Professional Documents
Culture Documents
GE Power Generation
GE Power Generation
1
GER-3764A
Table 1
GE-DESIGNED GAS TURBINE WORLDWIDE EXPERIENCE (AS OF FEBRUARY 1994)
WITH HEAVY ASH-BEARING FUELS
GT24235A
Figure 1. Firing temperature operating experience
2
GER-3764A
drive, logged 10,000 hours of service, nearly 8,000 tures of 1850F (1010C). No corrosion on uncoat-
of which were achieved on a variety of residual oils ed turbine buckets has been experienced. Three
which were desalted and treated on board. During types of magnesium additives, water soluble, oil
this period of operation the hot gas path was com- soluble, and suspendible solids, were evaluated,
pletely free of corrosion. and it was shown that magnesium oxide slurries
can be added to heavy fuels without any adverse
Continuing Experience — effects on fuel pumps and flow dividers.
Late 1960s On In addition to the numerous Frame 5
machines, many larger Frame 7 units were also
In the decade of the late 1960s to the late installed in this time period using heavy oil as the
1970s, over 150 GE machines were installed with primary fuel.
heavy fuel capability. The majority of these were Ten units (MS7001B) were operated by Florida
used for power generation, both utility and indus- Power Corp. at its Bartow and DeBarry stations. At
trial, with others operating as mechanical drive Bartow, the fuel was a high wax Libyan crude
machines and for ship propulsion. Within this which was electrostatically desalted and inhibited
time frame, more than one million hours were with an oil soluble magnesium additive; it was also
accumulated, and several units achieved in excess heated to 100/110F (38/43C) to avoid fuel filter
of 30,000 hours each. Unit ratings ranged from 10 plugging. These machines operated successfully at
MW to 65 MW, with firing temperatures of 1450F 1840F (1004C) firing temperature in peak load
to 1850F (788 - 1010C). mode between 1972 and 1976, when the crude
Nine Frame 5 machines in Indonesia (Caltex), fuel became unavailable. Turbine washing to
were used for power generation to pump crude remove combustion ash deposits was performed
oil. The fuel was a waxy crude with low vanadium every three months. Residual oil with up to 33
(0.5 ppm) that was water washed to reduce sodi- ppm sodium and 40 ppm vanadium was used at
um concentration from 10 ppm to less than 1 DeBarry and washed to reduce sodium to less
ppm. The units were baseloaded at a firing tem- than 1.0 ppm by a three stage electrostatic
perature of 1650F (898C). Although no current desalter; vanadium was inhibited by an oil soluble
operating data is available, the machines had magnesium additive.
accumulated well over 200,000 hours in 1984, with Another example of Frame 7 experience is the
more than 50,000 hours on some individual units. Alcoa Aluminum Bauxite plant in Paramaribo,
Hot gas path inspections were performed every Surinam. The unit went operational in 1976 using
10,000 hours, major inspections every 20,000 Trinidadian residual oil. The raw fuel had sodium
hours, and the U700 turbine buckets provided levels from 80 to 125 ppm and vanadium varying
excellent service to beyond 28,000 hours. Ten from 65 to 85 ppm. Fuel treatment is achieved
machines in France (Rhone-Poulenc), have with a De Laval centrifugal washing system and
logged well over one half million hours of service injection of oil and water soluble magnesium in
at firing temperatures of 1650F (898C). The units’ the ratio of three magnesium to one vanadium.
high-viscosity fuel requires heating to 140F (60C), Initial operation indicated some minor problems
and air atomization for combustion. Some individ- with the fuel pump, flow divider and fuel nozzle
ual units have delivered in excess of 50,000 hours plugging when using water-soluble additive. A
of service. stainless steel screw-type positive displacement fuel
Additional machines in North Africa and Italy pump and the addition of corrosion resistant
have also run at 1650F (898C) firing temperature materials to the flow divider eliminated two of the
on residual fuel containing high levels of vanadi- problems. Fuel nozzle plugging was eliminated by
um and sodium before washing. Electrostatic pre- more thorough mixing of the magnesium and
cipitators provided desalting, and the fuel was fuel with a centrifugal pump which allows the use
inhibited with an organic oil-soluble magnesium of the less expensive water-soluble additive; oil-sol-
additive. uble additive is retained as a backup.
