Professional Documents
Culture Documents
Contract A
Upper Dam and Appurtenant
Structures
INTRODUCTION
This method statement covers the construction works of Contract A for
the Siah Bishe Pumped Storage Project, particularly the general site
installation and the works necessary for the construction of the upper
dam and the appurtenant structures.
The following works and structures have already been presented and
are therefore not included in this document:
− Rehabilitation of diversion tunnels
− Construction of cofferdams.
The following method statements will be presented separately and is
therefore not included in this document:
− Underground works
For certain works, more detailed method statements will be presented
prior to their commencement. This statement refers to the following
works:
− Excavation
− Embankment
− Rock fill of body of the dam
− Concrete works, including plinth, concrete face of the dam,
spillway
− Roads
− Any other particular works in the project
Method StatementUpperDam.doc
1
It should be noted that it might be necessary to update this document
if during detailed design other solutions are proposed than the
assumed at this stage. Alternatively details of certain construction
procedures may be presented later in separate documents without
updating this method statement as new appendices. Since at that time
the document should be complete itself, then some of descriptions in
present document might be repeated in the above said appendix
briefly. Finally we will have a complete method statement.
In order to make it possible to read this document on its own, extracts
of the technical specifications have been included in this document
where necessary.
Method StatementUpperDam.doc
2
1.2 DESIGN ASPECTS
1.2.1 Main Dam
The dam is designed with upstream slope of 1:1.6 (v:h) and
downstream slope of 1:1.5 (v:h). The crest consists of a parapet wall of
3 meters height at the upstream edge and has a final width of 12m.
The foundation of the parapet wall is at elevation 2409.50 m above sea
level (asl) and at this elevation has a width of 16m, sufficient for the
equipment for the facing concrete.
The plinth and the transition zones, namely fine transition zone
(material 2AA), semi-pervious transition zone (material 2A) and coarse
transition zone (material 2B) should be founded on sound or slightly
weathered rock. The upstream part of the dam below the face (rockfill
3A) shall be founded on rock, whereas the downstream part of the dam
(rockfills 3A, 3B and 3C) will be founded on the alluvium and colluvium
encountered after stripping the topsoil, and removing loose overburden
to a level appropriate for the foundation of the dam body.
1.2.2 Spillway
The detail design of the spillway has not yet been finalized at this stage
and consequently the approval for it could not obtained so far.
Therefore the described arrangement shall be considered provisional
for the time being. The spillway is located on the left abutment of the
dam; with the 20 m wide ogee crest slightly downstream of the dam
axis. The approach channel to the ogee has its base at elevation 2390
m asl. The 20 m wide stepped spillway chute leads in eastern direction
from the ogee level of 2406.50 m asl down to elevation 2365.50 m asl
where a stilling basin is located. Until this point, the whole spillway
structure is founded on rock and made of concrete. After the stilling
basin the spillway crosses the stabilizing fill at elevation 2370 m asl
with minimum slope in a wider channel made of concrete and rip-rap,
possibly with some provisions for sealing the channel against the
stabilizing fill. The slope of the fill towards the river will be equally
protected with riprap against erosion.
Method StatementUpperDam.doc
3
1.3 SCHEDULE AND SEQUENCES OF WORKS: GENERAL
CONSIDERATIONS
In the following, the construction schedule, sequence of works and
important interdependences will be described briefly. Further details
are shown in Appendix 3.1, which highlights the sequence of the works
every 3 months in a graphic form and Appendix 3.2 contains the
detailed construction schedule for the activities at the upper dam site.
Method StatementUpperDam.doc
4
Other changes should be performed after the relocation of the Chalus
road, of which the most important is the construction of a new access
road to the site, because the existing access road will be crossed and
cut by the excavation of plinth. This phase of construction and
excavation is called 2nd phase.
The estimated volumes of excavation are detailed below:
• Left bank 150000 m3
• 1st phase of right bank 100000 m3
• 2nd phase of right bank 20000 m3
• 3rd phase of right bank 150000 m3
• Bottom of valley 100000 m3
Simultaneously with the excavation works described above,
embankment of the stabilizing fill will start with materials from the
dam, spillway and headrace tunnel excavations. The rock fill
downstream of the upper dam commenced in 2004, the embankment
of the downstream part will continue up to elevation 2340 m asl. After
the completion of excavation of right bank, embankment will continue
to the level 2365 m asl.
