You are on page 1of 81

{ÉÉ´É®ú ]ÅõÉƺɡòɨÉÇ®úºÉÇ B´ÉÆ Ê®úBC]õºÉÇ

Eäò ºlÉÉ{ÉxÉ, Eò¨ÉÒ¶ÉËxÉMÉ {ÉÊ®úSÉɱÉxÉ B´ÉÆ +xÉÖ®úIÉhÉ Eäò


ʱɪÉä +xÉÖnäù¶É

INSTRUCTIONS FOR INSTALLATION,


COMMISSIONING, OPERATION AND
MAINTENANCE OF

POWER TRANSFORMERS
&
REACTORS

¦ÉÉ®úiÉ ½äþ´ÉÒ <±ÉäÎC]ÅõEò±ºÉ ʱÉʨÉ]äõb÷, ¦ÉÉä{ÉɱÉ


BHART HEAVY ELECTRICALS LIMITED,
BHOPAL

1 Printed at Anupam Mudran Bhopal Ph: 9425025574


ºlÉÉ{ÉxÉ, Eò¨ÉÒ¶ÉËxÉMÉ, {ÉÊ®úSÉɱÉxÉ B´ÉÆ +xÉÖ®úIÉhÉ Eäò +xÉÖnäù¶É
JÉÆb÷ - II
(EÖò±É JÉÆb÷ - 2)

INSTALLATION, COMMISSIONING,
OPERATION AND MAINTENANCE
INSTRUCTIONS
VOL-II of II

3 Printed at Anupam Mudran Bhopal Ph: 9425025574


PREFACE

BHEL Transformers and Reactors are designed, manufactured and


tested with care. With proper attention during installation and use, the user
should receive from it the maximum expected service.
Before installing the transformers/ reactor read these instructions
carefully.
These instructions have been prepared to provide information on
assembly, installation, commissioning and regular maintenance of the
transformers/reactors and shall form part of Instruction Manual.
These instructions do not intend to cover operation and maintenance of
the transformer under abnormal conditions.
Should further information be needed or any problem arises which is
not covered by these instructions, please ask BHEL for further information.
In operating the Transformer/Reactor, Care should be taken that loading
limits as specified are strictly followed. For instructions regarding, general
information on accessories such as OLTC, WTI, OTI, Buchholz relay, fan,
pump, etc. Vol. I may please be referred.

5 Printed at Anupam Mudran Bhopal Ph: 9425025574


CONTENTS

Page No.
SECTION 1 GENERAL INFORMATION
1.1 INTRODUCTION 11
1.2 TRANSPORT OF TRANSFORMER / REACTOR 13

SECTION 2 INSTALLATION
2.1 RECEPTION AND ASSEMBLING OF TRANSFORMERS
/ REACTORS DESPATCHED PARTLY DISMANTLED
AND FILLED WITH NITROGEN 21
2.2 STORING OF TRANSFORMER / REACTOR DESPATCHED
FILLED WITH NITROGEN 33
2.3 ASSEMBLING OF EXTERNAL PIPES 35
2.4 INSULATING OIL, QUALITY AND TREATMENT 37
2.5 OIL FILLING UNDER VACUUM 43
2.6 OIL FILLING INSTRUCTIONS FOR CONSERVATORS
WITH AIR CELL 47
2.7 UNTANKING OF ACTIVE PART 53
2.8 MOUNTING OF GASKETS 55
2.9 WELDED COVER (IF APPLICABLE) 57
2.10 EARTHING OF ACTIVE PART AND CORE
INSULATION TEST 59
2.11 TOUCH-UP PAINTING 69

SECTION 3 COMMISSIONING
3.1 TESTING AFTER ASSEMBLY OF THE TRANSFORMER
/ REACTOR AT SITE 77
3.2 COMMISSIONING CHECKS - TRANSFORMER 79
3.3 COMMISSIONING CHECKS - REACTOR 93

SECTION 4 MAINTENANCE AND OPERATION


4.1 SUPERVISION OF TRANSFORMER / REACTOR 101
4.2 SUPERVISION AND CONTROL OF OIL 109
4.3 TROUBLE SHOUTING 109
4.4 PARALLEL OPERATION 119
4.5 DO'S AND DON'TS 137
4.6 DISPOSAL 145

7 Printed at Anupam Mudran Bhopal Ph: 9425025574


¦ÉÉMÉ-1
ºÉɨÉÉxªÉ VÉÉxÉEòÉ®úÒ

SECTION-1
GENERAL INFORMATION

9 Printed at Anupam Mudran Bhopal Ph: 9425025574


SECTION 1
GENERAL INFORMATION

1.1 INTRODUCTION
1.1.1 POWER TRANSFORMERS
Unlike shunt reactor and Neutral Grounding Reactors where standard
specification is generally followed by utilities, requirements of power
transformers vary depending upon the system design. Hence a tailor made
product becomes the answer. Depending upon the requirements two winding/
three winding/ auto connection/ split winding arrangement with ON LOAD or
OFF CIRCUIT tap changer, five limbs/ three limbs core construction, welded
or bolted tank construction are adopted.
Variation in capacity, impedance and transport profile result in different
sizes of transformer. Refer VoI I for specific requirements of the equipment.
1.1.2 SHUNT REACTORS
Shunt Reactors are used in high voltage systems to compensate
capacitive generation from long lightly loaded overhead lines or extended cable
systems and also for control of dynamic over voltages.
Gapped core construction is preferred for high system voltages over
coreless construction due to the high energy density that can be achieved in
gapped core construction. The core sections between consecutive air gaps
are moulded in epoxy resin to prevent movement between individual laminations.
The spacers forming the air gaps are blocks of ceramics with a high modules
of elasticity and the whole stacking of core modules is cemented together
during the assembly to form a solid column without possibility of rocking , or
rubbing between individual parts.
The core segments are of radial laminated configuration. The radial
laminations prevent fringing flux from entering flat surfaces of core steel which
would result in eddy current overheating and hot spots.
Five limbed core construction is adopted to achieve high zero sequence
impedance. In addition to the three gapped core limbs with windings, there
are two continuous outer return limbs. The two unwound side limbs help in
achieving zero sequence impedance approximately equal to the positive
sequence impedance. Other construction type can be a three limbed
construction. For single phase reactors e.g. 800 KV class middle leg wound
with two return legs type of construction is adopted.
Interleaved disc winding has been used for rated voltages 220 KV and
above. This type of winding configuration provides better impulse voltage
distribution. For lower voltage classes a continuous disc winding or a multi
layer helical winding are used. The tank is rectangular in construction with flat
cover welded to the tank rim at top. The associated cooling control equipment
is housed in a tank mounted weather proof marshalling box. The reactors are
equipped with all standard measuring and controlling fittings and accessories
as described in Volume I.

11 Printed at Anupam Mudran Bhopal Ph: 9425025574


Reactors have been designed for resting on concrete foundation as shown
in the foundation plan drawing. Rollers have been provided only for movement
of the reactor at site.
1.1.3 NEUTRAL GROUNDING REACTOR
When single pole reclosing is used on lines, the Neutral Grounding Reactor
is used.
The Neutral Grounding Reactors are connected between neutral point
of 400 kV/800 KV reactors and earth, where the neutral of shunt Reactor is
suitable for 145 kV class insulation.
The reactors are oil immersed type ONAN cooled (oil immersed with
natural air cooling) with continuous rating of 10/15 Amps and a 10 sec. rating
as indicated in the Rating Data sheet. As continuous losses of the reactors are
negligible, reactor tank surface is adequate for dissipation of these losses.
Hence radiators are not provided.
Considering linear impedance characteristic requirement upto rated short
time current a core less design with magnetic shielding of CRGO sheet has
been made. The magnetic circuit, therefore consists of rectangular frame of
CRGO steel lamination packets of adequate area. Area of magnetic circuit is
selected such that saturation does not take place under short time current. A
rigid clamping structure is provided for clamping of magnetic frame and a very
low flux density is used to minimize the vibration and achieve linear impedance
characteristic.
The graded disc type concentric winding suitable for a rated voltage of
145 kV and basic insulation level of 550 kVp has been provided without core
inside. Winding is held in position by way of special insulation structure inside
winding and finally kept under pressure between top and bottom yokes of
magnetic frame. Return path of flux is provided by way of two return limbs.
The line terminal is taken out through the tank cover via 145 kV, 800
Amps OIP condenser bushing provided with suitable terminal connector. The
neutral lead is taken out through the tank cover via a 36kV, 630 Amps porcelain
bushing.
The tank is of welded mild steel plate construction shot blasted on the
inside and outside to remove scales before painting. The tank is painted on the
inside with yellow paint and its outside surface is painted with two coats of
primer paint and finishing coat, of light grey paint to shade 631 of IS:5. This
is a standard painting scheme followed for all equipment .
The fittings include a conservator with a magnetic oil gauge, pressure
relief device, drain and filter valves, sampling valves, thermometer pockets,
Buchholz relay, temperature indicator for oil and silicagel breather .
These reactors are designed for mounting directly on plinth.
1.2 TRANSPORT OF TRANSFORMER/REACTOR
Power Transformers and Reactors hereinafter referred as "Transformers,"
depending upon the restriction imposed by transport weight and/or other
considerations, have to be transported either filled with oil or nitrogen as per
the description given below. The transformer is loaded on wagon as per loading
gauge drawing prepared in each case.

13 Printed at Anupam Mudran Bhopal Ph: 9425025574


1.2.1 WITH OIL
The Transformer is filled with oil such that about 10% of the tank
volume is left clear for expansion to limit the excess internal air pressure to
0.35 kg/cm2. Fittings dismantled before transport are packed in packing cases
in line with shipping list.
All openings resulting from removal of fittings for shipment are sealed
with suitable gasketted blanking plates during transport.
The balance oil quantity required for the complete filling of the reactor is
supplied separately.
A transformer despatched according to this method can be stored at
site or elsewhere for one year provided, that all insulating materials are covered
with oil and silicagel breather is mounted and quality of oil is maintained as per
IS: 1866. Measures to be taken on reception at site are given clause 2.1
1.2.2 WITH NITROGEN
Large oil filled transformers/reactors are not normally oil filled during
shipping due to weight limitations. To protect the active parts against moisture
the transformer tank is filled with dry Nitrogen at a positive pressure of 0.175
kg/cm2 (2.5 psi) at BHEL works before despatch. The internal pressure at the
time of shipment is painted on the tank.
All openings resulting from the removal of fittings for shipment are
sealed with suitable gasketted blanking plates during transport.
A Transformer despatched according to this method should normally be
stored upto 3 months after arrival at site or elsewhere.
For control of gas pressure and maintaining the pressure during transport
and possible storage before assembling, the transformer is equipped with an
automatic device. This device is called two stage N2 regulator and is kept in a
steel box and mounted on the frame provided on tank side for keeping two
back up Nitrogen cylinders. Nitrogen regulator is connected to two cylinders
by copper tubes and to tank by a rubber hose as shown in the Fig. 1.1.
N2 regulator reduces cylinder high pressure of 120 to 140 kg/cm2 to
required low pressure of 0.175 kg/cm2 in two stages. One gauge provided on
the first stage indicates the cylinder pressure, whereas other gauge provided
on second stage indicates the tank pressure. Regulator is fixed at factory.
When tank pressure falls below 0.15 kg/cm2, due to leakage/fall of
ambient temperature, regulator automatically feeds the gas from cylinders, to
build up required pressure in the tank.
The gas consumption during transport and possible storage is difficult
to estimate as it depends on ambient temperature variation, possible leakages
as well as on the duration of transport and storage. However, two back up
cylinders are provided to meet the gas requirement. Normally one cylinder is
kept open and the other shut. When the pressure of first cylinder falls to 10
kg/cm2 this should be considered as empty and immediately its valve should
be closed and the valve of second cylinder should be opened.
When cylinder is required to be removed for refilling, disconnect copper
tubing from cylinder valve.

15 Printed at Anupam Mudran Bhopal Ph: 9425025574


Use only dry Nitrogen gas to IS:1747 with 50 ppm moisture and 1%
oxygen by volume.
If the storage time exceeds 3 months, the transformer is filled with oil
according to directions given in clause 2.5. If for some reason oil filling is not
possible, then nitrogen must be continuously maintained at a positive pressure.
Measures to be taken on receipt at site are given in clause 2.1.
1.2.3 INSTRUCTIONS FOR FILLING DRY PURE NITROGEN GAS WITH
BACK UP CYLINDERS (AT WORKS)
Lower the oil level to the minimum necessary to dismantle the items
(such as bushing and turrets) which must be removed for shipping.
Pull 500 mm mercury vacuum after blanking off all openings.
Break the vacuum by admitting dry nitrogen through a convenient valve
at the top of the tank and drain the oil completely.
Continue to supply nitrogen until it maintains a steady pressure of 0.17
± 0.02 kg/cm2 above the atmosphere.
Pressure of nitrogen gas shall be maintained at 0.17 ± 0.02 kg/cm2 at
same reference temperature. Pressure would be monitored by taking three
readings within 24 hours to ensure that there is no leakage of gas.
Shut off the gas supply valve and fit dry nitrogen back up cylinders
through nitrogen regulator valve.

17 Printed at Anupam Mudran Bhopal Ph: 9425025574


¦ÉÉMÉ-2
ºlÉÉ{ÉxÉ

SECTION-2
INSTALLATION

19 Printed at Anupam Mudran Bhopal Ph: 9425025574


SECTION 2

2. INSTALLATION
2.1 RECEPTION AND ASSEMBLING OF TRANSFORMER/REACTOR
DESPATCHED PARTLY DISMANTLED AND FILLED WITH NITROGEN.
To ensure that a Transformer will function satisfactorily it is important
that handling, lifting, storing and assembling are carried out with great care
and cleanliness by experienced personnel who know the various working
operations very well.
This section gives instructions how handling, lifting, storing and
assembling should be carried out. For large Transformers it is recommended
that the work is done by BHEL or is under supervision by experts from BHEL.
2.1.1 INSPECTION
In connection with receiving and unloading at site, and at the final storing
place before assembling, the transformers shall be inspected carefully. External
visible damages as dents, paint damages etc. may imply that the transformer
has been subjected to careless handling during transport and/or re-loadings,
and a careful investigation is therefore justified.
After the arrival of the material at receiving points, the customer should,
in case of possible damage/loss of any component, make the necessary claims
with the contractors representatives under intimation to supplier so that such
claims can be registered with the transport agents. Before unloading, the
condition of packing and of the visible parts should be checked and possible
traces of leaks verified (condenser bushings). If necessary, appropriate
statements and claims should be made.
Drums containing oil which have been despatched separately should be
examined carefully for leaks or any sign of tampering. All drums are despatched
filled up to their capacity and any shortage should be reported.
In order to protect the active part against moisture, the transformer
tank is filled with nitrogen during transport at an over pressure of 0.17 kg/
sq.cm (2.5 psi) approximately at room temperature.
Check immediately the gas pressure at the arrival. A positive pressure
indicates that the tank and the transformer components respectively are tight,
and that the active part including the insulation materials is dry.
If there is no positive gas-pressure, transformer should be immediately
filled with dry Nitrogen gas at a pressure of 0.17 kg/cm2 (2.5 psi) without loss
of time as per instructions given para 1.2.3
Otherwise, it should be checked if the core isolation is satisfactory and
that accessories packed separately have not been damaged during the transport.
Instructions for checking of the core isolation are given in clause 2.10
2.1.2 UNLOADING
Typical unloading arrangement of the transformer is shown in fig 2.1.
Whenever rollers/trolleys are supplied with transformer, movement of
transformer at site is carried out by mounting these rollers/trolleys. For mounting
of rollers refer roller mounting drawing included in Vol.I.

