You are on page 1of 8

1 2

What is capital budgeting?


The Basics of Capital Budgeting:
Evaluating Cash Flows  Planning and evaluating investments in Fixed
assets with an expectation to receive cash
inflows for more than one year.
Should we
build this
plant? In other words:

 Finding out the best alternative for long term


investment.

Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

3 4

Some features of capital budgeting? What is the difference between


independent and mutually exclusive
projects?

 Indicates Analysis of potential Projects are:


additions to fixed assets. independent, if the cash flows of
 Involve large expenditures. one are unaffected by the
acceptance of the other.
 Featured as Long-term decisions;.
mutually exclusive, if the cash flows
of one can be adversely impacted
by the acceptance of the other.
Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

5 6

An Example of Mutually Exclusive


An Example of Independent Projects
Projects

BRIDGE vs. FERRY to get


War Tank vs. Public Bus vehicles across a river.

Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.
7 8
Capital Budgeting Evaluation
Techniques:

 Non Discounting Technique:


 Payback Period. Payback Period
 Discounting Techniques:
 NPV
 IRR

Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

9 10

What is the payback period? Criteria for accept/ reject decision:

The number of years required to  Mutually exclusive projects:


recover a project’s original cost or
Accept the project with lowest PBP.
investment.
Reject other projects.
or
 Independent projects:
How long does it take to get the
business’s money back? Accept projects with PBP less than target.
Reject projects with PBP greater than target.

Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

11 12

Formula for PBP: Payback for Project U

(A) For projects with uniform cash inflows:


Initial investment 0 1 2 3
PBP =
Annual cash inflow
CFt -100 40 40 40
(B) For projects with fluctuating cash inflows:
Remaining amount to be recovered
Immediately preceding PaybackU = 100/40 = 2.5 years
PBP = year of full recovery + Total cash flow in the
year of full recovery

Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.
13 14

Payback for Project F Strengths of Payback:


1. Provides an indication of a
project’s risk and liquidity.
0 1 2 2.4 3 2. Easy to calculate and understand.

CFt -100 10 60 100 80


Weaknesses of Payback:
Cumulative -100 -90 -30 0 50
1. Ignores the Time Value of Money.
PaybackF = 2 + 30/80 = 2.375 years 2. Ignores CFs occurring after the
payback period.
Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

15 16

Compare the following two projects: Discounted Payback: Uses discounted


rather than raw CFs.
Year A B 0 1 2 3
0 (20,000) (20,000) 10%
1 10,000 Nil
2 10,000 5,000 CFt -100 10 60 80
3 5,000 20,000
4 Nil 20,000 PVCFt -100 9.09 49.59 60.11
5 Nil 20,000
Cumulative -100 -90.91 -41.32 18.79
Question: # Which project are you going to select? Discounted
# Are you going to select the Project A payback = 2 + 41.32/60.11 = 2.7 yrs
only because it has the lowest PBP?
Why or why not? Recover invest. + cap. costs in 2.7 yrs.
Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

17 18

NPV: Sum of the PVs of inflows and


outflows.

n CFt
Net Present Value (NPV)
NPV   t
.
t 0 1  k

Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.
19 20

What’s Project F’s NPV? Using NPV method, which project(s)


should be accepted?
Project L:
0 1 2 3
10%
 If Projects 1 & 2 are mutually
-100.00 10 60 80 exclusive, accept 1 when
NPV1> NPV2 and vice versa.
9.09
49.59  If 1 & 2 are independent, accept
60.11 both if NPV > 0 for both.
18.79 = NPVF
Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

21 22

Rationale for the NPV Method

NPV = PV inflows – Cost = Net gain in wealth.

Accept project if NPV > 0. Internal Rate of Return


When NPV>0, value is added with the (IRR)
shareholders’ wealth.

Choose between mutually exclusive projects on


basis of higher NPV. That adds most value.

Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

23 24

Internal Rate of Return: IRR What’s Project F’s IRR?

IRR is the discount rate that results 0 1 2 3


IRR = ?
PV inflows = cost.
-100.00 10 60 80
That is, IRR is the discounting rate that results
PV1
NPV = 0.
PV2
0 1 2 3 PV3
0 = NPV
CF0 CF1 CF2 CF3
Cost Inflows IRRF = 18.13

Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.
25 26

Comparative Equations: NPV & IRR IRR with financial calculator:

NPV: Enter k, solve for NPV. 0 1 2 3


IRR = ?
n CFt -100 40 40 40
 t  NPV.
t  0 1  k 

IRR: Enter NPV = 0, solve for IRR. INPUTS 3 -100 40 0


n N I/YR PV PMT FV
CFt
t  0.
 OUTPUT 9.70%
t  0 1  IRR

Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

27 28

IRR with Numerical Calculation: IRR Acceptance Criteria

Use the Interpolation technique for


finding the Rate of Return where NPV
 If IRR > k, accept project.
will be ZERO.

