You are on page 1of 12

August - November, 2009

vxLr & uoEcj] 2009

MECON’s New Director (Commercial)


Shri Anup Kumar Ghosh has taken over as MECON’s New Director (Commercial) from 1st
September, 2009. Shri Anup Kumar Ghosh was born on 29th February 1952. He completed
B.Tech. in Mechanical Engineering with distinction from NIT, Nagpur and did his Post Graduate
Diploma in Business Management from AIMA, New Delhi. He did specialized training in
erstwhile USSR and INCOS course from IIT Kharagpur.

He was one of the first batch of MECON’s Graduate Trainee in the year 1974. He has been
shouldering the responsibilities of Ports, Material Handling and Infrastructure group as General
Shri Anup Kumar Ghosh
Manager of MECON since 2006. He has over 35 years of experience in design & engineering Director (Commercial)

and worked in various capacities and has been instrumental in steering MECON in completing large scale consultancy
engineering assignments. He has been responsible for completing large turnkey projects in the area of Ports, Harbour,
Bulk Material Handling and Infrastructure. He has vast experience in project execution and led from the front in the
turnkey execution of 5A & 6A berths at Mormugao Port for M/s. South West Port Limited and also for the development
of the complete Material Handling System for handling 5.0 Mt/yr coal within time.

He has to his credit turnkey execution of ADB funded 16.0 Mt/yr Coal Handling Plant at Ennore for Tamil Nadu Electricity
Board before schedule. He is presently leading a team for executing Lignite Handling System for 2 x 250 MW Thermal
Power Plant for Neyveli Lignite Corporation, Neyveli on turnkey basis and providing design and engineering services
for 6.0 Mt/yr Integrated Steel Plant of Bhushan at Meramandali, 6 Mt/yr Integrated Steel Plant of JSPL, Angul, JSPL
Patratu, JSL Duburi, Neelachal Ispat etc.

He was instrumental in MECON’s restructuring, revitalizing and largely contributed for establishment
of Design & Engineering of Ports & Harbour and Material Handling Division. He was associated with
prestigious projects and design & engineering activities like Bhilai 4.0 Mt expansion, NMDC Bailadila - 5,
JSW at Tornagallu, Bhushan Steel Ltd. & Bhushan Steel & Power Ltd., JSPL, Raigarh, Bokaro 4.0 Mt expansion. RSP
turnkey supply projects like BF highline upgradation, Sinter Base Mix Prep Plants, Sinter Fines disposal system,
Mangalore Pellet Plant, KIOCL.

He has completed major assignments in development of Ports and Material Handling facilities in major ports like
Mormugao, Ennore, Krishnapatnam, Hazira, Gopalpur, Dolvi, Abu Dhabi, Trinidad & Tobago, Qatar, Indonesia, Haldia,
Kolkata, Paradip, New Mangalore and Visakhapatnam.

He was instrumental in developing several software for in-house use and has hands on experience with softwares like
PROBELT, Auto CAD, MS Project, Primavera, etc.

He has also presented a number of technical papers in several high level conferences like 'International Conference on
advances in Bulk Material Handling in Ports, Power, Steel & Mines', '24th National Convention of Institution of Engineers
[I] (Mechanical)', 'International Convention of Metallurgical Process Technology' by Indian Institute of Metals, 'National
Convention of Bulk Silo Technology' by NMDC, Hyderabad.

He has organized two prestigious International Conference on "Bulk Material Handling" and has been selected on the
prestigious Conference Board of "Bulk Solids INDIA 2010". An International Conference & Exhibition on Storing, Handling
A House of & Processing Bulk Solids and Powder organized by NURNBERG - MESSE, BULK SOLIDS HANDLING, GERMANY.
Engineering Excellence
2

MECON NEWS
MECON Procures Order for Project Management Consultancy (PMC) Services for
GAIL’s Cross Country Pipeline Project
MECON has procured an order of Rs 21 Crores from M/s GAIL (India) Limited, New Delhi through open international
competitive bidding on 18th September 2009 for Providing Project Management Consultancy Services for Kochi-Kanjirkkod-
Banglore-Manglore-natural gas cross country pipeline project.
The project will be done in two phases:
Phase I: 24” X 27 Km, 12” X 28 Km, 8” X 41 Km
Phase II: 24” x 835 Km, 12” x 38 Km, 8” X 214 Km
Time Schedule for this project is 36 months (24 months for Phase I and 36
months for Phase II from the date of Fax of Acceptance)
The proposed pipeline project consists of pipeline from Kochi to
Mangalore via Kanjirkkod and Bangalore shall be of 24” line size and
the length shall be 862 km. There will be spur lines of varying sizes of
8” & 12” having total length of 252 Km. Design capacity of the pipeline
is 16 MMSCMD and pipeline design pressure is 92 Kg/cm2.
MECON’S SCOPE OF WORK : Route Map of Kochi-Mangalore-Bangalore Pipeline

The Project Management Consultant (PMC) is appointed for executing the project right from Design to Commissioning &
project close out on total and single point responsibility basis. The scope of work of the PMC broadly covers the following:
• Review of existing DFR inputs including technical & commercial aspects like technology, line sizing, pipeline
configuration, costs etc. Generally X-70 grade line pipes are used in GAIL projects. However, looking into the
technological advancements in line pipes, consultant may be required to use higher grade line pipe like X-80 grade
• Design & Detail Engineering
• Basic Engineering & Hydraulic study
• Planning & Scheduling
• Tendering/ Retendering & Ordering including purchase of all equipment and materials, Customs Clearance and
Transportation of materials/ equipments to site etc. The consultant has to follow GAIL’s C&P Procedure for all
purchases. It may be noted that GAIL has recently adopted e-procurement practices and the same practice is required
to be followed by the PMC for this project
• Inspection/ Expediting of equipment/Materials being manufactured by vendors including contractors supplied items
• Certification and forwarding the contractor’s bills to GAIL within the stipulated time
• Management of Construction Stores, Stores Accounting in GAIL’s ERP system based on SAP and assistance for
capitalization of the project in SAP
• Construction Management & Supervision
• Project Commissioning
• Project Cost Control, Management & Monitoring
• Risk Management of the project along with the detailed risk analysis (Qualitative as well as Quantitative)
• The Risk Management Plan (RMP) & Disaster Management Plan (DMP) is also to be prepared by the consultant
• Health & Safety Management
• Project closeout