21 Printed at Anupam Mudran Bhopal Ph: 9425025574


Alternatively for movement of transformer from loading bay to actual
site of the equipment, skidding on greased rails etc. can also be resorted to.
2.1.3 STORING
Dismantled equipment and components are packed to be protected
against normal handling and transport stresses. The instructions for lifting
given on the packages, must be complied with to avoid damages.
Goods stored outdoors must not be placed directly on the ground, and
should be covered carefully with tarpaulin or similar material.
Oil drums should be stored in horizontal (lying) position with both the
bungs also in horizontal position.
2.1.4 LIFTING
Lifting devices on the transformer tank are dimensioned for lifting of the
complete transformer filled with oil. The positioning of the lifting devices,
permissible lifting angles, minimum height to crane hook and transformer
weight, appear from the OGA drawings. Check at lifting of complete transformer
that the lifting wires/ropes are not in contact with bushing or other components
on the cover.
For lifting with hydraulic jacks, the transformer is provided with jacking
pads dimensioned for lifting of complete transformer filled with oil. The position
of the pads appear on the OGA drawings. If active part is to be lifted refer
instructions given in clause 2.7.
2.1.5 LOCATION AND SITE PREPARATION
a) Reactor shall always be placed on concrete plinth without rollers as
per foundation plan drawing whereas transformer may be even placed
with rollers. Therefore it is very important to refer foundation drawing
before placing the transformer/reactor on final location.
b) Transformer/reactor should be placed on the foundation so that easy
access is available all around and diagram plates, thermometers, valves,
oil gauges, etc. can be easily reached or read. Adequate electrical
clearances are also to be provided from various live points of the
transformer to earthed parts.
c) ONAN type transformers/reactors depend entirely upon the surrounding
air for carrying away the heat generated due to losses. For indoor
installation, therefore, the room must be well ventilated so that the
heated air can escape readily and be replaced by cool air . Air inlets
and outlets should be of sufficient size and number to pass adequate
air to cool the transformer. The inlets should be as near the floor as
possible and outlets as high as the building will allow. Where necessary,
exhaust fans can be installed for the purpose.
d) The transformers should always be separated from one another and
from all walls and partitions to permit free circulation of air. In this
connection reference is also drawn to IS: 10028 (Part II).

23 Printed at Anupam Mudran Bhopal Ph: 9425025574


e) Where rollers are not fitted, level concrete plinth with bearing plates
of sufficient size and strength can be adopted for outdoor transformers.
To prevent the formation of rust, it is essential to avoid presence of
air and water in the space between the plinth and the base of the
transformer by use of cretex or similar bituminous compound.
f) Where rollers are fitted, suitable rails or tracks should be used and
the wheels locked to prevent accidental movement of the transformer.
Where walls are provided, it should be ensured that the transformer
gets a good ventilation as mentioned above for indoor transformers.
Provision should be made for the emergency drainage of the oil from
the transformers (e.g. in case of fire in neighbouring apparatus or
bushing or the transformer tank), by surrounding the transformer plinth
with sump filled with small pebbles.
2.1.6 INTERNAL INSPECTION AND CHECK POINTS FOR ASSEMBLING
THE TRANSFORMER/REACTOR
(a) Check-points before starting assembly:
1. Conditions of leads.
2. Bracing, clamping of leads.
3. Connections.
4. Tapchanger checks.
5. General conditions of insulation.
6. Core check that it has not moved in transit.
7. Core-ground; this is checked with the megger after removing earth
connection.
8. CTs, including the secondary leads and their passage through metal
parts.
9. Check that shipping frame for bushings have been removed.
10. Check that coil position has not moved in transit.
11. Check for dirt, metal swarf, moisture.
12. Check that the bushing leads set without being too close to ground
or other points of different potential.
(b) Check-points during Assembly
By means of the Part list and the transformer/reactor OGA, the assembling
of a fully completed transformer is carried out according to the following
instructions. The following precautions are to be taken:
(i) Fire-fighting equipment shall be available at the oil-treatment
equipment as well as at work on and adjacent to the transformer .
(ii) Welding work on or adjacent to the transformer shall be avoided, but
if this is not possible, the work shall be supervised by fire-protection
personnel.
(iii) Smoking on or near the transformer shall not be allowed.
(iv) Transformer tank, control cabinet etc. as well as assembling and oil-
treatment equipment shall be connected with the permanent earthing
system of the station.

25 Printed at Anupam Mudran Bhopal Ph: 9425025574


(v) Check that there is no overpressure in the transformer when blanking
plates or connection lids are to be opened.
(vi) All loose objects, tools, screws, nuts etc., shall be removed from the
transformer cover before opening the connection and blanking lids.
(vii) All loose objects (tools, pencils, spectacles etc.,) shall be removed
from the boiler-suit pockets etc. before starting the work through
man holes.
(viii) Tools to be used inside the transformer/reactor -e.g. for tightening of
screw-joints- shall be fastened to the wrist or another fixed point by
means of cotton tape or string.
(ix) Tools with loose sleeves and tools with catches must not be used at
work inside the transformer.
(x) Greatest possible cleanliness shall be observed at work inside the
transformer/reactor, and at handling of parts to be mounted inside
the transformer.
(xi) Fibrous cleaning material should not be used as it can deterioate oil
when mixed with it.
(xii) All components despatched separately should be cleaned inside and
outside before being fitted.
(xiii) A transformer/reactor is best protected from damp hazard by
circulating warm, dry, deaerated oil through it until it temperature is
5° C to 100 C above ambient. This should be done before allowing
external excess to the interior of the tank. The warm oil should be
circulated all the time transformer is open to atmosphere,
(xiv) Oil pump & all joints in the oil pipe work should be airtight to avoid
entrance of air through leakage joints.
(xv) The active part (core and winding) should be exposed to the
surrounding air as short time as possible. Open therefore only one
blanking plate or connection lid at a time for remounting of bushings,
valves etc.
(xvi) Objects which-despite all precaution are dropped inside transformer/
reactor, must absolutely be brought up from the equipment.
(xvii) Check that the oxygen content inside the transformer tank is minimum
20% if a person is to enter the tank.
2.1.7 ASSEMBLY OF WHEELS
Mounting of wheels under reactor/transformer is to be done as per roller
arrangement drawing. The reactor however in service, is to be placed on
plinth with anti-earthquake fastening without rollers. Transformer placement
can be with or without rollers as per applicable OGA/foundation drawing.
2.1.8 ASSEMBLY OF BUSHINGS
In case the bushings are mounted on turrets on the transformer/reactor
cover, they are either delivered mounted on their turret or -incase of large
bushings dismantled from the turrets.

27 Printed at Anupam Mudran Bhopal Ph: 9425025574


The turrets are often individually adapted; check therefore that they are
re-mounted in correct places, which appear from the OGA drawing and ,part
list.
Assembling of bushings is carried out according to the detailed
information documents available.
2.1.9 ASSEMBLY OF VALVES
Valves which may affect the loading gauge, or will be subjected to
damages, should be dismounted before delivery. Re-mount the valves -the
positionings appear from the OGA drawing and part list. The gasketting surfaces
shall be cleaned well and new gaskets fitted. Check that all valves are closed.
2.1.10 ASSEMBLY OF COOLING DEVICES
Valves which are not dismantled like shut-off valves for radiators, coolers
and possible headers shall be provided with blanking plates during the transport.
Remove the blanking plates when the assembling of the coolers is to be
started. Check first that the valves are closed.
Check that each radiator and possible header are assembled in the correct
positions according to OGA drawing. In case of OFAF or OFWF cooler mounting
shall be done as per the relevant leaflet given in Vol.I
The shut-off valves against the transformer tank shall be closed until
the oil-filling is started.
2.1.11 ASSEMBLY OF OIL CONSERVATOR
The conservator, which may be with or without aircell is assembled
either on the transformer, or on a separate frame. Before the conservator is
assembled it shall be checked that belonging equipment -e.g. Oil-level indicator
-functions satisfactorily.
The breather is connected to the oil conservator, and it is very important
that joints and couplings in the pipe between breather and conservator are air
tight. Refer Clause 2.6 for detailed instruction for oil filling.
2.1.12 ASSEMBLY OF PIPE WORK
Pipes with flanges for connection of conservator, radiators, as well as
pipes for equalising of turrets etc. are mostly delivered completely ready for
assembling according to OGA & part list.
In certain cases -e.g. at a separately assembled oil conservator -certain
fitting and welding of pipes and flanges on site is however required. Instruction
for such assembly of external pipes is given in Clause 2.3
2.1.13 FLANGES, BLANKING PLATES
When re-mounting blanking plates, connection flanges etc., the gasketting
surface shall be cleaned well and new gaskets fitted.

29 Printed at Anupam Mudran Bhopal Ph: 9425025574


2.1.14 ACCESSORIES
Accessories like cooling fans, pumps, OLTC and components for
supervision and control, oil-level indicator, flow indicators, gauges, Buchnolz
relay, PRV, thermometers etc. are assembled according to leaflet/description
valid for the components (refer Vol. I).
2.1.15 CONTROL CABLING
Re-assemble the control cables according to the drawing of wiring system
and connect the cable ends to terminal blocks in instruments, terminal boxes,
junction boxes and control cabinets according to valid connection diagram.
2.1.16 GASKETS
The sealing system normally used against oil and gas in BHEL's
transformers and belonging components has rubber gaskets in grooves and
nitrile rubber bonded cork gaskets at other places. Refer clause 2.8 for general
information and assembly instructions for gasket mounting.
2.1.17 OIL FILLING
The completely mounted Transformer is oil-filled according to directions
in Clause 2.5 & 2.6. The oil shall be treated according to Clause 2.4.
The lower and upper shut-off valves for radiators/coolers and possible
headers shall be open during evacuation and oil-filling.
If coolers are placed on suspension beams, which are mounted at right
angle to the tank, the suspension beams shall be supported against the ground
during the evacuation. Also radiators mounted on the tank wall shall be
supported in a similar way.
The hose for filling of oil is connected to the bottom valve of the
transformer which must not be opened until the hose has been deaerated and
completely filled with oil.
2.1.18 CLEANING & PAINTING
The transformer and its equipment are cleaned carefully from dirt, oil,
lubricating grease, and damaged surfaces are touch-up painted with the primer
paints and finish paints delivered as per clause 2.11.
2.1.19 EXCHANGE OF BUSHING
When exchanging a damaged bushing or other component on the cover
of a fully oil- filled transformer, we should proceed according to the following:
Close the valve in the pipe between the transformer and the oil
conservator. Pump oil from the transformer tank into the oil conservator so
that the oil quantity which need be drained off to lower the oil-level enough
below the transformer cover is pushed to the conservator. As the oil is being
transferred from tank to conservator, fill up the tank with dry nitrogen via a
suitable valve on the cover or in turrets.
Exchange the faulty bushing and transfer then the oil from the conservator
to the tank by opening the valve in the pipe between conservator and main
tank. De-air the bushings and turrets.

31 Printed at Anupam Mudran Bhopal Ph: 9425025574


2.2 STORING OF TRANSFORMER/REACTOR DESPATCHED FILLED WITH
NITROGEN
2.2.1 STORING BEFORE COMPLETE ASSEMBLING
The storing place should be easily accessible for inspection and
maintenance of the transformer. The bedding for the equipment should be
larger than its bottom surface and dimensioned for the load. The transformer
is placed on boardings or beams so that good ventilation is obtained underneath
the transformer bottom.
Before storing, the transformer is inspected according to directions in
Clause 2.1 "Reception and assembling of transformer/reactors despatched
partly dismantled and filled with nitrogen".
A transformer without remarks may be stored up to 3 months after
arrival at the site without oil-filling. During the storing time, the inert gas
(nitrogen) filling shall be maintained and pressure regulated, so that exposure
of active part to atmosphere is avoided.
If the storage time is judged to exceed 3 months, the transformer should
be provided with oil conservator including oil-level indicator and breather, and
oil-filled according to Clause 2.5. "Oil filling under vacuum". Certain valves
must be re-mounted to enable the oil-filling being carried out. Furthermore, at
the time at oil-filling of a completely assembled transformer, certain rules in
Clause 2.5 & 2.6 must be complied with absolutely.
Wherever possible it would be most desirable to keep the transformer
energized even at a low voltage so that its temperature is higher than the
ambient temperature. The low voltage may be applied under open circuit or
short circuit conditions. It may be ascertained whether partial cooling is required
in such a case. The oil quality should also be periodically monitored. If for
some reason, oil filling cannot be carried out after a storage period longer than
3 months, the nitrogen pressure shall be maintained and supervised carefully.
If the storage time without oil exceeds 18 months BHEL should be consulted
about measures to be taken.
2.2.2 STORING OF COMPONENTS AND ACCESSORIES BEFORE
COMPLETE ASSEMBLING
Independent of the duration of the storing time, the directions below
apply for dismounted components and accessories, as well as for material to
be used in connection with the assembling work.
(a) Storing indoors
In such a room, the following articles should be stored:
(i) Insulation material as paper, pressboard, bakelite, wood, cotton tape
etc.
(ii) Insulated details as paper-insulated conductors, pressboard insulated
shielding bodies etc.
(iii) Chemicals as solvents, glues, varnishes, hardeners etc.
(iv) Breathers, drying agents.
(v) Terminal boxes, connection boxes, control cabinets.
(vi) Gas relays, oil-level indicators, thermometers, pressure valves etc.

33 Printed at Anupam Mudran Bhopal Ph: 9425025574


(vii) MBox, OLTC motor drive, Fans, Pumps, Instruments & fittings.
(Heating elements provided shall be connected to supply)
(b) Storing outdoors
The below components may be stored outdoors. They should be placed
above ground and covered with tarpaulin etc.
(i) Oil-conservator with blanking plates for all openings.
(ii) Radiators and coolers with blanking plates for all openings.
(iii) Structures, A frames, Pipe supports, Supports for oil-conservators,
radiators, control cabinets etc.
2.2.3 SUPERVISION
During the storing time, the storing place, transformer/reactor
components and accessories are inspected regularly. Tap changer if provided
should be operated at 6 monthly intervals. Two or three runs from one end of
the range to the other and back are sufficient. Observations, readings, measures
and dates should be noted and BHEL should be contacted for directions about
possible measures. Check at even intervals -and further more at weather
changes as rain, storm, frost or thawing the foundation material (boardings,
beams etc.) and the condition of the ground.
Inspect the transformer/reactor periodically with regard to possible
external faults and/or rust-damage.
Check also that screws and nuts in sealing joints (covers, lids etc.) are
tightened. Check every second week that the connected-in heating elements
in control cabinets function.
If the Transformer is inert gas filled, one shall check every second week
the overpressure or inert gas consumption.
If the reactor is oil-filled, one shall take oil-samples after 6 months, and
then min. once a year. The oil is investigated with regard to Electric Strength
(BDV) and moisture content.
Inspect periodically stored components and accessories with regard to
possible , external damages and/or rust damages. If any touching up of paint
is required it should be carried out as per clause 2.11. Check at the same time
that insulation material and insulated details are not damaged or have become
dirty.
2.3 ASSEMBLING OF EXTERNAL PIPES
2.3.1 This technical description shall be applied at assembling of
transformers, when external pipes, for some reasons, are not fully completed
at delivery but require some kind of machining or fitting at site.
At the design occasion it is judged which details that can be made fully
completed in the workshop and which details that must be fitted into position
at site. Fully completed details are delivered with complete surface treatment.
Details of the pipe work despatched can be seen at shipping list.
2.3.2 BREATHER PIPE
The pipe is normally made of 15 NB painted steel pipe. The pipe shall be
cleaned carefully after machining. Supplementary surface treatment is, not
required normally.

