Professional Documents
Culture Documents
Introduction
Decade 1990
US$ 141 mio US$ 12 mio US$ 9 mio US$ 29 mio US$ 55 mio US$ 9 mio US$ 24 mio
1999 TAV Bologna - Florence, Italy Collapse 2000 Metro Taegu, Korea Collapse
2005 Lausanne Metro, Switzerland Collapse 2005 Lane Cove Tunnel, Sydney Collapse 2007 Sao Paulo Metro, Brazil and so on Collapse
Significant increase in the number of claims Insurance income <<< Claims outcome Insurance paid >>> Initial cost of the work Difficulties to insure underground works
No construction project is risk free. Risk can be managed, minimised, shared, transferred or accepted. It cannot be ignored.
Sir Michael Latham, 1994
18.05.2011
Lessons Learnt from the Pinheiros Station Accident in Sao Paulo, Brazil
Introduction IPT Investigation Work and Report Main IPT Report Findings Conclusions and Recommendations
Pinheiros Station
GeologicalGeomechanical Model
N
Pinheiros Station
Pre-Bidding From impressiom packer in Pinheiros station area and reginal surveys (319 poles)
SM-8701
178200
Filonite (SR-07)
SP-8709
178180
SM-6532 SM-8708
SP-8711
SM-8719
SM-6803
SM-6802
SM-8714
S NA AS
Pinheiros Station: Geomechanical sections obtained from 3D interpolation using structural geology information
142645 142665 142685 142705 142725 142745 142765 142785 178245 178245
178225
178225
178205
178205
178185
178185
178165
178165
178145
178145
178125 142645
WSW
ENE
720
720
710
710
700
700
690
690
680
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
680
WSW
ENE
720
720
710
710
700
700
690
690
680 140
WSW
ENE
Brown weathered soil Dark gray RMR IV Medium gray RMR III Light gray RMR II (rock mass classification from designer)
720
720
710
710
700
700
690
690
680 140
eixo entrevias
SSE
NNW
eixo entrevias
SSE
720
720
720
720
710
710
710
710
700
700 700
700
690
690 690
690
680
10
20
30
40
50
60
70
80
90
100
110
10
20
30
40
50
60
70
80
90
100
110
680 120
NNW
eixo entrevias
SSE
NNW
eixo entrevias
SSE
720
720
720
720
710
710
710
710
700
700 700
700
690
690 690
690
680
10
20
30
40
50
60
70
80
90
100
110
10
20
30
40
50
60
70
80
90
100
110
680 120
GeologicalGeomechanical Model
Sub-vertical alternation of granitic and biotitic gneiss, with variable thickness (sub-parallel to the tunnel longitudinal section) Four families of discontinuities Rockmass is heterogeneous and anisotropic due to discontinuities and uneven weathering bedrock surface as egg box type Post-bidding investigation confirmed the GG model developed during the pre-bidding design
-5 Recalque (mm)
7.0+86 - P1 7.0+86 - P2
-10
-15
-20
Data
5,0
0,0
-5,0
-15,0
-20,0
-25,0
-30,0 7.0+86 7.0+96 -35,0 7.1+6 7.1+15 -40,0 15/08/06 25/08/06 04/09/06 14/09/06 24/09/06 04/10/06 14/10/06 24/10/06 03/11/06 13/11/06 23/11/06 03/12/06 13/12/06 22/01/07
Data
Meeting on 11/01/2007
Installation of bolts in the tunnel bench walls decided No enough bolts in stock, despite it was forecasted in the design as contingency action (15% installed but all borehole drilled) No clear definition on the need to stop the works (contradictory version among participants) Three blasting on the 12/01/2007 (two around 8 h, one in each platform tunnel, and a third one around 12 h)
The Colapse
Fall of small concrete blocks Fracture propagation from the shaft till 1/3 of the tunnel length, position 11 h Fall of 6 to 8 lattice girders in the left-hand side wall Colapse daylight on surface at 14h54 Colapse of the north wall of the shaft at 15h30 (last event)
eixo
1 0 -1 -2 -3 -4 -5 R e c alq u e (m m ) -6 -7 -8 -9 -10 -11 -12 -13 -14 23 /1 1/0 6 03 /1 2/0 6 13 /1 2/0 6 23 /1 2/0 6 02 /0 1/0 7 12 /0 1/0 7 22 /0 1/0 7
02/01/2007
13/12
23/12
TN.E-1 TN.E-2 TN.E-3 TN.F-1 TN.F-2 TN.F-3 TN.G-1 TN.G-2 TN.G-3 MS1 TN.H1 TN.H-3
Position Axis
Data
Observed / Calculated 17 19 10 22 13 95
Section 7,0+87
Section 7,1+04
Section 7,1+13
TN.H1
178205 178205
TN.G1
TN.E3
178175
178175
?
TN.H1
P-2 P-2
TN.G1
P-2
142765 142775 142785
178165
P-2
P-3
TN.F3
P-3
TN.E3
P-3 P-3
Non-validated design
7130
7125
7120
7115
7105
7100
Foreseeability
7080
Data
Clear under good practice of engineering Misty by faults in several engineering processes
Conclusions
Geological model complex but data was fully disclosure no major changes by no means claim based on Different Ground Conditions Causes are related to shortcomings in engineering processes (design and construction) systemic fault process Lessons and recommendations to engineering and contractual arrangements
Lessons Learnt
Pre-Bidding Documents
Geological and geotechnical data as much as possible Full disclosure of all GG data
Geological model GG Data Report Geotechnical Base Report Different Ground Conditions Owner
Lessons Learnt
Design Documents
Geomechanical model Structural model of the tunnel Assumptions, completeness and type of calculations and simulations Continuum media? Type of model and parameters 2D or 3D analysis? Monitoring threshold values
Design Reviewer
Lessons Learnt
Lessons Learnt
Construction
Faithful to the design agreement changes in
Quality control (materials and services) Integrated risk and construction management contingency and emergency actions
Lessons Learnt
Role of Contracts
Keep fair balance among quality, schedule and costs Mix of technical and performance specifications quality control Independent auditing and full disclosure of control parameters Incorporate risk management and risk sharing
Urban tunnelling is a great and increasing demand worldwide Urban tunnelling is challenging due to urban environment and constraints Urban tunnelling is likely dominated by limit admissible damage criteria Risk management has to be incorporated in all project phases
The worst happening is not to have an accident, it is to learn nothing from it.
Kovari, K. & Ramoni. M. (2004). Urban Tunnelling in Soft Ground Using TBMs. International Congress on Mechanised Tunnelling: Challenging Case Histories, Keynote Lecture, Politecnico di Torino, Turin, Italy (www.ita-aites.org). Munich Re (2006). Code of Practice for Risk Management of Tunnel Works: Future Tunnelling Insurance from the Insurers Point of View. ITA Open Session, ITA World Tunnel Congress, Seoul, South Korea. Munich Re (2007). Insurance Cover as Part of the General Risk Management Strategy. ITA Open Session on Public Private Partnership Projects, ITA World Tunnel Congress, Prague, Czech Republic. Seidenfuss, T. (2006). Collapses in Tunnelling. Master Thesis, Stuttgart University of Applied Sciences, Stuttgart, Germany, 179 p.