A comprehensive test program was run on a Unit operation through July 1987 occurred at a
Frame 5 unit at the GE facility in Lynn, firing temperature of 1750F (954C), and 25,000
Massachusetts to demonstrate the capability of hours were accumulated. Since a major overhaul
burning oils at high firing temperatures. Both in 1987, the unit had been exercised monthly
electrostatic and centrifugal desalting systems until November 1992, when it was placed back
were installed for evaluation, and the unit has run into continuous ser vice at reduced load.
on a variety of residual fuels up to firing tempera-
3
GER-3764A
Inspection results indicated little to no corrosion fuel. It appears that in the Central, Western and
problems on the turbine nozzles or buckets, and Southern regions of SCECO, turbine bucket fail-
nozzle corrosion life (FSX-414 material) far in ures due to corrosion have been common on
excess of 25,000 hours. competitors machines using light Arabian crude
and blends of crude/distillate. The problems
Saudi Arabian Experience seem to occur on the first and second turbine
stages after relatively few hours (10 - 15,000), and
Most recent operating experience with heavy
many machines have had both stages replaced at
ash-bearing fuels (in excess of two million hours)
least once in the past ten years. In addition, out-
has occurred on numerous GE-designed
put degradations of as much as 30% have been
machines in Saudi Arabia. Riyadh Power Plant #7
reported.
(PP7) is an outstanding example, where sixteen
A further comparison can be made with units
Frame 7E machines have run continuously on
situated in Taiwan, where GE Frame 7Es and com-
crude at a firing temperature of 1740F (949C) for
petitor units operate at the same site and on the
the past fourteen years. The fuel, light Arabian
same no. 6 residual fuel. Again, the competitor
crude, is supplied directly from the Riyadh refin-
units have suffered turbine bucket corrosion
ery and has 10 to 30 ppm vanadium; it is washed
requiring premature bucket replacement, while
on site and a magnesium additive is introduced in
the GE units have been free of these problems.
the ratio of 3:1 Mg:Va. Turbine base heating is
Overall, the GE machines have been utilized
normal, and the units start and stop on the crude
almost twice as much as the other manufacturers’
fuel. After more than one million hours at PP7,
equipment, with each GE unit accumulating
there have been no significant problems in the
approximately 1,600 hours per year as opposed to
hot gas path. Most of the units still have their orig-
about 900 hours on the competitors’ units.
inal turbine buckets. Turbine water washing is
performed on each unit at monthly intervals.
Currently at PP7, GE is installing 4 additional
Significance of Field Experience
Frame 7EA machines. These machines utilize the Extensive field operating experience accumu-
same crude oil as the existing 16 units. These lated on GE gas turbines burning heavy oils pro-
units have a firing temperature of 2000F (1093C) vides a time-tested evaluation of the ability of
and are expected to have a water wash interval of these machines to operate economically and reli-
approximately 1000 hours. ably over extended periods. Early experience of
In addition to PP7, there are twenty-eight other units operating at lower firing temperatures is
GE-designed machines operating in the Kingdom highly relevant to the heavy fuel operation of
either on similar crude or blends of distillate and today’s gas turbines with higher firing tempera-
crude. These units include Frame 5s, 6s and 7s tures. The extensive heavy-fuel technology devel-
installed in Saudi Consolidated Electric oped during this early period includes:
Company’s (SCECO) Central, Western, Southern • Determination of effects of trace metal con-
and Eastern regions at sites such as Jeddah, taminants (vanadium, sodium and potassi-
Tihama and Quaisumah. They have accumulated um) on high temperature materials
more than one million operating hours. employed in the turbine.
GE-designed machines in Saudi Arabia have • Development of appropriate fuel treatment
operated satisfactorily on various crudes and systems to remove or inhibit the corrosive
crude/distillate blends for over two million hours. trace metal contaminants.
Since the majority of the machines are used in • Determination of the relationship of fuel
baseload or mid-range applications, operating quality and trace metal contamination limits
hours continue to accumulate rapidly. to reliable operation.
• Evaluation of ash deposit rates, including
Competitive Experience methods of cleaning and their effect on per-
formance.
Heavy duty machines installed by our three
• Development and design of combustion sys-
major competitors have about half the total oper-
tems and fuel handling and control systems.
ating hours of GE units using heavy ash-bearing
This technology base has now been extended
fuels. Most current experience has been in Saudi
to the higher temperature MS7001EA and
Arabia, where several competitor units operate
MS9001E machines. The total GE experience on
side-by-side with GE machines and use the same
ash-bearing fuels is unparalleled in the industry.
