
outcrops. Proper measures must be taken in order to reduce the particulate matters
being emitted into the atmosphere. Once controlled properly, this activity may not be
common and impacts are not significant.
During post construction phase, operation of locomotives particularly diesel engines may
emanate particulate matters into the atmosphere. The distances to be traveled for all
three alternatives seem to be not much different from each other. In addition Table 2-1
Expected Traffic
Trace - A 5 5 10 1 1 2
Trace - B 5 5 10 1 1 2
Trace - C 5 5 10 1 1 2
Gaseous Emissions
During construction phase tunneling might create unhealthy situation where gaseous
emissions could result in. The risk of such emissions is very remote provided that proper
measures are taken. However, there are no marked differences in terms of adverse
impacts among alternatives.
During post construction phase, operation of locomotives may emit different gases such
as Carbon Monoxide (CO), Carbon Dioxide (CO2) Nitrogen Oxides (NOx) and Sulfur Dioxide
(SO2) etc. However the distances over which locomotives are designed to travel for three
alternatives and the number of trips per day are not significantly different hence the
impacts are more or less the same from all three alternatives.
Reconnaissance survey is done first in order to get familiarized with the key features and
the existing land use in the proposed corridors of the three alternatives. 100 m width of
the corridor will be subject to detail analysis as the other areas beyond the 100 m width
are insignificant in terms of noise levels. All the sensitive areas such as hospitals, places
of worship, places of education, court houses etc. that are found within the 100 m
corridor will then be marked using the 1: 10,000 or 1: 2000 maps for all three
Transportation of construction material may emanate high noise particularly in local road
network, which is once again common for all three alternatives. The same is even true for
traffic diversion. The traffic diversion may create local congestion, which could in turn
create insignificant noise pollution.
Deep foundation and tunneling could also be regarded as noise activities, which need
proper measures in order to minimize the adverse impacts. However, such impacts, if
occur may be the same for all three alternatives.
It is clear from the Table 2-2 that the alternatives 1 and 2 have 32 and 40 sensitive areas
respectively, and alternative 3 has only 19 such areas. Building barriers to curtail
excessive noise levels being transmitted into sensitive areas such as places or worship,
places of educations, hospitals and court houses etc. are very costly exercise. In Sri Lanka
there are no either standards or any forms of legislation in order to find the maximum
permissible noise levels pertaining to generated by trains. However it is accepted fact in
the other countries that the noise levels perceived within noise sensitive areas be less as
practically as possible.
It is therefore clear that the alternative 3 (i.e. the one goes from Kottawa to Horana) has
the less impacts compared to those of other three alternatives.
The development of service stations may also create excessive noise which could be
combated with mitigation measures easily. However the likely impacts are more or less
the same from three alternatives.
Blasting and drilling and deep foundation and piling may cause excessive vibration levels
resulting in either inconvenience to the neighbors or structural damage or even both.
Hence proper mitigation measures are required to minimize likely adverse impacts.
However, the impacts are more or less the same for all alternatives.
Operation of locomotives may cause enhanced vibration around the rail tracks but the
maintenance of a buffer will make it less predominant in the neighboring areas. This
activity is also same for all three alternatives.
As the changes in the land form is insignificant, no adverse impacts are likely to alter the
micro climate.
Odor
Diesel engines may create pungent odors when a train passes in a given area but it seems
to be sporadic and gets diluted very soon. Hence no adverse impacts are likely.
Trace C (i.e. One from Kottawa to Horana) is preferred to in terms of control of noise
levels particularly in sensitive areas such as places of worship, places of educations,
hospitals and court houses etc. followed by Trace B and Trace A respectively.
The study area would confine to a 500 m corridor either side of the proposed railway
line. We would enumerate flora and fauna using 100 m line transects in different habitats
found along the proposed trace. The proposed road trace that marked on a 1:50,000 or
1:10,000 land use maps will be referred to identify different locations and habitats types.