 If IRR < k, reject project.

Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

29 30

Decisions on Projects 1 and 2 per IRR Rationale for the IRR Method

If IRR > WACC, then the project’s


rate of return is greater than its
 If 1 & 2 are independent, accept both if cost. Here some return is left over
IRR1&2 > k .
to boost stockholders’ returns.
 If 1 & 2 are mutually exclusive, accept
1 if IRR1 > IRR2 and vice versa. Example:
WACC = 10%, IRR = 15%.
Profitable.
(15%-10%=5% is for shareholders)
Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.
31 32

Do NPV and IRR always give the same decision? NPV Profile

• NPV Profile is a graph that shows a


Usually yes.
project’s NPV at various rates of return.

In some special circumstances they differ. • Cross over rate is a rate of return where
If in the NPV Profile there is a cross over rate, they
the NPV of two projects are equal.
differ.
If before Cross over rate NPV(x)>NPV(y),
then after Cross over rate NPV(x)<PV(y).

Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

33 34
NPV ($) k NPVg Summary of NPV Profile:
NPVp
60
0 50 40
•At Cross over rate NPV(x)=NPV(y).
50 5 33 29
Crossover 10 19 20 •If before Cross over rate NPV(x)>NPV(y),
40
Point = 8.7% 15 7 12 then after Cross over rate NPV(x)<NPV(y).
30
20 (4) 5
• At a Rate of return above Cross over rate
20 g no conflict between NPV and IRR.
IRRg = 23.6%
10 p • At a Rate of return below Cross over rate
0 Discount Rate (%) NPV and IRR conflict.
0 5 10 15 20 23.6
-10
IRRp= 18.1% • Where the NPV curve cuts horizontal axis,
there we get the IRR of the project.
Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

35 36

Mutually Exclusive Projects NPV or IRR during conflict?

NPV k < 8.7: NPVp> NPVg , IRRg > IRRp  NPV assumes reinvest at k (opportunity
CONFLICT cost of capital).
P
k > 8.7: NPVg> NPVp , IRRg > IRRp  IRR assumes reinvest at IRR.
NO CONFLICT
 Reinvest at opportunity cost, k, is more
realistic, so NPV method is better. NPV
should be used to choose between
g IRRg
mutually exclusive projects.

k 8.7 k
%
IRRp
Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.
37 38
Because of the non conventional pattern
Can there be more than one IRR?
there are 2 IRRs: 25% and 400%.
0 1 2
NPV
NPV Profile
-1.6m 10m -10m
•This is a Non conventional pattern of cash flow. IRR2 = 400%
•Compare a Conventional pattern. 450
•In a Non conventional pattern of cash flow there 0 k
can be more than one IRR (Multiple IRR). 100 400

•In case of Multiple IRR, the IRR approach is not IRR1 = 25%
-800
usable.
Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

39 40

Managers like rates, i.e, prefer IRR to


NPV. Can we give them a better IRR?

Modified Internal Yes, Modified IRR (MIRR) is the


discount rate which
Rate of Return causes the PV of a project’s terminal
value (TV) to equal the PV of costs.
(MIRR) TV is found by compounding inflows
at WACC.
Thus, MIRR assumes cash inflows are
reinvested at WACC.
Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

41 42

MIRR for Project L (k = 10%) To find TV with 10B, enter in CFLO:

0 1 2 3 CF0 = 0, CF1 = 10, CF2 = 60, CF3 = 80


10%
I = 10
-100.0 10.0 60.0 80.0
10% NPV = 118.78 = PV of inflows.
66.0
10%
12.1 Enter PV = -118.78, N = 3, I = 10, PMT = 0.
MIRR =
158.1 Press FV = 158.10 = FV of inflows.
16.5%
-100.0 $158.1 Enter FV = 158.10, PV = -100, PMT = 0,
$100 = TV inflows
(1+MIRRL)3 N = 3.
PV outflows
MIRRL = 16.5% Press I = 16.50% = MIRR.
Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.
43 44

Why use MIRR versus IRR? When there are nonnormal CFs and
more than one IRR, use MIRR:

MIRR correctly assumes reinvestment 0 1 2


at opportunity cost = WACC. MIRR
also avoids the problem of multiple -800,000 5,000,000 -5,000,000
IRRs.
Managers like rate of return PV outflows @ 10% = -4,932,231.40.
comparisons, and MIRR is better for
this than IRR. TV inflows @ 10% = 5,500,000.00.
MIRR = 5.6%
Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

45 46

Accept Project P?

NO. Reject because MIRR =


5.6% < k = 10%.

Also, if MIRR < k, NPV will be


negative: NPV = -$386,777.
Thank You.

Md. Shariful Islam, IBA, RU. Md. Shariful Islam, IBA, RU.

You might also like