You are on page 1of 12

Master Data Setup for PPDS Subcontracting Process

Subcontracting is a form of procurement in which the product to be procured


is manufactured by a supplier (referred to as ‘vendor’ in this document) to
whom the procuring entity (referred to as ‘plant’ in this document) supplies
components for the purpose. The plant may provide these components to the
vendor either directly (using one of its plants), or indirectly (using another of
its suppliers). When the manufacturing process has been completed, the
vendor delivers the ordered product (referred to as ‘header material’ in this
document) to the plant by using the components provided.

This document describes how you can set up correct master data in order to
successfully implement the subcontracting process using APO PPDS Module.

For the subcontracting process, header material and all their components of
the BOM should be created at Vendor Location also in addition to plant
location. But, since material cannot be defined at vendor location in ECC, so
we cannot CIF these directly by material integration model. This document
describes how you can automatically create the header and components at
vendor location in APO automatically without creating them manually.

To create header material and all their components of the BOM at vendor
location in SCM, you should create and integration model for creating PDS
(Process Data structure) for the header material in APO system at vendor
location.

When you CIF the PDS into APO, system automatically creates the following
master data (in addition to the PDS) in APO:
 Header material at vendor location
 Components at the vendor location
 Transportation lane from Vendor to Plant for Header Material
 Transportation Lane from Plant to Vendor for.

Note: It should be noted that while the transportation lane is automatically


created, the means of transport is not added automatically .This has to be
maintained manually once for each lane (meaning each source destination
combination).

Master Data Requirement for Subcontracting Process :


ECC:
 Header material and component should be extended to the plant.
 Header material should have ‘Special Procurement Type = 30 setup in
the material master.
 BOM, Routing and Production version for the header material should
exist
 Subcontracting purchasing info record for the header material should
exist and version field should be populated in the PIR with the
production version.

CIF:
 All the header and component materials should exist in active
integration model
 Vendor should exist in active integration model.
 PIR should be transferred along with PDS for the header material.

APO:

What you should expect the transfer of CIF:


 Header material and components created at the plant as well as at the
vendor location
 PDS for the header material at the vendor location
 Transportation Lanes for header material where the source is Vendor
and target is plant
 Transportation Lanes for component material where the source is plant
and target is Vendor

What you have to do manually:

 Create means of transport in the two transportation lanes.

How to Setup: An Example:

Process flow for subcontracting material ‘8000000041’ @9002 and Vendor


location ‘1000826’.

Let us check Subcontracting Material ‘8000000041’ @ 9002 location in ECC.


Special Procurement type ‘30’ indicates that it is ‘subcontracting ‘.
Let us check the BOM for the material ‘8000000041’ in ECC.

Here you can see that, BOM of Material ‘8000000041’ has only one
component ‘2100014931’.

Let us check the production version of the material ‘8000000041’ in C223.

Here you can see that Production version ‘0001’ is created for the material
‘8000000041’.

Let us check in CFM5 Active integration model for material ‘8000000041’.

Here you can see that material ‘8000000041’ is available in the active
Integration Model ‘ZC2_MAT’.
Similarly check the active integration Model for the component material.

Purchasing Info Record in ECC:

Check the
Procedure to Create PDS in APO system.

When you create the PDS in APO, system does following.

1) Creates Header material and all the components of the BOM at vendor
location.
2) Creates the Transportation Lane for Start location as a vendor and
destination location as a Plant for header material and location as a
plant and destination location as a vendor for component materials.

The setup for the integration model should be as follows: (Material


filter may be different based on requirement)
Here you can see that, we have created New Integration model ‘CFM1_PDS’
and included PDS for the material ‘8000000041’ in this Active IM.

Activate the Integration model ‘CFM1_PDS’ and CIF the PDS in APO system.

Check the PDS in APO:


Run Transaction ‘/SAPAPO/CURTO_SIMU’

Vendor Location

Click in

Here you can see that PDS is created for Header material ‘8000000041’ at
vendor location. Also you can see that all the components of the BOM are
created at vendor location in APO System.

- Let us check the Vendor in the Active Integration Model in ECC.


Here you can see that vendor ‘1000826’ is available in active integration
model ‘VENDOR’.

- Let us check Active Integration Model for Purchase Info


Record.
Here you can see that Purchase Info record is available in Active Integration
model.

Let us check created External Procurement Relationship in APO system.


Run Transaction /N/SAPAPO/PWBSRC1

Here you can see that External Procurement Relationship is also available in
APO system.

Let us check the Transportation Lane in APO system

Here you can see that PDS has created Transportation Lane for Start
Location ‘1000826’ (Vendor Location) TO Destination Location ‘9002’
(Production location)
Here you can see that Transportation Lane is created for the Header Material
‘8000000041’ without Means of Transport.

Note- When we CIF ‘‘PDS/PPM’’ system only creates Transportation Lane


without Means of Transport. You need to create means of Transport
Manually.

Here you can see that PDS has also created Transportation Lane for Start
Location ‘9002’ (Production location) To Destination location
‘1000826’ (Vendor Location).

Here you can see that Transportation Lane is created for the component
material ‘2100014931’ without Means of Transport.

Let us create the Means of transport for Transportation Lane VENDOR


Location -> Production Location
Let us create the Means of transport for Transportation Lane ‘Production
Location -> VENDOR Location’

Let us create sales order in ECC.


Here you can see that Order ‘700000061’ has been created in ECC.

Let us check pegging structure for order ‘700000061’ in /n/sapapo/rrp3 in


APO system.

Here you can see that now Product view is showing full pegging
structure for order ‘700000061’ in APO system.

You might also like