Professional Documents
Culture Documents
The
Theviews expressed herein
environmental are those of the
assessment consultant
and reviewand do not necessarily
framework represent those
is a document of ofthe
ADB’s members,The
borrower.
Board of Directors, Management, or staff, and may be preliminary in nature.
views expressed herein do not necessarily represent those of ADB’s Board of Directors,
Management, or staff, and may be preliminary in nature.
CURRENCY EQUIVALENTS
(as of 26 April 2011)
ABBREVIATIONS
ST – safeguards team
STI – socially transmitted infection
TSS – total suspended solids
UNESCO – United Nations Educational, Scientific and Cultural Organization
ZSD – Zoological Survey Department
NOTE
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other
status of any territory or area.
The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members,
Board of Directors, Management, or staff, and may be preliminary in nature.
CONTENTS
I. Introduction ......................................................................................................................... 1
Annexes:
I. Introduction
1. The proposed Project 1 of the multitranche financing facility (MFF) for the Pakistan
Railway Sector Investment Program is the first in a series of projects to fully rehabilitate one
the country’s main railway corridors in the Punjab Province. This upgrade includes not only
railway work, but also (i) preparation of the railway sector roadmap, policy framework, and
investment plan; (ii) governance assessment; (iii) feasibility of the investment program; and (iv)
formulation of financing and implementation arrangements. Since this Project is designed as a
MFF, an understanding of the nomenclature of components of the railway investment program
is important. The MFF loan modality permits a government to proceed with a larger project via
a number of separate loan packages, thereby adding flexibility and a longer timeframe for the
delivery of preparatory materials. As such, the investment program consists of three tranches
(shown in Table 1), that, all together, aim to upgrade the 463 km railway line between Lahore
and Peshawar Cantt.
3. The first tranche (Project 1) will commence in 2011, with subsequent tranches to follow
as they are prepared. Project 1 will include the rehabilitation of the Lahore-Lalamusa railway
section, in addition to rehabilitation of the Lahore yard, and remodeling of the Shahdara and
Wazirabad yards for removing existing permanent speed restrictions, improvements in
telecommunication systems, and provision of a signaling system.
4. The second tranche (Project 2) will include realignment of Kaluwal–Pindora section and
removal of speed restrictions on Lalamusa-Rawalpindi section to increase the speed up to 120
Km/h, besides improvement in telecommunication system and provision of a signaling system.
The existing track of 53 km between Kaluwal (near Dina) and Pindora (near Gujar Khan) has
very sharp curves and ruling grades due to which speed is restricted to 65 kph. After
realignment of the section, the speed will be increased up to 105 kph and the distance will also
be reduced by about 17 km; thus reducing the travel time between Lahore and Rawalpindi to
about 3 hours. The existing line between Kaluwal and Pindora stations will be retained for
freight traffic and running of departmental trains.
5. The third tranche (Project 3) will include the rehabilitation of 174 km of track from
Rawalpindi to Peshawar Cantt section, besides improvement in telecommunication systems
The views
and expressed
provision of aherein are those
signaling of the consultant
system. The trackand do not necessarily
between represent those
Rawalpindi–Golra of ADB’s
Sharif members,
is double line
Board of Directors,
section, whereasManagement,
the remainingor staff, and may
section be preliminary
is single line. in nature.
2
6. At the national level, the Ministry of Environmental (MOE) is the main governmental
agency that pursues environmental policy, implements ministerial control and coordinates the
activities of natural resources’ use and protection. Previously named the Ministry of
Environment, Local Government and Rural Development, it was bifurcated in 2002 and an
independent MOE was established to focus on the issues of environment, ecology, human
settlement and forests in Pakistan.
9. Under the Pak-EPA, there are also Provincial Environmental Protection Agencies in
each province of Pakistan. Their primary responsibility of enforcing environmental protection
laws is delegated to provincial protection agencies under section 26 of the Environmental
Protection Act. Figure 1 shows the organizational structure for the Punjab EPA.
11. The Pakistan Environmental Protection Act of 1997 is the basic environmental law of
Pakistan. The apex body established under the Act is the Pakistan Environmental Protection
Council. Pakistan Environmental Protection Agency was created under Pakistan
Environmental Protection Ordinance 1983. Its powers were enhanced under the
Environmental Protection Act of 1997.