MECON Bags Order for Consultancy Services for Waste Heat Recovery System (WHRS)
of Rashtriya Ispat Nigam Ltd., Vizag
MECON has procured order for consultancy services for Sinter Cooler hot gas based Thermal Power Plant for Rashtriya
Ispat Nigam Ltd., Vizag on July 2009.
This unit will generate 20.6 MW electric power by utilizing hot gas emanating from the Sinter Cooler, which otherwise
would be exhausted into the atmosphere. This Model Project will generate electric power, encurtail emission of a green
house gases thereby ensuring benefit of carbon credit through CDM.
This will be the first installation in India of its kind.
3
MECON Entrusted with Detailed Project Report (DPR) for Gogi Uranium Mining Project
During last five decades, with the increasing demand of energy for the accelerated
agricultural and industrial growth, the nuclear power programme in our country has
gained considerable momentum. Uranium Corporation of India Limited (UCIL) is the only
organization in India, which supplies the nuclear fuel to
the country’s reactors. Augmentation of the production
capability to achieve the proposed enhancement in the
Headgear frame of vertical shaft at Gogi nuclear power generation capacities of the country has
invigorated development of new uranium mining and processing plants.
Encouraged with significant discoveries of uranium deposits at Gogi, Gulburga district of Karnataka,
UCIL has proposed to commence underground mining & matching process plant. Shaft sinking operation in progress at Gogi

UCIL has again entrusted MECON with preparation of Detailed Project Report, Mine Plan Report, EIA/EMP Report. Considering
the complexities of the uranium deposit, Gogi uranium mine is going to be one of the most complex underground mines designed
by MECON. Detailed engineering services shall also be rendered by MECON during the execution of the report. MECON is also
assisting UCIL for getting the project clearances from different Government statutory bodies, like Atomic Mineral Directorate
(AMD), Directorate General of Mines Safety (DGMS), Ministry of Environment & Forest (MoE&F) etc.

MECON Pioneered in 'India Electricity Fair', 2009


MECON participated in the India Electricity
Fair, 2009 organized by Federation of Indian
Chambers of Commerce and Industries (FICCI).
This mega event was held from 10th - 12th
September 2009, at Pragati Maidan, New Delhi.
Hon’ble Union Minister of State for Power, Shri
Bharatsinh Solanki inaugurated the fair.
A team of top brass MECONians, namely Shri
J. Mathew, ED (Power),Shri Rupak Biswas,
GM, MECON, Kolkata, Shri S.K Chaterjee, DGM
(Electrical PT & D) and Shri M.M Bakshi, DGM
Shri Bharatsinh Solanki, Hon'ble Union Minister for Power, with other dignitaries are being recieved at MECON Stall
(PP & EE), represented MECON as honorary
by Shri J. Mathew , Executive Director (Power), MECON Delegate in this prestigious event in power sector.
Many dignitaries visited MECON stall. Hon’ble Union Minister of State for Power, Shri Bharatsinh Solanki, Dr.Amit Mitra,Secretary
General,FICCI, Shri Y.K Modi, Chairman & CEO, GEEC Ltd and Former President, FICCI are to name a few. All of them appreciated
MECON’s endeavour in providing engineering assistance to the growing Power sector of the nation. The stall attracted large number of
visitors across the globe and number of queries related to power project development were entertained during the event. Shri R. Verma,
Administrative Officer, Ms. K.Sharma, Senior Administrative Officer and Ms S. Pradhan, Trainee Officer coordinated the MECON stall
during this fair.
MECON Successfully Completed Unit 9 of 2 x 120 MW Captive Power Plant of NALCO, Angul
MECON was awarded Detailed Engineering & Consultancy services of 2 x 120 MW Captive
Power Plant (Unit 9 & 10) by NALCO for their Aluminium plant at Angul. Unit 9 has been
commissioned successfully on 20.8.2009.
The work was executed based on different packages concept. The scope of work included
preparation of Technical specifications, selection of vendors, Engineering & Consultancy, day-
to-day site supervision, inspection & expediting, stores management, testing & commissioning
Unit 9 of 2 x 120 MW Captive Power Plant of
and performance guarantee. NALCO, Angul
4
Metex India 2009 - MECON Leaves an Imprint
MECON took part in the mega trade show - Metex India 2009
held at Trade Centre KPTO, Bangalore from 16th - 18th September
2009, MECON put up one stall displaying the areas of activities
in its four SBU’s (Strategic Business Units). The event was
inaugurated by Hon’ble Union Minister of Mines, Govt. of India,
Shri B. K. Handique. Shri Handique appreciated the recent Eco-
friendly exploration being conducted by different organisations.
Shri Siddharth Rungta, President, Federation of Indian Minaeral
Industries, Shri Sanak Mishra, President, IIM was also present in
the Convention.
Shri B. K. Handique, Hon’ble Minister of Mine, Govt. of India along
with other dignitaries visited the MECON stall and exchanged
Shri B.K. Handique, Hon'ble Minister of Mine, Govt. of India is being received at
his views with Shri N. Balakrishnan, General Manager, Bagalore. MECON Stall by Shri N. Balakrishnan, GM (Projects) MECON, Bangalore