It should be noted that it is important to complete the excavations of
the dam and construction of plinth on the valley bottom and some
higher elevations on both banks in 2005. Failure to complete this
would mean rockfill operations could not be followed intensively in
2006, which would cause significant delay to the time schedule.
Therefore excavation of both banks, bottom of valley and construction
of plinth, leading to rockfilling, lies on the critical path.
In the upstream part of the dam, foundation treatment and anchoring
works for the plinth are scheduled to start towards the end of year
2005, after reaching the final excavation depth in the bottom of the
valley.
Once the excavation works at the left bank have reached levels below
2400 m asl in the dam crest area and elevation 2370 m asl at the start
of the stabilizing fill, construction of the spillway can start.
According to the latest design of spillway, it can be divided in 3 parts:
• Upper part, consisting of intake and ogee area, and step wise
chute
• Middle part, consisting of “S” shaped channel
Method StatementUpperDam.doc
5
• Lower part, consisting of the channel leading to the river
Because of significant differences in location, structure, material and
method of construction of each part of spillway, each of above-
mentioned parts of spillway can be constructed independently. It is
desirable to start with the upper part, then the middle part and finish
with the lower part. This is because the main part of excavation of the
upper part should be performed at the same time as the excavation of
the left bank, while the excavation of the lower part will cut the access
road to the d/s part of the dam, which is necessary during construction
of body of dam. Thus the excavation of upper part of spillway is
foreseen to be done in 2005, but excavation of the “S” shaped channel
is in 2006, and the lower part will be left up to the time that the
elevation of embankment of body of dam has risen to elevation 2395 m
asl, by which time most of the rock fill will be completed.
In November and December, the access gallery to the drainage gallery
at elevation 2360 m asl in the right abutment of the dam will be
excavated.
One of the main activities during 2005 is related to the excavation and
completion of the plinth, mainly on left bank, bottom of valley, and at
least some part of the right bank up to an elevation such that the
embankment in 2006 could be started easily. At the moment the
excavation of plinth in valley bottom and low elevation portion of right
bank would generate a major problem of stability for the existing
Chalus road, but after relocation of this road it will be a major priority
to complete the plinth in this zone as well as the left bank.
At the downstream part of the dam, the embankment is scheduled to
reach elevation 2361 m asl in December, before winter, and also the
plinth in the upstream part should be finished. At the start of April
2006, rockfill will continue as a major activity and the remaining part
of construction of the plinth on right bank will be followed at the same
time, as required by the critical path.
The total volume of rockfill up to elevation 2361 m asl, which is the
first elevation of instrumentation, is estimated to be about 650,000 m3.
Approximately 100,000 m3 of this volume is planned to be completed in
2005. The daily progress for this part is planned to be approximately
2000 m3/day.
In addition, the random fill part of the stabilising fill will be performed
continuously. The main material for embankment of this part is the
Method StatementUpperDam.doc
6
material from dam abutment, spillway foundation, and headrace tunnel
excavations.
With regard to the drainage works, the excavation of the access to
drainage gallery in the right abutment will be started at middle of May
with a daily progress of 1m per day. The outdoor grouting works from
the plinth will start at the beginning of good weather on April of 2006.
Once the hydraulic model tests are completed, the construction works
at the spillway will start. All the concrete works of the structure; from
the intake down to the stilling basin at elevation 2370 m asl will be
executed during 2006 and 2007.
Method StatementUpperDam.doc
11
rock type but based on available data, it is expected that systematic
support measures may be needed to protect the stripped rock surface.
Commencement of works for excavation of the overburden material
requires previous completion of spillway excavation at least up to the
level of its inlet platform. Then the stripping works at the left bank
from the elevations below the intake access road will be started and
continued downwards. The lower limit of this excavation is the
temporary access road, shown in the Fig. 1. This road is the hauling
road for transportation of excavated material of the elevations above.
