THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

UNIT 3

THE TECHNIQUE OF PLANNING AND PRECONSTRUCTION ROAD WORK ( Part 2 )

OBJECTIVES

General Objective To understand the earth work operation and its problems occurred. Specific Objectives At the end of the unit you should be able to :

describe the earth work operation. state the highway machinery state the types of slope. state the problem and its solutions. describe the method of slope protection.

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

INPUT PLANNING TECHNIQUE AND PRECONSTRUCTION ROAD WORK ( Part 2 )


3.0 INTRODUCTION The sub-grade soil is prepared by bringing it to the desired grade and camber and by compacting adequately. The sub-grade may be either in embankment or in excavation, depending on the topography and the finalized vertical alignment of the road to be constructed. 3.1 EARTH WORH OPERATION The earth work quantities are estimated based on longitudinal and transverse section along the alignment of the road. In order to reduce the cost of construction, it is necessary to plan the movement of materials from cuts to the nearest fills. It is necessary to decide the limits of economical haul and lift. It is advantageous to plot a mass haul diagram to compute the haulage details. The swelling and shrinkage factor may also be considered in the excavation and compaction of earth.

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

3.1.1 Excavation Excavation is the process of cutting or loosening and removing earth including rock from its original position, transporting and dumping it as a fill or spoil bank. The excavation or cutting may be needed in soil, soft rock or even in hard rock, before preparing the sub-grade. The selection of excavation equipment and the cost analysis is made based on the stiffness of the materials to be excavated. Earth excavation work may be divided as excavation or cutting, grading and compaction. The depth of the excavation is decided, among other factors, on requirement of vertical profile of the road. The slope to be provided is governed by the type of soil including stratification, if any, and the depth of the cutting. The stability computations may help in arriving at maximum permissible slope for the complex problems. However highway cuts much flatter slopes are preferred from other considerations including aesthetics construction of side drains also require excavations along road side. a. Excavation equipment The excavation equipment commonly used in highway projects includes bull dozers, scrapers, power shovels, draglines, clamshells and hoes. However, in small projects excavation is carried out manually using hand tools. The machines that used are:i. Bull dozer and scraper Bull dozer and scraper may be used for shallow excavation work and for hauling the earth for relatively short distances. Bull dozer is considered to be versatile machine for many construction projects as it

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

may be used for clearing site. It can used for opening up pilot roads, moving earth for short haul distances of about 100m and also in several other jobs. Scraper is considered as one of the useful earth-moving equipment as it is self operating - it can dig, haul and discharge the material in uniformly thick layers. However scrapers are not capable of digging very stiff material.

Figure 3.1: Bull dozer

ii.

Power shovel Power shovel used primarily to excavate earth of all classes except

rock and to load it into wagons. Power shovels may be mounted on crawler tracks and so they can move at low speeds. Figure 3.2 shows the operation and basic parts of a power shovel, these including the mounting, cab, boom, dipper stick, dipper and hoist line. The power shovel can effectively operate the excavate earth from a lower level where it stands and when the depth of the face to be excavated is not too shallow.

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

Figure 3.2: Power Shovel

iii.

Dragline Dragline is used to excavate soft earth and to deposit in nearly

banks or to load into wagons. Dragline may also be mounted on crawler. It can operate on natural ground while excavating from a pit with the bucket, thus it is not necessary for the dragline to go into the pit in order to excavate. The basic parts and operation of a dragline are shown in figure 3.3. The bucket is thrown out from the dragline on the top of the earth to be excavated and then pulled back towards the base of the machine.

Figure 3.3: Dragline

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

iv.

Clamshell Clamshell consists of a bucket of two halves or shell which is

hinged together at top. The shells may be attached to the shovel-crane units or at the boom of a drag line. The open clam-shell bucket is thrown on the top of the loose material to be dug and as the bucket is lift, the two halves close en trapping the material into the bucket. Figure 3.4 shows the clamshell bucket. This equipment is useful for excavation of soft to medium materials and loose material at or below existing ground surface.

Figure 3.4: Clamshell v. Hoe Hoe is an excavating equipment of the power-shovel family. Hoe is meant to excavate below the natural surface where the machine is stationed and is capable of having precise control of depth of excavation at close range work (see figure 3.5). Hoe can exert high tooth pressures and hence can excavate stiff material which normally can not be excavated by dragline.

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

Figure 3.5 Hoe

The excavation equipment is selected depending on the natural of the material, the distance, to be hauled and the method of disposal. At times the selection may be made based on the availability also.

3.1.2 Embankment When it is required to raise line of a highway above the existing ground level it becomes necessary to construct embankments. The grade line may raised due to any of the following reasons: i. ii. iii. to keep the sub grade above the high ground water table. to prevent damage to pavement due to surface water and capillary water. to maintain the design standards of the highway with respect to the vertical alignment. The design elements in highway embankments are: i. ii. iii. height fill material settlements.