The fauna and flora found in each habitat type vary with the climatic zone, geology of the
area, soil types, and the microclimate of the specific site.
Since there are no previous records of habitats, fauna and flora for the project area and
this area will be directly impacted by the project a great deal of emphasis will be placed
on sampling the area demarcated for the proposed railway line. The fauna and flora
found in the surrounding area will also be noted if the habitat type extends beyond 500
m boundary.
Plant species found in all habitats of the project area will be recorded by walking along
the transects. Once the species identified in the field their botanical names, local names
and life forms will be entered in the field note book. In forest habitats (if any) the species
found in different strata (canopy, sub canopy under storey etc.) will also be recorded.
Herbarium specimens are prepared for the plant species that could not be identified in
the field and these will be identified by using published descriptions and taxonomic keys
provided by Dassanayake and Fosberg (Vol. I- VII, 1980 – 1991), Dassanayake, Fosberg
and Clayton (Vol. VIII-IX, 1994 - 1995), and Dassanayake and Clayton (Vol. X- XIV, 1996 -
2000). The taxonomic status of the species present could be determined according to
these publications. The conservation status of the species is determined according to
The proposed project area, for the alternative traces for railway connection to Horana, is
situated in the southwest wet zone of the country, in Colombo and Kalutara districts of
the Western Province. This area belongs to the floristic region five, ‘Northern wet
lowlands’ and the characteristic natural vegetation type is tropical wet evergreen or
lowland rain forests. However, natural climax vegetation formations such as rain forests
are not found in the project area due to the urbanization. For example, the highest
proportion of the urban population is centered in the Western Province and over 3213
and 1265 persons per km2 recorded from Colombo and Kalutara districts, respectively.
The mean annual rainfall is between 3000 and 3500 mm and the mean annual
temperature varies from 26.5 to 28.5 0C.
Based on the ecological parameters such as rainfall, vegetation, soils and present land
use, Sri Lanka can be divided into three major ago-ecological zones: Wet, Intermediate
and Dry zones. The sub division of the three major climatic zones into regions is based on
the amount and distribution of rainfall, elevation and soils which is the dominant
influence. The wet zone demarcates the area, which receives moderately high mean
annual rainfall of over 2500 mm with no rain shadow effect during monsoons and
comprises the southwest part of the island. The proposed project area belongs to the
Agro Ecological Region WL1b, WL2a and WL3 (Wet Lowlands), having >2500 mm average
annual rainfall, below 300 m elevation, 27.5 oC average annual temperature, and Red-
Yellow Podzolic and Low Humic Gley soils.
A reconnaissance survey was carried out to identify major habitats / vegetations in and
around the proposed project area. Rapid survey was carried out in order to prepare a
species inventory, to identify possible ecological impacts and to identify existing
environmental problems / issues within the proposed project area and out side of the
project area. This survey included field assessment using line-transect method going
through identified habitats / ecosystems and literature review of recent related
published material. A floristic survey of the higher plants was carried out to record the
plant species found in different habitats/ ecosystems. All groups of vertebrates such as
Birds, Reptiles, Amphibians, Fish and Mammals and one invertebrate group namely
Butterflies were the main groups of fauna focused in this survey.
Flora Sampling
General surveys were carried out in order to document the flora in the area. Direct
recording methodology was used to determine the diversity of flora. Lists of plants were
prepared with reference to different habitats / ecosystems of the study area. In addition,
threats and human disturbances associated with the habitats were also noted.
Fauna Sampling
Sampling of fauna was done in parallel to the floral transects. Visual Encounter Survey
(VES) methods were used to record faunal species. Both direct and indirect observations
(calls¸ foot marks, pellets, tracks) were made.