35 Printed at Anupam Mudran Bhopal Ph: 9425025574


It is very important that the pipe is tight. Possible leakage will cause
moisture on the transformer with the service disturbances.
Mounting of the breather pipe shall be as per OGA drawing.
2.3.3. OIL CONSERVATOR
For position of conservator along with necessary supports, refer OGA
drawing.
2.3.4 OIL CONSERVATOR PIPE
The pipe has dimension 80 mm usually and has welded flanges. The
pipe shall be painted internally with a yellow, oil-resistant paint, and externally
with a paint specified on the drawing. The pipes shall always incline upwards
minimum 2/3 degrees from the transformer.
2.3.5 EQUALISING PIPES
The pipe system in connection with the transformer cover is as a rule
manufactured in workshop. The pipe between transformer and conservator
may be pre-assembled.
The pipe is provided with weld-flanges. No pipe part is allowed to be so
long that internal inspection and cleaning is difficult to carry out. Besides
straight extensions, each pipe part may contain one bend.
The pipes shall always be placed with minimum 2/3 degrees inclining
upwards from the transformer. Internal surface treatment is with yellow oil
resistant paint. External surface treatment is made as specified on the drawing
as per specification. Cleanliness is extremely important.
2.3.6 COOLERS
The positioning of the radiators/coolers is indicated on OGA drawing.
These are positioned so that the highest point of the oil-pipe system is always
positioned below the bottom level of the conservator.
The pipe system is provided with filter valves at the start and finish to
enable pumping the oil through the system.
All places where air may be collected are provided with air release plugs/
valves.
2.3.7 COOLER PIPES
The pipe having dimensions as per OGA drawing and may be provided
with weld- flanges, expansion joints. No pipe part is allowed to be so long that
internal inspection and cleaning will be difficult.
The pipes shall be placed so that air release plugs will be positioned at
the highest point of the pipe part. The pipes shall be painted internally with a
yellow, oil-resistant paint and externally according to the paint as per
specification.
2.4 INSULATING OIL, QUALITY AND TREATMENT
2.4.1 QUALITY
The oil to be filled in transformer generally complies with the
requirements of the customer's specification. The characteristics of fresh oil
as per IS: 335 "Specification for New Insulating Oil" are given below:

37 Printed at Anupam Mudran Bhopal Ph: 9425025574


CHARACTERISTICS AND PARAMETERS OF NEW
INSULATING OIL

Sr.No. Characteristics Unit Requirement


1. Appearance The oil shall be clear,
transparent & free from
suspended matter or
sediments.
2. Density at 29.5°C gm/cc 0.89
3. Kinematic Viscosity
at 27° C (max.) Cst 27
4. Interfacial tension
at 27oC (Min) N/m 0.04
5. Flash Point (Min) o
C 140
6. Pour Point (Max) o
C -6
7. Neutralisation value
(Total acidity), (Max) mg/KOH/g 0.03
8. Corrosive sulphur : Non-corrosive
9. Electric strength
(breakdown voltage)
(Min)
(a) New untreated oil, kV (rms) 30
(If the above value is not
obtained the oil shall be
filtered in laboratory).
(b) After filtration kV (rms) 60
10. Dielectric dissipation
factor (tan δ) at 90°C
(Max) 0.002
11. Water content (Max) ppm 50
12. Specific resistance (Min)
at900C ohm-cm 35x1012
at27OC ohm-cm 1500 x 1012
13. Oxidation stability
a) Neutralisation value
(Max) mg/KOH/g 0.4
b) Total sludge after
oxidation (Max) mg/KOH/g 0.10%
14. Ageing characteristics
after accelerated ageing
(open beaker method
with copper catalyst).
a) Resistivity (Min)
at 900C ohm-cm 0.2x 1012
at 270C ohm-cm 2.5 x 1012
b) Tan δ at 90°C (Max) 0.2
c) Total acidity (Max) mg/KOH/g 0.05
d) Sludge content by weight (Max) 0.05%
15 Presence of oxidation Oil shall not contain
inhibitor oxidation inhibitor
Note: Methods of test shall be as per IS: 335

39 Printed at Anupam Mudran Bhopal Ph: 9425025574


2.4.2 SUPPLY AND TESTING
The transformer oil is despatched directly to site from oil refinery. The
oil is thoroughly inspected and tested at oil supplier's works in presence of
BHEL and/or customer's representative or their authorised representatives.
Test certificate giving values obtained for all characteristics is issued.
2.4.3 HANDLING
Transformer oil should be carefully handled at site to ensure satisfactory
service. Drums used for transport and storage should be kept under cover. In
practice owing to contamination in the containers, difficulty may be
experienced in maintaining the purity of the oil when it is transferred from
one vessel to another, and once a vessel or drum has been filled with moist
oil it is extremely difficult to clean. Drums should be clearly marked to indicate
whether they are for clean or for dirty oil and should be reserved for the type
indicated.
Oil drums should bestored at site in horizontal position with its bung at
45 degree downwards from the horizontal so that ingress of moisture is
prevented. It is always recognized that storage of oil in drums is not always
satisfactory, particularly when oil is stored in drums which have been bent
or otherwise damaged in transit or storage, and the transfer of oil from such
containers to electrical equipment should normally be through a suitable
treatment plant.
In substations with fixed oil handling equipment like oil storage tank,
the pipe work from the clean oil tank to the electrical apparatus should be
kept clean and free from moisture. Where portable oil handling equipment is
used, flexible pipe work and hand pump should be carefully inspected to
ensure that they are free from dirt and water and should be flushed with
clean oil before use. If the clean oil is from drums, it should have been
recently tested and filling oritices of the drums should be clean. Hoses used
for clean oil and dirty oil should be clearly marked and provided with plugs
for sealing the ends when not in use..
Special care must be taken for oil filtration machine, which is used
during treatment of oil. It is to be ensurd that there is on residual quantity of
oil left in oil filtration machine. The paper filters or centrifuges used with
filtration machine shall be cleaned or replaced as per supplier's
recommendation. The pipe/hoses used with filtration machine should be
properly blanked after use.
Before using oil tankers and filtration plant for handling of oil, the
internals/chambers need to be thoroughly cleaned using good transformer oil
so that the residual of earlier used chemical/oil is removed totally.
2.4.4 RECONDITIONING
Transformer oil is usually contaminated during handling, transport and
storage due to ingress of moisture and solid impurities. Hence, oil shall be
vacuum filtered separately at 50 0C to 60 °C using a suitable filtration machine
and a spare clean tank before filling in the transformer. Details of filtration are
given in Clause 13 of IS:1866. Oil treatment shall be terminated when the
following parameters are attained.

41 Printed at Anupam Mudran Bhopal Ph: 9425025574


TABLE 2.1
kV Class of transformer Recommended Permissible limit
Electric Strength Moisture Content
(BDV) in kV (Min) ppm (Max)
Upto 145 60 20
245 65 15
420 70 15

Storage tank shall be as per typical arrangement shown in Fig 2.2


Electric strength and moisture content shall be determined following
the test procedure of IS: 335.
2.5 OIL FILLING UNDER VACUUM
2.5.1 APPLICATION
Transformers and Reactors with vacuum-proof tanks shall be filled with
oil according to this method.
2.5.2 STORING TIME
Generally it applies that Transformers and reactors which during transport
are filled with dry nitrogen on arrival at the site shall be evacuated and oil
filled. Before storing, the equipment shall be inspected according to the
directions given in Clause 2.1 "Reception and assembling of transformer/reactor
despatched partly dissembled and filled with nitrogen". During the storing
time, overpressure shall be maintained, and nitrogen consumption checked
according Clause 2.2.
2.5.3 FLOW CHART FOR HANDLING
In Annexure 2.1 is given a flow chart of handling procedures. The pressure
should be measured at different times. The pressure is OK if it is maintained
according to instructions given in Clause 2.2. Reference is also drawn to para
9.0 of IS: 1866 regarding handling and filling of oil.
2.5.4 UNITS
Annexure 2.1 gives the relation between different units.

43 Printed at Anupam Mudran Bhopal Ph: 9425025574


2.5.5 EVACUATION
The transformer tank (excluding cooler bank & conservator) shall be
evacuated to a pressure of 1.00 torr. max. The pressure shall be maintained
for the time given in Table 2.2.
TABLE 2.2
VACUUM TREATMENT

System Voltage Evacuate and hold Standing time after oil


vacuum for circulation before
application of voltage
kV hours hours
Upto 145 12 12
145 & upto 420 24 48
Above 420 36 120

The equipment required for vacuum treatment and oil-filling under vacuum
should generally be as per Annexure 2.2. The transformer tank and electrical
terminals shall be earthed for safety reasons.
No electrical test on the Transformer is permitted during the evacuation.
Fig. 2.3 shows a typical example of pipe work and valve positioning.
Oil conservators are not evacuated. Valve 7 shall be closed. Valve 6
shall be open unless a breather is fitted.
2.5.6 OIL FILLING
2.5.6.1 OIL QUALITY
The transformer/reactor shall be filled under vacuum with oil which has
been purified and degassed according to Clause 2.4
2.5.6.2 OIL FILLING IN MAIN TANK
The oil shall be heated to a temperature of 500- 60°C measured at the
filter outlet valve. The pressure during the filling shall be max. 1 torr. During
the oil-filling, a transparent plastic tube (5) can be used as an oil-level gauge.
The tube which should be a wall thickness of 5-8 mm, may be connected to a
top and a bottom valve on the transformer.
Oil-filling of the tank is done through valve (12) at a low level on the
transformer and at a maximum rate of 4-5 kL/hour. The pressure in the oil
pipes shall be kept positive and shall be checked by a manometer 13 (if
provided). When the oil-level has reached about 50 mm below the cover/the
vacuum pump is stopped it is preferred that dry nitrogen is introduced in the
tank by opening valve (8). Valve (7) is then opened .and valve (6) closed and
the filling is continued in tank and conservator until the correct oil- level has
been reached in the conservator.
Conservator supplied with rubber air cell shall be filled according Clause
2.6. For oil filling in diverter switch assembly of a OLTC refer leaflet (Vol.1).

45 Printed at Anupam Mudran Bhopal Ph: 9425025574


Separate vacuum-proof cooler system/radiators can be evacuated for
about 1-2 hours and filled separately with purified and degassed oil. The oil is
then circulated through the vacuum filter at least twice via drain valves as
near as possible to the transformer. When the oil circulation has been
completed the valves between coolers and main tank shall be opened.
Care should be taken to keep all air release plugs and valves open to
allow escape of trapped air during oil filling operation. These valves/plugs
should be closed after completion of oil filling.
2.5.7 HOT OIL CIRCULATION/ DRYING OUT
To facilitate oil-penetration and absorption of possible gas bubbles, the
temperature of transformer shall-after completed oil-filling-be increased by
circulating the oil through the vacuum filter and with circulation direction
according to Fig. 2.4.
The oil will be circulated through a high vacuum filter machine at 55OC
to 60OC of transformer oil temperature for minimum 3 days and record the IR
value '2' hourly. Also record the IR value along with temperature, vacuum of
m/c & IR value till oil parameter achieved as per table 2.3 Polarisation Index
should not be less than 1.5.
TABLE 2.3
kV Class of Recommended Permissible Limits
Transformer
Electric Moisture Resistivity * Tan delta*
Strength Content at 90oC at 90oC
(BDV) in ppm (Max) (Ohm-cm)
kV (min)

Upto 72.5 40 25 1x1012 0.05


145 50 20 1x1012 0.05
245 and 420 60 15 1x1012 0.05

* Subject to availability of testing facility at site.


Method of test for Electric Strength and moisture content shall be as
per IS:335.
CAUTION:
The temperature during oil circulation should not increase beyond 70oC
otherwise this may cause oxidation of oil.
2.5.7.1 SAMPLING
Oil sampling at various stages shall be done in accordance with IS:
6855. when samples are taken from transformer tank, oil will be drawn from
bottom of the tank. When it is desired to know gas content and composition
of dissolved gases in transformer oil before commissioning for reference
purposes (required for interpretation of Dissolved Gas Analysis results during
service), sampling shall be done as per IS 9434.

47 Printed at Anupam Mudran Bhopal Ph: 9425025574


2.5.8 STANDING TIME
Standing time is the time between 'finished oil circulation' and
'energisation'. The time appears from table 2.2.
2.5.9 FINAL OIL FILLING OF TRANSFORMERS/REACTORS DESPATCHED
OIL FILLED.
Smaller transformers/reactors are often factory-filled with degassed oil
up to about 10% below the cover and transported in this condition. The final
filling up to the correct level in the conservator is made at site.
2.5.9.1 TRANSFORMERS/REACTORS WITH SYSTEM VOL TAGE < 36 KV
Previously degassed oil (e.g., at the factory) stored in tight drums may
be used for the filling. Check the dielectric strength of the oil which should be
as per Clause 2.4.4. If accepted, the oil is pumped into the conservator and
in this way fed into the transformer. To prevent any free water in the drums
from entering the reactor the opening of the suction tube must lie 0.1 m
above the lowest point in the drum. A suitable valve on the cover and/or
valves or upper tightening nuts at the bushings have to be opened for complete
removal of air below the cover and in the bushings. When the oil is seeping
out at these points, shut the valves and tighten the nuts at the bushings.
2.5.9.2 TRANSFORMERS/REACTORS WITH SYSTEM VOLTAGE > 36 KV
The filling is performed as described above, but at least a paper filter
must be used for drying the oil.
2.6 OIL FILLING INSTRUCTIONS FOR CONSERVATORS WITH AIR CELL
2.6.1 INTRODUCTION
In all transformers specially in high voltage class, maintenance of
insulating oil notably its dielectric property forms one of the determining factors
of reliability of equipment in service. Oxidation and contamination of
transformers/reactor oil can be avoided in a simple and effective way by use
of above oil preservation system. The complete system is known as
"Conservator with Air Cell".
In this oil preservation system a flexible air cell made of oil resistant
nitrile rubber is placed inside the conservator and floats on the oil surface. The
air cell inflates or deflates as the oil level in the conservator falls or rises
depending on the ambient temperature and load on the reactor. The inside of
the rubber bag (Air Cell) is put into communication with atmosphere by means
of a silica gel breather which ensures dry atmosphere inside the air cell. In
addition to the above this system provides following advantages.
(i) It avoids saturation of absorbed gases.
(ii) As no gas is used in this system, which operates at constant
pressure, this formation of gas bubbles at low ambient temperature
and load is eliminated. The system thus preserves the oil quality
particularly its dielectric properties.

49 Printed at Anupam Mudran Bhopal Ph: 9425025574


The conservator with air cell is provided with a magnetic oil gauge
having one electrical contact. The indication shown on the dial physically
corresponds to the oil level in the conservator which is due to balance of
static pressure between the oil of the conservator and the atmospheric air
inside the air cell. This system is also provided sometimes with a set of
pressure and vacuum valves. These valves operate to pass either oil or air in
the event of over filling or under filling the conservator during installation.
2.6.2 DESCRIPTION OF OPERATION
Figure 2.5 indicates the general arrangement of oil preservation system,
The oil connection between conservator and transformer tank is made through
Buchholz relay and valves are provided in between.
The flexible air cell is connected to the top of the conservator through
gasket joint. Under normal condition air cell is completely surrounded by oil
and floats in the conservator. The air cell inflates/deflates as the oil volume
changes. The float of the MOG which is always in contact with under side of
the air cell moves up and down and indicates the oil level. The cell will sink in
the remote event if it is damaged and MOG alarm will operate. The conservator
then functions as a conventional conservator without effecting the performance
of the transformers/reactor.
2.6.3 INSTALLATION
This system is shipped separately from main tank. The air cell is shipped
fitted in the conservator. A low positive pressure of less than .07 kg/sq.cm (1
psi) is maintained to avoid excessive movement of air cell in the conservator
during transit. MOG is also shipped fitted on the conservator. Install the
conservator and associate parts except breather as per transformers/reactor
outline drawings and assemble oil pipe work.
2.6.4 OIL FILLING
The following procedure is recommended.
(i) Close and blank the valve (14) to isolate the conservator from main
tank. Fill the oil in transformer under vacuum upto Buchholz level as
per instructions given else where. '
(ii) After filling the oil in transformer and breaking the vacuum, oil can
be filled in the conservator either through reactor or by drain valve
(4).
(iii) Remove the inspection cover (11) provided on the side of the
conservator and check the air cell assuring that it is inflated. The air
cell must remain in fully inflated condition during oil filling operation.
If the air cell is found deflated fit the inspection cover and inflate the
air cell with dry air/nitrogen gas to 0.035 kg/sq.cm max. through
connection (8). A gauge may be put by removing plug (10). After
filling close these connections.
(iv) Remove air release plugs (5) (6) and (7) provided on top of the
conservator.