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

iv. v.

stability of foundation, and stability of slopes

a. Height The height of the embankments depends on the desired grade line of the highway and the soil profile or topography. Also the height of the fill is some times governed by stability of foundation, particularly when the foundation soil is week. b. Fill material Granular soil is generally preferred as highway embankment material. Silts and clays are considered less desirable. Organic soils, particularly peat are unsuitable. The best of the soils available locally is often selected with a view to keep the lead and lift as lowers possible. At times light-weight fill material like cinder may be used to reduce the weight when foundation soil is weak. c. Settlement The embankment may settle after the completion of construction either due to consolidation and settlement of the foundation or due to settlement of the fill or due to both. If the embankments foundation consists of compressible soil with high moisture content, the consolidation can occur due to increase in the load. The settlement of the fill is generally due to inadequate compaction during construction, and hence by proper compaction this type of settlement may be almost eliminated. Whatever be the type of settlement, it is desired that the settlement is almost complete before the construction of saturated. Foundation clay, vertical sand drains are sometimes constructed. These are vertical columns of sand installed in the compressible foundation like marshy soils in order to decrease drainage path and thus accelerate the rate of consolidation. The

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

vertical sand columns may be of 30 to 60 cm diameter and 2.5 to 6 meter spacing, arranged in hexagonal pattern. A horizontal sand blanket, 40 to 60 cm thick is placed at the top of the drains extending across the entire width of embankment at its bottom. This helps the water to flow out with ease. d. Stability Of Foundation When the embankment foundation consists of weak soil just beneath are at a certain depth below in the form of a weak stratum, it is essential to consider the stability of the foundation against a failure. This is more essential in the case of high embankment. The foundation stability is evaluated and the factor of safety is estimated by any of the following approaches. i. Assuming a certain failure surface such as a circular arc or

any other composite shape and analyzing it with Swedish circular arc analysis or method of wedges. As the case may be. ii. Estimating the average shear stress and strength at the foundation layers by approximate methods and estimating the factor of safety. iii. Using theoretical analysis base on elastic theory.

The factor of safety in the case of compressible soil foundation is likely to be minimum just after the completion of the embankment. increase in the foundation factor of safety. Later due to consolidation of foundation and consequent gain in strength there will be an Thus it is evident that in such compressible foundation soils, the vertical sand drains would be useful also to increase the rate of gain in strength. By proper design of vertical sand drains, it is possible to limit the decrease in foundation factor of safety due to the construction, within the allowable value.

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

e. Stability Of Slopes The embankment slopes should be stable enough to eliminate the possibility of a failure under adverse moisture and other conditions. Hence the stability of the slope should be checked or the slope should be designed providing minimum factor of safety of 1.5. Often much flatter slopes are preferred in highway embankment due to aesthetic and other reasons. 3.1.3 Construction of embankment The embankment may be constructed either by rolling in relatively thin layers or by hydraulic fills. The former is called rolled-earth method and is preferred in highway embankments. Each layer is compacted by rolling to a satisfactory degree or to a desired density before the next layer is placed. Compaction is carried out at optimum moisture content so as to take advantages of maximum dry density using a specified compacting effort and equipment. The thickness of the layers may vary between 10 and 30 cm depending on various factors such as soils type, equipment, specifications etc. The practice of dumping the earth without compacting properly and allowing the fill to get consolidated under weather during few subsequent seasons should be avoided as the settlement will continue for a very long period. If pavement is constructed before the settlement of the fill is almost complete, the pavement is likely to become uneven and also fail later-on. Compaction of soil is discussed separately in topic Soil Compaction.

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

ACTIVITY 3A

Lets test your understanding before we continue to the next input. GOOD LUCK.
3.1 Earth work operation can be divided into two categories. Name the work by filling in the chart below.

EARTH WORK OPERATION

3.2

Match the excavation equipment listed below with its description. Then unite the words in the boxes provided.

HOE

CLAMSHELL

DRAGLINE

POWER SHOVEL

BULLDOZER/SCRAPPER

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

Im used for shallow excavation work and for hauling the earth for relatively short distances.

Im used primarily to excavate earth of all classes except rock and to load it into wagons.

Im used to excavate soft earth and to deposit it nearby banks or into wagons.

Im useful for excavation of soft to medium materials and loose materials at or below existing ground surface.

Im useful to excavate below natural surface.