12. The Act particularly focuses on the implementation of the Pakistan Environmental
Protection Council’s
The views expressed policies,
herein are thosedelegation of power
of the consultant to necessarily
and do not government agencies,
represent those of enforcement of
ADB’s members,
national Environmental
Board of Directors, Management, Quality
or staff, andStandards, andin nature.
may be preliminary introduction of EIA/IEE review
procedures/systems. The Act also addresses the regulatory regime for hazardous
substances/wastes, resource generation through establishment of a Provisional Sustainable
4
Development Fund and levying of Pollution Charges and providing appellant forum for
environmental cases.
13. The National Environmental Quality Standards (NEQS), on the other hand, specify the
following standards:
14. The negative impacts associated with major transportation projects are described in the
Pakistan Sectoral Guidelines for Environmental Reports. Those are part of a package of
regulations and guidelines, which includes:
15. The environmental laws, regulations, and standards which control the environmental
impacts of each environmental parameter are described by the Pakistan Environmental
Legislation and the National Environmental Standards issued in October, 1997. The
description of the environmental impacts controlled by the Pakistani environmental laws and
regulations are described in Table 2. The relevant environmental laws and regulations are
presented in Table 3.
5
The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members,
Board of Directors, Management, or staff, and may be preliminary in nature.
6
16. The Environmental Impact Assessment (EIA) is a rapidly growing field of work and has
become a mandatory legal requirement in Pakistan. The formalized arrangements for the
implementation of an EIA system in Pakistan evolved over a period of fifteen years. It started
with the promulgation of the Pakistan Environmental Protection Ordinance (PEPO) of 1983
(repealed in 1997). The following are the key milestones that Pakistan’s environmental
protection requirements have passed through:
(i) EIA became mandatory for all new projects in July 1994;
(ii) Documentation of sectoral guidelines as an EIA Package became
effective in1997;
(iii) Enactment of the Pakistan Environmental Protection Act, 1997;
(iv) Development of the Pakistan IEE/EIA Regulations of 2000;
(v) Finally, the National Environmental Policy was developed in 2005. It
describes
The views expressed herein areintegration of the and
those of the consultant environment into represent
do not necessarily development
those of planning
ADB’s members,
Board of Directors, Management,
through or staff, and may be
the implementation of preliminary in nature.at the project level. It also
the EIA process
promotes Strategic Environmental Assessment (SEA) as a tool for
integrating the environment into the decision-making process.
8
Screening Process
EIA required refer Schedule-II IEE required, refer Schedule-I No IEE/EIA required refer
Schedule-III
N
Scoping/baseline collection of data from site
Finding of
Non- Yes
*Then Process for approval
Submitted to Significant to EPA is concerned
Impact analysis to indentify EPA i t
Environmental impacts during
construction and operation
periods
Consideration of mitigation
measures
Public
EIA report submitted for involvement/
consultation
Approval
Not Approved
Redesign Implementatio
n and Follow
Resubmitted
18. In terms of the steps in the IEE/EIA preparation process itself, according to Pakistan’s
requirements, developers shall consult with the responsible project authority to confirm the
categorization of the project, and to ensure that they are aware of the procedures that apply at
the earliest possible time. Proponents may have already engaged consultants at this time,
and shall be aware that the proper specification of the consultant’s task will only become clear
as the work on the IEE and other scoping activities are undertaken. Proponents and their
consultants shall visit the site, talk with local people about their values and the proposals,
collect available data, and consult with other departments and stakeholders. Figure 3
illustrates the EIA working layout.
9
19. To help the proponent throughout the preparation of the EIA report, the Pakistan
Environment Protection Agency in collaboration with other key stakeholders have prepared an
“EIA Package” which includes both General Guidelines and Sectoral Guidelines. The following
are the general guidelines that shall be followed in the railway sector projects:
(i) Policy and procedures for making the EIAs, review and approval of
environmental assessments;
(ii) Guidelines for the preparation and review of environmental reports;
(iii) Guidelines for public consultation;
(iv) Guidelines for sensitive and critical areas; and
(v) Pakistan environmental legislation and National Environmental Quality
Standards (NEQS).