Method StatementUpperDam.doc
13
1.4.3 Excavation of the downstream part of the Main Dam
The downstream part of the dam is not necessary to be founded on
rock. The general criterion is that the foundation shall consist of
material with adequate deformation and shear strength characteristics.
In practise this means that all topsoil, organic and clay material has to
be removed. In the case of alluvial and colluvial overburden material
removal must take place to reach layers with an estimated SPT value of
at least 15, or equivalent characteristics. Generally it is an accepted
practice that the alluvial material can be left in place at the riverbed,
except in a limited part near the plinth. These layers of coarse material
usually have high modules of compressibility that some times may be
more than modulus of compressibility of rockfill material. In this
condition usually settlement is not a major problem. But sandy
material area, in which the risk of liquefaction is high, is the exception
and in the upper and lower dams the risk of liquefaction is not possible.
At the upper dam site, it was expected to find granular or non-PI
material in the riverbed in a few meters depth. Some test pits in the
riverbed in different depths, for which the sieve test curves attached,
confirmed existence of this material at this depth. General specification
of this material shows non-PI with the classification GP/GW. The
percentage of fine material is less than 10% that is a good and suitable
bed for rock filling on down stream part of the upper dam. Sampling
from depths about 1.5m below the riverbed has been done and the
results were similar to the previous samples.
The necessary excavation will start in the bottom of the valley. In
parallel with the rising rock fill embankment in the downstream part of
the dam, which will be used as a platform, the necessary overburden
material to be removed at both valley flanks will be excavated with a
loader and/or backhoe and transported by trucks to the stabilizing fill
and/or deposit area. In cases the material to be removed would reach
too far into the slope and therefore endanger the local slope stability
and consequently the equipment and personnel in charge of these
works, excavation would locally start from a higher point.
The borders of the excavation area should be well defined based on
existing condition. Excavation in the left abutment is in the form of
stripping that can be limited to rock outcrops, but in the right
abutment the case is completely different. In this abutment, the main
problem is that excavation is not possible because of risk of slide of the
Method StatementUpperDam.doc
14
Chalus road. Collapse, slide and instability will certainly occur in this
case as shown in Fig No. 2.
Material in the right abutment may include organic material or
weathered rocks, slope wash, topsoil or crushed material which was
produced during the construction of Chalus road. It is not possible to
start any excavation before relocation of the Chalus road.
One of the main problems is seepage of underground water to
excavation area, while operations are going on. Seepage has two main
resources:
• Right and left abutments
• Up streamside of the working area.
Underground water and also above-ground water, which penetrates
the whole area and is drained into the excavated area, is the source of
seepage from the abutments. Unfortunately at this stage there is no
chance to prevent this penetrated water. The only practical way is to
conduit the penetrated water into sumps and then pump the water
from the sump behind the cofferdam into the diversion tunnel.
Method StatementUpperDam.doc
16
Fig. 4- General view of right bank of upper dam
• 1st phase: excavation before relocation of Chalus road, mainly
between new and old road
• 2nd phase: construction of new access road from existing state
road to the job site
• 3rd phase: excavation after relocation of Chalus road, mostly
below the road
It is desirable to start the 1st phase as soon as possible, before the
opening of new road. However based on the latest construction
drawings, it seems that new road should be supported against any
probable collapse or sliding during and after excavation of right bank.
It should be mentioned that sliding in this area is a serious problem. It
is noted on some documents which have been prepared before this
tender, that some parts of the Chalus road in the vicinity of the Duna
sliding mass, sliding and settlement of the Chalus road has been a
problem for many years and every time after this settlement the
surface of state road has been repaired by some layers of asphalt. The
thickness of asphalt is up to 1m in some areas. This problem has been
observed during hard winter of 2005, as well as after disposing some
material from excavation of new road near the old Chalus road, as
shown on Fig.5. The surface of road has serious cracks and settled
about 30 centimetres.
Method StatementUpperDam.doc
17
Fig. 5: Deep cracks on the surface of the road due to disposal of excavated
material on top of the adjacent hill
The overburden stripping operation on the right bank needs to have
reliable information about the depth of rock and depth of over burden.