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

3.3

Complete the chart of design elements in highway embankments below

HEIGHT

DESIGN ELEMENTS IN HIGHWAY EMBANKMENTS

STABILITY OF SLOPE

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

FEEDBACK ON
3.1

ACTIVITY 3A
EARTH WORK OPERATION

EXCAVATION

EMBANKMENTS

3.2

BULLDOZER/SCRAPPER Im used for shallow excavation work and for hauling the earth for relatively short distances.

POWER SHOVEL Im used primarily to excavate earth of all classes except rock and to load it into wagons.

DRAGLINE Im used to excavate soft earth and to deposit it nearby banks or into wagons.

CLAM SHELL

HOE

Im useful for excavation of soft to medium materials and loose materials at or below existing ground surface.

Im useful to excavate below natural surface.

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

3.3

HEIGHT

FILL MATERIAL

DESIGN ELEMENTS IN HIGHWAY EMBANKMENTS SETTLEMENTS

STABILITY OF SLOPE

STABILITY OF FOUNDATION

HOW DO YOU FIND THE ACTIVITIES? FUN ARENT THEY? LETS PROCEED TO THE NEXT INPUT..

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

3.2

SIDE SLOPE OPERATION

There are two types of side slope in Highway Engineering. Alignments of highways through hilly and rolling topography result in many cut and fill slopes of exposed soil. Highway construction until recently has been simply a matter of location and design. Very little consideration has been given to the possibility of erosion or sloughing on cut and fill. 3.2.1 CUT SLOPES There have several types of strata in the soil and rock. When the soil and the rock are being cut and excavated, the stability of the content will decrease, meanwhile, the renovating have to be done to get the slope cutting ready and safe. The safety works are important to prevent erosion and sloughing. Slope excavation takes place when the original soil level higher then the level of new road formation to be built.

i. Shallow cutting

ii. Deep cutting ( by storey )

Figure 3.1 : Cut slope for equivalent soil strata.

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

Sand

Granular

Rock

Figure 3.2:

Cut slope for variable soil strata.

Type of soil Cutting depth Solid rock Rock Sand Sandy soil 05 Compact earth 5-10 Sand, loose 5-10 Clay soil 0-10 Clay-stone 5-10 Table 3.1: Table for safety slope cutting

sloping 1:0.3 1:0.0 1:0.5 1:1.2 1:0.5 1:1.0 1:0.8 - 1:1.2 1:1.0 1:1.2 1:1.2 1:1.5 1:0.8 1:1.2 1:1.2 - 1:1.5

3.2.1.1

Problems in cut slope

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

There are several problems that will be stated in cut slope. a. Landslide

Land slide is a problem that always happens in the work of slope cutting. It is because the cut of soil influence the stability of the soil. There are a few ways to overcome the problem. i. ii. iii. iv. Prepare the slope with suitable slanting degrees. Turfing the slope areas to maintain the soil stability Hydro seeding is use to plant the plant on the alkali soil. By using Geofabric or geotextile to avoid the diffusion of ground water. Rock slope is dangerous because the area of cutting does not have stable binding ability. If the failure of stone happen, it will cause the accident and dangerous for us. There are some methods which had being used in our country to overcome the problems. i. ii. iii. Build the fencing along the slope areas. Use a net. Gabion block.

b.

Water Infiltration

Water infiltration in soil also influences the soil stability. Storey and soil drainage system are important. Sub-soil drains are always used to control the flow of infiltration. 3.2.2 EMBANKMENT SLOPE

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

Slope embankment takes place when the original soil is under the level of new road formation to be built. Embankment slope is built by equivalent or different types of materials depend on soil strata.

1:1.5 1.5 2.0m 1:1.8 1:2.0 ii. Step Slope i. Normally Cut Slope

Figure 3.3: Embankment by equivalent materials

1:0.5 Rock 1:1.0 Sand Compact earth 1:2.0

Figure 3.4: Embankment by different materials

Tables 3.2: of safety sloping degree in soil banking Types of material ( well graded sand ) Height ( m ) 06 Slope: Hor. To Ver. 1:1.5 1:1.8

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

( poorly graded sand ) Rock Clay 3.2.2.1

6 15 0 10 0 10 10 20 0-6

1:1.8 1:2.0 1:1.8 1:2.0 1:1.5 1:2.0 1:1.8 1:2.0 1:1.8 1:2.0

Problems in slope banking

There are several problems that are related to the embankment slope. Landslide There are some ways to overcome the problem. i. ii. iii. Turfing - Planting the plants for slope protection Prepare the slope with suitable slanting degrees. Use Geofabric and geotextiles to avoid the diffusion of ground water.

Erosion Soil erosion happens because of infiltration and the flow of water run-off. To prevent the erosion, a few methods can be used: i. ii. Prepare the drainage system to let the water flow easily. Grow plants to cover the slope surface.