20. In regard to the sectoral guidelines, the Pakistan Sectoral Guidelines for Environmental
Reports shall be followed as well as the format of the IEE/EIA as prescribed in the EIA
Package (i.e., Pak EPA Regulations for the year 2000).
The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members,
Board of Directors, Management, or staff, and may be preliminary in nature.
10
21. With the exception of Project 2, the MFF will mainly involve rehabilitation of existing
track and rehabilitation of bridges, culverts, and other associated drainage structures; site
preparation; land clearing; disposal of gravel, soil, vegetation, and unstable material; setting up
of temporary construction camps to house workers; extraction of material for embankments
using cut and fill procedures; protection of landslide, measures to protect critical side-slopes;
and works, and asphalt plants.
22. The second tranche project (Project 2) will include the realignment of the Kaluwal–
Pindora section and removal of speed restrictions on the Lalamusa–Rawalpindi section to
increase the speed up to 120 kph, besides improvement in telecommunication system and
provision of CBIS signaling system. The existing track of 53 km between Kaluwal (near Dina)
and Pindora (near Gujar Khan) has very sharp curves and ruling grades due to which speed is
restricted. Realignment of the section would require preparation of a land acquisition and
resettlement action plan. Detailed information about the type of land along the approved
alignment and its market price will be collected during the field survey for costing purposes.
The area is generally barren and hilly with cultivation in patches. The people are mostly
agriculturists but their holdings are too small to provide subsistence. An EIA study will also be
conducted besides carrying out social development and poverty alleviation.
23. Application of mitigative and monitoring actions should be applied as defined in the
model environmental mitigation and monitoring plan (Appendix 1).
24. The Ministry of Railways will act as Executing Agency and the overall technical and
administrative authority for this MFF. Leading the day-to-day implementation of the project as
a whole will be a Program Management Unit (PMU) located within the MoR. The PMU will,
inter alia, conduct package screening, classification, information disclosure and consultation
with project-affected people. It will also incorporate all consulting services under the project,
including assistance to the provinces and will oversee the conduct of feasibility studies
(including environmental studies) by project consultants.
26. The MoR will be the executing agency (EA) for the individual subprojects. That is, they
form a PMU who will hire a Construction Supervision Consultant (CSC) and also establish a
Safeguards Team (ST) to oversee the planning and implementing of monitoring and mitigation
measures during detailed design and rehabilitation of the railway section. The actual work
during the construction period will be completed by the contractors. For the operation period
the responsibility will be handed over to Pakistan Railways as the implementing agency. The
implementing agency’s (IA) responsibilities will include:
(i) Ensuring that EMP tasks including relevant mitigation and monitoring measures
needing to be incorporated during the pre-construction stage are implemented;
(ii) Ensuring that any EMP tasks including relevant mitigation and monitoring
measures needing to be incorporated during the construction stage by the
contractor are included in the bidding documents and are implemented;
(iii) Ensuring that contractors have access to the EIA or IEE and EMP reports of the
projects, confirming that contractors understand their responsibilities to mitigate
environmental problems associated with their rehabilitation and construction
activities;
(iv) Investigating and reporting on environmental effects stemming from any design
and construction changes added after the detailed design is completed, leading
to unpredicted environmental impacts;
(v) Submission to the ADB of semi-annual reports on implementing EMPs,
including any emergency programs;
(vi) Submitting project environmental mitigation and monitoring completion report to
ADB, three years after the start of the operating period of the project; and,
(vii) Ensuring that EMP tasks including relevant mitigation and monitoring measures
needing to be incorporated during the operating period are implemented
2. The Contractor
27. Unless the IA has inspectors in the field constantly and undertakes the construction-
period mitigation and monitoring, the contractor must fill that role. Often contractors have no
such expertise and must either hire staff or a consultant to provide the expertise to help them
implement all mitigative and monitoring tasks defined in the EMP. The contractor is therefore
responsible for:
12
(i) Reviewing EIA or IEE reports prepared by the EA, or the consultant on their
behalf and provide a no objection note as needed;
(ii) Undertaking annual environmental review missions for category A and B
sensitive projects; and
(iii) Disclosing to the public on the ADB website, the executive summary of the EIA
and IEE (for category B sensitive projects only), but preferably the entire EA
documentation in English and the local language.