At the moment, the construction drawings indicate that 3 possible
situations may occur:
1- The depth of bedrock is less than 2 meters. In this case no
retaining wall is needed
2- The depth of bedrock is more than 2 meters but less than 6
meters. In this case a gabion retaining wall should be constructed.
3- The depth of bedrock is more than 6 meters. In this case a
reinforced retaining wall should be constructed.
Unexpectedly as some parts of the road, the depth of bedrock is more
than ten metres for stretches up to forty metres. In this area some
other solutions must be found before October 2005, when the wet
season starts and there will be danger of instability of high
excavations. (See fig.6)
Method StatementUpperDam.doc
18
Fig.6: Right bank of upper dam- against the gully, beneath the new road, where
the depth of bedrock is more than 10 meters
Method StatementUpperDam.doc
19
Fig. 7: Situation of access road to the site during excavation of right bank of
upper dam
The 3rd phase is related to the completion of the right bank excavation,
and will be done after the phase 2. The main principles for excavation
is just similar to left bank but the depths of over burden are estimated
to be greater than for the right bank.
It is noted that some excavated material has been disposed by other
parties in the vicinity of the new road, just above old road that was the
source of slide of Fig. 5. These materials are on the downstream part of
the dam, near the toe. They have been deposited without any
compaction, and have a significant failure potential. For these reason
these materials should be removed.
The estimated volume of excavation is as below:
• Left bank 100,000 m3
• 1st phase of right bank 100,000 m3
• 2nd phase of right bank 20,000 m3
• 3rd phase of right bank 150,000 m3
• Bottom of valley 80,000 m3
• Reservoir 80,000 m3
Method StatementUpperDam.doc
20
• Upper part of spillway 100,000 m3
• Middle part and lower part of spillway 45,000 m3
TOTAL ESTIMATED VOLUME
OF EXCAVATION 675,000 m3
Method StatementUpperDam.doc
23
Fig. 8 : Access Roads on the left abutment
Method StatementUpperDam.doc
24
Fig. 9: Access Roads on the right abutment
Location volume
estimated duration
(m³)
(days)
• Left bank 100,000 m3
140
Method StatementUpperDam.doc
25
• 1st phase of right bank 100,000 m3
90
• 2nd phase of right bank 20,000 m3
20
• 3rd phase of right bank 150,000 m3
150
• Bottom of valley u/s 120,000 m3
45
• Bottom of valley d/s 20,000 m3
30
• Reservoir 80,000 m3
88
• Upper part of spillway 60,000 m3
90
• Middle part and lower part of spillway 125,000 m3
30
TOTAL ESTIMATED VOLUME
OF EXCAVATION 775,000 m3
The machinery resources needed for performing of each of these
activities have been calculated based on assumptions about the
performance of bulldozers as 500 m3 per shift, and 0.5 hour for each
cycle of travel for each truck. The results are on attached tables and
are considered in the PRIMAVERA file of time schedule.
Method StatementUpperDam.doc
26
Section Water Layer Roller Number of
added thickness passes lifts
1 200 l/m3 80 cm 4 4
2 200 l/m3 80 cm 6 4
3 200 l/m3 100 cm 4 4
4 200 l/m3 100 cm 6 4
Method StatementUpperDam.doc
27
Deep excavation in the right bank is forbidden because of the danger of
instability of the road, so after the traffic is diverted from the existing
road there will be two strategic activities:
1. Starting the 2nd and 3rd phase of excavation of the right bank
2. Starting the excavation of the plinth at the bottom of the
valley
While the excavation and construction of the plinth in the bottom of
the valley and low levels of both abutments is going on, excavation on
right bank will continue in parallel and rock fill of downstream on the
right side will be done subsequently. The upstream embankment will
start after constructing the plinth in the bottom of the valley and will
be done in the same stages as the downstream part. From elevation
2340 m asl embankment in both the upstream and downstream parts
will continue to elevation 2361 m asl, which is the first elevation of
instrumentation above the foundation. So the upstream and
downstream parts of the dam will be placed together from elevation
2340 m asl.