MECON Dazzled in Delhi High Level


Conference on "Climate Change Technology Development and Transfer"
MECON participated in Delhi High Level Conference on 'Climate Change Technology Development and Transfer' at Vigyan
Bhawan, New Delhi on October 21st to 23rd, 2009. MECON had setup a beautiful stall in the exhibition held at Vigyan
Bhawan, New Delhi. This International Exhibition was inaugurated on 21st October, 2009 by Shri Pranab Mukherjee, Hon’ble
Finance Minister, Govt. of India alongwith Shri Jayram Ramesh, Minister of State for Environment & Forest, Govt. of India
alongwith with vast number of International and Indian personalities.
A team headed by Shri M.K. Deshmukh, Director (Engineering) alongwith Shri S.K. Singhal, General Manager, Dr. Veejinathan,
Shri Ashutosh Bhatt and Shri Rana. S. Chakravarty participated in this exhibition cum high level conference.
MECON’s stall was highly appreciated by all the visitors. MECON stall depicted the strength of its Environmental Engineering
Division. MECON’s endeavor towards CLEAN AND GREEN ENGINEERING was highly appreciated. The recent prestigious
project wherein MECON is the consultant for carrying out the model project for waste heat recovery system from sinter cooler
(sintering plant) at Rastriya Ispat Nigam Ltd. Visakhapatnam alongwith NEDO and Steel Plantech Company, Japan, is one
first project in India aiming towards the concept of clean and green engineering. MECON also depicted the Environmental
Laboratory setup which is recognized by Central Pollution Control Board and MoE&F New Delhi alongwith other state
pollution control board. MECON is facilitating various clients in the field of Clean Development Mechanism.
The conference on Climate Change Technology
Development was inaugurated on 22nd October,
2009 at Vigyan Bhawan by Hon’ble Dr. Manmohan
Singh, Prime Minister of India, wherein he stressed
upon India’s commitment towards reduction of
Green House Gases. The guest of honour was H E
Mr. Mohamed Nasheed, President of the Maldives,
Shri Jairam Ramesh, Minister of State, Environment
and Forest, Govt. of India, Mr. Sha Zukang, Under
Secretary General, United Nations, Department of
Economic & Social Affairs (UNDESA), Shri Vijai
Sharma, IAS, Secretary MOE & F, Govt. of India and
host of International and Indian personalities in the
field of Climate Change and Environment.
MECON Stall at the "Climate Change Technology Development and Transfer" Conference
5

The 62nd Anniversary of Independence was celebrated with lot of pomp and show
at MECON Football Ground, Shyamali, on 15th August, 2009. All MECONians,
SAIL employees, members of Commercial Audit and their family members
assembled for the flag hoisting ceremony. Shri Drona Rath, CMD, MECON,
the Chief Guest of the function unfurled the National Tricolour with the
National Anthem sung by the students of JVM Shyamali. Shri A.S.
Mathur, Executive Director, CET, SAIL, was the guest of honour
of the function and read the Independence day message and
congratulated all MECONIANS and SAIL Employees.
Shri M.K. Deshmukh, Director (Engineering), MECON gave the
Shri Drona Rath, CMD, MECON
Independence Day message in Hindi. Shri A. Bhattacharya, then Director
(Commercial), Shri B. Sankararaman, Director (Projects), Shri L.R. Singh, Director (Technology) of MECON, Shri
N.K. Jha, Executive Director I/c SAIL (RDCIS), Shri S.Y.K. Minz, CVO and General Managers of MECON and a large
number of employees were present on this occasion.
On this auspicious occasion a friendly football match was played between MECON football team and Veteran players of
MECON in the MECON Stadium. A cultural programme was also organized in the evening at Community Hall, Shyamali.
Glimpses of Celebration

Shri L.R. Singh, Director (Technology) is being welcomed by a Shri B. Sankararaman, Director (Projects) is being welcomed by a
student of JVM, Shyamali student of JVM, Shyamali

Shri M.K. Deshmukh, then Director (Engineering) reading out the Shri A.S. Mathur, ED I/c RDCIS, SAIL, reading out the
Independence day message in Hindi Independence day message

Mrs. R. Rath distributing sweets to a boy at Ispat Hospital, Mrs. Deshmukh handing over a bax of sweets to a patient at Ispat
Shyamali Hospital, Shyamali
6

MECON observed ‘Sadbhavna Diwas’


On 20th August 2009, the birth anniversary of Late Prime Minister of India, Rajeev Gandhi, MECON Limited observed
‘Sadbhavna Diwas’.MECON office was ornated with colorful banners with message of national Integrity.
MECONians gathered at the reception hall to take the ‘Sadbhavna Diwas’ pledge. Shri A.Bhattacharya, the then Director
(Commercial) elaborated about the importance of ‘Sadbhavna Diwas’ in today’s world. Sri B.Sankararaman, Director
(Projects) and Shri L.R Singh, Director (Technology) read out the ‘Sadbhavna Diwas’ pledge in English and Hindi respectively.
All MECONians took the oath of irradicting violence and promoting goodwill among the people and creating a healthy
environment in the work place.
MECON also celebrated Communal harmony Fortnight from 20th August to 3rd September,2009.

From Left to Right : Shri L.R. Singh, Director (Technology), Shri B. Sankararaman, Director MECONIANs taking the Sadhavna Pledge
(Projects) and Shri A. Bhattacharya, then Director (Commercial) conducting the pledge ceremony

MECON Employees Union Election 2009–11


Congratulation!
MECON Employees Union election for the term 2009 – 2011 was held on 7th
Major Ratnesh Kumar
August ,2009 at MECON Head Office, Ranchi. 223 non-executive employees
Singh, son of Shri S.
franchised their rights to
V. Singh, DGM, Elect
choose their representatives.
(PT&D) has been
The Returning Officer
awarded the prestigious
Shri M.K. Roy and Asst.
Major Ratnesh Kumar “SHAURYA CHAKRA”
Returning Officer Shri S.S.
on Independence Day 2009 for act of
Prasad conducted the MEU
exceptional bravery and gallantry while
election smoothly. Shri
fighting with terrorists in J&K. He was
Mahadeo Oraon and Shri
a pioneer student of Jawahar Vidya
Debasis Banerjee were
Mandir prior to joining the National
The newly elected Members of MECON Employes Union (MEU) declared President and Vice
Defence Academy in 1998. He was later
President respectively.For the other posts Shri Kadir Quarashi was elected as
commissioned in the RAJPUT REGIMENT
the General Secretary. Shri Bimal Karkusha, Shri M.S. Pathak & N. Horo were
of the Indian army in June 2002. The award
selected for the three posts of Secretary.
will be conferred to him personally by Smt.
Shri Santosh Kachhap was elected as the Treasurer and Shri R. Kerketta were Pratibha Devi Singh Patil, Honourable
elected as Jt. Treasurer. President of India in a ceremony to be held
Shri Birsa Kachhap, Shri Durga Lal Hela, Shri Lagan Ram, Shri B.Kujur, Shri at the Ashoka Hall, Rashtrapati Bhawan.
Suraj Kumar Balmiki, Shri Shiv Shankar Kewat, Shri Rang Dhari Singh, Shri He has also been awarded the “Chief of
Ravindra Gond, Shri Md. Moinuddin, Shri Ram Sewak Ram, Shri Rajendra the Army Staff” Commendation Card for
Kumar and Shri Nand Lal Ram were declared as the Executive members of the gallantry on two earlier occasions.
Union. Our heartiest congratulations to all the elected members.
7