The observed floral and faunal species were identified by using published descriptions
and taxonomic keys provided by Dassanayake and Fosberg (1980 - 1991), Dassanayake et
al. (1994 - 1995), Dassanayake and Clayton (1996 - 1999), D’Abrera (1998), Harrison
(1999), Phillips (1935), Kotagama (2005), Goonatilake (2007), Manamendra-Arachchi and
The conservation status of the species was recorded according to The 2007 Red List of
Threatened Fauna and Flora of Sri Lanka (IUCN SL and the ME&NR, 2007).
Table 2-3: Key references used for identification, nomenclature and taxonomic status
of species
Group Source
Ten main natural and man made habitats were identified in and around the project area
during the study. Paddy land (PL), Abandoned paddy lands (AP), Coconut lands (CL),
Rubber plantations (RP), Road Side vegetation (RD) and Home gardens (HG) are
identified as man made habitats and Marshlands (ML), Rivers (RV), Streams (ST),
Secondary forest (SF) are the main natural habitats in and around the project area. (Table
2-4).
Proposed Habitats
Trace RD PL AP CL RP HG ML RV ST SF
Trace A X X X X X X X X X
Trace B X X X X X X
Trace C X X X X X X X
Road Side vegetation (RD), Paddy land (PL), Abandoned paddy lands (AP), Coconut lands
(CL), Rubber plantations (RP), Home gardens (HG), Marshlands (ML), Rivers (RV), Streams
(ST), Secondary forest (SF)
The common plant and animal species recorded from different habitats during the
reconnaissance visits are given below.
Ludwigia sp., Colocasia esculenta (Gahala), Cyperus spp., Eleocharis spp., Marsilia
quadrifolia, Monochoria vaginalis (Jabara), Hygrophila ringens, Limnocharis flava,
Panicum repens, Rhynchospora corymbosa
Rubber Plantations
Marshlands
Annona glabra (Wel Atha), Phragmites karaka, Pandanus kaida (Wetake), Barringtonia
racemosa (Diya Midella), Cerbera odollam (Gon Kaduru), Ludwigia sp., Ludwigia
peruviana, Nymphaea pubescens (Olu), Colocasia esculenta (Gahala), Lagenandra ovata
(Ketala), Ipomoea aquatica (Kankun), Typha angustifolia (Hambu Pan), Cyclosorus
interruptus, Polygonum glabrum, Ceratopteris thalictroides, Flagellaria indica (Goyi Wel),
Schoenoplectus grossus, Rhynchospora corymbosa, Fimbristylis spp., Eleocharis spp.,
Cyperus spp., Hydrocera triflora,
Rivers
Annona glabra (Wel Atha), Phragmites karaka, Pandanus kaida (Wetake), Ardisia elliptica
(Balu Dan), Barringtonia racemosa (Diya Midella), Cerbera odollam (Gon Kaduru)
Streams
Colocasia esculenta (Gahala), Lagenandra sp. (Ketala), Blyxa auberti, Marsilia quadrifolia,
Eichhornia crassipes (Japan Jabara), Monochoria vaginalis (Jabara), Salvinia molesta,
Ludwigia sp., Ludwigia peruviana,
Secondary Forest
Alstonia macrophylla (Hawari Nuga), Pagiantha dichotoma (Divi Kaduru), Dillenia retusa
(Goda Para), Macaranga peltata (Kenda), Mallotus tetracoccus (Bu Kenda), Symplocos
cochinchinensis (Bombu), Clerodendrum infortunatum (Pinna), Mussaenda frondosa
(Mussanda), Dillenia suffruticosa (Diya Pra), Artocarpus nobillis (Wal Del), Gomphia
serrata (Bo Kera), Trema orientalis (Gadumba), Euodia lunu-ankenda (Lunu Ankenda),
Acronychia pedunculata (Ankenda), Ziziphus rugosa (Maha Eraminiya), Ziziphus oenoplia
(Heen Eraminiya), Toddalia asiatica (Kudimiris), Carallia brachiata (Dawata)
Home Gardens
Mangifera indica (Amba), Alstonia macrophylla (Hawari Nuga), Areca catechu (Puwak),
Cocos nucifera (Pol), Artocarpus hetarophyllus (Kos), Artocarpus incisus (Rata Del),
Anacardium occidentale (Caju), Terminalia catappa (Kottan), Swietenia macrophylla
(Mahogani), Syzygium malaccense (Jambu), Psidium guajava (Pera), Nephelium
lappaceum (Rambutan), Musa x paradisiaca (Kesel)
A total number of 164 plant species with 5 endemic and 2 nationally threatened species
recorded from the study area during the field visit. (Table 2-5)
Table 2-5: Summary of the flora species recorded during the field visit