51 Printed at Anupam Mudran Bhopal Ph: 9425025574


(v) Slowly pump the oil through the main reactor/drain valve (4).
Temporarily stop filling operation when oil starts coming from opening
(5) and (6) after ensuring that no air bubbles come out through
these air release holes. Fit the two air release plugs.
(vi) Continue oil filling till oil start coming from air release plug (7) stop
oil after ensuring that no air bubbles come out. Fit the plug (7).
(vii) Now release the air pressure held inside the air cell from point (8)
and continue oil filling until magnetic oil gauge (3) indicates 35°Clevel.
(viii) Remove oil pump and connect air cell to breather (9) from point (8).
Also remove pressure gauge and put plug (10).
(ix) The system is now properly filled. Air release plugs (5), (6) and (7)
are fitted in normal operation.
2.6.5 PRECAUTIONS
(i) Oil filling in the conservator and also draining whenever required
must be done very slowly. During oil filling, pressure in the air ce]l
should not exceed 0.1kg/sq.cm (1.5 psi).
(ii) If a pressure or vacuum is ever applied to the main reactor tank the
conservator must be disconnected and a blanking plate fitted on
shut off valve.
(iii) Do not weld on conservator to avoid damage to the air cell.
(iv) Once all the air has been driven out during oil filling in the conservator
do not remove air release plugs (5), (6) and (7). Otherwise air will be
sucked inside the conservator.
2.6.6 MAINTENANCE
Little maintenance work will normally be required except routine visual
inspection. However, it is desirable to check the breather opening to ensure it
is not blocked. Further silicagel should be regenerated/replaced when its colour
changes from blue to pink.
2.6.7 AIR CELL
Air cell is made from Nylon fabric coated with Nitrile rubber, In the
event it becomes necessary to replace or test the air cell for leaks the following
method is recommended.
(i) De-energise the transformers/reactor.
(ii) Isolate the conservator by closing the valves (14).
(iii) Drain the oil from the conservator through the valve (4) by removing
air release plugs (5) and (6).
(iv) Remove inspection cover (11) if necessary, Install the pressure gauge
on point (10).

53 Printed at Anupam Mudran Bhopal Ph: 9425025574


(v) Pressurise the air cell (2) by dry air/nitrogen to a max. pressure of
1.5 psi and seal. Check the pressure for 6 hours.
(vi) If leaks are found, air cell to be repaired by patching or replaced by a
new air cell.
(vii) For taking out the air cell from conservator, remove the air cell flange
and loops from hooks provided on inside of the conservator top.
Collapse the air cell slowly and fold, remove it from conservator
very carefully.
(viii) In the event air cell is not available immediately, conservator may be
used as a conventional conservator.
2.6.8 OIL PRESSURE TEST
Oil pressure test on fully erected Transformer/Reactor to be conducted
as per annexure 2.3 before hot oil circulation.
2.7 UNTANKING OF ACTIVE PART
2.7.1 GENERAL
If for some reason it becomes necessary to untank the active part (core
and windings) of a large reactor/transformer, it ought to be done under
supervision by BHEL erectors. Universal instruction for the untanking procedure
cannot be given, as the design practices of large equipment vary. The following
general directions are, however, applicable in most cases.
The untanking must be done indoors. If there is no suitable hall available,
lifting can be done in the temporarily arranged room. e.g. a tent. The oil & the
internal parts of the transformer must not in any case be exposed to rain or
humidity.
In case of bell shaped transformer, only bell cover is lifted for access to
active part.
2.7.2 OIL DRAINAGE
Drain off the oil from the transformers/reactor either partly or completely.
2.7.3 DISCONNECTING
Disconnect leads to bushings, current transformers, winding temperature
devices and earthing leads between active part and cover or tank side.
Disconnections mentioned above can usually be made through handholes
in cover or tank side.
2.7.4 REMOVAL
Remove all large bushings, cover mounted conservator and lightning
arrestors (if provided). Break all connections between cover and tank-piping to
oil conservator and cooler thermometers etc.
Remove the cover bolts. If the cover is welded to the tank flange, free
the cover according to directions given in Clause 2.9.

55 Printed at Anupam Mudran Bhopal Ph: 9425025574


2.7.4.1 COVER
When lifting the cover use the cover-lifting eyes which are designed for
a minimum angle of 60 degrees between sling branches and the horizontal
plane. The length of the sling should therefore be sufficient for at least this
angle.
Place the cover on suitable wooden supports and in such a way that
thermometer pockets, small bushing etc. underneath the cover are not damaged.
No grinding or cleaning up of the tank flange is to be carried out before
the active part is lifted out of the tank.
2.7.4.2 UNTANKING
Loosen locking devices, if any, between top core clamps and tank side.
Lift the active part by means of lifting eyes or lifting lugs provided on
the top core clamps. The untanking height is shown on the outline drawing.
To avoid damages on the active part it is important that it is centered carefully
in the tank during lifting procedure.
After untanking, place the active part on a horizontal foundation.
2.7.5 RETANKING
Grinding or/and cleaning up of the tank flange has to be done before the
active part is lowered into the tank. Check that the tank inside is free from
contaminations.
Retanking is then done in the reverse order that is outlined above. Note
that guiding pins or blocks are welded to the tank bottom to prevent the
active part from moving in the tank. When lowering the active part, check that
it fits exactly the guiding pins or blocks.
2.7.6 REASSEMBLING
Wipe the underside of the cover free from any dirt or foreign matter
before lifting it into correct position above the reactor tank. Lower the cover
the last few inches exactly into position without sliding on the gaskets.
Reassemble bolts nuts of supporting devices. Weld the cover when the
welded construction is used. Reassemble Bushings, conservator etc., and
reconnect pipings, leads to bushings, current transformers, etc. Reassemble
inspection covers.
After the transformer is completely assembled, it may be necessary to
dry it before oil fining- see clause 2.5.
2.8 MOUNTING OF GASKETS
2.8.1 The gaskets have a circular/flat cross-section and are made of oil
and heat- resistant synthetic nitrile rubber/nitrile rubber bonded cork. For small
gaskets, O-rings are used with diameter 3,5.0 or 8.0 mm, while round rubber
cords with diameters 8,12 or 19 mm are used for large gaskets.

57 Printed at Anupam Mudran Bhopal Ph: 9425025574


The groove is normally milled or turned, but for large flanges the groove
is created by means of steel bars welded on top of the flange. The width of
the groove is slightly smaller than the cross-section diameter of the gasket in
order to keep the gasket in position during the assembling work.
Opened sealing joints may be sealed again using the same gasket
provided that the same has not been damaged. If the gasket has become
hard or got small cracks on the surface, it is recommended to change the
gasket by a new one.
When handling and lifting flange, cover etc. with gasket grooves, care
should be taken when using tools and lifting devices to avoid that the grooves
getting damaged or deformed.
Before assembling of groove gaskets, it is checked that the grooves and
contact-surface in the joint are free from foreign particles and that the paint is
free from thick coatings, trickles and drops.
When assembling the rubber cord in the groove, the cord length shall be
continuous . The gasket is given a small surplus length to compensate for
shrinkage.
The gasket is pressed down into the groove without stretching or
slackening.
To prevent the gasket from falling from the groove on vertical surfaces,
the gasket may be spot-glued to the bottom of the groove.
The screws in the sealing joint shall be tightened so that an even pressure
is obtained on the gasket. This is obtained preferably by means of a moment
spanner. Rubber gaskets in grooves need not normally be re-tightened.
Above description is followed generally for turrets, inspection cover
etc. For main tank rim joint, LV turrets of Generator Transformers where metallic
stops are provided, nitrile rubber bonded cork is used, for which following
instructions shall apply.
2.8.2 (i) Gaskets when supplied loose, have no bolt holes in them. They
are usually cut to the size and shape required, although they may
be supplied as straight, angled pieces from which complete gaskets
can be built up.
(ii) Scarfed joints should be used. A 40 mm scarf in 5 mm thick
material is recommended. Joints should be located away from
corners and bolt holes, and should be well bonded, smooth and
free from local thickening. Neoprene solution is used as an adhesive
for joints.
(iii) Gaskets are best stored in hermetically sealed containers in a cool
place. They must be protected from damp, oil and grease-
(iv) To make a gasket joint, first clean the metal surfaces ensuring
that they are free from oil, rust, scale etc. Using one of the flanges
as a template, punch the necessary bolt holes. Insert the bolts
and tighten the bolts sequentially, a little every time so that uniform
pressure is exerted on the gasket until the gasket is compressed
to about 2/3 of its original thickness. Joints should not be subjected
to pressure until tightening is complete. If care is taken in making
joints, and in handling the gasket, it is possible to break and re-
make a joint several times, using the same gasket.

59 Printed at Anupam Mudran Bhopal Ph: 9425025574


(v) For making leak proof and good gasket joints, it is necessary
that uniform pressure is achieved all over the gasket after
matching rims/ flanges have been clamped with bolts/studs.
Following instructions be followed for proper tightening of bolts/studs.
a) Tighten lightly the bolts/studs diagonally in the sequence as shown
in the fig. 2.6.
b) Tighten again bolts/studs in the same sequence with the torque
given below :
Bolt/Stud Max. Torque
Size (Kg-M)
M 10 1
M 12 2
M 16 6
M 20 12
M 24 20
M 30 30
In case of metallic stoppers tighten until metal to metal contact is achieved.
c) Do not overtighten, otherwise gasket will get crushed.
2.9 WELDED COVER (IF APPLICABLE)
In order to obtain a good sealing between the transformer tank and the
cover a welded joint is recommended. The welding is performed in a certain
way to permit opening and new welding repeated a number of times. The
chiselling up and re-welding will take about the same time as dismantling and
reassembling of bolted cover .
If the welded cover for any reason has to be removed proceed as follows:
2.9.1 OPENING THE COVER
When opening the cover the welding joint should be removed by a suitable
grinding wheel. The cover should be clamped to the frame by means of G-
clamps to prevent iron chips from penetrating into the tank. Any parts of the
weld which may possibly remain on the tank flange should be removed by a
chisel to enable a good result of the re-welding.
2.9.2 REASSEMBLY
When fitting the cover again cork-rubber gaskets, 25 x 5 or as specified
are fitted on the tank flange, see fig. 2.7.
The gaskets are kept in the correct position with glue base on rubber
base. The cover should be clamped to the tank flange by means of G-clamps
evenly distributed along the flange with about 600 mm spacing. Tack welding
is carried out with about 100 mm spacing. An extra G-clamp is used during
the tack welding and is moved along the flange during the progress of the
work. The continuous weld is then applied. Finally the weld should be cleaned
and painted.
WARNING
When welding, a fire-extinguishing equipment should be available, and
the work supervised by fire-protection personnel.

61 Printed at Anupam Mudran Bhopal Ph: 9425025574


2.10 EARTHING OF ACTIVE PART AND CORE INSULATION TEST
2.10.1 REACTORS
The ground-connection terminals for the reactor active part are located
in a box at the tank end, close to the bottom. Please see fig. 2.8.
The terminal are protected by a cover. The cover can be removed with
the tank oil- filled.
The terminal box contains a terminal block with three terminals.
-The terminal marked CL is connected to the core laminations.
-The terminal marked CC is connected to the core clamps.
-The terminal marked G is connected to ground (the tank).
For the core-insulation test, remove the cover. Disconnect the closing
link that connects the two terminals CL-G. Use perferably 1000V megga
direct voltage between CL and CC + G. The tank shall be grounded during
the test. The insulation value after 1 min. test- time shall be minimum 1000
kohms. There is no general requirement on the insulation level CC-G .
2.10.2 TRANSFORMERS
For checking core insulation incase of transformers refer Fig. 2.9 for
connection details.
2.11 TOUCH-UP PAINTING
2.11.1 PURPOSE
A basic principle at touch-up painting should be to restore a damaged
paint coat on a surface to the same quality and finish as of the surrounding
surface. The touch-up painting should be limited to a surface as small as
possible.
2.11.2 CLEANING
Both damaged and surrounding surface should be cleaned so that all
grease, dust and other impurities will be removed.
2.11.3 GRINDING OF DAMAGES
Large damages and defects are ground by means of a coarse abrasive
paper, e.g. No.100. The surface is then ground with a finer paper in connection
with the damage, e.g. 150 or 180. Damages that are limited to the paint coat
only, should be ground off completely at which glazing can be avoided.
2.11.4 PRIMER PAINTING
Damages on the primer paint and grinding down to the steel surface
should be painted with two coats of anti-corrosive priming paint.

63 Printed at Anupam Mudran Bhopal Ph: 9425025574


2.11.5 FINISHING PAINT
Two coats of finishing paint should be applied as per specification which
is generally light grey shade No.631 of lS: 5. Please refer Table 2.4 for suppliers
reference.

TABLE 2.4

SI Suppliers Suppliers Reference


No. Name Anti corrosive High Quality full Oil resistant air
priming paint for gloss outdoor drying synthetic
outside painting finishing paint enamel

1. Addison IS 2907 Shade 631 of IS 5 jasmine yellow


shade no.397
of IS 5 for
inside painting
2. Asian 32/F 3257 Apcolite synthetic -
3. Berger BPL Red oxide Luxol 3H1 Glass -
Zinc Chromate synthetic enamel -
4. Alkali 32-781 Dulux synthetic -
Chemicals enamel
5. Garware PR-4460 - -
6. Shalimar Sample No. 5999/1 Superlac synthetic 7377/1

7. Goodlass 205/023 500 Series 548/101

65 Printed at Anupam Mudran Bhopal Ph: 9425025574


ANNEXURE 2.1
FLOW CHART FOR HANDLING

ARRIVAL AT
SITE

MEASUREMENT OF
PRESSURE

ASSEMBLY

EVACUATION AND OIL


FILLING

OIL-CIRCULATION
THROUGH FILTER

STANDING TIME
ACCORDING TO TABLE 2.2.

VOLTAGE APPLICATION

Relationship between different units


1 bar = 105 Pa = 750 Torr = 14.5 psi = 1.02 kg/sq.cm
1 Torr = 1.33 mbar = 0.133 kPa
1 kPa = 103 Pa = 10 mbar = 7.501 Torr
1 MPa = 106 Pa

Force Volume
1 kp = 9.807 N 11itre = 0.26 US gallons
1 US gallon = 3.781itres
11itre = 0.22 Imp gallons
1 Imp = 4.551itres gallon

Temperature
C = 5 x (F-32)/9
F = 9 x (C+32)/5

67 Printed at Anupam Mudran Bhopal Ph: 9425025574


ANNEXURE 2.2
EQUIPMENT FOR OIL-FILLING UNDER VACUUM
(i) High-vacuum 2 stage oil filtration plant provided with thermostat-
controlled oil heaters and vacuum-proof hoses with independant
vacuum pumping system for tank evacuation. Capacity: 6000 lph.
(ii) Oil-storage tanks provided with silica-gel breathers and inlet/outlet
valves for oil circulation. Recommended capacity 20 kL -30 kL (Clause
2.4)
(iii) Vacuum gauges provided in filtration plant.
(iv) Equipment for measurement of electric strength (BDV) of oil- 100 kV
set.
(v) Equipment for moisture content of oil.
(vi) Equipment for measurement of Resistivity and Tan delta at 90o C.
(vii) Oil-sampling cans or bottles.
(viii) Transparent vacuum-proof tubes for checking of oil-level during oil
filling.
(ix) Valves, fittings, gaskets etc.
(x) Dry nitrogen cylinders.

