Professional Documents
Culture Documents
Crate&Barrel
Founded in 1962 Headquartered in Northbrook, IL 145 Stores $1.4 Billion Annual Sales 7,000 Employees Retailers of Housewares & Furniture Emphasis on People, Product and Presentation
Crate&Barrel
We dont use prototypes Each store is a unique design. No efficiency Complex articulation in plan and elevation Neo-Modernist approach to design and detailing Difficult materials to source High sensitivity to delivered facility. Building as Brand End users have powerful voices.
3
Crate&Barrel
What doesnt work with traditional delivery:
Longer production of Contract Documents Long Lead Items cannot be procured early Subcontractors cannot provide input in detailing and specifications Team Members still operate in their traditional silos of risk and reward
4
Crate&Barrel
Advantages we have in implementing IPD
Same consultants Same construction managers Same Systems Same end goal Willingness to absorb more project risk
5
Crate&Barrel
Our process In House Architecture and Design produces Schematic Design package In House Construction Department acts as CM at Agency Outsourced Associate Architecture (CDs & CA), Structural Engineering, MEP Engineering CM at Risk using the 1997 AIA A111 and A201 contract Large Amount of Owner Furnished Materials
6
Crate&Barrel
Our schedules 6 week conceptual design phase 24 week document schedule 32 42 week construction schedule 4 week commissioning period Start after January 15th Finish before November 15th Only open on a Thursday One opening per week
7
Crate&Barrel
Costs A/E: CM@Risk OFM FF&E Misc Total $450,000 $9,000,000 $1,500,000 $1,500,000 $550,000 $13,000,000
Crate&Barrel
We like to think of Integrated Project Delivery as the difference between Mixtures, Solutions, and Compounds. Mixtures: two or more Entities which have been organized such that each Entity retains its own traditional identity and is active only during certain phases of the process Solutions: A mixture of two or more Entities which have been organized and managed such that each Entity has a non-traditional identity during most phases of the process Compounds: A Solution of Entities which have been organized and managed such that each Entity has an identity defined by the compound during all phases of the process. A compound usually has properties unlike those of its constituent elements.
9
Crate&Barrel
Our Basic Principles Focus on optimizing our schedule Adjust traditional project roles to support the schedule Orchestrate meaningful collaboration Eliminate Low Value-Add Steps
10
Crate&Barrel
Most traditional (nonintegrated) delivery methods produce Mixtures Most IPD thinking produces Solutions At Crate&Barrel, we are trying to create a process that produces Compounds
11
Crate&Barrel
Integration Steps
Performance Metrics Workflow Standards AECO Team Solution Prime Subcontractor Awards Long-Lead Systems Operations Inclusion
12
Crate&Barrel
Crate&Barrel
Workflow Standards Integration
Web-based Project Management for more and more workflow Acrobat file format for all deliverables BIM deliverables Web conferencing with sync Audio that is recorded and stored Owner-controlled shipping and reprography Blackberrys Synchronized Travel
14
Crate&Barrel
15
Crate&Barrel
Crate&Barrel
One of Our Strongest IDP Partner: SteelFAB
17
Crate&Barrel
Our Greatest Success: Steel, Steel, Steel
Benefits from: Good SER and Fabricator relationship; Mutually Beneficial Use of BIM: RAM to Tekla; and A Process-Oriented Fabricator Have been: 190 tons to 140 tons Average Project Weight Fabrication Times reduced from 6 weeks to 2 weeks. Shop Drawings Produced in 3 weeks instead of 6 weeks. Erection Times reduced to 3 weeks from 6 weeks. Almost Complete Elimination of Field Re-Work due to Fabricator Error
18
Crate&Barrel
Crate&Barrel
The New Kids on the IPD Block: Hill Mechanical, Johnson Controls, JF Ahern
20
Crate&Barrel
Crate&Barrel
Our Current Focus: Pre-Fabrication and Modularization
22
Crate&Barrel
Operations Inclusion
Business Critical Systems Providers are brought in prior to SD to begin planning design, procurement, , fabrication, delivery, installation, commissioning, and operations integration These Providers may be OwnerContracted, some may be CMContracted. Specifications and detailing conducted with Providers, AEs, CMs, and Operations to integrate all facets of need. Such integration has led to modularization and prefabrication of switchgear and doors
23
Crate&Barrel
Things we have learned that do not work with IPD
Activating team members too early Procuring material too early Focusing Technology of the wrong trade Silo-Scheduling Design-Building the wrong thing
24
Crate&Barrel
Things that we will never repeat with IPD AEs that didnt understand critical fabrication issues Assemblies that were procured too late and caused overtime CMs that didnt understand operations concerns Spending one month of time reworking miscoordinated disciplines
25
Crate&Barrel
Success Stories CD schedules have reduced from 24 weeks to 8 weeks Well Coordinated Contract Documents Transparent Workflow Tonnage reduction from 220 to 160 tons. Well Liked HVAC systems Elimination of overtime charges due to late deliveries Happier projects
26
Questions
jmoebes@crateandbarrel.com
27