All materials will be placed according to the zoning of the dam shown
on the drawings or as adjusted based on material availability, filled and
compacted as indicated in the specifications and determined from the
trial embankment tests. Temporary haul roads within the rockfill
embankment will be built with slopes of maximum gradient of 13%.
According to the technical specifications, section 6.1.3.1, approach or
construction ramps on the faces of the embankment will be removed
and ramps and haul roads inside the embankment will be thoroughly
scarified and re-compacted before placing new lifts of fill material on
top of them. No ramps will be built in the transition zones 2A and 2B,
which will be constructed in horizontal layers from abutment to
abutment.
The following sub-chapters detail the procedure for each of the fill
materials in the embankment, approximately in the order of their first
use.
Method StatementUpperDam.doc
28
The rockfill zone 3A will be placed along the bottom of the valley to a
thickness of 6 meters in order to serve as drainage layer. The material
will be delivered from quarry No.1 with 35-ton dump trucks, spread by
bulldozer to reach lift thickness of 80 centimetres and compacted with
a 10-ton vibratory roller.
3A material will be dumped over the previous layer and bulldozer is
used to push and spread this material (See fig. 10). This causes coarse
material to go to the bottom of layer and fine material to come to the
top and this natural segregation makes a layer with higher amount of
horizontal permeability in each layer that results in more permeability
for the body of dam. (See fig. 10)
Water required for sluicing can be obtained from the river after the
outlet of the diversion tunnel, and pumped into the location under high
pressure. Compaction with 4 passes of the ten ton roller will then take
place.
Method StatementUpperDam.doc
29
1.6.4 Stabilizing Fill Embankment Zone 3A beneath
spillway channel-middle part
Due to the changed spillway design, which does not anymore include a
concrete chute over the stabilizing fill, but rather a channel protected
by shotcrete and riprap it could be possible to construct the whole of
the stabilizing fill with non-rock fill material. However, since during
detail design the necessity arose to place 3A material below the
spillway channel, that material would be placed according to the
corresponding specifications. In addition, in order to minimize the
unfavourable post construction settlements below the spillway
channel, (which crosses the stabilizing fill almost horizontally at
elevation 2370 m asl and on the downstream slope towards the river)
the following general measures may be adopted in the detail design
and indicated correspondingly on the construction drawings:
• The best quality disposal material 3A, preferably from quarry No.1
will be placed beneath the spillway channel
• The uppermost 5 meters beneath the spillway channel will be
placed in layers of maximum 1.0 meter in order to obtain best
compaction.
Method StatementUpperDam.doc
31
1.6.8 Main Dam Embankment Zone 3C
Zone 3C or random rockfill zone is located at the downstream part of
the dam, between zones 3A and 3B. It consists either of rockfill 3A or
3B, depending on the actual quarry operation and results. In case that
the quarry would produce larger amount of fines than allowed in zones
3A and 3B, the permitted amount of grain size 20 mm will be increased
to 40%.
The procedure for building the embankment in zone 3C is the same as
for 3A and 3B described above. The layer thickness may vary between
1.0 and 1.5 meters.
Method StatementUpperDam.doc
32
1.6.10 Main Dam Embankment Zone 2A
The semi pervious transition zone 2A will be placed beneath the
upstream concrete face to provide a continuous support for the
concrete face slabs and to reduce the seepage through the dam when
leakage develops due to defects in the joint waterstops or slabs. The
constant horizontal width of this zone is 4.0 meters according to the
technical specifications, but will be reduced to 3.0 meters due to the
use of an extruded lean concrete berm below the face slab (see below).
The semi pervious transition material 2A consists of processed, crushed
rock with a maximum size of 80 mm, between 55 and 75% passing a
20 mm sieve, between 30 and 45% passing a 5 mm sieve and between
3 and 7% passing a 0.1 mm sieve. The grading of this semi pervious
transition material will be carefully controlled at regular intervals
throughout the construction in accordance with BS 1377 or ASTM 422
(grain size distribution) and as required in the technical specifications.
The semi pervious transition material will be selected from moderately
weathered to fresh rock for processing. The suitability of the material
will be tested in accordance with the relevant standards.
The total quantity of 2A material for the upper dam is some 65,000 m3.