69 Printed at Anupam Mudran Bhopal Ph: 9425025574


(1) HAULAGE HOLE- JÉÓSÉxÉä Eäò ʱɪÉä ÊUôpù
(2) JACKING LUG- VÉäËEòMÉ ±ÉMÉ
(3) JACK- VÉäEò
(4) RLY. WELL WAGON- ®äú±É´Éä ´Éä±É ´ÉäMÉxÉ
(5) 90 LB. RAIL - 90 B±É ¤ÉÒ ®äú±É
(6) SUPPORTS TO PREVENT SLIPPING- Ê¡òºÉ±ÉxÉ ºÉä ¤ÉSÉxÉä Eäò ʱɪÉä +ÉvÉÉ®ú
(7) GROUND LEVEL- ¦ÉÚ欃 ºÉiɽþ
(8) THESE SLEEPERS WILL BE PUT AT SITE AT THE TIME OF UNLOADING- <xÉ º±ÉÒ{É®úÉå EòÉä =iÉÉ®úxÉä Eäò
ºÉ¨ÉªÉ ºÉÉ<]õ {É®ú ®úJÉå

70
Fig. 2.1 Typical Unloading Arrangement of the Transformer
ÊSÉjÉ 2.1 ]ÅõÉƺɡòɨÉÇ®ú EòÉä =iÉÉ®úxÉä EòÒ ´ªÉ´ÉºlÉÉ EòÉ xɨÉÚxÉÉ

Printed at Anupam Mudran Bhopal Ph: 9425025574


71
1. OIL SAMPLING VALVE 15 mm 2 Nos. iÉä±É ºÉä¨{É˱ÉMÉ ´Éɱ´É 15 ʨɨÉÒ. 2 xÉÆ.
2. FILLTER VALVE 50 mm 2 Nos. Ê¡ò±]õ®ú ´Éɱ´É 50 ʨɨÉÒ. 2 xÉÆ.
3. DRAIN VALVE 80 mm 1 No. bÅä÷xÉ ´Éɱ´É 80 ʨɨÉÒ. 1 xÉÆ.
4. DRAIN PLUG 15 mm 1 No. bÅä÷xÉ {±ÉMÉ 15 ʨɨÉÒ. 1 xÉÆ.
5. MAN HOLE 1 No. ¨ÉèxÉ ½þɱä É 1 xÉÆ.
6. VACUUM APPLICATION VALVE 25 mm 1 No. ´ÉäCªÉÚ¨É ´Éɱ´É 25 ʨɨÉÒ. 1 xÉÆ.
7. BUSHING MOUNTING HOLES WITH BLANKING FLANGE 3 Nos.
¤ÉÖ˶ÉMÉ ±ÉMÉÉxÉä Eäò ʱɪÉä ÊUôpù ¤±ÉåËEòMÉ }±ÉéVÉ ºÉʽþiÉ 3 xÉÆ. Fig. 2.2 Typical Arrangement of oil Storage tank
ÊSÉjÉ 2.2 iÉä±É ºÉÆOɽþ Eò®úxÉä EòÒ ]ÆõEòÒ EòÉ xɨÉÚxÉÉ

Printed at Anupam Mudran Bhopal Ph: 9425025574


1. Oil-filtering plant with heater (1) ½þÒ]õ®ú Eäò ºÉÉlÉ iÉä±É Ê¡ò±]õË®úMÉ {±ÉÉÆ]õ
2. Oil-storage tank (2) iÉä±É ºÉÆOɽþ Eò®úxÉä Eäò ʱɪÉä ]åõEò
3. High-vacuum pump (3) =SSÉ ÊxÉ´ÉÉÇiÉ {ɨ{É
4. Conservator (4) EòxVÉ®ú´Éä]õ®ú
5. Oil-level indicator (5) iÉä±É-ºiÉ®ú ºÉÚSÉEò
6. Valve (6) ´Éɱ´É
7. Valve (7) ´Éɱ´É
8. Valve (8) ´Éɱ´É
9. Valve (9) ´Éɱ´É
10. Valve (10) ´Éɱ´É
11. Dry-N2 container (11) ¶ÉÖ¹Eò xÉÉ<]ÅõÉäVÉxÉ ºÉÆOɽþEò
12. Valve Fig. 2.3 (12) ´Éɱ´É
13. Manometer ÊSÉjÉ 2.3 (13) ¨ÉäxÉÉä¨ÉÒ]õ®ú

72 Printed at Anupam Mudran Bhopal Ph: 9425025574


TRANSFORMER
REACTOR
VACUUM
]ÅõÉƺɡòɨÉÇ®ú/Ê®úBC]õ®ú ]ÆõEòÒ
FILTER
´ÉèCªÉÚ¨É Ê¡ò±]õ®ú

Fig. 2.4
ÊSÉjÉ 2.4

73 Printed at Anupam Mudran Bhopal Ph: 9425025574


OIL PRESERVATION SYSTEM WITH AIR CELL
+É<±É Ê|ÉVÉ´Éæ¶ÉxÉ ÊºÉº]õ¨É BªÉ®ú ºÉä±É Eäò ºÉÉlÉ

GENERAL ARRANGEMENT
ºÉɨÉÉxªÉ ´ªÉ´ÉºlÉÉ
SL.No. DESCRIPTION Ê´É´É®úhÉ
Gò. ºÉÆ.
1. AIR CELL BªÉ®ú ºÉä±É
2. MAGNETIC OIL GAUGE ¨ÉäMÉxÉäÊ]õEò +É<±É MÉäVÉ
3. BREATHER ¥ÉÒnù®ú
4. DRAIN VALVE bÅä÷xÉ ´Éɱ´É
5. AIR RELEASE PLUGS BªÉ®ú Ê®ú±ÉÒVÉ {±ÉMÉ
6. FLANGE FOR TRANSFORMER CONNECTION ]ÅõÉƺɡòɨÉÇ®ú ºÉä VÉÉäc÷xÉä Eäò ʱɪÉä }±ÉåVÉ
7. AIR CELL SUPPORTING LUGS BªÉ®ú ºÉä±É Eäò +ÉvÉÉ®ú ±ÉMÉ
8. OIL iÉä±É
9. PRESSURE GAUGE CONNECTION (WITH PLUG) |Éä¶É®ú MÉäVÉ EòÉ EòxÉäC¶ÉxÉ ({±ÉMÉ Eäò ºÉÉlÉ)
10. PRESSURE GAUGE |Éä¶É®ú MÉäVÉ
11. BREATHER CONNECTING FLANGE ¥ÉÒnù®ú VÉÉäc÷xÉä ´ÉɱÉÒ }±ÉåVÉ
12. CONSERVATOR END COVER EòxVÉ®ú´Éä]õ®ú Bxb÷ Eò´É®ú

13. INSPECTION COVER <xºÉ{ÉäC¶ÉxÉ Eò´É®ú

Fig. 2.5
ÊSÉjÉ 2.5

74 Printed at Anupam Mudran Bhopal Ph: 9425025574


Fig. 2.6
ÊSÉjÉ 2.6

Fig. 2.7
ÊSÉjÉ 2.7

75 Printed at Anupam Mudran Bhopal Ph: 9425025574


Fig. 2.8
ÊSÉjÉ 2.8

76 Printed at Anupam Mudran Bhopal Ph: 9425025574


Fig. 2.9
ÊSÉjÉ 2.9
NOTE:
1. WHILE DISCONNECTING/EARTHING CONNECTION BETWEEN CORE/YOKE
CLAMP & TANK, REMOVE THE LINK.
1. EòÉä®ú/ªÉÉäEò C±Éä¨{É B´ÉÆ ]ÆõEòÒ EòÉ ¦ÉÚºÉÆ{ÉEÇò ʴɪÉÖHò Eò®úxÉä Eäò ʱÉB ªÉ½þ Eòb÷Ò ½þ]õÉ nåù*
2. WHILE PUTTING IN SERVICE PLACE LINKS IN POSITION.
2. {ÉÊ®úSÉɱÉxÉ Eäò ºÉ¨ÉªÉ ªÉ½þ Eòb÷Ò VÉMɽþ {É®ú ±ÉMÉÉ nåù*

Earthing Connections from core and top yoke clamp.


EòÉä®ú B´ÉÆ ]õÉì{É ªÉÉäEò C±Éä¨{É ºÉä ¦ÉÚºÉÆ{ÉEÇò ªÉÖÊHò

77 Printed at Anupam Mudran Bhopal Ph: 9425025574


ANNEXURE 2.3
PRESSURE TESTING OF TRANSFORMER / REACTORS AT SITE
1. After completion of oil filling, lock PRV and pressurise the air cell
by filling nitrogen/ dry air to 5.0 p.s.i. (0.35 Kg/cm.sq.).
2. Maintain above pressure for at least 12 hours.
3. Inspect all joints for leakage, if any.
4. Record pressure testing as given below.
5. After pressure testing unlock PRV and release the nitrogen/ dry air
pressure of air cell.
NOTE: In case of conventional oil preservation system (without air cell)
pressurise conservator by filling nitrogen/dry air in conservator .

RECORD OF PRESSURE TESTING AT SITE


DATE TIME
1. Date & Time of testing (a) Started on ......... .........

(b) Finished on ......... .........

2. Initial pressure ....................................

3. Pressure after 12 hours ....................................

4. Leakages observed if any YES /NO


location of leakages ....................................

5. If leakages are observed. Same to be arrested and pressure test-


ing is to be repeated.

79 Printed at Anupam Mudran Bhopal Ph: 9425025574


¦ÉÉMÉ-3
Eò¨ÉÒ¶ÉËxÉMÉ

SECTION-3
COMMISSIONING

81 Printed at Anupam Mudran Bhopal Ph: 9425025574


SECTION 3

3 COMMISSIONING
3.1 TESTING AFTER ASSEMBLY OF THE TRANSFORMER/ REACTOR
AT SITE.
After the transformer/reactor has been assembled at site, it shall be
tested in order to check that it has not been damaged during transport and
assembly to such an extent that its future operation will be at risk. Regarding
the performance of the test, refer to the testing method as per standards. The
results of the test shall be documented as detailed in Clause 3.2 "commissioning
checks -Transformers" and Clause 3.3 commissioning checks - Reactors.
3.1.1 APPLICATION OF VOLTAGE
If possible, the voltage should be increased step by step up to rated
voltage. This may be done by connecting the transformer/reactor to a generator
whose voltage is raised slowly. The higher the rated voltage of transformer/
reactor the more important it becomes that the application of the voltage is
done as described. If it is not possible to use a generator, the transformer/
reactor may be connected directly to a live line after ensuring voltage &
frequency are same.
After the first application of voltage, the transformer/reactor shall be
checked carefully (gas relay, temperatures, leakages).
When the transformer/reactor has been is service for some weeks with
normal working temperature, all sealing joints shall be re-tightened.
3.1.2 ENERGISING
Low voltage test carried at site after erection and drying out, shall be
compared with factory test results. In case of any difference in values BHEL
must be informed & clearance to be obtained for energisation. DGA of
transformer oil shall be carried out after 24 hrs of commissioning & the
value should be informed to BHEL. The initial magnetising current at the time
of switching will be very high. This depends on the particular moment in the
cycle. The transformer should always be soaked for few hours under constant
care i.e. keep it energized. If the breaker trips on differential, Buchholz or
any other device, the cause must be investigated before re-energising the
transformer or reactor. After successful charging, performance of the
transformer/reactor , OTI, WTI readings should be monitored for 24 hours
and ensured that they are as per loading.
3.1.3 ANALYSIS OF GAS
The gas collected in the relay will help to identify the nature of the
fault. It is suggested that the following checks are made at convenient
intervals or following the indication of accumulation of gas through alarm
signal.
1. Rate of gas collection- The greater the rate of gas collection, the more
severe is the nature of the developing fault.
2. Colour of the gas helps in finding the affected material as follows.

83 Printed at Anupam Mudran Bhopal Ph: 9425025574


Colour Identification

White Gas of decomposed paper and cloth insulation.

Yellow Gas of decomposed wood insulation.

Grey Gas of overheated oil due to burning of iron portion

Black Gas of decomposed oil due to electric arc.

3. Combustibility of Gas- A small amount of gas drawn through the top


pet cock if brightens the test flame, then the gas is combustible.
Incombustible gas indicates air.

4. Chemical Analysis of the Gas -The principles of working gas analyzing


equipment is illustrated in the figure 3.1.
Two solutions are prepared as detailed below and best results are obtained
with freshly prepared solution.
Solution 1: 5 gms of silver nitrate (AgNO3) dissolved in 100 ml
distilled water.
Solution 2: A week solution of ammonia in water is slowly added to
100 ml of solution 1, until a white curdled precipitate
which forms first disappears in the mixture.
The gas analyser loaded with these solution is then connected to the
top pet cock. Small quantities of gas collected in the relay is allowed to pass
through the two solutions as illustrated.
The results are identified as follows:
1. Both solutions are clear : Gas is air .

2. Solution 1 -White precipitate


turning brown on exposure to
sunlight : Gas of oil decomposition.

3. Solution 2 -turning to
Dark brown precipitate : Gas of decomposed paper,
cotton or wood insulation.

Note: THE ABOVE INFORMATION ON GAS ANALYSIS ARE AS


DETAILED IN IS:3638-1966. PLEASE REFER IS:3638-1966 FOR
ALTERNATIVE METHOD OF CHEMICAL ANALYSIS.
3.2 COMMISSIONING CHECKS -TRANSFORMER
3.2.0 SCOPE
This schedule covers the tests to be done at site after transformer has
been installed and dried out.

85 Printed at Anupam Mudran Bhopal Ph: 9425025574


3.2.1 GENERAL
Check the following:
Sl.No. Description
1. Breather Silicagel (Blue when dry)
2. Oil in the Breather housing cup.
3. All valves for their correct opening and closing sequence.
4. Oil level in conservator tank.
5. Oil in cooling system.
6. Oil level in bushings.
7. Release air, wherever necessary.
8. Cooling accessories (Pump motors, Fan motors etc.) for direction and O/L
setting.
9. Buchholz, oil level indicator, pressure gauges, thermometer,Temp. indicators
etc. for operation.
10. Earthing of main tank M.Box T/C driving gear, diverter, Pump Fan motor etc.
11. Neutral earthing.
12. Earth Resistance of Electrodes.
13. Earthing of bushing test tap.
14. Check oil leakage for 24 hrs.
15. Check Auxiliary circuit voltage (415 V).
16. Calibration of OTI/WTI with hot oil.
17. Check Working of WTI/RTD repeaters at control room.
18. IR of core to earth.
3.2.2 INSULATION RESISTANCE TEST
Sl. Description Date Time Megger IR Temp. Remarks
No. in Hrs used Value oC
1. Control wiring (Not less
2. Tap Changer than 500 V
a) Motor megger)
b) Control
3. Cooling system
a) Motor Fan
b) Motor pump
c) Control wiring
4. Main winding
a) HV/E+LV
(Not less
b) IV/E+HV than 1000V
c) LV/E+HV+IV megger)
d) HV/IV
e) IV/LV
f) HV/LV
NOTE :
(1) While checking these values no external line, lightning arrestors etc. should
be in circuit.
(2) Special care should always be taken while meggering the transformer
winding to ensure that there is no leakage in the leads.