ACTIVITY 3B

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

Lets test your understanding before we continue to the next input. GOOD LUCK.
3.4 There are two types of side slope in Highway Engineering. Name the types by filling in place below.

Two types of slopes?

3.5

Match the two type slope as the answer from question 3.4 with its description. Write the words in the boxes provided.

Its take place when the original soil is under the level of new road formation to be built.

Its takes place when the original soil level higher then the level of new road formation to be built.

3.6

Name the problems of the fffembankment slope by filling the chart

below.

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

Embankment Slope

FEEDBACK TO ACTIVITY 3B

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

3.4

The answers are.. Cut Slope Embankment Slope

3.5 Its take place when the original soil is under the level of new road formation to be built. Embankment Slope Its takes place when the original soil level higher then the level of new road formation to be Cut Slope built.

3.6 Embankment Slope

Landslide

Erosion

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

HOW DO YOU FIND THE ACTIVITIES? FUN ARENT THEY? LETS PROCEED TO THE NEXT INPUT..

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

Question 3 - 1
The excavation equipment commonly used in highway projects. Describe about the machine as listed below. a. b. c. Bulldozer and scraper. Power shovel. Hoe.

Question 3 - 2 Question 3 - 2
Describe all the problems in slopes and the solution to overcome the problem.

Question 3 - 3
There are several factors that contribute to the increase of design. Explain briefly two factors that contribute to the increment.

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

Answer 3.1
a. Bull dozer and scraper

Bull dozer and scraper may be used for shallow excavation work and for hauling the earth for relatively short distances. Bull dozer is considered to be versatile machine for many construction projects as it may be used for clearing site. It can used for opening up pilot roads, moving earth for short haul distances of about 100m and also in several other jobs. Scraper is considered as one of the useful earth-moving equipment as it is self operating - it can dig, haul and discharge the material in uniformly thick layers. However scrapers are not capable of digging very stiff material. b. Power shovel

Power shovel used primarily to excavate earth of all classes except rock and to load it into wagons. Power shovels may be mounted on crawler tracks and so they can move at low speeds. Figure 1 shows the operation and basic parts of a power shovel, these including the mounting, cab, boom, dipper stick, dipper and hoist line. The power shovel can effectively operate the excavate earth from a lower level where it stands and when the depth of the face to be excavated is not too shallow.

Figure 1: Power Shovel

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

c.

Hoe

Hoe is an excavating equipment of the power-shovel family. Hoe is meant to excavate below the natural surface where the machine is stationed and is capable of having precise control of depth of excavation at close range work (see figure 2). Hoe can exert high tooth pressures and hence can excavate stiff material which normally can not be excavated by dragline.

Figure 2: Hoe

Answer 3.2
1. Problems in cut slope

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

There are several problems that will be stated in cut slope. a. Landslide Land slide is a problem that always happens in the work of slope cutting. It is because the cut of soil influence the stability of the soil. There are a few ways to overcome the problem. i. ii. iii. iv. Prepare the slope with suitable slanting degrees. Turfing the slope areas to maintain the soil stability Hydro seeding is use to plant the plant on the alkali soil. By using Geofabric or geotextile to avoid the diffusion of ground water. Rock slope is dangerous because the area of cutting does not have stable binding ability. If the failure of stone happen, it will cause the accident and dangerous for us. There are some methods which had being used in our country to overcome the problems. i. Build the fencing along the slope areas. ii. Use a net. iii. Gabion block.

v.

Water Infiltration

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

Water infiltration in soil also influences the soil stability. Storey and soil drainage system are important. Sub-soil drains are always used to control the flow of infiltration.

Problems in slope banking

There are several problems that will be stated in embankment slope. Landslide There are some ways to overcome the problem. iv. v. vi. Turfing - Planting the plants for slope protection Prepare the slope with suitable slanting degrees. Use Geofabric and geotextiles to avoid the diffusion of ground water.

Erosion Soil erosion happens because of infiltration and the flow of water run-off. To prevent the erosion, a few methods can be used: iii. iv. Prepare the drainage system to let the water flow easily. Grow plants to cover the slope surface.

Answer 3.3
a. Height

Highway Engineering

THE TECHNIQE OF PLANNING AND PRE-CONSTRUCTION ROAD WORK

C3010 / UNIT3

The height of the embankments depends on the desired grade line of the highway and the soil profile or topography. Also the height of the fill is some times governed by stability of foundation, particularly when the foundation soil is week. b. Fill material

Granular soil is generally preferred as highway embankment material. Silts and clays are considered less desirable. Organic soils, particularly peat are unsuitable. The best the soils available locally is often selected with a view to keep the lead and lift as lowers possible. At times light-weight fill material like cinder may be used to reduce the weight when foundation soil is weak.