29. Considering the potential environmental impacts of the future subprojects and the
relevant environmental requirements of ADB and the Government of Pakistan, the following
environmental criteria should be applied for the selection of future subprojects in the Railway
Development Investment Program:
(i) Each Project must not have any one of ten activities that are classified as
restricted in Annex 5 of ADB`s 2009 Safeguard Policy Statement;
(ii) Each Project shall only involve activities that comply with government
regulations;
(iii) Each Project should not permanently degrade any culturally, archaeologically or
environmentally important site, habitat or species designated as protected or
significant by the GoP or an international agency; and
(iv) The alignment and design changes planned for each Project will be discussed
in detail with local communities along the RoW and suggested modifications
considered, recorded and implemented if appropriate; before the detailed
design stage is completed.
30. ADB classifies all of its projects into one of three environmental assessment
categories, namely “A” through “C”. Projects with potential for significant adverse
environmental impacts are classified into category A, requiring a complete EIA. Projects
judged to have some adverse impacts, but less severe, mostly reversible effects, and where
impacts and mitigative measures are well understood (based on past experience), are
classified as category B projects. These require an initial environmental examination (IEE).
The IEE can also act as an EIA screening document and indicate when a full EIA is needed to
fully address environmental matters. Under ADB guidelines, if an EIA is not needed, the IEE is
regarded as the final environmental assessment report.
31. The guidelines to prepare ADB-compliant environmental assessment are found in the
ADB`s 2009 Safeguard Policy Statement (SPS) Annex 1 on www.adb.org/Safeguards.
32. If ADB funding is involved in any future project, ADB`s EA process is the preferred
procedure to be applied. Otherwise, the categorization and process defined in GoP
regulations, with reference to all appropriate regulations should be applied. For existing and
future projects the ADB process is to be applied, but with careful consideration of and
compliance with GoP standards. To that end the ADB`s step-by-step process, annotated with
the GoP requirements is summarized below
13
1. Screening
33. STEP 1: All future subprojects to be included in the MFF will be screened to determine
their environmental category based on the ADB’s Rapid Environmental Assessment Checklist
(REA). A suggested template of the REA, based on the ADB’s format, is provided in the
Appendix. Categorization is established by defining the most environmental sensitive
component and the extent and duration of the impact on that component. If this analysis
identifies a significant impact and the component affected is in a special category and even if
other components remain unaffected, the project is classified according to the most sensitive
component.
35. Railway upgrading and rehabilitation subprojects that do not involve any of the three
conditions defined above and which do not trigger any of ADB’s 10 no-funding conditions
(Annex 5, ADB SPS, 2009) are classified as B.
36. Projects involving training and purchase of equipment usually do not involve any
impacts and are classified as category C. These still require a short report justifying their
classification and why no impacts are predicted.
37. GoP classifies any railways project as one needing an EIA to be completed.
2. Scoping
39. With the screening and scoping completed, yielding a project classification and
boundary, the planning and execution of the field program is the next important task. This work
should involve an experienced environmental assessment practitioner, and is summarized on
the following eight subsections.
40. In GoP’s requirements the scoping phase as a vital one that determines valued
environmental components that could be affected by a project. It is described as a process of
interaction between the public, the government, and the proponent.
3. hereinIdentifying
The views expressed Baseline
are those of the consultantConditions and Impacts
and do not necessarily represent those of ADB’s members,
Board of Directors, Management, or staff, and may be preliminary in nature.
41. STEP 3: Establishing the baseline conditions for the components of the environment
likely affected by the project is completed with a thorough review of existing information, site
14
visits and the collection of any available and relevant databases, such as for
terrain/topography, soils, geology, forest cover, protected areas, land use, and all ambient air,
noise and water quality conditions in the project corridor. This baseline will become the
conditions against which any changes due to project effects will be measured. All data must be
collected so that their source can be traced by anyone who picks up the document.