87 Printed at Anupam Mudran Bhopal Ph: 9425025574


3.2.3 OIL CHARACTERISTICS
Take necessary precaution (regarding rinsing the bottle, cleaning hand,
air bubble etc.) while withdrawing the samples (Please refer IS:6855). Each
sample should be free of air bubbles and should not be tested when it is hot
The sample should satisfy IS:1866.
Sl. Oil Sample Time & Condition Moisture Break Resisti Tan- Rem
No. From Date Time Weather in PPM down vity at 90oC arks
Voltage at 90oC
in kV (in ohm
-cm)
1. Tank
Top Sample
Bottom Sample
2. Cooling system
Top Sample
Bottom Sample
3. OLTC Diverter
(each phase)

3.2.4 TESTS ON CT
1. Ratio
2. Polarity
3. Magnetising current
4. IR value.
3.2.5 ON LOAD TAP CHANGER

Sl. Description Date Observation Remarks


No.
1. Visual Inspection of equipment.
2. Hand operation on all taps.
3. Complete wiring of the circuits.
4. Limit Switch
5. Over running device.
6. Remote Panel wiring.
7. Over load Device of Driving Motor.
8. Local Operation (Electrical).
9. Remote Operation (Electrical).
10. Tap Position Indicator.
11. Step by step contractor.
12. Out of Step Relay.
Note : While operating the mechanism on Electrical Control, check once again
limit switches, step by step contractor, over running device etc. for
their actual operation and ensure that they are functioning properly.

89 Printed at Anupam Mudran Bhopal Ph: 9425025574


3.2.6 OFF CIRCUIT TAP SWITCH
Tap switch handle should not be left halfway and/or unlocked.
3.2.7 CONTINUITY TEST
Continuity between line and neutral (for neutral end TC) or line to line
(for line end TC) with multimeter on all taps and phases to be confirmed.
3.2.8 MEASUREMENT OF WINDING RESISTANCE:

Winding Tap No. Phase U Phase V Phase W Temp Remarks


HV 1
Winding 2
3
4
5
6
7
8
9(a)
9(b)
9(c)
10
11
12
13
14
15
16
17

IV
Winding

LV
Winding

91 Printed at Anupam Mudran Bhopal Ph: 9425025574


3.2.9 VOLTAGE RATIO TEST
Ratio on all taps is to be checked by hand operation only. This can be
done any time, once the tap changer is completely erected. Start the tap
changer from lowest tap and then go on increasing tap by tap while checking
the value instead of starting from normal tap.
Tap Voltage applied Voltage Measured Ratio obtained Remarks
Nos.

1.
2.
3.
4.
5.
6.
7.
8.
9. (a)
9. (b)
9. (c)
10.
11.
12.
13.
14.
15.
16.
17.

3.2.10 MAGNETISATION CURRENT


a) Apply 3 phase 415 V on HV Terminals and keep LV open.
Voltage Applied Current measured Remarks
U-V Volts U phase m Amps
V-W Volts V phase m Amps
U-W Volts W phase m Amps
Note: In case of single phase transformer, apply 230 V, 1 phase supply
between line terminal and earth.
b) Apply 3 phase 415 V on LV terminals and keep HV open.

u-v volts u phase m Amps


v-w volts v phase m Amps
u-w volts w phase m Amps

Note: In case of single phase transformer apply 230 V, 1 phase between


two line terminals.

93 Printed at Anupam Mudran Bhopal Ph: 9425025574


3.2.11 VECTOR GROUP
Check the vector group of the transformer by connecting in a suitable
manner.
Vector Diagram of Diagram as connected Remarks
group connection for test

CONDITIONS TO BE PROVED VOLTAGE MEASURED


1. 1.
2. 2.
3. 3.
3.2.12 FINAL IR CHECKS
The megger readings finally after the transformer is connected to the
system
Date ......................... Time ........................Temp .......................
Windings Megger Value obtained in Remarks
used Mega ohms
HV/E+LV
IV/E+HV+LV
LV/E+HV+IV
HV/IV
IV/LV
HV/LV

3.2.13 OTHER TEST


WTI Setting Set for Proved OTI Setting Set for Proved

Alarm Alarm
Trip Trip
Fan Start
Fan Stop
Pump Start
Pump Stop

95 Printed at Anupam Mudran Bhopal Ph: 9425025574


3.2.14 PROTECTION AND ALARMS
Prove the tripping of associated breakers by actual operation of the
various devices and relays.
UNDER NO CIRCUMSTANCES SHORTING OF ELECTRICAL
CONNECTIONS SHOULD BE DONE.
Sl.No. Device Set for Proved Remarks
Alarm Trip Alarm Trip
1. Buchholz
2. Excessive Winding
temperature
3. Excessive Oil Temp.
4. Oil flow failure
5. Water flow failure
6. Differential pressure
(OFWF cooling system)
7. Fan failure
8. Low oil level
(conservator tank)
9. Pressure relief valve
10. Differential relay
11. Over current relay
12. Earth fault (REF)
13. Instt. Earth fault
14. Inter trip, if any
15. Trip free check.

3.2.15 RECORD THE FOLLOWING AFTER CHARGING


a) No load current at relay terminal
U phase A
V phase A CT Ratio
W phase A

b) Temperature (at the time of charging)


O.T.I. o
C
W.T.I. o
C
Ambient o
C
c) Maximum temperature after 24 hours. o
C

97 Printed at Anupam Mudran Bhopal Ph: 9425025574


3.3 COMMISSIONING CHECKS REACTOR
Customer W.O. No.
Site Sl.No.
Rating Voltage class
Scope
This schedule covers the tests to be done at site after reactor has been
installed and dried out.
3.3.1 GENERAL
Check the following :
Sl.No. Description Remarks
1. Breather Silicagel (Blue When Dry)
2. Oil in the Breather Cup.
3. All valves for their correct opening and closing sequence.
4. Oil level in conservator tank.
5. Oil in cooling system.
6. Oil level in bushings.
7. Release air, wherever necessary.
8. Buchholz, oil level indicator, thermometer, temp. indicators etc.
for operation.
9. Earthing of main tank, M. Box.
10. Neutral earthing.
11. Earth Resistance of Electrodes.
12. Earthing of bushing test tap.
13. Check oil leakage for 24 hours.
14. Check auxiliary circuit voltage (415 V).
15. Calibration of OTI/WTI with hot oil.
16. Check Working of WTI/RTD repeaters at control room.
17. IR of core to earth.,

3.3.2 INSULATION RESISTANCE TEST


Sl. Description Date Time Megger IR Temp. Remarks
No. in hrs. used Value
1. Control Wiring 500 V
2. Main Winding
a) HV/E >1000V

99 Printed at Anupam Mudran Bhopal Ph: 9425025574


Note:
(i) While checking these values no external lines, lightning arresstors
etc. should be in circuit.
(ii) Special care should always be taken while meggering the reactor
winding to ensure that there is no leakage in the leads.
3.3.3 OIL CHARACTERISTICS
Take necessary precaution (regarding rinsing the bottle, cleaning hand,
air bubble etc.) while-withdrawing the samples. Each sample should be free of
air bubbles and should be tested when it is hot. The sample should satisfy
IS:1866.
SI. Oil Sample Time & Condition Moisture Break Resisti Tan- Rem
No. From Date Time Weather in PPM down vity at at arks
Voltage 90oC 90oC
in kV (in ohm-
cm)

1. Tank
Top Sample
Bottom Sample
2. Cooling system
Top Sample
Bottom Sample

3.3.4 TESTS ON CT
1. Ratio
2. Polarity
3. Magnetising current
4. IR value
3.3.5 MEASUREMENT OF WINDING RESISTANCE
Phase U Phase V Phase W Temp. Remarks
Winding

3.3.6 CURRENT MEASUREMENT


a) Apply 3 phase 415 volts on HV Terminals.

Voltage Applied Current measured Remarks


U-V Volts U Phase mA
V-W Volts V Phase mA
W-U Volts W Phase mA

Note: In case of single phase reactors apply 230 V, 1 phase between


line terminal and earth.

101 Printed at Anupam Mudran Bhopal Ph: 9425025574


3.3.7 FINAL CHECKS
The megger readings finally after the reactor is connected to the system.
Date Time Temperature
Winding Megger used Value Obtained Remarks
in megaohms
HV/E

3.3.8 OTHER TEST


WTI Setting Set for Proved OTI Setting Set for Proved
Alarm
Trip

3.3.9 PROTECTION AND ALARMS


Prove the tripping of associated breakers by actual operation of the
various devices and relays.
Note: Under no circumstances shorting of electrical connections be done.

Sl.No. Device Set for Proved Remarks


Alarm Trip Alarm Trip
1. Buchholz
2. Excessive Winding
Temperature
3. Excessive Oil Temp.
4. Oil Level
(Low & Max.)
5. Pressure Relief Valve.

3.3.10 RECORD THE FOLLOWING AFTER CHARGING


a) No load current at relay terminal
U phase mA
V phase mA CT Ratio
W phase mA
b) Temperature (at the time of charging)
O.T.I. o
C
W.T.I. o
C
Ambient o
C
c) Maximum temperature
after 24 hours. C
o

103 Printed at Anupam Mudran Bhopal Ph: 9425025574


104 Printed at Anupam Mudran Bhopal Ph: 9425025574
¦ÉÉMÉ-4
+xÉÖ®úIÉhÉ B´ÉÆ {ÉÊ®úSÉɱÉxÉ

SECTION-4
MAINTENANCE AND OPERATION

105 Printed at Anupam Mudran Bhopal Ph: 9425025574


SECTION 4

4. MAINTENANCE AND OPERATION


4.1 SUPERVISION OF TRANSFORMER/REACTOR
4.1.1 GENERAL
In order to avoid faults and disturbances, it is important that a careful
and regular supervision and control of the reactor and its components is planned
and carried out.
The frequency and extent of such a supervision and control is dependent
on climate, environment and service conditions etc.
The directions for a certain transformer/reactor are therefore preferably
based on experiences from comparable transformer/ reactor installations.
A supervision and maintenance program according to schedule in
ANNEXURE 4.1 is recommended.
Spare transformers/reactors are supervised and maintained according
to the same schedule as transformers/ reactors in service.
4.1.2 GENERAL MAINTENANCE
Dirt/Dust
The external transformer surfaces shall be inspected regularly and when
required cleaned from dust, insects, leaves and other airborne dirt.
Possible Leakage
After energising of the transformer, a certain settling may appear in
sealing joints. These should therefore be retightened according to schedule in
ANNEXURE 4.1. This applies especially to sealing joints with plain gaskets
that are not placed in grooves.
Rust damages, touch-up painting
A regular inspection of the external surface treatment of the reactor
should be carried out. Possible rust damages are removed and the surface
treatment restored to original state by means of primer and finish paints.
4.1.3 OIL PRESERVATION SYSTEM, MOISTURE ABSORPTION
Transformer oil absorbs easily moisture from the surrounding air. The
moisture absorption has been prevented by means of rubber sack in
convservator which acts as a separating wall between the oil and the
surrounding air.
The moisture absorption is further prevented by a breather connected
to the conservator. The active drying agent (silica gel) should be exchanged or
regenerated when 2/3 of the agent has been Pink-coloured by absorbed
moisture.

107 Printed at Anupam Mudran Bhopal Ph: 9425025574


The breather contains also an oil-seal that prevents spontaneous air
circulation. This seal should be filled with oil to the level specified.
4.1.3.1 OIL LEVEL INDICATOR FOR OIL CONSERVATOR
The Transformer oil conservator is provided with an oil-level indicator.
At an oil temperature of 45oC, the conservator should be half filled. If the level
exceeds the value “full”, oil must be drained off. If the value is “low”, oil must
be filled in, Normal oil level should be at 35oC mark.
4.1.3.2 GAS-OPERATED RELAY (BUCHHOLZ RELAY)
The use of gas-operated relay as protection for oil-immersed transformers
is based on the fact that faults as flash over, short-circuit and local overheating
normally result in gas- generation. The gas- bubbles gathering in the gas-
operated relay affect a float- controlled contact which gives an alarm signal.
4.1.3.3 MOISTURE
If the oil has been subjected to moist air, the moisture content and the
electric strength of the oil shall be checked.
4.1.3.4 SLUDGE, ACID
Normally the BHEL transformers have uninhibitated oil.
Sometimes inhibited oil is used. The inhibitor works so that it breaks the
chain reaction by which sludge and acid are produced. This retards the ageing
process and extends the utilization time of the oil.
If sludge is being produced in the oil, the oil changes colour and becomes
darker and turbid. The sludge can be removed by means of filtering, but if the
sludge formation has started, it will increase with time. The oil should therefore
be exchanged if the neutralisation value according to IS:1866 exceeds 0.5 mg
KOH/g or precipitable soluble sludge is produced.
The oil exchange should preferably be carried out when the transformer
is warm and the oil viscosity is low.
The exchange should be as complete as possible, because old oil will
affect the new one, speeding up the ageing.
Oil which is not too much oxidized may in certain cases be regenerated,
but this is economical only for large oil quantities.
4.1.3.5 OIL, MISCELLANEOUS
For supplementary information about transformer oil, see clause 4.2
“Supervision and control of oil”.
4.1.4 TEMPERATURE SUPERVISION
The service life of a transformer is highly dependent on the temperature
prevailing in the core and windings under operation. It is thus important to
keep the oil and winding temperatures under observation continuously. The
temperatures should be read regularly and the measured values registered.
These values will give guidance for judging the service life of the
transformer, cooling system functions etc.

109 Printed at Anupam Mudran Bhopal Ph: 9425025574


4.1.4.1 OVERLOAD
A Transformer can normally be overloaded at a low ambient temperature.
However, the permissible overload must not be judged only with regard to the
oil temperature. We must also consider that the temperature difference between
winding and oil will increase with the load. Therefore, also the winding
temperature must be supervised during overloading.
For determination of the overload capacity for modern transformers refer
IS:6600.
If the temperature in a transformer shows a tendency of rising without
a corresponding increase of the load, this may be caused by a reduction of the
cooling ability of the cooling equipment (dirt, dust). The thermometer should
also be checked in this case.
4.1.4.2 THERMOMETER FOR MEASUREMENT OF TOP-OIL TEMPERATURE
The thermometer consists of a cylindrical sensing body with a flange, a
capillary tube, and a thermometer housing with dial and contact-device. The
measuring system is filled with a liquid, which changes its volume at
temperature variations, and affects spring bellows. The movements of the
bellows are transferred to the pointer and signal contacts via a link system.
The thermometer is provided with two signal contacts of mercury switches.
The contacts can be set independently of each other.
For control and adjustment of the thermometer, see OTI leaflet.
4.1.4.3 WINDING-TEMPERATURE INDICATOR
The thermometer system consists of a sensitive body with assembling
details, a capillary tube and a thermometer housing, which contains a scale
with an indicating pointer and a max. pointer, heating and adjusting resistor,
as well as contact- device for four switches.
For further information about function, control and adjustment of winding
temperature indicator, see WTI Leaflet.
4.1.4.4 REMOTE CONTROL OF WINDING TEMPERATURE
For remote control of winding temperature a resistance temperature
device has been used with a heating element built into the same housing. The
heating element is fed by the secondary current of a current transformer.
For setting of the heating element there is a parallel connected adjusted
resistor installed in the control cabinet.
For further information about function and calibration, see RTD Leaflet.
4.1.4.5 RADIATORS
The external cooling surfaces shall be inspected regularly and when
required cleaned from dust, insects, leaves or other airborne dirt. This is
especially important in case of fan cooling. The cleaning is suitably carried out
by means of water flushing at high pressure.