4
GER-3764A
5
GER-3764A
nozzles and buckets are also internally cooled, path. The vibration-resistant design has enabled
similar to the first stage. GE gas turbines to operate reliably while subject-
Buckets are subjected to gas forces which can ed to these stimuli.
cause bucket vibration. Resonance between forces Several test techniques are used to assure ade-
and bucket natural vibration modes are avoided at quate vibration margin. Stationary bench testing
full operating speed. However, resonance cannot is used to drive a bucket through a range of fre-
be avoided during startup and shutdown. All GE- quencies to identify its natural modes. Wheelbox
designed turbines incorporate features to sup- testing is performed in a large, evacuated cham-
press resonant vibration. These include the long- ber in which full turbine stages are run through-
shank bucket with a friction type connection at out the operating speed range to determine buck-
the bucket platform and a tip shroud (Figure 3). et vibration response. Gas force excitation is
In the long-shank bucket design, damping is generated by an array of nozzles which direct high
introduced near the midspan by placing axial pins velocity air at the buckets. Vibration data from
underneath the platform between adjacent buck- strain gauges mounted on the buckets is fed
ets. In the first stage, the damping provided by through slip rings into a processing facility, where
these pins virtually eliminates all vibration involv- both tape recording and on-line analyses are pos-
ing tangential motion and controls vibration in sible. Thorough testing, combined with extensive
the other modes. The shank also provides thermal service experience, provides a sound design basis.
isolation between the gas path and the turbine Since 1958, when these concepts were introduced,
wheel dovetail. Since the shank is a uniform unre- no bucket of this design has experienced a vibra-
strained section, stress concentrations in the dove- tion failure in the shank or dovetail.
tail are minimized.
The integral tip shroud is the second major Combustion Design
vibration control feature. These are used on the
All modern GE heavy-duty gas turbines use
long second and third stages. The individual
multiple reverse-flow combustors similar to that
bucket shrouds are interlocked to form a continu-
illustrated in Figure 4. Each combustor is com-
ous band during operation. The natural tendency
posed of a liner, transition piece, and fuel nozzle,
for the buckets to untwist under centrifugal load
chosen for its fuel flexibility, maintainability, and
is used to force the mating faces of adjacent
ease of testing at full pressure, temperature, and
shrouds together, providing friction damping.
flow conditions in the laboratory. The design
The tip restraint provided by the continuous
objectives for a combustor are listed in Table 2.
shroud band eliminates the first flexural mode of
Air atomizing fuel nozzles (Figure 5) are uti-
vibration, which is the most sensitive.
lized for liquid fuel applications. Air pressure
Turbine deposits from heavy fuels cause ran-
atomizes the fuel to assure complete combustion
dom aerodynamic vibration stimuli in the gas
and a smoke-free stack over the operating range
of the gas turbine.
Figure 4 shows that compressor discharge air
flows around the transition pieces while cooling
them. It enters the combustion liner through vari-
ous air passages in the liner. Fuel injected into the
GT19690A
Table 2
COMBUSTION DESIGN OBJECTIVES
GT24242
7
GER-3764A
8
GER-3764A
9
GER-3764A
GT24521
Figure 10. Deposits of sea salt on MS7001 first-stage nozzle partitions and buckets. Note condensates
in locally cooled surfaces
10
GER-3764A
GT24527
11
GER-3764A
GT03480B
12
GER-3764A
GT8909E
presence of only a few parts per million (ppm) of Figure 16. Hot corrosion (high-temperature
such contaminants in the fuel, or equivalent in type)
the air, is sufficient to cause this corrosion.
Sodium can be introduced in a number of ways
such as salt water in liquid fuel, through the tur-
bine air inlet at sites near salt water or other con-
taminated areas, or as contaminants in
water/steam injections.
There are now two distinct forms of hot corro-
sion recognized by the industry, although the end
result is the same. These two types are high tem-
perature (Type 1) and low temperature (Type 2)
hot corrosion.
High temperature hot corrosion has been
known since the 1950s. It is an extremely rapid
GT11639
form of oxidation which takes place at tempera-
Figure 17. Hot corrosion (low-temperature
tures between 1500F (816C) and 1700F (927C) in type)
the presence of sodium sulfate (Na 2 SO 4 ).
