Professional Documents
Culture Documents
Circle team to send the list of sites being planned for I&C, 2 days in advance to the Backend support team. This will help the team to configure the sites in the application. - The mail has to be sent to 'wqts@connectm.com' (The list should include the Site Name, SAP ID, Site Address) Before starting to the site on every day morning, the field team should inform the 'RTU serial number' & the 'Site details' (Site name, SAP ID, Site address) to the Backend support team over the phone. - Phone number of the Backend support team are 080-67127509 / 08067127521 / 080-67127542 / 09243510530 / 09243326979 / 09243326980 Field team to carry their own GPRS enabled mobile phone along with GPRS enabled DOCOMO SIM card to the site for checking the GPRS availability at site. Field team should seek appropriate clarification from backend team for connecting the AC / DC Energy meter incase of any ambiguity before powering ON of the RTU, by calling on the above numbers from the site.
No. of AC Energy meters installed at site No. of DC energy meters connected to RTU Make & model of each DC EM BTS loads connected to each channel of the DC EM Availability of the DOCOMO GPRS at the site PIU/ Non-PIU site Rating of the CTs No. of CTs installed at site DC Energy meter make No. of operators EB / Non-EB site
Backend support team will configure the site in TOC application and they will load the latest program into the GPRS module (depending upon the make/model & the No. of AC and DC Energy meters connected to the RTU at site ) & will confirm back to the Field team.
II. Commissioning:
a. Plug in all the RS485 connector one by one to all the AC & DC EM meters while checking the data on the RTU display. b. RTU display should show the respective Energy data from each meter. In case any of the meters data is not displaying on the RTU LCD display, corresponding meters wiring /settings need to be checked. c. If RTU switches off, while connecting any of the RS485 cable to AC or DC EM, it indicates a faulty meter and this needs recorded in the commissioning checklist. d. Ensure that CT wiring and connections are done as below. Note: If CT wiring is not done as below, then Power factor (PF) reading in the meter would show very less (around 0) & energy calculations and energy displays from the meter will become wrong. Whereas the correct value of PF should be around 1
KEY
IN SET(PROGRAMMING) MODE To select value and accept value (It act as a RIGHT key in programming mode)
UP
DOWN
To edit value/system type down-wand in edit mode and scroll through the parameters
f. Set the Slave ID on the 1st DC energy meter (either external / built-in) to 6, 2nd DC EM to 7 and so on. g. If it is a PACE or Invendys make DC energy meter, slave ID can be set using the password by entering the password as 232 h. When the load is on EB, Verify that EB energy and EB run hours are updating on the AC energy meter display and also on the RTUs LCD display
i. Switch off the EB supply and when the DG runs & load is on DG, DG energy and DG run hours should be updated on the AC energy meter display and on the RTU display. j. Compare the EB energy and EB meter readings for same energy consumption readings by checking for 30 minutes to 1hour. The acceptable deviation is 0.1 units /Hr. If energy consumption readings are beyond the tolerance then it indicates either wrong installation of the CT or additional loads are connected between EB meter and ConnectM AC EM. The same has to be corrected and recorded in the I&C check list. Communicate all the meter readings to backend team. k. Compare the DG Run hour, DG Energy readings with that DGs Run hour meter & energy meter, if available, for the same Run hour & energy consumption by checking for 30 minutes to 1hour. If Runhour readings are not tallying, it indicates either wrong wiring or faulty DG run hour meter at site. The same has to be corrected and recorded in the I&C check list. Communicate all the meter readings to backend team. l. Check whether all Energy meters data are verified on the RTU display & the same data is shown in the TOC application Note: Field team to carry out the activities at site & provide the necessary details as requested by the backend team while verifying the Energy data (Like switching on/off of the EB/DG, measuring of the currents & voltages etc)
III. Sealing the RTU and the AC EM box (As applicable). RTU Seal Photographs - Option 1
AC EM Seal Photograph:
IV. Documentation
a. Fill up the AT report & get the AT signed off by the customer after verifying the data in the application (incase GPRS is available) / on the RTU display (incase GPRS is not available) b. Fill up the Commissioning report & the Site survey checklist. c. Email all the below 3 documents to WQTS@connectm.com or Submit the hard copies at respective ConnectM Circle office along with site installation photos. 1. Commissioning Report 2. Site Survey checklist 3. AT document d. Should there be any components/device failure, a fault report should be filled up and kept/sent along with the faulty material for repair.