MECON'S MAGNANIMITY, A PANACEA FOR SOCIETY


Former President Visits Cheshire Home

Dr. Kalam with the inmates of Cheshire Home Dr. Kalam in an interactive session with the inmates.
Former President Hon'ble Dr. APJ Abdul Kalam paid visit to
Cheshire Home that brought cheers to the physically challenged
children residing there. Former President distributed sweets /
chocolates to the residents of Cheshire Home and met them
individually.
Former President also inaugurated the Kitchen Block and
Cow Shed constructed by MECON. MECON has been
providing constant support to Cheshire Home in their
endevor of helping physically challenged children in and
around Ranchi.
Dr. Kalam handing over a Calipers to a physically challenged boy,
Shri H.L. Choudhury, Chairman CDC & GM Civil assisting Dr. Kalam

Blood Donation Camp Medical Camp


For MECON, social responsibility has always been of Under the “Community Medicine Program”, MECON’s
paramount importance. As an act of benevolence towards Community Development Committee (CDC) along with Ispat
society, Ispat Club of MECON Shyamali has organised a Hospital, Shyamali, organized a day long “Medical Camp”
blood donation camp for its members and employees of and “HIV/AIDS Awareness Program” on 30.07.2009 at “Holy
MECON, RDCIS & CET-SAIL with the help of Ispat Hospital,
Faith Mercy Home (for Orphanage)”, Joda Bagicha, Khunti.
Shyamali & Jharkhand State Aids Control Society at Ispat
Club premises on 12th of July, 2009. Dr. Gajendra Kumar, Dr. S. K. Mishra & Dr. J. K. Rath of
A large number of volunteers came forward and donated Ispat Hospital examined the patients in the medical camp.
blood for a noble cause denouncing once again that they About 150 people including children of “Mercy Home for
are mere mercinaries. Orphanage” and adjoining areas were examined and given
The blood donated at this camp will go to the needy and medicines for various diseases. They were also explained
poor being treated at Govt. Hospitals in Ranchi district. about importance of hygine and sanitation.

Volunteers donating blood at Ispat Club "HIV/AIDS Awarness Programme" at Joda Bagicha, Khunti
8

