Project :EID Parrys ORN No :M3T296 Sl No AREA Instrument

Commissioning Report
Status Target

Date:20.12.2004 Remarks Temperature RTD's/Thermocouples to be commissioned. M/s ELECTRONET, supplier repersentative is already on the job to rectify the problems related to these.

Raw Juice Heaters and Sulphered Juice Heaters

Control Valve and RTDs

Ready for operation from DCS in Manual Mode

To be put in AUTO mode to control Heater Temperatures by 26.12.2004

Sulphur Burners

Control Valves and RTDs

Ready for operation from DCS in Manual mode.

To be put in AUTO to control the Temperatures by 25.12.2004

Temperature RTD's/Thermocouples to be commissioned. M/s ELECTRONET, supplier repersentative is already on the job to rectify the problems related to these.

Film type sulphur burners

Control Valves and RTDs

Hook up to be done

Clearance reqd from EID Inst. Dept.

Clearance reqd from EID Inst. Dept.

Calibrated using Buffer Solutions. 4 Juice Sulphitation pH Transmitters and Control Valves Ready for operation from DCS in Manual Mode To be put in AUTO mode to control the SHOCK & FINAL pH by 23.12.2004 THL & EID to co-ordinate.

Evaporator

RTDs, Pressure Transmitters, Level Transmitters, Brix Transmitters, Control Valves, Motorized Actuators Absolute Pressure Tx. & Condensor control valves

Loop checking completed

To be put in AUTO mode to control the level by 05.01.2005.

THL working on the same.

Batch Pan (A PANS)

Commissioned & Working satisfactorily

To be put in AUTO mode to control the PAN THL & EID Process to co-ordinate. vaccum by 25.12.2004

A-Centrifugal Area

Level Transmitters and Control Valves

Level Transmitters working satisfactorily as per THL. Control To be put in AUTO mode to control the level THL & EID Process to co-ordinate. Valves are operating in Manual Mode by 25.12.2004 from DCS. Level Transmitters working THL has arranged the visit of Product satisfactorily as per THL. Control To be put in AUTO mode to control the level Expert for attending the Ultra Sonic Valves are operating in Manual Mode by 26.12.2004 Level Transmitter on 20.12.2004 from DCS. Field Wiring, Termination Completed. EID clearance required for hook-up of the instruments. To commission all the instruments and to put the valves in AUTO mode by 05.01.2005 To put in Manual Operation from DCS by 25.01.2005.

Horizontal Crystalizers

Level Transmitters and Control Valves

Continous Pan

All Control Valves, WPR'sinstruments

All

THL & EID to Co-ordinate

10

Mill Area

All

Pending

Cable shortage, Level Switches and Chute Level sensors

PAGE 1of 2

Project :EID Parrys ORN No :M3T296 11 Other Areas All Pending

Commissioning Report

Date:20.12.2004

To be put in Manual Operation from DCS by Cable Shortage, Level switches, DP 20.02.2005 capillary LT.