Sodium sulfate is generated in the combustion corrosion characteristically shows no denuded
process due to the reaction between sodium, sul- zone, no intergranular attack, and a layered type
fur and oxygen. Sulfur is present as a natural con- of corrosion scale.
taminant in the fuel. Besides the alkali metals such as sodium and
Low temperature hot corrosion was recognized potassium, other chemical elements can influence
as a separate mechanism of corrosion attack in or cause corrosion on bucketing. Most notable are
the mid-1970s. This attack can also be very aggres- vanadium, primarily found in crude and residual
sive if the conditions are right. It takes place at oils, and lead, most frequently resulting from
temperatures in the 1100F (593C) to 1400F automobile exhaust emissions or as a transporta-
(760C) range and requires a significant partial tion contamination from leaded gasolines.
pressure of SO2. It is caused by low melting eutec- The lines of defense against both types of cor-
tic compounds resulting from the combination of rosion are similar. First, reduce the contaminants.
sodium sulfate and some of the alloy constituents Second, use materials that are as corrosion resis-
such as nickel and cobalt. It is somewhat analo- tant as possible. Third, apply coatings to improve
gous to the type of corrosion called “fireside cor- the corrosion resistance of the bucket alloy.
rosion” in coal-fired boilers.
The two types of hot corrosion cause different High-Temperature Oxidation
types of attack, as shown in Figures 16 and 17.
These are metallographic cross sections of corrod- Metal oxidations occurs when oxygen atoms
ed material. High temperature corrosion features combine with metal atoms to form oxide scales.
intergranular attack, sulfide particles, and a The higher the temperature, the more rapidly this
denuded zone of base metal. Low temperature process takes place, creating the potential for fail-
13
GER-3764A
relatively rapid oxidation attack of some materials Figure 18a. Photomicrograph showing sound
can occur unless there is a barrier to oxygen diffu- miscrostructure of a coated bucket
sion on the metal surface. Aluminum oxide which has been in service
(Al203) provides such a barrier. Aluminum oxide
will form on the surface of a superalloy at high
temperatures if the superalloy aluminum content
is sufficiently high. Thus, the alloy forms its own
protective barrier in the early stages of oxidation
by the creation of a dense, adherent aluminum
oxide scale. However, many high strength superal-
loys in use today cannot form sufficiently protec-
tive scales because the compositional require-
ments for achieving other properties, such as high
strength and metallurgical stability, do not allow
for the optimization of oxidation/corrosion resis-
tance in the superalloy itself. Therefore, most of
today’s superalloys must receive their oxidation
protection from specially engineered coatings.
High-Temperature Coatings
These are the types of coatings that are used on
the first stages of all machines, and also might find
some application in selective downstream stages. GT21639
14
GER-3764A
Figure 19. Types of coatings although some of the bucket areas showed coat-
ing thinning. Only at some very small locations on
the leading edge of the coated bucket was the
Platinum-Aluminide Coatings coating breached, and then to only a depth of
All first stage buckets have been coated since 0.001 to 0.002 inches (0.025 to 0.051 mm).
the late seventies. Up until mid-1983, the coating
used by GE on most first stage buckets was a plat- PLASMAGUARD™ Coatings
inum-aluminum (PtAl) diffusion coating. This The new, GE-developed and patented
coating was selected over the straight aluminide PLASMAGUARD™ coatings are now our stan-
coatings because it provided superior corrosion dard first stage bucket coatings - GT-29 PLUS™
resistance both in burner test rigs and in field tri- for solid buckets, GT-29 IN-PLUS™ for cooled or
als. The platinum-aluminum coating is applied by hollow vaned buckets.
electroplating a thin (0.00025 in. (0.06635mm)) PLASMAGUARD™ coatings are examples of
layer of platinum uniformly onto the bucket air- overlay coatings and differ from diffusion coatings
foil surface, followed by a pack diffusion step to such as the platinum-aluminum coatings in one
deposit aluminum. This results in a nickel-alu- major respect. At least one of the major con-
minide coating with platinum in solid solution or stituents (generally nickel) in a diffusion coating
present as a PtAl2 phase near the surface. The is supplied by the base metal. An overlay coating
platinum in the coating increases the activity of has all the constituents supplied by the coating
the aluminum in the coating, enabling a very pro- itself. The advantage of overlay coatings is that
tective and adherent Al2O3 scale to form on the more varied corrosion resistant compositions can
surface. be applied, since the composition is not limited by
A Rainbow example of comparative corrosion the base metal composition, nor is thickness limit-
on PtAl coated and uncoated IN-738 buckets, run ed by process considerations.