CVC’s Guidelines on Tender


PRE-TENDER STAGE appointed for the consultancy services up to the commercial
operation date with a provision to escalate rate on account of wage
Pre-Tender Stage can be sub-divided into two stages revision. Awarded another work of consultancy for the supply and
• Appointment of Consultant installation of infrastructure project management software and
hardware to another Central PSU. Consultancy charges were 46%
• Preparation of Detailed Project Report (DPR)/Detailed
higher than estimated cost of supply of hardware and software
Estimate
which was not justified by any standard practice.
Appointment of Consultants: At best two consultants for the complete job should have been
appointed duly adopting a proper tender system.
The consultant should be appointed in a transparent and
competitive manner for need based and specialized jobs containing
adequate provisions for penalizing the defaulting consultant. Preparation of DPR/Estimate:
Consultant’s fee should be based on some fixed value of the Successful contract performance depends on the quality of Detailed
contract. Project Report. The detailed project report is prepared on adhoc
basis based on some old project and not as per the present site
Some deficiencies in the appointment of consultants as well requirements, then there shall be delays, deviations, resulting in
as in operating the consultancy contracts has come to notice time and cost overrun. The detailed project report is prepared in
such as – a hurried manner without checking the conformity/consistency
• Arbitrary appointment without publicity & competition among various schedule of items, drawings, specifications, and
• Restrictive criteria adopted in pre-qualification contract conditions etc. leading to time and cost overrun leaving
opportunity for the contractor to exploit and gain profits out of
• Pre-qualification carried out not as per notified criteria
ambiguity in the contract.
• Credentials not verified
Estimates should not solely rely on last accepted rates only.
• Offer of L1 ignored on flimsy grounds
Quoted rate needs to be reasonable and justified and compared
• Decision making left to the consultant with the estimated rates. If the last accepted rates are high for
Case-1 : One consultancy firm was appointed as consultant for any reason, it results in award of the contract at higher rates since
a housing work costing Rs. 60 crores without inviting tenders. no analysis of circumstances under which the last contract was
ordered is gone into. This new awarded rate becomes the basis
Organisation should have invited open tenders from capable
for estimation of rates for the next tender. Thus this problem has
consultants.
a cascading effect.
Case-2 : Limited tenders were invited from known consultants Organisations do not prepare estimates based on actual site
for a Hydro Power Project costing Rs. 130 crores instead of open conditions but based on the borrowed quantities from some
tendering. previous similar project, without modifications for the current
Case-3 : Initial payment of Rs. 3 crores was paid to the consultant project resulting in large-scale deviation, especially in foundation
for mobilizing resources for consultancy. The consultant neither items.
deployed the required man-power as per agreement nor supplied Case-1 : In case of an ‘earth filling package’ of one thermal power
the design and drawing in time defeating the very purpose of project, an estimate amounting to Rs. 73 crores was prepared
granting mobilization advance. taking into account the local site conditions such as lead involved
Department should have insisted on timely services from the in the transportation of earth, cost of the earth etc. L1 bidder
consultant and deployment of sufficient staff. quoted Rs. 129 crores which was on the higher side in comparison
to the estimated rates. Tender Evaluation Committee decided to
Case-4 : Estimate was prepared by an outside consultant, which look into the reasonableness of the estimated cost and concluded
was to be checked by the department. Even the basic rates of that an amount of Rs. 100 crores could at best be justified. The
various items such as cement and steel had been taken on a higher tenders were discharged.
side. Other coefficients for labour and machinery were also taken
Total revision of estimate was carried out and in place of initially
on the higher side. Thus effective control was not exercised on
proposed borrow area involving 4-5 kms. lead, a fresh borrow
the consultant’s job resulting in inflated estimates.
area involving 14 kms lead was stipulated and an estimated cost
Case-5 : A Power Sector PSU appointed 4 Consultants on of Rs. 103 crores was worked out. Lowest bid was for Rs. 192
nomination basis. One Consultant was appointed for the crores. The option of assigning the work to some other PSUs
preparation of the feasibility report for the different sites. Another engaged in construction work was explored. Most of the PSUs
Consultant for verifying the estimated cost. A Central PSU was were excluded and finally the work was assigned to NBCC at a
9
cost of Rs. 118 crores. Since, the estimate of Rs. 103 crores was • Prepare Estimates on the basis of detailed analysis of rates
worked out considering all the relevant factors and current rates, considering rates prevailing at the project site to arrive at
assigning the work at a cost of Rs. 118 crores thereafter, does not realistic cost.
appear to be justified. • Ensure conformity among nomenclature of the item,
drawings and specifications to avoid ambiguities at a later
The work was being executed by way of borrowing earth from
stage.
the area involving a lead of 4-5 kms only, whereas the estimate
amounting to Rs. 103 crores was prepared involving a lead of 14
kms. There appears to be no justification for preparing an estimate
TENDER STAGE
and justifying the cost of award of work considering a borrow area Tender Stage can be sub-divided under four headings
involving a lead of 14 kms. • Preparation of tender documents
Case-2 : Detailed estimate for a power project ‘X’ was prepared • Inviting and opening of tenders
based on the rates borrowed from another previously executed
• Pre-qualification
power project ‘Y’. In Project ‘X’ the electricity & water
supply was supplied to the contractor free of cost. In project • Evaluation of bids and award of work
‘Y’ contractors were to arrange electricity & water supply.
Obviously, the estimated cost of project ‘X’ should have been Preparation of Tender Documents:
less than for the project ‘Y’. An ambiguous agreement leads to poor contract performance
Quantity of ‘extraction of rock’ in the coal handling area deviated and gives an opportunity to a contractor to make profit out of
from 5000 cum to 56000 cum, which indicates that estimate was ambiguous conditions. Often they are prepared in a hurried
not prepared on the basis of actual site conditions. manner without checking the conformity among the schedule of
items, drawings, specifications, and contract conditions etc. due
Organisation should have prepared realistic estimates considering to the reason that different parts of the tender document such
the local conditions. as schedule of quantities, specifications, drawings, and general
Case-3 : In another case of thermal power package, estimates conditions prepared by different people are compiled without
were taken from the award value of an exactly similar package of correlating them. Sometimes they are copied from old tenders
another work which was awarded at Rs. 1,860.33 crores in April, without giving a thought to the applicability of the conditions to
2004. Estimates for the new package prepared in November, 2004 the present work.
were, however, taken as Rs. 2,250.38 crores, 20% higher than
the last award rates within a time span of 5 months without any Inviting & Opening of Tenders:
justifiable reasons on record. Award of Public Contract through open tender is to ensure –
Case-4 : One PSU awarded the work on nomination basis to transparency in public procurement, to maximize economy and
another Central PSU without arriving at a realistic estimated efficiency in public procurement, to promote healthy competition
cost. As the initial cost was not properly worked out before among tenderers, to provide for fair and equal treatment to all the
award, an amount of Rs. 30.50 crores was allowed in addition to tenderers and to eliminate irregularities, interference and corrupt
the initial cost without any justification. After issuing the LOA, practices by authorities concerned. This is also required by the
an amendment letter to this effect was issued later on. Even the Article 14 of the Constitution of India.
sanction of the cost estimate was issued after approximately 15 In an open tender, bids are invited giving wide and adequate
months of issue of LOA. The work awarded on nomination basis publicity.
to the PSUs are getting executed through private agencies by a
back to back arrangement. Keeping the estimates loose in the In the case of small value works, urgent works and in case
beginning results in award of work at higher rates to private parties only a few bidders are available in the market, limited tenders
in a non-transparent manner. from such bidders who have been empanelled are invited.
Empanelment should be done in a transparent way and updated
The estimated rate is a vital element in establishing the periodically.
reasonableness of the prices being offered. It is very important