42. STEP 4: This step involves predicting likely change as a result of major construction
activities and operation of the railway, by relating cause with effect such as changes in traffic
volume, fleet makeup and traffic patterns degrading air quality and noise. The locations where
base data are collected, or where monitoring takes place and the timing of these activities
should remain uniform or at least easily traceable, permitting future comparative analysis or
audits of the technical credibility of the assessment. While following strict scientific methods in
preparing an EIA is far too costly and time consuming, every effort should be made make the
EA work ‘transparent’ and traceable.
44. STEP 5: The objective of public consultation is to engage the general affected public as
well as government officials at several levels in a dialogue leading to better mitigative
measures, helping to identify oversights regarding impacts. The consultation must be
preceded by the provision of information on the project to the affected communities; often via a
written short booklet accompanied by an invitation to attend a workshop/information session. It
is important to provide enough lead time (at least 3 weeks) for communities to attend such
sessions.
46. STEP 6: The preparation of the EMP is one of the two most important outputs of an
environmental assessment. The EMP must be practical, specific and systematic, such that it
can easily be converted to mitigative and monitoring actions which:
47. Therefore each mitigative measure needs to be matched with a monitoring activity.
48. Good EMPs not only identify the source of the impact, the effect on the biophysical
environment and the monitoring action to be taken, but also where, how often, when and who
should implement each mitigative and monitoring action and who is responsible. This is the
same for both EIAs and IEEs.
49. With a record of impact source, impacts and location, the EIA/IEE team should at this
point systematically record each predicted impact occurrence, define an appropriate mitigative
action that either prevents the impact or reduces it a level acceptable under national standards
or international best practice, and then specifies when, where and who should implement and
supervise each action.
50. The PMU is required to review and update the EMP as soon as the contractor has
been appointed and the mobilization date is established.
15
52. STEP 7: involves the identification of the agencies and units at the national and
provincial level that will likely be involved in the management, implementation and supervision
of the mitigation and monitoring actions from preconstruction through the operating period. The
EMP should identify the lead implementing and supervising agencies and their provincial
counterparts involved in all mitigation and monitoring actions. The assessment, using mostly
the interview approach, should be short and focused, identifying needs based on obvious
gaps, such as lack of experience in any international-level assessments or lack of experience
with preparation and implementation of EMPs. Careful interviews will almost always result in
those needing assistance identifying what they need most. Finally appropriate capacity
building actions addressing both longer term and short term requirements, in relation to
realistic budgetary limits need to be specified and costed.
53. Since the contractors play such an important role in EMP implementation, they must
not be left out of the analysis and a general approach to strengthening their safeguards skills
must be included in the analysis, and recommended actions.
54. GoP’s process has similar related to the capacity and training needs of the project
management entities.
55. STEP 8 involves costing of each of the mitigative and monitoring actions as well as the
institutional capacity building. Costing details must be systematic and include rates and unit
costs and an indication of actions that, while referred to as environmental, are normally found
in other budget items, for example slope stabilization, re-vegetation, fuel handling and storage
protocols and work camp waste management; therefore reducing the risk of double counting.
This estimation is done by using the EMP columns that identify the mitigative action and
associated monitoring task, then estimating the cost to undertake each. It is important to
separate capital or one-time expenses to reoccurring costs, such as compliance monitoring
during the construction period.
56. Costing of mitigation and monitoring is undertaken under the GoP's environmental
assessment process.
8. Reporting
57. STEP 9. While listed as the last EA step, the preparation of the EA document should
begin at the very start of the work, with the completion of a detailed Table of Contents (based
on the mandatory content defined in the ADB’s SPS (2009) (Annex 1 & 2) or as specified in
the relevant national standards. Having a clear vision of what must go into the EA document,
helps with the collection and analysis of the appropriate information. .
58. GoP requirements explain in great detail the reporting requirements, and what
constitutes successful reporting. It also provides details on the report review process.
The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members,
Board of Directors, Management, or staff, and may be preliminary in nature.
16
59. The EA team, in collaboration with the project Executing Agency, needs to present the
project, its location and timetable for implementation, an overview of the EA process, and any
findings on impacts and benefits. These findings must be defined as tentative or interim,
indicating that participants’ input can still be applied to project planning and design. The
participants should be explicitly invited (not instructed) to provide comments and corrections to
what is presented. Adequate and convenient contact information for use by participants should
be provided.
