1. Introduction 2. Cost Analysis 3. Specification chosen by you 4. Details of Material Complete) 5. Detail of Material (Stage wise) 6. Abstract of Cost a. Brick Work b. Roofing c. Steel Work d. Plastering & Pointing e. Wood Work f. Flooring g. Painting h. Electrical Work i. Water Supply & Sanitary j. Development Work (Boundary Wall, Grassy Lawn etc.)
7. Details of Quantities a. Brick Work b. Roofing c. Steel Work d. Plastering & Pointing e. Wood Work f. Flooring g. Painting h. Electrical Work i. Water Supply & Sanitary j.
8. Thank You!
1) Introduction
Resp. Mr. Kuldeep, First of all we would like to thank you for choosing GharExpert.com. Gharexpert.com can save you money during construction and if planned properly we all can save 10% or more on our home construction projects.
2) Benefits
Broad benefits of the detailed cost estimate are.
3) Documents Reviewed
In order to arrive at this detailed estimate we did the following. Reviewed the architectural plans sent by you. Researched the rates of material and labor. Studied your requirements for the tiles, paint, woodwork, kitchen work, bathroom and other areas.
Tipsrelatetoyourplan(DosandDonts)
1. You must Use Cement Concrete as per your structural drawings but it should be done with Mechanical mixer and vibrator to increase the strength and life of the structure and safety against earthquake and other natural disasters. 2. Provide sun shade on outer doors and windows to protect them from heat and rain. 3. Use coarse aggregate and fine aggregate after washing with water. 4. Use wet bricks in brick masonry. 5. Do proper curing so that cement work may get full strength. 6. Fix doors and windows frames during masonry work.
1. Do not use salty water in cement concrete to avoid rusting of steel. 2. Do not use fine sand and sand containing silt in cement concrete work as it reduces the life of structure.
# 1 2 Total Area Total Cost Cost per Sft.(Total Area/Total Cost) 3214 Sft. Rs.3170162 (Rupees Thirty One lac Seventy Thousand One Hundred and sixty Two) Rs.987 (Rupees Nine Hundred Eighty Seven per Sft.)
Your Reply:
We Ask:
Your Reply:
Stage wise material will help you procure the raw material properly. A lot of times, the building owner do not keep track of the material used in their construction and the labor uses this lack of information to either use sub standard material or use less than the specified quantity.
# 1 2 3 4 5 6 7 8 9 10 11 Cement Sand
Material
Quantity 1250 3600 3200 1000 50400 200 1600 10896 866 3200 52
Unit Bags Cft Cft Cft No.s Kg Sft Kg. Sft. Sft. Sft.
Bazari or Stone Chippings 12 to 20 mm gauge Stone Blast / Brick Blast Bricks Bitumen Polythene Sheet MS steel bars of different diameter Ceramic Tiles Vitrified Tiles Granite
To know more about purchasing tips of Cement and Bricks click or copy the link below: http://www.gharexpert.com/articles/Start-Construction-1460/Purchasing-Guidelines-Cement-Bricks_0.aspx Cft=Cubic Feet
Foundation
# 1 2 3 4 5 6 7 8 9 10 11 Cement Sand Bazari or Stone Chippings 12 to 20 mm gauge Stone Blast / Brick Blast Bricks Bitumen Polythene Sheet MS steel bars of different diameter Ceramic Tiles Vitrified Tiles Granite Material Quantity 180 650 550 350 8000 250 250 1719 ---Unit Bags Cft Cft Cft No.s Cft Cft. Kg. ----
Ground Floor
# 1 2 3 4 5 6 7 8 9 Cement Sand
Material
Bazari or Stone Chippings 12 to 20 mm gauge Stone Blast / Brick Blast Bricks Bitumen Polythene Sheet MS steel bars of different diameter Ceramic Tiles
10 11
1764 28
Sft. Sft.
First Floor
# 1 2 3 4 5 6 7 8 9 10 11 Cement Sand
Material
Quantity 500 1350 1250 300 20000 175 1350 4340 430 1436 24
Unit Bags Cft Cft Cft No.s --Kg. Sft. Sft. Sft.