15
GER-3764A
16
GER-3764A
GT5419B
Figure 24. MS7001EA simple-cycle, single-shaft,
heavy-duty gas turbine borescope
inspection locations
formance, will determine the most economical
time for a scheduled outage. The timing of the
disassembly outage thus becomes a judgment
GT16233B
based on known machine condition, rather than
Figure 22. MS7001 first-stage turbine buckets, the historical approach based upon generalized
radial view operating factors and usage.
TURBINE DEPOSITS
Nature of Deposits
Ash-bearing fuel oils generally require the use
of suitable additives to inhibit corrosion. A discus-
sion of additives is presented in the “Fuel
Additives” section. Deposits of ash from these
fuels can adhere to the hot gas path parts and
restrict the flow of gas, thereby reducing the out-
put and efficiency of the turbine. The rate at
GT24218B
which these deposits accumulate, and the ability
Figure 23. MS7001EA first-stage nozzle for to remove them, will depend upon a number of
heavy fuels factors including fuel composition, treatment
effectiveness, turbine design, and firing tempera-
through trailing-edge rectangular slots and tures.
through large pressure-side film holes which are The nature of the deposits changes with tem-
not subject to plugging by ash deposits. perature. Figure 25 shows an example of deposits
formed at 1750F (954C) on a cooled turbine noz-
Borescope Inspection Techniques zle partition. The deposit next to the metal is
water soluble MgSO4. The deposits on top of this
GE gas turbines have provision for borescope layer are insoluble MgO. These deposits, because
inspections of internal conditions, thereby mini- they are insulated from the nozzle surface, were
mizing disassembly and outage time. formed at higher temperature than those next to
The borescope access is provided at strategic the metal. The relationship between temperature
locations in the turbine for inspection of the com- and sulfur content, both of which determine the
pressor and turbine (Figure 24). Evaluation of the equilibrium between MgO and MgSO4, is also
results of borescope inspections, in conjunction given in this figure.
with the practice of periodically monitoring per-
17
GER-3764A
GT00103B
Figure 25. Layered ash deposit on first-stage nozzle
GT24219A
GT24220A
Figure 26. Vapor diffusion Figure 27. Vapor diffusion/condensation/
Four distinct processes may result in ash parti- solidification
cle deposits on the nozzle airfoils: the probability of sticking to the surface is
• Vapor particles migrate through the bound- reduced (Figure 27).
ary layer toward the cool wall. If the bound- • Liquid and solid particle impaction occurs
ar y layer temperature is below the dew when ash particles form nuclei for the con-
point, condensation takes place at the wall densation of low-melting point species either
(Figure 26). inside or outside of the boundary layer. The
• If the temperature of the boundary layer is condensate which the solid particle may pick
below the melting point of the species, and up forms the binder which causes the parti-
the particle has a long enough residence cle to stick to the wall Figure 28).
time in the boundary layer, then the vapor • A liquid droplet deviates from the streamline
particle condenses and solidifies before it and impacts the wall due to its own inertia
reaches the surface. If the liquid particle is at (Figure 29).
a temperature well below its sintering tem-
perature by the time it gets to the surface,
18
GER-3764A
GT24221A
GT24222
Figure 29. Liquid particle impaction
Heated, non-vitiated air is delivered to the test Figure 30. Turbine simulator, high-pressure
apparatus (Figures 30 and 31) at flows up to 8 test facility
19
GER-3764A
GT23875
Figure 32. Nozzles before washing
20
GER-3764A
GT23876
Figure 33. Nozzles after water washing
tors for 30 minutes. This removed 60-70 per- fuel and the differing hours of operation. The tur-
cent of the deposits. Additional washing had bine in Case II was run continuously for 185
no noticeable effect. The appearance of the hours, and showed a low deposit rate of 1.5 per-
deposit after this sequence is shown in cent per 100 hours. Each combustion chamber
Figure 33. About 30-40 percent of the origi- was washed with 25 gpm (1.6 lps) water flow for 10
nal deposit remained. minutes. In both cases, turbine cleaning (wash,
2. The rig was refired to 1950F (1066C) for one soak and refire), completely restored the turbine
hour. Inspection after shutdown showed that performance. Figure 35 is a picture of the com-
the nozzle was essentially 100 percent clean bustion liner from the same turbine showing no
(Figure 34). It was surmised that water pene- blockage of the cooling passages.
trated through the porous deposit during
the water wash and when the rig was refired,
the water flashed into steam creating suffi-
FUEL ADDITIVES
cient pressure to fracture the deposits.
