Professional Documents
Culture Documents
Acknowledgement
Two fold mechanisms may be involved with top soil erosion: i) Raindrop impact energy loosens the top soil Before failure
After failure
3 jabbar@ce.buet.ac.bd
Geojute Sample
Pegs Root matrix
500 gsm 750 gsm Roll width: 1200 mm Opening area about 50% Moisture absorption about 4~5 times its dry weight Cost: BDT 1.60 per sft for 500 gsm Durability: 2 monsoon More than 6000 tons (12 million square meter) exported each year
jabbar@ce.buet.ac.bd 4
Laid over exposed surface, Geojute takes away about 40% of the raindrop impact energy. Geojute reduces surface runoff to about 35% by absorbing 4 to 5 times water of its dry weight. The reduced runoff flows gently (spillway effect) over the Geojute covered surface due to miniature dam effect. Weft
Storage
5 jabbar@ce.buet.ac.bd
Geojute absorbs water required for vegetation growth and acts as mulch on its biodegradation. This helps growth of vegetation in almost half the time required for same amount of growth without Geojute. As the Geojute degrades with time, grasses and trees grow up and take over the job of Geojute.
6 jabbar@ce.buet.ac.bd
7 jabbar@ce.buet.ac.bd
(2.0 m)
Using concrete blocks near bridge approach Cost: BDT 110-120 per SFT
Using clay cladding elsewhere along the road Cost: BDT 70-80 per SFT
8 jabbar@ce.buet.ac.bd
A stretch of mild sloped roadside selected for protection with geojute and vegetation
Sieve Analysis of Ranirhat Bridge Top Soil
100 90 80 70 60 50 40 30 20 10 0 10
Coarse sand Medium sand Fine sand
% F in er
1 Particle Size in mm
0.1
0.01
10 jabbar@ce.buet.ac.bd
2) SPREADING FERTILIZER
11 jabbar@ce.buet.ac.bd
12 jabbar@ce.buet.ac.bd
5) INSERTING U-HOOK
13 jabbar@ce.buet.ac.bd
7) PLANTATION
14 jabbar@ce.buet.ac.bd
9) GRASS SEEDING
Work finished within 3 days, i.e. on: 18/07/2008 Cost of the system: 3.50 BDT/sft 4.00 BDT/sft
jabbar@ce.buet.ac.bd 15
Performance Monitoring
10/08/08 (Middle of monsoon) (appx. 3 weeks after completion of the work)
Grass growing
16 jabbar@ce.buet.ac.bd
Performance Monitoring
10/08/08 (Middle of monsoon) (appx. 3 weeks after completion of the work)
Performance Monitoring
22/08/08 (Middle of monsoon) (appx. 5 weeks after completion of the work)
22/08/08
Grass growing
18 jabbar@ce.buet.ac.bd
Performance Monitoring
22/08/08 (Middle of monsoon) (appx. 5 weeks after completion of the work)
22/08/08
19 jabbar@ce.buet.ac.bd
Performance Monitoring
25/12/08 (Winter) (appx. 21 weeks after completion of the work)
Performance Monitoring
25/12/08 (Winter) (appx. 21 weeks after completion of the work)
22 jabbar@ce.buet.ac.bd
Dangerous Curve
2203847.49N and 9200749.53E
100 ft 75 ft 130 ft
Initially, a small retaining wall at the hill-foot and two stairs cum drain at both wings were constructed. Once the site was prepared, geojute and vegetation was used to stabilize the slope against raincut erosion.
25 jabbar@ce.buet.ac.bd
jabbar@ce.buet.ac.bd
27 jabbar@ce.buet.ac.bd
28 jabbar@ce.buet.ac.bd
29 jabbar@ce.buet.ac.bd
Work finished within 3 days, i.e. on: 10/08/2008 Cost of the system: 3.50 BDT/sft 4.00 BDT/sft
30 jabbar@ce.buet.ac.bd
Performance Monitoring
22/08/08 (Middle of monsoon) (appx. 2 weeks after completion of the work)
Grass growing
31 jabbar@ce.buet.ac.bd
Performance Monitoring
19/09/08 (End of monsoon) (appx. 5 weeks after completion of the work)
32 jabbar@ce.buet.ac.bd
Performance Monitoring
19/09/08 (End of monsoon) (appx. 5 weeks after completion of the work)
The slope sustained half of the monsoon. No sign of topsoil erosion is observed.
33 jabbar@ce.buet.ac.bd
Performance Monitoring
25/12/08 (Winter) (appx. 18 weeks after completion of the work)
Wild type of grass seed was applied, not aesthetic, but performance is satisfactory.
34 jabbar@ce.buet.ac.bd
Selection of Vegetation
Vetiver: The root system goes up to 14 ft deep in 6 to 8 months time Locally available similar type of grass/plants may be used instead
35 jabbar@ce.buet.ac.bd
Selection of Vegetation
Conclusion
Performance highly satisfactory. Geojute survived one monsoon and five months without biodegradation. Cost 1/20 th of concrete protection system and 1/5 th of clay cladding system. No special equipment or labour required. All the materials are locally available and eco- friendly. Robust solution may be achieved by proper selection of vegetation available in the zone.
37 jabbar@ce.buet.ac.bd