BILL NO.

3 - THE BUILDING GH¢

SUBSTRUCTURE

Item EXCAVATION AND EARTHWORK

A Clear site of all bushes 384 m2 2.0 768.00

B Excavate oversite average 150mm deep to


remove vegetable top soil and clear away
from site 384 m2 1.2 460.80

C Excavate foundation trench not exceeding


1.50m deep commencing at surface strip
level 42 m3 6.0 252.00

D Excavate pit for column bases not


exceeding 1.50m deep do. 5 " 7.5 37.50

E Selected excavated material in back filling


around foundations 34 " 4.0 136.00

F Remove surplus excavated material from


site 13 " 3.5 45.50

Hardcore Filling

G Approved compacted laterite filling to make up


levels under floors 116 m3 22.0 2,552.00

CONCRETEWORK

PLAIN IN-SITU CONCRETE

Concrete (1:4:8 - 40mm aggregate ) in:

H 50mm Blinding under column bases 6 m2 7.5 45.00

To Collection GH¢ 4,296.80


3/1
Item Concrete (1:2:4 - 20mm aggregate ) in:

A Foundations 13 m3 150.0 1,950.00

B Steps 1 " 150.0 150.00

C 150mm thick bed 384 m2 22.5 8,640.00

REINFORCED IN-SITU VIBRATED


CONCRETE

Concrete (1:2:4 - 20mm aggregate ) in:

D Column bases 2 m3 180.0 360.00

E Columns 1 " 180.0 180.00

REINFORCEMENT

Mild steel rod reinforcement to B.S. 4449


cut, bent, hoisted and fixed as described:

F 12mm Diameter in column bases 80 Kg 1.8 144.00

G 12mm Diameter in columns 68 " 1.8 122.40

H 10mm Diameter as links in columns 28 " 1.8 50.40

To Collection GH¢ 11,596.80

3/2
Item FORMWORK

Sawn to:

A Vertical sides of columns 6 m2 12.0 72.00

B Edge of bed 150mm wide 124 m 1.8 223.20

C Risers of steps diito 8 " 1.8 14.40

D Sides of steps 1 m2 12.0 12.00

BLOCKWORK

Sandcrete blockwork in cement and sand


(1:4) mortar in:

E 150mm Solid walls 75 m2 24.0 1,800.00

PLASTERWORK
20mm cement and sand (1:4)
smooth rendering finished with a wood
float on:

F Concrete or blockwall 75 " 3.8 285.00

PAINTING AND DECORATIING

Prepare and apply three coats of 'Coral'


emulsion paint on

G Rendered walls 75 " 4.5 337.50

To Collection GH¢ 2,744.10

3/3
Page No COLLECTION

3/1 4,296.80

/2 11,596.80

/3 2,744.10

SUBSTRUCTURE
Carried to Summary GH¢ 18,637.70

3/4
Item BRICKWORK AND BLOCKWORK

BLOCKWORK

Sandcrete blockwork in cement and sand


(1:4) mortar in:

A 150mm Hollow walls 124 m2 24.0 2,976.00

BRICKWORK AND BLOCKWORK


Carried to Summary GH¢ 2,976.00

ROOFING

CORRUGATED OR TROUGH SHEET ROOFING

B Longspan aluminium roofing sheet 437 m2 28.0 12,236.00

C 450mm girth type ridge/hip


capping 30 m 12.0 360.00

ROOFING
Carried to Summary GH¢ 12,596.00

CARPENTRY

STRUCTURAL TIMBERS

Solignum treated sawn" Dahoma" hardwood

D 50 x 150mm 84 m 6.5 546.00

CARPENTRY GH¢
Carried to Summary 546.00

3/5
Item
METALWORK

COMPOSITE UNITS

A Supply and fix mild steel mesh along periphery


of blockwall 149 m2 10.0 1,490.00

METAL WORK
Carried to Summary GH¢ 1,490.00

3/6
Item

PLASTERWORK AND OTHER FLOOR


WALL AND CEILING FINISHINGS

IN-SITU FINISHINGS

20mm cement and sand (1:4)


smooth rendering finished with a wood
float on:

A Blockwalls 248 m2 3.8 942.40

B 50mm cement and sand screed to floors 384 " 6.5 2,496.00

PLASTERWORK AND OTHER FLOOR


WALL AND CEILING FINISHINGS
Carried to Summary GH¢ 3,438.40

3/7
Item

PAINTING AND DECORATING

Prepare and apply three coats of Coral emulsion


paint on:

A Rendered walls 248 m2 4.5 1,116.00

PAINTING AND DECORATING


Carried to Summary GH¢ 1,116.00

3/8
BILL NO. 3 - THE BUILDING

SUMMARY
Page
No.

3/4 SUBSTRUCTURE 18,637.70

SUPERSTRUCTURE

3/5 BRICKWORK AND BLOCKWORK 2,976.00

3/5 ROOFING 12,596.00

3/5 CARPENTRY 546.00

3/6 METALWORK 1,490.00

3/7 PLASTERWORK AND OTHER FLOOR, WALL


AND CEILING FINISHINGS 3,438.40

3/8 PAINTING AND DECORATING 1,116.00

BILL NO. 3 - THE BUILDING


SUB- TOTAL 40,800.10

ADD PRELIMINARIES 5% 2,040.01

ADD CONTINGENCIES 10% 4,080.01

TOTAL ESTIMATED COST OF WORKS GH¢ 46,920.12