Bazari or Stone Chippings 12 to 20 mm gauge Stone Blast / Brick Blast Bricks Bitumen Polythene Sheet MS steel bars of different diameter Ceramic Tiles Vitrified Tiles Granite
5. Abstract of Cost
Abstract of cost is used for the planning purposes. From the abstract of cost, we will get stage wise and item wise expenditure. With the help of this we can control the expenditure item wise and stage wise and also in better position to deal with contractor & supplier. # Description Earth work in excavation in foundation of columns walls includidng dressng the side and ramming the bottom up to 5' lift Earth filling with earth available at site from excavation Quantity Unit Rate Amount
2124
Cft
6372
2124
Cft
2124
around columns footings , plith beam and masonary in layers including watering and compacting. Earth filling under floor with earth brought from out side including carriage of earth, loading, un loading watering and compacting the same. at site around columns footings , plith beam and masonary. Supplying and laying sand filling in foundation of footing under PCC
3275
Cft
13100
827.6
Cft
50
41380
Pcc 1:5:10 with granite stone aggrigate of 40mm and down size mechnically mixed and vibrated including laying compacting as per requirement. Cement concrete 1:1.5:3 with stone chipping or bazri 12 mm to 20 mm gauze in fondation of columns footings, plinth beam etc including centering and shuttering but excluding steel reenforcement mechanically mixed and vibrated complete in position asper specification.
366.4 Cft
70
25648
6. Detail of Quantities
Abstract or detail of quantities provides us quantities required to complete the construction. With the help of this we are able to know the quantities of each item stage wise, unit wise and this will help in doing agreement, procurement of raw materials according to need. Save wastage in materials , labor. and timely construction.
Particulars Earth work in excavation in foundation of columns walls includidng dressng the side and ramming the bottom up to7' lift Columns footings Footing I Footing II
No.s
4 8
4 4
4 4
5 5
320 640
cft. cft.
Footing IV Plinth beam bed1,2 and toilet vertical Plinth beam bed1,2 and toilet internal Plinth beam toilet internal Plinth beam toilet internal Plinth beam right side Plinth beam living, study, kitchen. Plinth beam kitchen. Plinth beam kitchen. Plinth beam living
4 2
4 40
5 1.5
5 1.5
400 180
cft. cft.
4 1 1 1 3 1 1 1
Recommendations
a. Use clean water free from salt, organic matter and insoluble impurities. In general drinking water is suitable for construction work. b. All materials like bazari, coarse sand should be cleaned and free from dust, organic matters and other foreign material, silt etc. c. Sand used in cement concrete should be coarse sand having silt less than 4%.
d. All cement concrete work should be mixed with mechanical mixer and vibrated with mechanical vibrator. e. Cement plaster taken at item serial No.8 is bearing plaster which should be done on top of wall before laying RCC slab. It reduces the chances of cracks at the junction of roof and wall which is formed due to expansion and contraction of RCC slab due to change in weather. f. All cement concrete mix should be 1:1.5:3 instead of 1:2:4 according to new guide line for earth quack safety
g. Sand used in cement concrete should be coarse sand having silt less than 4%. h. The rates provided for vitrified tiles, ceramic tiles are from repudiated make, steel railing and wood work are of best quality material & supplied by you. i. j. k. All cement concrete mix should be mechanical mix and vibrated. The formwork of R.C.C. column should be steel (FARMA) not by giving temporary support of wooden batten/ planks or brick support. It is advisable that at the time of purchasing or allotting the work to any contractor rates should be verified at least from three to four contractors from the local market with the quality of the materials and work. There is very high fluctuation in the rates. The rate varies with the quality and specification of the materials. Item taken at sr no 3 is concrete mixed with cement and sand duly compacted. Generally it is seen that contractor laid dry brick ballast which should be avoided.
l.
m. The rates for the water supply and sanitary work are of medium quality. n. For electrical work labor for laying pipe, junction, box, wiring, switches, and main switches etc has been taken in the estimate. o. At item no 50 cost of pipes junction box, fan hook switches, sheets M C B & wires etc have been taken. Fans, A.C, decorative light & exhaust fans are not taken.