This wash, soak, refire procedure was repeated Background
in several tests and has been proven in the field in The successful burning of heavy fuels in gas tur-
removing deposits formed at 1850F (1010C) fir- bines depends on the use of additives to prevent
ing temperature. Refiring to full speed at no load hot corrosion of hot gas path components. The
after the water soak removes the deposits. cause and nature of this type of corrosion is dis-
cussed in the “Turbine Gas Path Materials and
Field Experience Corrosion” section. Briefly, it is due to vanadium
Two examples of residual fuels experience on or to vanadium plus sodium trace contaminants in
the MS7001 gas turbines are of interest with heavy fuels - crude oils, residual oils and blended
respect to nozzle deposition rates and deposit residual oils - which destroy protective oxide films
removal (Table 3). on hot gas path parts. Certain selected crude oils
The difference in deposit rates is attributed to contain less than the 0.5 ppm threshold limit for
different amounts of vanadium and sodium in the vanadium inhibition, but most heavy fuels have
21
GER-3764A
GT23877
Figure 34. Nozzles after water washing and refiring
Before After
Figure 35. Combustion liner before and after wash, soak and refire
22
GER-3764A
Table 4.
COMPARISON OF MAGNESIUM-TYPE VANADIUM INHIBITORS
23
GER-3764A
Table 5
APPLICATION OF MAGNESIUM ADDITIVES
24
GER-3764A
25
GER-3764A
GT243530
Figure 36. Fuel system for heavy fuel applications
GT24539
26
GER-3764A
GT01939
27
GER-3764A
28
GER-3764A
GT24534
Figure 42. Elements of a two-stage fuel wash
system
• Centrifuge Desalting System
GT10235B
A centrifuge desalting system is normally
Figure 41. Heavy-fuel treatment system–with
batch-type inhibition composed of a centrifuge, water skid, and
demulsification skid. The centrifuge system
and rust. Tank design should enhance settling. is illustrated in Figure 43. Performance of
Floating suctions help to avoid the pumping of centrifuge systems is excellent. A typical two-
fuel from the tank bottoms which may contain stage system can reduce sodium from 150
concentrated contaminants. To reduce contami- ppm to less than 1 ppm for heavy salts.
nant entrainment, the operator should fill tanks Centrifuges also have excellent capability for
and allow time for contaminants to settle before removing solids.
using the stored fuel. Water should be periodically • Electrostatic Desalting System
drained to prevent buildup of microorganisms at The electrostatic process is similar to cen-
the fuel/water interface. trifuging. The primary feature of the electro-
Fuel treatment is accomplished in three stages: static system is that the water is coalesced to
• Washing the fuel to remove the water-soluble large droplets to enhance settling. For exam-
trace metals such as sodium, potassium, and ple, a 100 to 1 diameter increase in water
certain calcium compounds. Washing also droplet diameter in turn increases the set-
removes much of the particulate material tling rate by 10,000 to 1 according to Stokes
prior to forwarding to the filtering systems. Law. Electrostatic systems require longer
• Inhibiting the vanadium in the fuel with suit- start-ups and more filtration than centrifugal
able additives. systems. They are also less adaptable to fuels
• Filtration to remove particle contaminants. of varying quality.
29
GER-3764A
GT02040
Figure 43. Typical centrifuge installation
inhibit corrosion induced by this contaminant. requires the use of oil soluble additives that
Inhibitors may also be used to counteract sodium remain in solution during storage and subsequent
and to modify ash deposits. Two systems are handling. The advantage of this system is the abili-
applied for inhibition injection. These are the on- ty to check the fuel for proper treatment prior to
line system and batch processing systems. delivery to the gas turbine. Figure 41 incorporates
The on-line system is illustrated by Figure 44. a batch-type system for inhibition.
This system injects the additive in the fuel as it is
delivered to the gas turbine. Most heavy fuel fired Fuel Forwarding, Heating and
installations use this system. It allows the use of Filtration
either oil soluble or less costly water soluble addi-
tives. The fuel forwarding, heating and filtration sys-
The batch-type system, sometimes called the tem delivers fuel from the storage tank to the gas
total certification system, inhibits fuel as it is deliv- turbine at the required pressure, temperature,
ered to the treated fuel storage tanks. This system and cleanliness.