60. For a category A project consultation is required at least twice during the EIA: (i) first as
part of the scoping stage to define the project and to get feedback on options, and (ii) fter the
draft EMP has been prepared.
61. Public consultations for full EIAs include newspaper advertisement(s) in the regional
and national news papers at least one month before the session(s) is to take place. The
announcement should provide a brief project description, location and specific contact data
(including telephone numbers). Sometimes, a project website is created containing more
details on the project and a link provided in the announcement.
62. For category B projects, nearly all conditions as defined above are the same except
only 1 consultation session is needed., there is no newspaper advertisement, and no written
invitations (a list of potential attendees and contact should be made). Often, the consultation
session takes place at the time when the EMP is being prepared.
63. Consultation sessions must have minutes and attendance sheets prepared and
included as part of the environmental assessment documentation.
64. ADB requires that the Project Executing Agency (Ministry of Railways) establish and
maintain a grievance redress mechanism to receive and facilitate resolution of affected
peoples’ concerns and grievances about its delivery of environmental safeguards at the project
level, as defined in the assessment documents (primarily the EMPs). The grievance redress
mechanism should be scaled to the risks and impacts of the project. It should address affected
people's concerns and complaints using an understandable and transparent process that is
gender responsive, culturally appropriate, and easy to access.
65. To that end the Executing Agency, in cooperation with the Punjab Province and
impacted areas, will establish an environmental issues’ specific Grievance Redress
Committee(s) (GRCs). At the provincial level these will be comprised of the head of the
environmental planning department and two members, one being a woman and one being
identified as the point of contact for any grievance claim. A local government representative for
district specific issues shall also be included in the GRCs. The Pakistani environmental
guidelines describe procedures for the appointment of Environmental Monitoring Committees.
The roles of such committees would have to be further described to take the ADB
requirements into consideration.
17
VI. Monitoring and Reporting
A. Monitoring
66. Monitoring is required during all three stages of a project, i.e. planning, rehabilitation
and operation to record the mitigative actions taken and the resulting effects designed to either
avoid or reduce predicted impacts. The preparation and oversight of any monitoring work is the
responsibility of the Executing Agency and its consultant.
67. Monitoring during the planning stage usually takes place twice; once to incorporate
mitigative measures in the planning process and then at the end of that stage to monitor
compliance. Works’ monitoring takes place at regular intervals throughout the project period,
usually quarterly, with bi-annual monitoring reports.
68. Operating period monitoring is dependent on the types and duration if impacts
identified during the environmental assessment, but usually are completed annually for three
years, for a variable time period. Some of the monitoring during both the implementation and
operating periods will require sample collection as well as field measurements
B. Reporting
69. The best approach to reporting is to use the EMPs mitigation and monitoring tables,
collapse these into one table showing the mitigative measures and monitoring requirements;
then add columns to record actions taken, dates and results observed. This plus some text
would form the monitoring reports.
70. Well prepared EMPs present the impacts mitigative actions and monitoring
requirements throughout the project, including not only what needs to be monitored but where
and for what duration.
71. During the planning stage the Executing Agency will be required to prepare a planning
stage monitoring checklist confirming all the items listed in the EMP.
72. Prior to the mobilization of the contractor(s) the EMP’s construction period mitigation
and monitoring tasks need to be converted into a construction period action plan by the
contractor, working in cooperation with the PMU. This plan then forms the basis of the
construction period mitigation and monitoring task list and can be used as a monitoring
checklist. Major responsibility for implementation of these actions will rest with the
contractor(s), supervised by the Executing and Implementing Agencies or the PMU. Interim
monitoring reports are to be complete every 6 months, but monitoring checklists every 3
months.
73. Within 4 months of the end of the construction period the Executing Agency or its PMU
should instruct the contractor(s) to prepare the construction period environmental mitigation
and monitoring summary. This report needs to be handed to the operating unit of the Project.
74. The railway operator, likely PR, will use this report and the items defined under
Operating Period in the EMP, to develop its monitoring activity, and file bi-annual reports (short
checklists usually no more than 2-3 pages).
The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members,
75.