that the same is worked out in a realistic and objective manner Award of contracts on nomination basis is to be resorted to only
on the basis of purchases made by other organizations, prevailing under exceptional circumstances such as natural calamities and
market rates, the market trend and assessment based on intrinsic emergencies or there were no bids to repeated tenders or where
value etc. only one supplier has been licensed (proprietary item) in respect
of goods sought to be procured.
Few check points for preparation of Detailed Project Report: In Nagar Nigam, Meerut Vs Al Faheem Meat Exports Pvt. Ltd. case,
• Prepare DPR as per actual site requirement in consultation Hon’ble Supreme Court emphasized that all the public tenders
with the field staff; otherwise it may lead to deviations & should be in an open and transparent manner with adequate
delays. publicity.
10
Publicity : Widest possible publicity through well-circulated finally awarded was having a list of all the documents enclosed in
national and local newspapers is essential for greater transparency the bid. However, in the same bid, a letter indicating a discount
in open tenders in addition to uploading NIT on the website. was also enclosed but this letter was not having any mention on
Website publicity is to be given even in the case of limited the first page of the price bid which was containing the list of all
tenders. the enclosures. Incidentally, this bidder could become L1 only after
considering the discount as per this letter, which leaves enough
Receipt of tenders : Suitable arrangements for receipt of sealed
room for suspicion that the discount letter might have been added
tenders at the scheduled date and time through conspicuously
at a later stage.
located tender boxes needs to be ensured. In case of bulky tender
documents the provision for submission of bids to designated Case-7 : In a case of award of a project of Rs. 3400 crores by a
officials by hand should be made in the tender document itself. Power Sector PSU to another Central PSU on negotiation basis,
the justification was given that one Stage Government has also
Opening of tenders : CVC in its circular dated 08.06.2004 has
given the work to the same Power Sector PSU on negotiation
instructed to open the bids in the presence of bidders.
basis. The PSU skipped the normal tendering procedure to award
Case-1 : One power sector PSU ‘N’, awarded the work of the work to the Central PSU. This procedure is not correct due to
main plant and off site civil work of a power projct to another the following reasons:-
construction PSU ‘H’. The PSU ‘H’ had an adhoc panel of four firms
The procedures followed by the State Government may not be
for piling work. The PSU ‘H’ invited bids from three firms and the
taken as precedence to obviate procedures adopted in a Central
4th firm was left out. Two out of these three were not interested,
Govt. Organisation.
so only one firm was left in the fray. Since there was no broad
based panel of contractors that was prepared in a transparent way, Considering the amount involved and the long gestation period
there was lack of competition. The PSU ‘H’ got very low margin of the project it is not found prudent to skip the tender process
percentage. Even when, one other interested party contacted this just to save some time.
PSU ‘H’, it even did not bother to consider their offer.
As per the Govt.’s sanction, this project was to be executed in the
In the same work, the PSU ‘H’ made out a panel for pre-tender tie 10th Plan period and, therefore, there was sufficient time available
up by taking the six firms who had approached them and adding for the organization to go in for a regular tender process.
three more working contractors. The panel was prepared in a
Opening of tenders in the presence of trade representatives should
totally arbitrary manner.
be scrupulously followed. While opening the tenders by the tender
Case-2 : The work of cooling tower (costing Rs. 62 crores) for opening officer / committee, each tender should be numbered
a power project was awarded on nomination basis to a private serially, initialed and dated on the first page. Each page of the
firm even though there are a number of agencies in the market tender should also be initialed with date and particularly the
executing similar work. The concerned PSU should have invited prices, important terms and conditions etc. should be encircled
competitive tenders. and initialed by the tender opening officer / committee. Alterations
should be initialed legibly to make it perfectly clear that such
Case-3 : In another case, Commission’s guidelines violated.
alteration, erasing or cutting was present on the tender at the time
If L1 bidder backs out due to any reason, there should be a re- of tender opening and this fact be also recorded by the tender
tender in a fair and transparent manner. opening officer / committee.
Case-4 : In one case, the Tender Receipt Register was not found
maintained. In case of bulky size of the tender documents, Pre-qualification:
information to be displayed at the entrance/reception to ensure The pre-requisites of pre-qualification process –
a convenient approach for the bidders for submission of the • Transparency, Fairness, Competition should be ensured.
tender. • Neither too stringent nor too lax.
Case-5 : In another case, the corrected quoted amount was Rs. Following deficiencies were observed –
40.79 crores, which was just Rs. 5 lakh less than the L2 quote of • Stringent PQ Criteria resulting in poor competition
Rs. 40.84 crores. In the price bid, a discount of 11% on total price
• Unduly restrictive criteria, creating entry barrier for
is seen to have been mentioned below the stamp and signature
potential bidders.
of the tender opening committee. Incidentally, this insertion also
was not attested by the tender opening committee leaving a doubt • Evaluation criteria not notified to the bidders, making the
as to when the discount amount was added i.e. whether after the PQ process non-transparent.
opening of the price bid ? Such manipulations were possible in • Credentials of the bidders not matched with the notified
this case as the column reflecting number of corrections was blank criteria.
and was prone to be misused by any interested party. • Credentials of the bidders not verified.
Case-6 : In another project of a Power Sector PSU, the covering The purpose of any selection procedure is to attract the participation
letter of the price bid of one of the bidders to whom the work was of reputed and capable firms with proven track record. It should
11
be ensured that the PQ criteria are exhaustive, yet specific and • Conduct pre-bid meeting (i) to bring clarity regarding
there is fair and adequate competition. It should be ensured that spirit of various provisions & (ii) to bring necessary
the PQ criteria are clearly stipulated in unambiguous terms in modifications, if required. Make minutes of the pre-bid
the bid documents. meeting as part of agreement.
• Provide clause to deal with ambiguous provisions (order
Tender Evaluation and Award of Work: of precedence) in the tender document and ambiguity in
the tender submitted by the contractor.
This is the most sensitive area susceptible to corruption. Corruption • Stipulate all prevailing Govt. policy orders such as
is inversely proportional to transparency and fairness. To ensure purchase preference policy (CVC’s Circular dated 15.03.99
that evaluation is done in most transparent and fair & open manner, & DPE’s Circular dated18.07.05), customs exemptions for
following points should be taken care of :- material to be imported etc.
• Evaluation of tenders exactly as per the notified criteria. • Provide enough safeguards against misuse of mobilization
• Timely decision within validity period. advance (CVC’s Circular No. 4CC-1-CTE-2 dated 10.04.07).
• Complying with Commission’s circular regarding • Notify objective evaluation criteria in the tender document.
negotiation. • Stipulate condition regarding splitting of quantities, if
• Ensuring that conditions / specifications are not relaxed in required, in the tender document.
favour of contractor to whom the work is being awarded. • Notify criteria of splitting in the tender document itself if
• Ensuring that L1 is not ignored on flimsy grounds. splitting of work / supply order is envisaged (splitting is
envisaged when L1’s capacity is less than required or to
• Compliance with the purchase preference policy of the Govt. avoid heavy reliance on one firm).
• Ensuring that work order / supply order is placed within
justified rates.
Inviting Tenders
CVC guidelines issued vide following circulars: • Prefer open tendering as far as possible.
• Circular No. 8(1)(H)/98(1) dated 18.11.1998 • In case limited tenders are resorted to, prepare & update
• Circular No. 98/ORD/1 dated 24.8.2000 / 15.03.1999 panel of contractors / vendors in a transparent way.
• CVC’s Office Order No. 13/3/05 (005/VGL/4) dated • Ensure adequate & wide publicity. (Web publicity is
16.03.2005 necessary even in case of limited tenders).
• Circular No. 06-03-02-CTE-34 dated 20.10.2003 • Ensure adequate time for submission of offers.
• Circular No. 004/DSP/11-6594 dated 24.02.2005 • Upload NIT & tender document on website, even in case
• Circular No. 005/CRD/012 dated 03.03.2007. of limited tenders (CVC’s Circular dated 11.02.2004).
• Notify complete address of place of tender submission
(CVC’s Circular dated 08.06.2004).