Figure 44. On-line inhibition schematic Gas turbines can start and stop on light crude
oils, simplifying the forwarding system. When this
30
GER-3764A
OPERATION AND
MAINTENANCE
REQUIREMENTS
Startup and Shutdown
GT24237A
In order to ensure that the entire turbine liquid
fuel system will remain free from any waxy fuel Figure 45. The effect of firing temperature and
vanadium content on deposition rate
buildups or plugging, startup and shutdown of
the gas turbine must occur while burning distillate pared with the costs incurred for deposit removal
#2 fuel oil. On startup, the lower viscosity distillate shutdowns.
ensures proper light off fuel atomization, and The allowable amount of deposit on the first stage
heats up the onbase piping to normal operating nozzle is dependent upon the ambient temperature
temperatures. Fuel transfer to the ash bearing fuel of the site. The lower the ambient temperature, the
can occur after unit has been synchronized to the higher the mass flow will be through the turbine. For
grid. The fuel transfer typically requires a gradual this reason, the amount of first stage nozzle plugging
5 minute transfer time. This transfer time allows at low ambients will range from 5 - 7 %. At tempera-
for the onbase piping and hardware to slowly heat tures above 59 F, (15 C), the allowable plugging of
up to the supply temperature of the ash bearing the first stage nozzle will be 10 %. Referring back to
fuel, (which in some instances can approach 275F Figure 45, one can estimate what the turbine water
(135C)), thus ensuring that no frozen blocks of wash interval will be for various levels of vanadium
ash bearing fuel form. content versus unit firing temperature.
On shutdown signal, the unit will automatically One method used for extending the period
unload itself and then transfer to distillate #2 fuel between turbine washing is to incorporate a tur-
oil. The shutdown must occur on distillate to bine abrasive cleaning system. This type of clean-
purge the onbase hardware and make sure that ing can be done online, and restores 10 to 50% of
there is no solidification of the ash bearing fuel the lost performance through injecting nutshells
throughout the fuel system. at the first stage turbine nozzles which removes
some of the ash deposits. The effectiveness of the
Normal Running Operation abrasive cleaning cycle on the turbine is dramati-
During normal operation it will be it will be cally affected by the nature of the deposits. The
necessary to periodically remove the ash deposits harder the deposit, the less effective the abrasive
which form on the first stage nozzle. The rate of cleaning. Since the hardness of the deposit is a
deposit buildup on the first stage turbine nozzle is direct result of the firing temperature of the gas
primarily dependent upon the firing temperature turbine, a relationship between the two exists such
of the gas turbine and the amount of vanadium that whenever the rated firing temperature of the
contained in the fuel, (Figure 45). This plot illus- unit exceeds 1900F, the effectiveness of abrasive
trates the effect of firing temperature and vanadi- cleaning becomes negligible. But, at lower firing
um content on the deposition rate. This plot illus- temperatures, a softer deposit forms and abrasive
trates that the higher the level of vanadium in the cleaning becomes more effective.
fuel, the more pronounced the effect that increas- Even when utilizing abrasive cleaning, eventual-
ing the firing temperature will have on the rate of ly an offline turbine water wash will be required in
deposition. The faster the rate of deposition, the order to remove the accumulated deposit. The
shorter the interval between deposit removal shut- turbine water washing system for ash bearing fuels
downs. Because of this relationship, the selection will consist of a turbine water wash skid, onbase
of turbine firing temperature should be tailored turbine wash piping, and controls. The procedure
for each specific site and customer. The benefits for offline turbine water wash, as contained in GE
of increased output and efficiency must be com- instruction books, is detailed in Table 6.
31
GER-3764A
Table 6
PROCEDURE FOR OFFLINE
TURBINE WASH
Procedure Time
Gas turbine will be shut down and put on 9
crank speed, (540 rpm), to allow wheel- hours
space temperatures to cool to 300 F.
With turbine at crank speed, a detergent/ 5
water solution for compressor water wash min.
will be injected into the compressor.
