Pasupati Bridge - Indonesia

Precast segmental balanced cantilever bridge


with overhead launching gantry

INSERT SCANNED PHOTO


HERE

Curved section of east viaduct

The Pasupati bridge is the The 44.5m typical span viaduct is The typical cycle is 12 days for
incoming elevated highway in formed of 2.95m long precast erection of 15 segments with this
central Bandung, West Java, segmental, three cell, concrete, box free balanced cantilever method.
Indonesia. The bridge will facilitate girder. The 21.53m wide single The gantry may not launch before
busy traffic from Pateur toll road deck is designed to accommodate closure work including stressing of
exit and western area of Bandung two ways road with two traffic lanes continuity tendon since the gantry’s
to eastern destination directly and in each direction. rail support will load the middle of
vice versa. span while launching.
Two overhead launching gantries
The 2282.4m long elevated road are operated by VSL Indonesia for
consists of a 1278.7m long west erection of 663 segments. Two sets
viaduct followed by 303.5m long of lowbed trailer are engaged to
main bridge (cable stay) and a deliver the segments from Baros
700.2m long east viaduct. casting yard to the site of erection.
The 143t (max) segment is
attached to gantry’s spreader beam
Scope of works performed
with four 40mm dia. VSL CT INSERT SCANNED PHOTO
by VSL Indonesia
stressbars. The VSL CT stressbars HERE
• Segments erection
are also used to temporarily secure
• Temporary & permanent PT
and compress the epoxy coated
• Erection method and analysis
segments joint. After one pair
• Geometry control & survey
segments erected, six permanent
• Shop drawing for precasting
cantilever tendons are installed and
• Segments handling at casting yard
stressed with four 460t VSL
• Gantry assembly and dismantling
prestressing jacks.
Field segment erection at Jl. Dago
One important feature of the
PROJECT
viaduct is four reverse curved Pasupati Bridge
sections with radius of 285m
(min.) and 6% superelevation OWNER
(max.) along the road deck. This Ministry of Public Works
option is actualized to follow the ENGINEER
existing road alignment. Halcrow – Indec – Inco – LAPI ITB

Architecturally, the ‘’Y-shape’’ MAIN CONTRACTOR


Wika – Waskita – CGC JO
piers look elegant to support the
girder - with laterally ribbed SPECIALIST CONTRACTOR
cantilever slab - and give wide PT VSL INDONESIA
space for existing traffic below as Jl. Bendungan Hilir Raya No. 50
well. JAKARTA 10210 – INDONESIA
Phone (+6221) 5700786
Fax (+6221) 5731217
To spread the longitudinal E-mail : vslin@vslin.com
earthquake load through all piers,
a pair of lock up device (LUD) are
Top deck view of east viaduct
www.vslin.com
Viaduct crossing Jl. Dago
HEADQUARTERS

VSL International AG
Switzerland
Phone: +41 32 613 30 30
Fax: +41 32 613 30 35

REGIONAL OFFICES

Asia & Pacific


VSL-Intrafor Asia,
Hong Kong
Phone: +852 2590 22 88
Fax: +852 2590 02 90

Central East Europe,


Pier segment erection Middle East,
installed at every pier (except fixed
French speaking Africa
bearing) while lateral load is Phone: +41 32 613 30 30
resisted by bearings. Fax: +41 32 613 30 35

Another unique design of the


bridge is the expansion joints that Iberian Peninsula,
exist at the middle of span which South Africa
and Latin America
gives particular challenge in the
CTT Stronghold
erection method. Spain
Phone: +34 93 289 23 30
Underneath view of viaduct Fax: +34 93 289 23 31
Job Report edited in 2005