Sap Manual - Basic

1. Creating Project

2. WBS Structure

3. Network

4. Activity

5. Cost Planning

6. Reports
2

Step 1
3

Step 2

CLICK PROJECT BUILDER

Path : Logistics Project System Project Project Builder

Transcation : CJ20N
4

Step 3 : Create Project

CLICK Project
5

Step 4

FILL FILL

PRESS ENTER FILL

Project def.: Project Code


Project Description – Name of the Project

Project Profile: With Project Stock (Select from dropdown menu)


6

Step 5

PRESS ENTER
FILL

FILL

FILL

Start date: Project start date as per contract signature (Select from drop down menu)

Finish date: Project finishes date as per contract signature (Select from drop down menu)
7

Step 6

CLICK

FILL

Long txt: Brief description of the project – Country, Owner, Client, and Scope
8

Step 7

DOUBLE
CLICK

PROJECT CREATED
9

Step 8

CLICK
10

Step 9 : Create WBS

FILL FILL

PRESS ENTER

Level: 1 (1st WBS Element should be at level 1)


WBS Element: Same as the Project code (WBS codes and structure to be finalised before uploading the data in
SAP)
Description: Contract
11

Step 10

FILL
LEVELS
FILL

FILL FILL
LEVEL FILL

Complete the WBS uploading with correct level, code and description.
Keep saving the data in between to avoid any loss of data due to sudden power failures.
12

Step 11

DOUBLE
CLICK
13

Step 12

CLICK

VIEW WBS
14

Step 13

CLICK

Expand all the WBS elements


15

Step 14
16

Step 15

CLICK

CLICK
WHEREVER
REQUIRED

PE: Planning Element ( Planning to be done at the lowest level)


Acct: Accounting ( Accounting to be done at the lowest level)
Bill: Billing (Billing to be done at the Contract Level)
17

Step 17

CLICK
18

Step 18: Create Network

CLICK
19

Step 19

FILL

FILL

FILL

PRESS ENTER

NETWORK CREATED

Network: Description same as WBS element


Network profile: Activity acct. ass. No plan costs (Select from the dropdown menu)
MRP Controller: 010 (Select from the dropdown menu)
20

Step 20

CLICK
21

Step 22

CLICK
22

Step 23: Create Activity

CLICK
23

Step 24

FILL

PRESS ENTER
24

Step 25

CLICK

ACTIVITY CREATED
25

Step 27: WBS Release

CLICK
26

Step 28

CLICK
27

Step 29

CLICK

WBS RELEASED
28

Step 30

CLICK
29

Step 31

CLICK
30

Step 32

CLICK

USER STATUS CHANGED :


INIT TO BUDG
31

Step 33: Component Uploading

CLICK
32

Step 34

FILL
FILL

PRESS ENTER
33

Step 35: Cost Planning

CLICK

Path: Logistics Project System Financials Planning Costs in WBS


Overall values Change

Transcation Code: CJ40


34

Step 36

CLICK
35

Step 37

CLICK

CLICK
36

Step 38

CLICK

CLICK

Primary Costs: Direct Costs i.e Raw Material, Semifinished Produts, Subcontracts, Services etc.
Activityinput: Indirect Costs i.e Hourly Rates
37

Step 39

FILL ACTIVITY TYPE


CLICK

CLICK FILL
FILL HOURS AS PER
THE COST SHEET

FILL COST CENTRE

PRESS ENTER
38

Step 40

CLICK

PLANNED VALUE FOR


THE WBS ELEMENT
DISPLAYED
39

Step 41

CLICK

PLANNED VALUE FOR


THE WBS ELEMENT
DISPLAYED

PLANNED VALUE FOR


THE WBS ELEMENT
DISPLAYED
40

Step 42

CLICK

FILL

FILL
41

Step 43

CLICK
42

Step 44

CLICK
43

Step 45

CLICK

Path : Logistics Project system Financials Copy Costs and Revenues Copy Project
Costing (Ind)

Tranx code: CJ9FS


44

Step 46

CLICK

FILL

FILL CLICK

FILL CLICK

Template Version: 0
Target Version: 1
45

Step 47

CLICK
46

Step 48

CLICK

CLICK
47

Step 49

CLICK
48

Step 50

CLICK
49

Step 51

CLICK

Path : Alstom Add on menu Project Management Reports ZPROJCOSTBOILER – Proj Review
50

Step 52

CLICK

FILL
51

Step 53

CLICK
52

Step 54

CLICK

SELECT THE VALUE WHICH


WHICH NEEDS TO BE CHECKED
53

Step 55

CLICK
54

Step 56
55

Step 57

Tranx: PS 91
56

Step 58

CLICK
57

Step 59

CLICK
58

Step 60