Opening of Tenders
• Open the bids in presence of bidders.
• Attest and account for corrections, omissions, insertions,
overwriting.
• Prepare ‘on the spot summary’ in tender opening
register.

Pre-qualification
Shri Solomon Yash Kumar Minz, IPS, CVO, MECON Limited receiving Vigilance Excellence • Keep the PQ criteria neither too stringent nor too lax.
Award, 2009 from Shri Pratyush Sinha, Central Vigilance Commissioner, Delhi in a function
organized by Vigilance Study Circle at Jubilee Hall, Hyderabad on 10/08/09 • Prepare the PQ criteria specific to the requirement of the
work in clear terms.
Check points suggested to prevent
• Notify the evaluation criteria in the PQ document
above deficiencies:
Preparation of Tender Documents • Verify PQ credentials.
• Adopt updated standard bidding document • Evaluate the bids exactly as per the notified criteria.
• Ensure conformity among nomenclature of items, • Retender if relaxation in PQ criteria is necessary.
specifications, drawings, general and special conditions. (excerpts reproduced from CVC’s Study on Preventive Vigilance
• Avoid stipulating such conditions in the contract, which in Public Procurement)
are not feasible to be operated.
For important CVC Circulars, please browse ‘meconinfo’
• Stipulate performance guarantee clause to eliminate non-
serious bidders. Vigilance
12