GT07410B
Unit will be shut down and allowed time 20 Figure 47. Typical combined cycle performance
to soak. min. variation with time – residual oil
With turbine at crank speed, compressor 20 fuel
will be rinsed. At this time copious min. approximately 3 % for every 1 % of blockage of
amounts of water will be injected in the the first stage nozzle.
hot gas path via the atomizing air piping,
(all combustors at the same time). A typical combined cycle performance varia-
tion is illustrated in Figure 47. This particular
Based on this procedure, a typical water wash example illustrates the “saw tooth” performance
inter val for shutdown to start up should be loss that is associated with ash-bearing fuels and
approximately 10 - 12 hours, recognizing that the water wash/nutshell intervals.
overall cycle should be adjusted based on the
experience of cleaning effectiveness. Inspection Intervals
To assist the customer in selecting the optimum Inspection intervals for optimum turbine ser-
operating rating for the gas turbine, a plot illus- vice are not fixed for every installation, but rather
trating the recoverable performance degradation developed through an interactive process by each
versus time will be developed for each unique user, based on past experience and trends indicat-
application, (Figure 46). This plot illustrates the ed by key turbine factors. The condition of the
operating hours for a unit which has nutshelling hot gas path parts provides a good basis for cus-
capability versus a unit which does not. The tomizing a program of inspections and mainte-
amount of running hours gained is depicted in nance. Expected maintenance interval ranges for
“X” hours. In order to better quantify the poten- ash-bearing fuels are identified in Table 7.
tial performance degradation due to fouling of The intervals are, in part, based on hydrogen
the hot gas path, GE estimates an output loss of content of the fuels, because heavier hydrocarbon
fuels frequently contain corrosive elements and
generally release a higher amount of radiant ther-
mal energy. This results in higher combustion sys-
tem hardware temperatures, which reduces
inspection intervals (Figure 48).
GE utilizes a fired hours and/or a fired starts
philosophy for determining inspection intervals.
This criteria recommends an inspection whenever
Table 7
EXPECTED MAINTENANCE
INTERVAL RANGES
32
GER-3764A
GT16662A
Major Inspection
Figure 48. Fuel hydrogen content and The purpose of the major inspection is to
combustion hardware temperatures
examine all of the internal rotating and stationary
the fired hours or starts limit is reached. The lim- components from the inlet of the machine
its are based on two different criteria. The fired through the exhaust section of the machine. This
hour limits are based on corrosion, oxidation, and inspection includes the elements of the combus-
creep, while the start limits are based on low cycle tion and hot gas path inspections, in addition to
fatigue of components resulting from thermal laying open the complete flange-to-flange turbine
cycling of the unit. to the horizontal joints (Figure 49). Proper
machine centerline support using mechanical
Inspection Scope jacks and jacking sequence are necessary to assure
proper alignment of rotor to stator, obtain accu-
The shutdown maintenance inspections rate half shell clearances, and prevent twisting of
include the “combustion”, “hot gas path”, and the casings while on the half shell.
“major” inspections. These inspections require
disassembly of the turbine in varying degrees. Inspection Duration
Figure 49 illustrates the turbine sections involved
during each of these inspections. It is difficult to estimate the number of man-
hours required for each type of shutdown inspec-
Combustion Inspection tion, primarily because of the wide range of expe-
The combustion inspection is a relatively short rience, productivity, and working conditions that
disassembly inspection which concentrates on the exist around the world. Based upon the mainte-
combustion liners, transition pieces, and fuel noz- nance inspection man-hour assumptions in Figure
zles, components recognized as being the first to 50 however, an estimate can be made, as shown in
require repair and/or replacement in a good Table 8.
maintenance program. The shutdown inspection man-hours will vary
depending upon preplanning, availability of parts,
Hot Gas Path Inspection
The purpose of the hot gas path inspection is
GT07094B GT10238C
Figure 49. Major inspection work scope Figure 50. Maintenance inspection assumptions
33
GER-3764A
Table 8
TYPICAL ACHIEVED CREW SIZE AND SKILLS COMBUSTION,
HOT-GAS-PATH AND MAJOR INSPECTION
© 1996 GE Company
34
GER-3764A
LIST OF FIGURES
LIST OF TABLES
Table 1 GE-designed gas turbine worldwide experience (as of February 1994) with heavy
ash-bearing fuels
Table 2 Combustion design objectives
Table 3 Residual fuel experience
Table 4 Comparison of magnesium-type vanadium inhibitors
Table 5 Application of magnesium additives
Table 6 Procedures for offline turbine wash
Table 7 Expected maintenance interval ranges
Table 8 Typical achieved crew size and skills combustion, hot-gas-path and major inspection
For further information, contact your GE Field Sales
Representative or write to GE Power Systems Marketing
GE Power Systems
8/96