This document describes how you can set up correct master data in order to
successfully implement the subcontracting process using APO PPDS Module.
For the subcontracting process, header material and all their components of
the BOM should be created at Vendor Location also in addition to plant
location. But, since material cannot be defined at vendor location in ECC, so
we cannot CIF these directly by material integration model. This document
describes how you can automatically create the header and components at
vendor location in APO automatically without creating them manually.
To create header material and all their components of the BOM at vendor
location in SCM, you should create and integration model for creating PDS
(Process Data structure) for the header material in APO system at vendor
location.
When you CIF the PDS into APO, system automatically creates the following
master data (in addition to the PDS) in APO:
Header material at vendor location
Components at the vendor location
Transportation lane from Vendor to Plant for Header Material
Transportation Lane from Plant to Vendor for.
CIF:
All the header and component materials should exist in active
integration model
Vendor should exist in active integration model.
PIR should be transferred along with PDS for the header material.
APO:
Here you can see that, BOM of Material ‘8000000041’ has only one
component ‘2100014931’.
Here you can see that Production version ‘0001’ is created for the material
‘8000000041’.
Here you can see that material ‘8000000041’ is available in the active
Integration Model ‘ZC2_MAT’.
Similarly check the active integration Model for the component material.
Check the
Procedure to Create PDS in APO system.
1) Creates Header material and all the components of the BOM at vendor
location.
2) Creates the Transportation Lane for Start location as a vendor and
destination location as a Plant for header material and location as a
plant and destination location as a vendor for component materials.
Activate the Integration model ‘CFM1_PDS’ and CIF the PDS in APO system.
Vendor Location
Click in
Here you can see that PDS is created for Header material ‘8000000041’ at
vendor location. Also you can see that all the components of the BOM are
created at vendor location in APO System.
Here you can see that External Procurement Relationship is also available in
APO system.
Here you can see that PDS has created Transportation Lane for Start
Location ‘1000826’ (Vendor Location) TO Destination Location ‘9002’
(Production location)
Here you can see that Transportation Lane is created for the Header Material
‘8000000041’ without Means of Transport.
Here you can see that PDS has also created Transportation Lane for Start
Location ‘9002’ (Production location) To Destination location
‘1000826’ (Vendor Location).
Here you can see that Transportation Lane is created for the component
material ‘2100014931’ without Means of Transport.
Here you can see that now Product view is showing full pegging
structure for order ‘700000061’ in APO system.