esdkWu esa jktHkk"kk foHkkx


esdkWu esa jktHkk"kk lIrkg
gekjs laLFkku ds eq[;ky; esa 14 flrEcj dks *fgUnh fnol* ds volj ij fnYyh dk;kZy; esa jktHkk"kk lIrkg
*jktHkk"kk lIrkg* dk mn~?kkVu fd;k x;kA bl volj ij egk&izca/kd Jh gekjs fnYyh dk;kZy; esa 14-09-2009 ls 19-09-2009 rd jktHkk"kk lIrkg dk
vkj-lh-[kksokyk us Hkkjr ljdkj ds x`g ea=h Jh ih- fpnEcje] egk&izca/kd vk;kstu fd;k x;kA jktHkk"kk lIrkg dk 'kqHkkjaHk fnukad 14-09-2009 dks
Jh ts- eSF;q us bLikr ea=h Jh ohjHknz flag rFkk egk&izca/kd Jh Vh-ds- ?kks"k fd;k x;kA gekjs funs'kd ¼vfHk;kaf=dh½] Jh fefFkys'k dqekj ns'keq[k }kjk
us bLikr jkT; ea=h Jh ,-lkbZ izrki }kjk tkjh vihy dk okpu fd;kA mi nhi izTofyr dj lekjksg dk fof/kor~ mn~?kkVu fd;k x;kA bl volj ij
egk&izca/kd izHkkjh ¼dkfeZd½ Jh Ñ-c-iz-flag us lekjksg dh v/;{krk dh ,oa funs'kd ¼okf.kfT;d½ Jh ,-ds-?kks"k] funs'kd ¼ifj;kstuk½] Jh ch-'kadjjke.k
rFkk gekjs vU; ofj"B vf/kdkjhx.k mifLFkr FksA lekjksg dh fof'k"Vrk ;g
jgh fd gekjs v/;{k&lg&izc/k funs'kd] Jh Mh- jFk us lekjksg ds nkSjku
vk;ksftr okn&fookn izfr;ksfxrk esa Lo;a lfEefyr gksdj izfr;ksfxrk esa Hkkx
ysus okys oDrkvksa dk mRlkgo/kZu fd;kA gekjs dk;Zikyd funs'kd Jh ih-
Mh- fMMokfu;k us lekjksg dh v/;{krk dhA *jktHkk"kk lIrkg* ds nkSjku dbZ
dk;ZØeksa dk vk;kstu fd;k x;kA fnukad 19-09-2009 dks jktHkk"kk lIrkg
dk iqjLdkj forj.k lekjksg vk;ksftr fd;k x;kA lekjksg esa eq[; vfrfFk ds
:i esa vius izsj.kkLin lacks/ku esa iwoZ dsUnzh; ea=h ,oa iwoZ jkT;iky] MkW- Hkh"e
ukjk;.k flag us dgk fd *fgUnh dks jktHkk"kk ds :i esa Lohdkj fd;k x;k
gS vkSj fganh Hkk"kk dks leLr Hkkjr esa lEeku izkIr gSA* bl volj ij Jh
fMMokfu;k] lykgdkj j{kk ifj;kstuk Jh gfj 'kadj flag] mi egk&izca/kd]
^^jktHkk"kk uhfr dk dk;kZUo;u** fo"k; ij ppkZ djrs gq, bLikr ea=ky; ds la;qDr funs'kd ¼jktHkk"kk½] Jh ,-ds-flUgk] ofj"B izca/kd ¼fctyh½ Jh iadt JhokLro us Hkh vius
Jh osn izdk'k flag ,oa esdkWu ds iwoZ funs'kd ¼vfHk;kaf=dh½] Jh ,e-ds- ns'keq[k]
mi egk&izca/kd izHkkjh ¼dkfeZd½ Jh Ñ-c-iz- flag] ,oa izca/kd ¼jktHkk"kk½] MkW- jekifr frokjh mn~xkj O;Dr fd;sA
mifLFkr dkfeZdksa dks fgUnh esa dke djus dk ladYi djk;kA izc/a kd ¼jktHkk"kk½]
MkW- jekifr frokjh us dk;ZØe dk lapkyu fd;k rFkk jktHkk"kk lIrkg ds nkSjku nqxkZiqj dk;kZy; esa jktHkk"kk lIrkg
vk;ksftr fd;s tk jgs dk;ZØeksa dh tkudkjh nhA mi egk&izc/a kd izHkkjh] [kfut izfro"kZ dh Hkk¡fr bl o"kZ Hkh gekjs nqxkZiqj dk;kZy; esa 14 flrEcj ls 19
,oa [kuu vuqHkkx] Jh gjh'kpUnz feJ us dk;ZØe ds var esa lHkh ds izfr vkHkkj flrEcj] 09 rd *jktHkk"kk lIrkg* dk vk;kstu fd;k x;kA jktHkk"kk
O;Dr fd;kA jktHkk"kk lIrkg ds nkSjku jktHkk"kk rduhdh laxks"Bh] fuca/k] fgUnh lIrkg dk fof/kor 'kqHkkjEHk 14 flrEcj 09] dks gqvk ,oa 18 flrEcj dks
fVIi.k ,oa izk:i ys[ku izfr;ksfxrk rFkk fgUnh dk;Z'kkyk dk vk;kstu fd;k fuca/k izfr;ksfxrk fo"k; % *Xykscy okfeZZax o fo'o dk vfLrRo* ,oa Hkk"k.k
x;kA jktHkk"kk rduhdh laxks"Bh esa izfl) lkfgR;dkj o dfo MkW- [kxsUnz Bkdqj izfr;ksfxrk dk fo"k; % *iznw"k.k dk [krjk ,oa blds jksdFkke ds mik;* nks
bl lekjksg ds eq[; vfrfFk rFkk izfl) dFkkdkj Jh lqj's k izlkn] iwoZ mi eq[; izfr;ksfxrkvksa dk vk;kstu fd;k x;kA
dkfeZd izc/a kd] lhlh,y fof'k"V vfrfFk ds :i esa mifLFkr FksA izc/a kd ¼jktHkk"kk½
us jktHkk"kk rduhdh laxks"Bh dk fo"k; izo's k djk;kA la;Dq r egk&izc/a kd ¼dkfeZd caxyq: dk;kZy; esa jktHkk"kk lIrkg
,oa iz'kklu½ Jh ekS-frdhZ us eq[; vfrfFk MkW- [kxsUnz Bkdqj rFkk mi egk&izc/a kd gekjs caxyq: dk;kZy; esa 14 flrEcj ls 19 flrEcj] 09 rd *jktHkk"kk
¼dkfeZd½ ,oa izHkkjh] jktHkk"kk foHkkx Jh Ñ-c-iz-flag us fof'k"V vfrfFk Jh lqj's k lIrkg* euk;k x;kA fnukad 14-09-2009 dks dk;Zikyd funs'kd Jh nh-
izlkn dks esdkWu dh vksj ls 'kkWy HksVa dj lEekfur fd;kA mi egk&izc/a kd] dq-clq us nhi tyk dj jktHkk"kk lIrkg dk mn~?kkVu fd;k ,oa lHkh dks
ihih,.MbZb]Z Jh 'kSyUs nz ih-frokjh us lHkh ds izfr vkHkkj O;Dr fd;kA gekjs jktHkk"kk ds vf/kdkf/kd mi;ksx djus ds fy, izsfjr fd;k vkSj deZpkfj;ksa
funs'kd ¼okf.kfT;d½ Jh vuwi dqekj ?kks"k us jktHkk"kk lIrkg ds iqjLdkj forj.k ls izfr;ksfxrkvksa esa vf/kd ls vf/kd la[;k esa Hkkx ysus dks dgkA dk;Zikyd
lekjksg dh v/;{krk dh rFkk fofHkUu vuqHkkxksa esa jktHkk"kk fgUnh esa dke djus funs'kd ds usr`Ro esa lHkh egk&izca/kdx.k vkSj dkfeZdksa us ladYi fy;kA
jktHkk"kk lIrkg ds nkSjku 15-09-2009 dks vuqokn izfr;ksfxrk vkSj 16-09-
okys o fgUnh izfr;ksfxrkvksa esa mYys[kuh; LFkku ikusokys vfHk;arkvksa o dkfeZdksa
2009 dks fgUnh dk;Z'kkyk vk;ksftr dh xbZ ftlesa lgk;d egk&izca/kd]
dks uxn iqjLdkj nsdj lEekfur fd;kA vius v/;{kh; lEcks/ku esa mUgksua s teZuh]
Jh ,l-frokjh us fgUnh dk;Z'kkyk dk lapkyu fd;kA 17-09-2009 dks y?kq
Ýkal] phu vkfn ns'kksa dk gokyk nsrs gq, dgk fd *;s lHkh ns'k viuh&viuh Hkk"k.k izfr;ksfxrk vk;ksftr dh xbZA iqjLdkj forj.k lekjksg 19-09-2009 dks
jktHkk"kk esa dke djrs gS]a fdUrq Hkkjr esa jktHkk"kk fgUnh esa dke ugha gksuk fpark vk;ksftr fd;k x;kA jktHkk"kk dk;kZUo;u lfefr ds v/;{k rFkk egk&izc/a kd
dh ckr gSA* iz[;kr Hkk"kkfon~ o dks'kdkj vkpk;Z MkW- fnus'oj izlkn us eq[; ¼lsok,¡½ Jh fn- egk'kCns us fotsrkvksa dks iqjLdkj forfjr fd,A fotsrkvksa
vfrfFk ds :i esa izfrHkkfx;ksa dks lEcksf/kr djrs gq, dgk fd *fgUnh dk nk;jk dks c/kkbZ nsrs gq, mUgksaus *jktHkk"kk lIrkg* dks lQ+y cuus gsrq lHkh dks
u flQZ Hkkjr esa vfirq fo'o esa Hkh cgqr rsth+ ls c<+ jgk gSA ;fn ge lPps eu gkfnZd /kU;okn fn;kA
ls blds fy, iz;Ru djsa rks Hkkjr vYikof/k esa gh fodflr ns'kksa dh Js.kh esa vk mDr dk;kZy;ksa ds lkFk&lkFk gekjs] laLFkku ds dksydkrk] cuZijq ] jkmjdsyk] psUubZ]
ldrk gSA* bl volj ij Jh Ñ-c-iz-flag] MkW- jekifr frokjh ,oa vU; vf/kdkfj;ksa eqEcbZ] fHkykbZ] nkeutksMh+ ] dk;kZy;ksa esa Hkh lgdfeZ;ksa }kjk mYykliwod
Z fgUnh
us Hkh vius fopkj O;Dr fd,A mi egk&izc/a kd izHkkjh ¼foi.ku lsok,¡½ Jh fnisu fnol ,oa jktHkk"kk lIrkg euk;k x;k ,oa bl nkSjku vf/kdkf/kd dk;Z fgUnh esa
dqekj fo'okl us dk;ZØe ds vUr esa lHkh ds izfr /kU;okn Kkfir fd;kA djus dk ladYi fy;k x;k rFkk fgUnh izfr;ksfxrk,¡ vk;ksftr dh xbZAa

Edited and Published by Shri Rana S. Chakravarty, Incharge Corporate Communication, MECON Limited
and Printed at Kailash Paper Conversion Pvt. Ltd., Bharatpuri, Purulia Road, Ranchi

You might also like