It will be placed in layers of 0.4 m at the correct moisture content and
compacted by at least 4 passes of a 10 ton vibrating roller, together
with the 2B material and in accordance with the results of the trial
embankment tests. The surface of each layer will be wetted during
compaction by spraying with water. The main procedure for regulation
and protection of surface of embankment is construction of an
extruded lean concrete berm along the upstream edge of the
embankment before placing the transition material. The 0.40 m high
curb section has the external face inclined at the dam face upstream
slope of 1:1.6 (v:h) and a semi vertical internal face to act as a lateral
support for the 2AA and 2A materials to be compacted. A 10 to 12 cm
wide crest allows for a minimum overlapping of the curb at successive
layers.
Typically, a mix of 75 kg/m3 cement content, 1.9 mm maximum size
aggregate, 50% of sand and 125 l/m3 of water can be extruded at a
rate of some 40 to 60 m/hour. Some hours after the curb has been laid
out; the transition material can be placed and compacted with the
vibratory roller. Contained laterally, the material will need compaction
only horizontally to the required specifications by the vibratory roller.
Method StatementUpperDam.doc
33
Compared with the “traditional” methods of surface protection by
shotcrete or similar materials, this so-called “Ita method” has the
following main advantages:
- Safer execution and easier access for workers,
- Less vulnerability to erosion due to heavy rain and
consequent repair works,
- Constructions of the fine transition zone and of the slab are
facilitated and the width of the semi pervious transition zone 2A can be
reduced to 3.0 meters,
- Provision of a planar upstream surface with possible
consequent saving in the facing concrete,
- Elimination of any interference between the plinth grouting
works and simultaneous embankment works above,
- Adequate protection against excessive infiltration through
the rockfill embankment in case of eventual unforeseen floods during
the construction period.
Method StatementUpperDam.doc
34
The two upstream transition zones 2A and 2B, both placed together in
0.40 m lifts, must follow the progress of the rockfill material rising
(zone 3A) and the extruded lean concrete berm rising on the upstream
edge.
Method StatementUpperDam.doc
35
1.6.13 Equipment for Rockfill Materials Placement
The 3A material will be delivered from quarry No.1 with 35-ton dump
trucks, spread by bulldozer to reach lift thickness of 100 centimetres
and compacted with a 15-ton vibratory roller.
As for layer 3A in the stabilizing fill area, the 3A main dam
embankment material will be dumped over the previous layer and
bulldozer will be used to push and spread this material (See Fig. 10).
The daily performance of each bulldozer is assumed 1800 m3 per day.
The machinery for spreading of 5000 m3 rock fill material per day, and
the duration of transportation of this material from quarry No.1 is
calculated in the attached sheets and are considered in the
PRIMAVERA time schedule.
Method StatementUpperDam.doc
39
crest. The concrete slabs will be placed in 12 m width with waterstops
at the vertical joints.
Conventional concrete in permanent contact with water (concrete
C25/38) has been specified for the concrete facing slabs. However, it
should be noted that for the concrete slab, impermeability and
durability are most important whereas high strength is not required, as
more cement means more heat of hydration and more shrinkage.
Target strength for the concrete of between 20 and 25 MPa at 28 days
is normal for this type of construction. Tests will be performed prior to
start concreting works, but an initial concrete mix may use low heat
alkali Portland cement with some 15% puzzolan as cement
replacement. The w:c ratio shall be kept below 0.5, and workability will
be achieved by using plasticizers in order to result a working slump of
6 to 9 cm.
The S400 steel reinforcement will be applied to 0.4% of the design
concrete cross section for vertical bars and 0.3% for horizontal bars,
except within 20 m of the perimeter and near the change of the plinth
slope, where 0.4% reinforcement in both directions is specified. The
reinforcement will be placed with a cover of 100 to 150 mm. For areas
near the perimeter joint in the starter slabs, two layers of
reinforcement with the same steel ratio will be used to improve the
bending and torsional strength of the slabs.
Method StatementUpperDam.doc
40
1.8.2 Concrete Face Slab
Once the starter slabs have been finished and the dam embankment
has reached elevation 2409.50 m asl which corresponds to the level of
the parapet wall foundation at the crest, the installations for the
execution of the concrete face slab will start.