VU-Vulnerable, EN - Endangered
Table 2-6: Summary of the faunal species recorded during the field visit
Butterflies 17 0 0 0
Reptiles 3 0 0 0
Mammals 2 0 0 0
Fishes 5 0 0 0
Amphibians 3 0 0 0
Garcinia quaesita (Goraka), Litsea longifolia (Rat Keliya), Artocarpus nobillis (Wal Del),
Syzygium operculatum (Batadamba) and Lagenandra sp. (Ketala) are endemic plant
species inhabit in proposed project area. Lagenandra ovata (Ketala) and Calamus rotang
(Heen Wewel) are nationally endangered and vulnerable in conservation status.
Summary of Findings
The reconnaissance survey revealed that there would be more ecological impacts of the
Trace A, Pinwatte to Horana compared to other two traces B & C; Ratmalana to Horana
and Kottawa to Horana. Trace A traverse through marsh areas along Bolgoda river and
the lake while other two traces intersect more built up areas, paddy fields and home
gardens. Therefore, considering the impacts on semi-natural habitats in the project area
such as marshes, abandoned paddy fields etc. Traces B and C would be more appropriate
for detailed studies on impacts due to the propose project activities.
The main objective is to analyze the socio-economic feasibility of the railroad proposed
to connect Horana to other feasible destination/s. The analysis of the socio-economic
component will generate supplementary inputs for overall analysis (Multi-criteria-MCA)
of the feasibility study including social impact assessment of the EIA.
Stepwise approach will be followed in data collection, data analysis and report writing.
The steps intend to follow and the analyses attempts at each step are described below:
Step – 1- Contribution for selecting suitable trace for intensive study
The sociologist and his team will work in close integration with other consultants of the
study team in the selection process of a suitable trace. The socio-economic parameters
(indicators) will be used to assess the suitability of a trace for intensive feasibility study.
The parameters those will be used for screening process include:
Social Impact Assessment (SIA) will provide study based empirical information to
evaluate the likelihood social impacts of the proposed rail road to be connected to
Horana. The same information will be used to assess the socio-economic feasibility of the
project. The activities involved in the SIA are described below:
The analyses of the SIA will be based on separated sections of the road trace (The road
trace will be separated into sections for creating units for specific assessments). Three
hierarchical levels of geographical units will be used for data collections and analysis of
Immediate vicinity of the 500 meter corridor of land will be All relevant data on the
project studied as required for the EIA. This socio-economic environment
corridor will include about 20M land that are required for
belt of ROW that is required for comprehensive analyses of
project implementation and also the the likelihood impacts of the
immediate vicinity of the ROW project
Project implementing This will be the land belt that needs -do-
area complete clearance for
implementation of the proposed rail
road project
The likelihood impacts identified during reconnaissance visit to Pinwatta – Horana line
trace are mentioned in Table 2-9.
A 125 Raigama GN division – Some houses might get affected, but low
Anguruwathota road density population
A 140 Rajamaha vihara Mawatha, Densely populated area with large houses.
Pokunuwita
The locations along the trace where significant negative impacts observed are
summarized in Table 2-10
B50 Borupona road, Ratmalana Deaf & blind school, and many other houses
are located
B90 Sri Rahula Mawatha, New Large number of houses are located
town Katubedda
B 100 to Devala road, Dandeniya Large number of houses belong low income
B110 watta, New town Katubedda group.