111 Printed at Anupam Mudran Bhopal Ph: 9425025574


Normally, no measures are necessary for keeping the internal cooling
surfaces clean as long as the oil is in good condition. If, however, sludge
formation has set in, the sludge may deposit on horizontal surfaces in radiators.
In such a case, the radiator should be flushed internally with clean oil.
If the sludge does not loosen, we can firstly flush with petrol etc. and
then with oil.
4.1.4.6 CONTROL CABINET
The operation of the control cabinet and devices normally included, are
described in Vol. I.
4.1.4.7 BUSHINGS
Bushing porcelains shall be cleaned from dust and dirt regularly. In areas
where the air contains impurities as salt, cement dust, smoke or chemical
substances, shorter intervals are required. See also the Instructions in the
special information documents about bushings that are included in vol.I.
4.1.4.8 CONNECTIONS
In order to avoid prohibited temperature rises in the electrical connections
of the transformers/reactor, all screw-joints should be checked and re-tightened
according to schedule enclosed.
4.1.4.9 ACCESSORIES
Separate leaflet/instructions should be followed for various fittings (as
applicable) for Fans, Pumps, Flow indicators, Pressure Gauges, Oil Gauge,
Pressure reducing valve, OLTC, Off circuit tap switch, OFAF/OFWF Coolers
etc.
These leaflet are enclosed with Vol I.
4.1.5 MAINTENANCE SCHEDULE
Maintenance schedule given at Annexure 4.1 should be followed. With
proper maintenance as per this schedule normal life of Transformer or reactor
can be expected.
4.1.6 IR TEMPERATURE RELATION
It has always been the question from our customers as to how the IR
value can be converted at different temperatures. We have drawn a curve
(Fig. 4.1) for guidance of the operating staff on the basis of our experience.
So that they can judge the IR Value at any temperature. This curve cannot be
taken for absolute value but will serve as a good guide for conversions of IR
values at different temperatures. A simple example is given as to how to
calculate the value at different temperature.
Suppose IR value of 70oC is 300 M Ohms and we want to convert at
40 C, the curve will give you a factor K for difference in temperature i.e.
o

(70oC-40oC)=30oC.
K for 30oC temperature difference = 4.2
So the value at 40oC = 4.2x300 = 1260 M. Ohms.
Value thus converted fairly tally with the actual
Value when cooling the transformer. The factors are tabulated as below:

113 Printed at Anupam Mudran Bhopal Ph: 9425025574


Difference
in temp. 10oC 20oC 30oC 40oC 50oC
Factor K 1.65 2.6 4.2 6.6 10.5

4.2 SUPERVISION AND CONTROL OF OIL


4.2.1 GENERAL
The oil in a reactor provides an electrically insulating and a cooling
medium. The service reliability of an oil-immersed transformer/reactor is
therefore mainly, depending on the oil quality.
In service, oil is subjected or normal deterioration due to the conditions
of use mainly due to air, water and solid particles/sediment.
4.2.2 SCHEDULE
The oil should be maintained as per the guidelines of IS:1866. Periodicity
of test and permissible limits for important parameters of oil - electric strength,
water content, resistivity, tan-delta, neutralization value, sediment and
precipitable sludge, flash point and interfacial tension are given in Annexure
4.2. Health of reactors can be effectively monitored by Dissolved Gas Analysis
(DGA) technique described in detail in IS:9434 and IS:10593. This technique
helps in detection of incipient faults in reactors.
4.3 TROUBLE SHOOTING
General measures for trouble shooting are described in this section.
4.3.1 Items to be informed to BHEL in case of trouble.
Followings are items to be informed to BHEL.
1. Transformer or Reactor specifications
Capacity
Serial number & work order No.
Year of manufacture.
2. Load current (A) or load (kW)
3. Operating tap position (In case of Transformer)
4. Conditions at time of trouble.
a) Date, time
b) Trouble phenomena
c) Checked items and results
4.3.2 Transformer troubles and check items. Troubles, their possible causes
and items to be checked are given in Table 4.1 & 4.2.
4.3.3 Detective devices and their functions. Refer to table 4.3
4.3.4 Check items and judging standard Refer to table 4.4.
4.3.5 Detection method of oil or gas leaks. Refer to table 4.5.

115 Printed at Anupam Mudran Bhopal Ph: 9425025574


116 Printed at Anupam Mudran Bhopal Ph: 9425025574
117 Printed at Anupam Mudran Bhopal Ph: 9425025574
Table 4.3: Detective devices and their functions

No. Detective Description


device
1. Buchholz This relay detects the gas evolution due to internal trouble and
relay gives alarm, and is suited to the detection of minor or slowly
(1st stage) developing faults. The nature of the detected fault can be judged
to an extent by analyzing the gas and oil. In case of nitrogen gas
sealed transformer, part of dissolved nitrogen gas comes out due
to the sudden temperature drop, which sometimes results in the
actuation of this relay.
2. Buchholz When a major fault suddenly takes place inside the transformer,
relay oil flows suddenly from the transformer tank to the conservator.
(2nd stage) The second stage of Buchholz relay is actuated by this oil flow. If
the second stage of the relay functions independently, check the
air breather, nitrogen gas sealing device etc. If it functions
combinedly with the over current relay etc. it is suspected that a
serious internal defect is existent. In such a case take all tentative
measures and contact BHEL immediately.
3. Pressure When the internal pressure of the transformer rises above the set
relief device value, the pressure relief device functions. It also functions, though
occasionally by the choking of the air breather. The self- excited
pressure relief plate is subject to brittleness caused by secular
change. Comprehensive judgment based on the inspection of other
protective relays is the key to determining whether the function of
this device is an erroneous operation or a normal operation caused
by internal defect.
4. Differential This relay detects the internal defect by comparing the input current
relay and the output current of the transformer. If it functions combinedly
with other protective devices, it is indicative, in almost all cases,
of an internal fault. Note that this relay sometimes operates due to
inrush current when the transformer is energized, and this is of
course not an internal fault.
5. Dial thermo This thermometer gives alarm when the temperature rises beyond
meter alarm the preset value. Insufficient cooling effect of cooling equipment
contact due to contamination of cooling fins, Stoppage of oil pumps, fans
and so forth is one of the reasons that operates this device.
6. Overcurrent These are intended for detecting faults in the electric system
relay, ground connected with the transformer. A fault in the transformer results
fault relay in the function of these relays, which is always accompanied by
the actuation of protective devices of the transformer. Detection
of the fault in the electric system should therefore be made on the
basis of a comprehensive judgment of these functions.
7. Voltmeter If a sudden change in voltage or current is noted when no
ammeter abnormalities are detected in the electric system, or an abnormal
unbalance of voltage or current is noted between phases, investigate
the cause.
8. Human Note that human senses also play an important role in fault
senses detection. Following are the points to be checked by your senses.
1) Discolouration or odour of insulation oil (blackening or stink). If
pieces of insulating materials or copper particles are found in
the oil, it is suspected that an internal defect has developed.
2) Abnormal vibration or sound.

119 Printed at Anupam Mudran Bhopal Ph: 9425025574


Table 4.4: Check and refer standards
No. Check Point Description Judging standard
1. Measurement Grounding fault can be detected by Judgment to be
of insulation this measurement, though to some made by comparison
resistance extent. The measurement must be with values obtained
proceeded after disconnecting the by periodical
transformer from lines and cleaning inspection.
of bushing surfaces.

2. Measurement This is a primary means to be Judgment to be made


of winding employed for detecting the fault of by comparison with
resistance windings. The resistance should the factory test report.
preferably be measured independently
by the D.C. drop of potential method.

3. Measurement This can be conducted by applying a Judgment to be made


of voltage ratio voltage of about 200V which can be by comparison with
readily obtained at job-site. Accurate the factory test report.
measurement at job site entails some
difficulties due to source voltage
variation and errors of instruments.
In case of 3 phase transformers, it is
essential to measure the ratio phase
by phase and check the variation of
the ratio between phases.

This measurement is very useful to 1 Comparison of


4. Measurement detect fault in windings and/or cores. the measured
of exciting Local short- circuit in windings or values with
current cores often causes an increase in the previously
exciting current. The test can be made obtained ones.
by applying a low voltage (200-400 2 Significant
volts) to a winding. difference in
value among
phases.

5. Checking of Measurement of dielectric loss factor Judgment to be made


insulation oil Tan delta can be checked with sharing with reference to
bridge. Annexure 4.1 & 4.2.

6. Measurement Measure dielectric strength and check Judgment to be made


of dielectric for carbon sludge, offensive odour and by comparison with
loss factor, discoloration. values obtained by
tan periodical inspection.

7. Analysis of gas When gas is accumulated in the Contact BHEL


accumulated in Buchholz relay,its composition must
Buchholz relay be clarified by the gas chromatograph
analyzer to check for the possible
internal defect.

8. Analysis of Existence of internal defect can be Contact BHEL


dissolved gas judged, though to a limited degree,
in oil by sampling and analyzing oil by a
gas chromatograph. (Refer 4.3.2).

121 Printed at Anupam Mudran Bhopal Ph: 9425025574


Table 4.5 Method for detecting oil or nitrogen leaks

Leak Measures Description


Oil leak Clean the suspected leak The following are susceptible
part with thinner or gasoline to leakage.
apply chalk powder to it. (1) Gasketed joints.
The leak part will present (2) Welded parts.
itself as a soiled spot.

Nitrogen leak Step up Nitrogen gas pressure The following are susceptible
(in case of to 0.17 kg/cm2 to leakage
Nitrogen sealed (1) Accessories for pressure
system) relief
(2) Flanges
(3) Welded parts

4.3.6 GAS ANALYSIS ON TRANSFORMER OIL


Incipient faults in oil filled transformer are usually the result of electrical
or thermal excess stress of either the transformer oil or insulating materials.
It is known that such excessive stresses produce a mixture of gases
characteristic of which give an indication of the type of faults, and materials
associated with the faults.
It is recommended that analysis of dissolved gases in transformer oil by
gas chromatographic equipment is made, the time of commissioning and then
after an interval of one year for transformers of 145 kV class and above.
4.3.7 ANALYSIS METHOD
4.3.7.1 SAMPLING OF OIL FROM TRANSFORMERS
Oil in transformers can be sampled through drain or sampling valve near
bottom of the tank. Special care shall be taken not to introduce air, foreign
matter, or dirty oil into sampling container. For this purpose, first 0.5-1.0 litre
of oil from the transformer shall be over-flown through the oil container. Shape
of the sampling container may be that of shown in Fig. 4.2 and sampling
method shall be in accordance with Fig. 4.3. See also IS:9497 Sampled oil
shall not be exposed to air before analysis.
4.3.7.2 GAS ANALYSIS
Gases to be analysed and criteria for the gases found in transformer oil
are tabulated in table 4.6.
4.3.8 ASSESING THE TEST RESULTS
Test results on gas contents in oil by some typical faults in transformer
active part models are shown in table 4.7.
Table 4.6 and table 4.7 may by referred to evaluate transformer condition.
To analyse DGA test results, flow chart given at Appendix A of IS:10593
should be followed. Standard values may be taken from CBIP Technical report
no. 62 of April 88 titled "Guide for testing of Transformer by Sampling and
analysis of free and dissolved gases" Ratio technique of IS:10593 should be
used to know the nature of fault. IS:9434 and IS:10593 have been adopted
from IEC pub 567 and IEC pub 599.

123 Printed at Anupam Mudran Bhopal Ph: 9425025574


Table 4.6 Gases to be analysed and criteria

1. Gases to be analysed normally O2, N2, H2, Co, Co2, CH4


2. Gases to estimate abnormality H2, CH4, C2H2, C2H4, C2H6
3. Gases to estimate deterioration Co, Co2, CH4

Table 4.7 Gas content in oil by faults


Sl. Type of faults Decomposable gases in
transformer oil
1. Overheat of oil CH4, C2H4, H2, (C2H6, C2H2,C3H6 C3H8)

2. Arcing in oil H2, C2H2, (CH4, C2H4)


3. Overheat of solid insulating materials CO, CO2, (H2, C2H4)
4. Overheat of oil and paper combination CH4, C2H4, CO, CO2, H2
5. Arcing of oil and paper combination H2, C2H2, CO, CO2, (C2H4)

( ) shows gas contents which appear rarely.


4.4 PARALLEL OPERATION
(i) If it is desired to parallel a transformer which is not identical in
design with BHEL transformer, it is preferable to refer the matter to
BHEL for advice.
(ii) The voltage ratings/ratios and impedance values at all taps should
match for the two transformers that are to be paralleled. Only certain
combinations of vector groups are capable of being paralleled. The
table 4.8 below indicates the more common permissible combinations.

Table 4.8
TRANSFORMER (B)
H.V. Delta Star Delta Star
L.V. Star Delta Delta Star
H.V./L.V.
Delta/Star Yes Yes No No
TRANSFORMER (A) Star/Delta Yes Yes No No
Delta/Delta No No Yes Yes
Star/Star No No Yes Yes

125 Printed at Anupam Mudran Bhopal Ph: 9425025574


(iii) Reference to the connection diagrams of two transformers should
indicate the terminals to be paralleled.
(iv) The reversal of two leads on either side of a three-phase transformer
will reverse the polarity changing them in sequence (e.g. form UVW
to VWU or WUV) will swing the vectors through 120.
(v) Phase sequence and polarity can be checked by energising both
transformers on the primary side before paralleling and measuring
the open-circuit voltage appearing across each pair of terminals which
will ultimately be paralleled.
(vi) IS:2026 and IS:10561 may also be referred.

127 Printed at Anupam Mudran Bhopal Ph: 9425025574


ANNEXURE 4.1
MAINTENANCE SCHEDULE

SI Items to be Inspection notes Action required


inspected
HOURLY
1. Ambient - -
temperature
2. Winding Check that temperature Shutdown the transformer and
temperature rise is reasonable. investigate, if either is persistently
3. Oil temperature higher than normal.

4. Load amps/Load Check against rated figures An improper tap position can
voltage cause excessive core loss. Voltage
and tap position should be
corrected.
DAILY
1. Oil level in Check oil level from oil Top up, if found low.
transformer gauge
conservator
2. Oil level in tap Check oil level from the Top up, if found low.
changer diverter gauge glass.
switch.
3. Oil level in Check the oil level from Top up, if found low.
bushings. gauge glass/gauge.

4. Pipework and Inspect the transformer for If leakages are observed tighten
accessories for leakages. evenly the gasket joints. Replace
leakages ‘O’ ring or washer suitably.
Replace gasket if needed.
MONTHLY
1. Buchholz Relay Check oil level Release collected gas/air
2. Dehydrating Check colour of silicagel. Reactivate/replace with new
breather charge, if found pink Investigate
3. Leakages of - and rectify after taking shutdown.
water into
cooler.
QUARTERLY
1. Bushings Examine for dirt deposition Cracked porcelain should be
and tightness of oil filling rectified/replaced.
plugs. Examine for cracks
in porcelain.Clean and
tighten plugs.
2. Transformer oil Check for di-electric Take suitable action to restore
and tap changer strength and moisture quality of oil.
oil content.
3. Cooler fan, Check contacts, manual Lubricate the fan bearings.
bearing and control and interlocks. Replace worn out contacts and
controls, other parts. Clean/ adjust controls
pumps. and interlocks.

129 Printed at Anupam Mudran Bhopal Ph: 9425025574


4. On load tap Examine contacts, check Replace all worn out and burnt
changer step by step mechanism contacts. Set limit switches in
operation, end position position. Clean/ replace brake shoe
limit switches and brakes. lining. Lubricate all bearing and
Also check oil in driving coupling points suitably. (Refer
gear mechanism. Separate leaflet.)

5. Dehydrating Check oil level in the cup Top up, if found low. Clean air
breather and ensure air passages passages.
are free.
YEARLY
1. Transformer oil Check for characteristics in Filter/replace as required to restore
line with IS:1866 the quality.

2. Cable box Check for proper scaling of Replace sealing washer, if found
compound filling holes. damaged.
Check for cracks in the
compound (if used).