The width of the embankment at the mentioned elevation will be 16 m.
The installations for the face slab at this platform include among others
the following:
− Transfer trolleys for slipform and reinforcement installation with
crest anchors (dead-man) and corresponding winches,
− Hopper and half drum chutes for concrete conveyance,
− Crane for handling of reinforcement panels and other material,
− Reflectors for the night shift illumination.
The face slab concrete will be placed by slipforming (as an alternative,
a road paving machine could also be considered). Prior to setting any
slipform rails, the entire upstream face will be surveyed to determine
the variation in the face profile from design lines and levels. Slipform
rails and side forms will be fixed to the embankment face in such a
manner that they can be accurately aligned and do not become
dislodged or misaligned during the construction of the face slabs. The
fixation of the slipform rails will take into consideration the variable
thickness of the concrete face. As for the starter slabs, a bond
prevention agent will be painted over the curb elements before
placement of the face slab to prevent adhesion between the two
concretes.
Reinforcement will be held in place using stools, which will be installed
as the slipform progresses. Once the slipform has completed a section,
it will be jacked up and lowered down the rails and moved to its next
location from the toe of the dam. The slipform will be of standard
design for concrete faced rockfill dams, heavy enough to withstand the
uplift force of the wet concrete with vibrators in use. Two winches will
be utilized for moving the slipform, with each having the capacity to lift
the structure on its own. The platform will be slung such that in the
event of a failure of either winch the structure will still be in service.
Two separate cables, each capable of carrying the structure will be
used, and each will be rated much higher than the load.
Concrete will be piped down from the crest of the dam to a hopper.
From the hopper flexible hose into the form will place the concrete.
Method StatementUpperDam.doc
41
Two hoppers will be used, allowing a continual flow of concrete to the
form. It is anticipated that the slipform will move at an average speed
of some 3 m per hour, i.e. typically 10 to 15 m3/hour. The sliding of one
slab will precede without interruption to its conclusion in day and night
shift, thus avoiding any horizontal joints. For concreting the longest
slab of some 140 m, some 40 hours will be required to finish the slab.
The concrete will be vibrated to ensure that the form is full and that no
honeycombing occurs. A finishing platform will be part of the slipform,
and curing will be carried out from the downstream part of this
platform. Water will be supplied to the platform by pumping for the
lower reaches and from the crest for higher levels.
Only trained operators will be allowed on the slipform platform and
each person will be provided with safety equipment. Communication
will be provided to/from the slipform by walky-talkies from the dam
crest. Operation of the winches will be carried out from the slipform
platform.
During the concreting of one slab, reinforcement placing works will be
done simultaneously for adjacent slabs. The reinforcements will be pre-
erected in large panels, which are trolleyed to their final location on
the slope.
Prior to starting the works on the face slab, a detailed method
statement including safety measures for all the involved operations will
be delivered to the engineer.
1.8.3 Joints
• Perimeter joints: This type of joint between plinth and concrete
facing slab is described in detail in appendix 4.
• Vertical Joints: The horizontal face slab reinforcement will be
interrupted at all vertical contraction joints. The joints will be sealed
with a bottom copper waterstop that is supported by a 6 mm thick
bituminous felt strip or PVC band and asphaltic mortar pad. It should
be mentioned that during detail design an alternative with continuous
reinforcement may be considered.
• Vertical Joints below minimum waterlevel: For joints near the
abutments and for the central joints below the minimum operation
level a similar joint system as for the perimeter joint will be applied.
• Horizontal construction joints: No horizontal construction joints
are foreseen in the face slab since the concreting will be done for each
Method StatementUpperDam.doc
42
panel continuously up to the crest. At the construction joint between
the starter slabs and the face slab the reinforcement will go through
and the old concrete will be thoroughly treated before placing new
concrete on top.
Method StatementUpperDam.doc
43
1.9.2 Finishing Works
The final crest at elevation 2410.15 m asl will be 12 m wide. It will be
provided with a pavement constructed in accordance with highway
practise. The crest will be drained with a gentle slope
Method StatementUpperDam.doc
44