The locations along the trace where significant negative impacts observed are
summarized in Table 2-10
C50 to C70 East Kumbuka, South Kumbuka, Moderate densely population &
Gonawala GN division, Moragahahena moderate number of houses
road
Concluding remarks
As far as negative social impacts are concern, Pinwatta – Horana trace and Kottawa –
Horana trace received high scores. Ratmalana – Horana received the lowest scores. In
terms of positive impacts especially likely economic benefits generated in the post
construction phase Ratmalana – Horana would be the most significant trace.
The topography traversed has an influence on the alignment and design speed of the track.
Topography affects both horizontal and vertical alignments, but its effects are more
significant on vertical alignment. Topography is broken in to two classifications: level, and
rolling.
In this study, the trace lengths is divided into segments of 1 - 2 km and terrain condition of
those segment will be estimated using the contours of the topo sheets. Terrain condition of
the sections that contours are not cleared is determined during the field visit. This would
help to estimate the number of sections in different terrain conditions on proposed
alternative traces. The maximum grade for a rail line is a function of land use, terrain and
design speed. The sections with higher grades should be aligned to get the allowable
maximum grade. Track length of cut and fill and possible deviation to the trace will be
estimated. Infrastructure requirements such as bridges, culverts, retaining walls etc. and
stations and access roads to stations will also be taken in to account in the comparison of
alternatives.
In addition changes in accessibility and mobility in the area due to the railway line, possible
safety issues and other transport system requirements such as changes to existing bus
routes, terminals are also be considered.
According to the preliminary findings it can be seen that Trace C rank will be the best
alternative followed by Trace A and Trace B.
After getting the overview about the project, reconnaissance survey was carried out with
the team, to familiarize with the area. Available data and information were reviewed with
field survey data and photographs. Detail land use maps were used to understand the
gravity and present scenario. Based on the information collected possible impacts were
identified for each trace and given in the scoping matrix. Once the preferred alternative is
selected detail mitigatory measures will be proposed to minimize the negative impacts.
Preliminary investigations suggest that the Trace B from Ratmalana will contribute more to
land use development in the area as compared to other two alternatives. Trace C rank
number two followed by Trace A.
The selection of the preferred alternative was done based on a quantified and graded
matrix. For this environmental parameters were given an importance value based on multi
criteria ranking technique. The importance is based on the significance to the environment
due to an effect on the particular environment parameter. The importance values were
assigned on local, regional and global context. Information for this exercise was gathered
from the field visits, interviews with locals and experts. Finalization of significance values
was done by the entire team and the finally agreed values are given in Table 3-1 below:
Table 3-1: Significance values selected for the analysis
Environment Significance values
Parameter Mean of Std. Selected
individual inputs Deviation Value
Water 7.5 2.4 7
Air & Noise 8.4 2.4 8
Hydrology 11.7 1.5 12
Earth 8.7 1.9 9
Ecology 6.7 3.0 7
Land Use 12.0 3.1 12
Aesthetics 6.1 2.0 6
Human Interest 16.5 4.4 16
Transportation 12.3 3.9 12
Economic 11.0 2.2 11
Each expert was asked to distribute the agreed significance value for a given environment
parameter among the sub parameters used for the analysis. These values are given in the
matrices in Annexure B. Based on the field studies each expert identified the activities that
may cause positive or negative impact on the environment parameter under consideration.
After assigning the magnitude of impacts each project activity would have on the respective
environmental parameters on a scale of 1-3 they were multiplied by the corresponding
significance of the environment parameter under consideration to arrive at a representative
value of the impact an activity would have on an environmental parameter.