Board ofThe ADBManagement,
Directors, requires that monitoring
or staff, and mayreports should
be preliminary in be submitted 2 times per year during
nature.
the construction period and also twice a year for three Project operating years.
18
Instructions:
(i) The project team completes this checklist to support the environmental classification of a project. It
is to be attached to the environmental categorization form and submitted to the Environment and
Safeguards Division (RSES), for endorsement by Director, RSES and for approval by the Chief
Compliance Officer.
(ii) This checklist focuses on environmental issues and concerns. To ensure that social dimensions are
adequately considered, refer also to ADB's (a) checklists on involuntary resettlement and
Indigenous Peoples; (b) poverty reduction handbook; (c) staff guide to consultation and
participation; and (d) gender checklists.
(iii) Answer the questions assuming the “without mitigation” case. The purpose is to identify potential
impacts. Use the “remarks” section to discuss any anticipated mitigation measures.
Country/Project Title:
Sector Division:
Protected Area
Wetland
Mangrove
Estuarine
20
Small Islands Small islands generally have land areas of less than 10,000km2 in area, though Papua New Increased salinity increases corrosion of
Guinea and Timor with much larger land areas are commonly included in lists of small island materials which can break-down, Alignment
developing states. Low-lying islands are especially vulnerable to storm surge, tsunami and sea- is eroded by increased wave action,
level rise and, frequently, coastal erosion, with coral reefs threatened by ocean warming in some Increased flooding from overtopping of sea-
areas. Sea level rise is likely to threaten the limited ground water resources. High islands often water over facility or salt-water intrusion in to
experience high rainfall intensities, frequent landslides and tectonic environments in which groundwater,
landslides and earthquakes are not uncommon with (occasional) volcanic eruptions. Small islands
may have low adaptive capacity and high adaptation costs relative to GDP.
Mountain Accelerated glacial melting, rockfalls/landslides and glacial lake outburst floods, leading to Damage to infrastructure from landslides and
Ecosystems increased debris flows, river bank erosion and floods and more extensive outwash plains and, mudflows, permafrost melting causes
possibly, more frequent wind erosion in intermontane valleys. Enhanced snow melt and damage to facilities, glacial lake outbursts
fluctuating stream flows may produce seasonal floods and droughts. Melting of permafrost in wash out river-crossings.
The views expressed herein
someareenvironments.
those of the consultant
Faunal andandfloral
do not necessarily
species represent
migration. those of ADB’s
Earthquakes, members,
landslides and other
Board of Directors, Management, or staff,
geophysical andmay
hazards mayalso
be preliminary in nature.
occur in these environments.
Volcanic Recently active volcanoes (erupted in last 10,000 years – see www.volcano.si.edu). Often fertile Damage and loss of railways, insecurity for
22
Example Impact on Transportation
Environment Natural Hazards and Climate Change
Infrastructure
Environments soils with intensive agriculture and landslides on steep slopes. Subject to earthquakes and works crew and maintenance
volcanic eruptions including pyroclastic flows and mudflows/lahars and/or gas emissions and
occasionally widespread ash fall.
23
I. Rehabilitation Phase
1. Air Quality
Dust and emissions
generated from machinery
Dust control measures such as spraying of
and vehicles, movement of Included in
work sites and stock piles; covering vehicles Rehabilitation
trucks and trains to transport Environment Rehabilitation
and trains transporting materials, proper Sites and vicinities Contractor Punjab-EPA
materials. Gaseous Protection Investment Period
maintenance of equipment, fuel efficiency, and
emissions from vehicles Table
minimizing idling of machinery
operating during the
rehabilitation works.
2. Water and wastewater
24
The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members,
Board of Directors, Management, or staff, and may be preliminary in nature.
26
Noise Barriers (also for safety) meter 3,200 0.02 55.25 $848,000
Sub-total 59.07 mill $695,000
2. Water
D. Capacity Building
Training in environmental monitoring 12.75 $150,000
lump
Training in environmental management sum 12.75 $150,000
Sub-total: 25.5 $300,000
D. Environmental Impact Assessment
Studies
EIA for Project 2 12.75 $150,000
EIA for Project 3 12.75 $150,000
Sub-total: 25.5 $300,000
Grand Total: $2,183,070