3. Alarm and Check all protections and Replace burnt out fuses Adjust the
protection alarm circuits by actual setting and check wiring circuits.
circuits. external initiation. Check Adjust relay setting, if needed.
operation of relays and Replace damaged relays.
their sensitivity.

4. OTI & WTI Check oil in the WTI and Replenish, if required
pockets OTI pockets.

5. Earth strip Check earthing resistance Take suitable action, if resistance


is noted high.
6. Packing gaskets Inspect the condition of Replace if worn out or resilience
of fans packing gaskets. lost.

7. Fan motors Check IR value of motor Dry out, if found low, check
winding after rainy season. balancing of fans.
Noise & vibration of fans.

8. Tank and Check painting and surface Touch up/repaint, if required


accessories finish. Mechanical Replace any component found
inspection of all damaged.
accessories.

Check the tightness of


9. Gasket joints bolts Tighten evenly all loose bolts,
nuts, locking etc.
One year after
10. Diverter servicing commissioning Draw out diverter, clean, tighten
contacts.
Check the contacts for
11. Diverter switch burning or pitting marks. Recondition/replace if required.
of on-load tap
changer

131 Printed at Anupam Mudran Bhopal Ph: 9425025574


12. Diverter switch Filter oil irrespective of Replenish with new oil,if oil is too
oil strength. much contaminated.

13. Tank cover and Dirt, Dust, Surface Clean touch-up painting.
conservator

14. Bushing top Check contact joints Retighten.


connectors.
TWO YEARLY
1. Oil conservator General Inspection Clean, if required. Ensure proper
including checking the functioning of indicator/Replace if
operation of gauges on it. punctured.
Check heathiness of air
cell.

2. Transformer oil Examine values as per Filter oil if required.


IS:1866

3. Buchholz relay Mechanical inspection of Set floats, if required.


buchholz
7-10 YEARLY
1. Transformer and Overall internal inspection Tighten all clamping arrangement,
tap changer including lifting of core and loose cleatings etc. Tighten all
Assembly coil assembly nuts and bolts and check locking
arrangements and fasteners.
Wash core and coil with dry
transformer oil.

NOTES:
1. In addition to the above instructions, reference should be made to
IS:10028 “Code of practice for selection installation and maintenance
of transformer’’
2. Reference of IS:1866 "Code of practice for Maintenance and
Supervision of Mineral insulating oil in equipments'' should be made
for maintenance of oil while transformer is in service. Table 1&2 of
IS:1866 are given at annexure 4.2 & 4.3 for ready reference.
3. The inspection schedule specified for longer periods automatically
includes those specified for shorter period.
4. All maintenance test results and observations should be specifically
recorded.
5. Where matter given in the inspection book differs from that given in
standards referred to, the transformer user should follow the instruction
book.
6. In case of anything abnormal occuring during service, advice from
BHEL should be obtained giving them complete particulars as to the
nature and extent of occurrence, together with the name plate
particulars in order to assist identification of the transformer.
7. As efforts are being constantly made to improve designs and service,
the transformer supplied may differ in minor details from data given
herein.

133 Printed at Anupam Mudran Bhopal Ph: 9425025574


ANNEXURE 4.2
APPLICATION AND INTERPRETATION OF TESTS ON OIL IN TRANSFORMERS AND
REACTORS (INCLUDING SELECTOR TANKS OF ON-LOAD TAP CHANGERS
(CLAUSE 5.1 (a), 5.2, 6.0 and 7.1)
Sl.No CHARACTERISTIC EQUIPMENT TEST METHOD TEST VENUE SUGGESTED PERMISSIBLE ACTION IF
VOLTAGE (REF TO IEC/ISO F=FIELD INITIAL LIMIT OUTSIDE
OR APPENDIX) PERIODICITY SATISFACTORY PERMISSIBILE
L=LABORAT- OF TESTS FOR USE LIMIT SEE ALSO
ARY
(1) (2) (3) (4) (5) (6) (7) (8)
(i) Electric strength 145 kV and IS:6792-1972* F/L After filling 50 kV Recondition
(breakdown above (average of 6 or re-filling (Min) or alternatively
voltage-kV) brealdowns prior to If more econmic
72 kV and on one cell filling energizing, 40 kV or other tests
less than with 2.5 mm gap then after (Min) dictate, replace
145 kV spacing) three months oil.
and after one year
Below 72.5 kV 30 kV
(Min)

(ii) water content 145 kV and IS:335-1983 L After filling 25 PPM Recondition oil
(ppm) above or re-filling (Max) or alternatively
prior to If more econmic
Below 145 kV energizing, 35 PPM or other tests
3 months dictate, replace
and after one year oil.
(iii) Specific resistance All voltages IS:6103-1971 L After filling 0.1X1012 Recondition if
(resistivity or re-filling ohm-cm the value of the
ohm-cm) at prior to (Min) at DDF permits,
900C (see Note 9) energizing, 900C reclaim or replace
3 months if not.
and after 2 years

(iv) Dielectric dissipation 145 kV and IS:6262-1971 L After filling 0.2 (Max) Reclaim or
factor (tan δ) above or re-filling replace oil (limit
at 900C Below 145 kV prior to 1.0 (Max) to be adopted
energizing, then depends on the
after 2 years type of equipment
and instructions
from the
manufacturer).
(v) Neutralisation All voltage IS:1448 (P:2) F do 0.5 mg Reclaim or replace
value (total 1967 or KOH/g oil
acidity (see L (Max)
Note 10)

(vi) Sediment and/ All voltage Appendix A L do No sediment Recondition oil


or precipitable or precipltable if sediment is
sludge sludge should detected
be detectable
alternatively
if more economic
or other test
dictate replace
oil. Reclaim or
replace oil if
precipitable
sludge is
detected.
(vii) Flash point All voltage IS:1448 (P:21) L do Decrease in Reclaim or
(see Note 11) 1970 the flash point replace oil after
15oC (Max) of knowing causes.
the inital value
minimum value
125oC

(viii) Interfacial All voltage IS:6104-1971 L do 0.018 N./m Reclaim or


tension (Min) replace oil.
at 27oC
(ix) Dissolved gas 145 kV and IS:9434-1979 L After filling IS:10593 Reclaim or
analysis above or re-filling 1983 replace oil.
prior to
energizing,
3 months and
after one year.

135 Printed at Anupam Mudran Bhopal Ph: 9425025574


Note 1 The voltages indicated in col 3 are highest system voltages.
Note 2 The full application of these recommendations to small transformers
upto 1 MVA or below 36 kV will be technically necessary only in
cases where high reliability is required. It will normally be uneconomic.
In most cases, it could be limited to the simpler field tests and the
periodicity of tests will be determined with relation to the reliability
required. Inspection of oil in pole- mounted transformers is assumed
to be uneconomic.
Note 3 Characteristics are normally well above the permissible limits given
in col 7 at the time of test of transformer in the manufacturer’s
works. However, no separate limits have been fixed for this stage.
Note 4 Higher limits may be required for electric strength and lower limits
for water content prior to testing in the factory and prior to energizing
the transformer. Special instructions given by the manufacturer may
be followed.
Note 5 Suggested initial periodicity of tests have been given in col. 6.
Subsequent intervals may vary depending on previous test results
(progress of ageing) and on changed service conditions.
Note 6 Instructions of equipment manufacturers should be taken into account
in adoption of the recommendation of this table.
Note 7 For application and interpretation of test in diverter tanks of on-load
tap changers, guidance shall be taken from the manufacturer.
Note 8 Alternatively an indication of the presence and effect of water content
can be obtained from a resistivity comparison at 27oC and 90oC (see
6.4.1.2).
Note 9 Water content and acidity influence the values of the specific
resistance. The limit is indicative only and when value falls below
this limit the cause should be ascertained by other tests.
Note 10 Perform test more frequently when value exceeds 0.3 mg KOH/g.
For transformers subject to test (ii), method(s) it will be necessary
to test more frequently to establish when neutralization value (total
acidity) exceeds 0.1 mg KOH/g.
Note 11 This test may also be required when an unusual odour is noted or
when an internal fault has occured.

137 Printed at Anupam Mudran Bhopal Ph: 9425025574


ANNEXURE 4.3
GUIDELINES FOR THE CHARACTERISTICS OF OIL TO BE OBTAINED BEFORE
ENERGIZING NEW TRANSFORMERS USING NEW INSULATING OILS ACCORDING
TO IS:335-1983

SL. CHARACTERISTIC EQUIPMENT TEST METHOD PERMISSIBLE


NO. VOLTAGE (REF TO IS:OR LIMIT
APPENDIX)
SATISFACTORY
FOR USE
(1) (2) (3) (4) (5)
(1) Electric strength Below 72.5 kV IS:6792-1972 40 kV (rms) min
(breakdown
voltage kV) 72.5 kV and less 50 kv (rms) min
than 145 kV

145 kV and 60 kV (rms) min


above

(ii) Specific All voltages IS:6103-1971 1X10 12 ohm-cm


resistance (min)
(resistivity ohm-
cm at 90oC)

(iii) Dielectric All voltages IS:6262-1971 0.05


dissipation
factor (tanδ) at
90oC Max.

(iv) Water content, Below 72.5 kV IS:335-1983 25 ppm


ppm Max.
72.5 kV and less 20 ppm
than 72.5 kV

145 kV and 15 ppm


above

(v) Interfacial All voltages IS:6104-1971 0.030


tension at 27oC
(Min) N/m

(vi) Dissolved gas 145 kV and (Under


content above Consideration)

139 Printed at Anupam Mudran Bhopal Ph: 9425025574


140 Printed at Anupam Mudran Bhopal Ph: 9425025574
141 Printed at Anupam Mudran Bhopal Ph: 9425025574
4.5 DO’S AND DON’TS
4.5.1 DON’TS FOR POWER TRANSFORMER/REACTOR
1. Do not energise without thorough investigation of the transformer/reactor, whenever
any alarm of protection has operated.
2. Do not re-energise the transformer/reactor, unless the Buchholz gas is analysed.
3. Do not re-energise the transformer/reactor without conducting all pre-commissioning
checks. The results must be comparable with results at works.
4. Do not handle the off-circuit tap switch when the transformer is energised.
5. Do not energise the transformer, unless the off-circuit tap switch handle is in
locked position.
6. Do not leave-off circuit tap switch handle unlocked.
7. Do not leave tertiary terminals unprotected outside the tank, connect them to
tertiary lightning arrestors protection scheme, when connected to load.
8. Do not allow WTI/OTI temperature to exceed 55oC during dryout of transformer,
and filter machine temperature beyond 60oC.
9. Do not parallel transformers which do not fulfil the condition given in clause 4.4.
10. Do not use low capacity lifting jacks on transformer/reactor for jacking.
11. Do not move the transformer/reactor with bushings mounted.
12. Do not overload the transformer other than the specified limits as per IS:6600.
13. Do not change the settings of WTI and OTI alarm and trip frequently. The setting
should be done as per the site condition.
14. Do not leave red pointer behind the black pointer in OTI and WTI.
15. Do not leave any connection loose.
16. Do not meddle with the protection circuits.
17. Do not allow conservator oil level to fall below 1/4 level.
18. Do not allow oil level to fall in the bushings, they must immediately to be topped
up.
19. Do not leave marshalling box doors open, they must be locked.
20. Do not switch off the heater in marshalling box except to be periodically cleaned.
21. Do not allow dirt and deposits on bushings, they should be periodically cleaned.
22. Do not allow unauthorised entry near the transformer/reactor.
23. Do not leave ladder unlocked, when the transformer/reactor is ‘ON’ in service, in
case it is provided.
24. Do not change the sequence of valve opening for taking standby pump and motor
into circuit.
25. Do not switch on water pump unless oil pump is switched on.
26. Do not allow water pressure more than oil pressure in differential pressure gauge.
27. Do not mix the oil, unless it conforms fully to IS:335.
28. Do not allow inferior oil to continue in transformer/reactor. The oil should be
immediately processed and to be used only when BDV/ppm conforms to IS:1866.
29. Do not continue with pink silicagel, this should immediately be changed or
regenerated.
30. Do not leave secondary terminal of an unloaded CT open.
31. Do not store transformer/reactor for long after reaching site. It must be erected
and commissioned at the earliest.
32. Do not keep the transformer/reactor gas filled at site for a longer period.

143 Printed at Anupam Mudran Bhopal Ph: 9425025574


4.5.2 DO’S FOR POWER TRANSFORMER/REACTOR
1. Check and thoroughly investigate the transformer/reactor whenever any
alarm or protection operated.
2. Check air cell in conservator.
3. Attend the leakages on the bushing immediately.
4. Examine the bushings for dirt deposits and coats, and clean them
periodically.
5. Check the oil in transformer and OLTC for di-electric strength and moisture
content and take suitable action for restoring the quality.
6. Check the oil level in oil cup and ensure air passages are free in the
breather. If oil is less, make up the oil.
7. Check the oil for acidity and sludge as per IS:1866.
8. If inspection covers are opened or any gasket joint is to be tightened,
then tighten the bolts evenly to avoid uneven pressure.
9. Check and clean the relay and alarm contacts. Check also their operation,
and accuracy and if required change the setting.
10. Check the protection circuits periodically.
11. Check the pointers of all gauges for their free movement.
12. Clean the oil conservator thoroughly before erecting.
13. Check the buchholz relay and readjust the floats, switches etc.
14. Inspect the painting and if necessary retouching should be done.
15. Check the OTI and WTI pockets and replenish the oil, if required.
16. Remove the air through vent plug of the diverter switch before you energise
the transformer.
17. Check the oil level in the diverter switch and if found less, top up with
fresh oil conforming to IS:335.
18. Check the gear box oil level, if less top up with specified oil.
19. Examine and replace the burnt or worn out contacts as per Annexure 4.1
of Maintenance Schedule.
20. Check all bearings and operating mechanism and lubricate them as per
schedule.
21. Open the equalising valve between tank and OLTC, wherever provided
at the time of filling the oil in the tank.
22. Connect gas cylinder with automatic regulator if transformer is to be
stored for long, in order to maintain positive pressure.
23. Fill the oil in the transformer/reactor at the earliest opportunity at site
and follow storage instructions.
24. Check the door seals of marshalling Box. Change the rubber lining if
required.
25. Equalise the diverter compartment of the OLTC by connecting equalising
pipe between flange joints provided on the tap changer head.

145 Printed at Anupam Mudran Bhopal Ph: 9425025574


4.6 DISPOSAL
The items to be disposed off are mineral oil, silicagel, gasket and other
insulating material. For disposal of these items, following procedure is
recommended.
4.6.1 INSULATING OIL :
The transformer oil is mineral Hydro Carbon (Petroleum) oil. No special
risks are involved in the handling and use of transformer oil. Howerver, attention
is drawn to the need for personnel hygiene i.e washing of skin & clothing,
which has come in contact with oil by personnel dealing with these products.
Hands in such cases should be washed carefully before eating and drinking
and contaminated clothing should be changed. Also inhalation of fumes or
vapours should be avoided.
When used oil has to be disposed off, certain precautions are necessary
to avoid risk of environmental pollution such as large spillage and leakage
from the containers, which may otherwise result into destruction of greenary,
water birds, fishes.
Normally, non contaminated oil free of PCB (Poly Chlorinated Biphenyls)
can be destructed by burning or sent to local authorities for asphalt production.
However contaminated oil containing PCB shall be filled in drums and sent to
local authorities for disposal.
4.6.2 SILICAGEL :
When silicagel can not be regenerated and to be disposed off, it can be
dumped in a pit and covered with earth.
4.6.3 GASKET AND OTHER INSULATING MATERIAL :
Crok Gaskets & Nitrile Rubber Gaskets can be disposed off by burning
in a place separately marked and prepared for the purpose. In case these can
not be burnt, these can be dumped in a pit and covered with earth.

147 Printed at Anupam Mudran Bhopal Ph: 9425025574

You might also like