The three alternatives were compared based on the scores obtained above. Analysis was
carried out based on the total scores obtained, positive and negative scores for different
stages of the project and the weighted score that takes in to account the number of sub
Economic feasibility study will consists of two parts. Pre feasibility study that will be carried
out to identify the preferred alternative and subsequently a detail economic feasibility will
be done for the selected alternative. The transport analysis of the pre-feasibility study will
be done in number of steps as follows:
Study reports on relevant previous studies such as Environment Impact Assessment for the
Matara Kataragama Railway Extension, 2008, Study and Evaluation of Alternative Routing of
Matara – Kataragama Railway Extension, Dept. of Civil Engineering, University of Moratuwa,
1992, feasibility Study for the Matara – Kataragama Railway Extension, Korean Consultants
International, 1991 are to be reviewed. Further, feasibility studies for the proposed Horana
Export Processing Zone, International Stadium at Diyagama (if available) will be reviewed.
Latest information on Southern Highway Project and other data available with RDA have
been requested. Information on development proposals and relevant land use maps and
satellite images were obtained from the Urban Development Authority. Tentative traces for
the alternatives proposed were identified on 1:50,000 maps and 1:10,000 maps were
available. A criterion used was to minimize the relocation of people, avoid difficult terrain
and avoiding environmentally sensitive areas.
Step 2: Initial Field visits
Initial field visits in the study area were carried out to verify the land use patterns.
Appropriate locations to carry out traffic survey were identified based on the anticipated
travel patterns within the study area.
Step 3: Traffic Surveys
Manual classified traffic counts along with Origin – Destination (O-D) survey were carried
out at five different locations. Origin destination (O-D) trip matrix estimation from traffic
count surveys is regarded as the most economical and effective methodology in road
network analysis for transport planning. Information about where people go, why, when
and how they choose to get there is assume as an important resource for planning
A Separate bus passenger counts also carried out at these survey locations. Summary of the
traffic surveys are given in Annexure C.
An inventory of all road links in the study area that may experience some effect due to
proposed changes will be prepared based on the information collected. In addition for each
trace, details on land use and location of all anticipated structures; culverts & bridges,
number of buildings within the project affected areas, number of road crossings, ground
profile along the trace were collected. Summary of this information is given in Appendix D.
Collection of information and data pertaining to the determination of land acquisition cost,
vehicle operating cost, congestion cost, rail construction and maintenance cost, accident
costs, pollution costs and value of passenger travel time will also be done prior to analysis.
Some of this information has already been collected.
Once the identified preferred alternative is agreed, detail geotechnical and hydrological
studies will be carried out. Based on the findings of the above, geometric design of the rail
track and the improved cost estimate for construction of the proposed rail road will be
carried out.
Based on the traffic and passenger data collected the potential passenger & freight
movements for the proposed railway operation under existing conditions and future
development scenarios will be estimate. The overall economic benefits for each of the
above scenarios will also be carried out. Finally overall cost benefit analysis will be
conducted.
It is proposed submit four reports prior to the preparation of the final report as indicated in
the Table 6-1 below:
ANNEXTURE Page 48
ANNEXURE B: MATRICES
ANNEXTURE Page 49
ANNEXURE C: SUMMARY OF TRAFFIC COUNTS
ANNEXTURE Page 50
ANNEXURE D: SUMMARY OF INVENTORY SURVEYS
ANNEXTURE Page 51
ANNEXTURE – List of Consultants
Prof. Saman Bandara (Team Leader – Traffic Engineering Specialist)
B.Sc. Eng. (Hons), Ph.D.(Calgary), CMILT
Professor in Civil Engineering, Department of Civil Engineering, University of Moratuwa
ANNEXTURE Page 52
Mrs. Nilanthi Bandara (Environmental Assessment Specialist)
B.Sc. (Hons) (Chandigrah), M.Sc. (Chandigrah), M.E.Des (Calgary)
Senior Lecturer, Department of Forestry and Environmental Science, University of Sri
Jayewardenepura
ANNEXTURE Page 53