You are on page 1of 6

International Journal of Project Management Vol. 17, No. 5, pp.

317±322, 1999
# 1999 Elsevier Science Ltd and IPMA. All rights reserved
Printed in Great Britain
0263-7863/99 $20.00 + 0.00

PII: S0263-7863(98)00048-9

Integrating quality systems in


construction projects: the Chilean
case
Alfredo Serpell
Department of Construction Engineering and Management, Ponti®cia Universidad CatoÂlica de Chile,
Casilla 306, Correo 22, Santiago, Chile

A summary of the principal characteristics, problems, limitations and bene®ts of the integration
of quality systems based on the ISO 9000 in Chilean construction projects, is presented. These
implementation processes were carried out by di€erent construction companies with no previous
experience on quality systems or ISO 9000, at the requirement of one owner. The particular and
general characteristics of the processes and the lessons learned are analysed according to the
appraisal of the di€erent participants. Special focus is given to the impact that quality systems
had on the relationship between the owner and its contractors. Finally, some recommendations
are proposed for a successful integration of quality systems in construction projects, as well as
for future implementations in countries with limited experience on this regard. # 1999 Elsevier
Science Ltd and IPMA. All rights reserved
Keywords: quality systems, ISO 9000, construction projects, owners' requirements, construction procurement

Introduction Research was carried out to understand the pro-


blems, limitations and bene®ts expected from the inte-
During the last decade, the activities of quality assur-
gration of quality systems (QS) in an environment
ance in most of Chilean construction companies have
with limited knowledge and experience in this topic,
been limited only to meet the technical speci®cations
and how the relationship between an owner and its
of ®nal products, with a strong dependency on the
contractors can be a€ected by this situation. An ad-
owner's inspection.1 However, this approach is chan-
ditional focus of this study was to observe how it poss-
ging rapidly and several owners are now transferring ibly a€ects the procurement of construction services.
the responsibility for quality assurance to contractors. In the cases studied, QS was a procurement obligation
This situation has impelled construction companies to and the longer term issue here is whether it should
make e€orts to implement quality systems in their pro- always be one or whether QS becomes `second nature'.
jects. It is important to note that in Chile, most of the To achieve the previous objectives, three construc-
construction projects are contracted using the tra- tion companies which were running ®ve construction
ditional approach and that other approaches like the projects between November 1993 and April 1994 were
design-construction or turn-key contracts are seldom observed and interviews applied to projects' personnel.
used. The contractors were contractually required by the
Quality assurance and quality management are owner to apply quality systems based on ISO 9000
topics that have received high level of attention during series during the execution of mining projects. The
the last decade in many countries and industrial sec- description of the projects observed in the study is
tors. As stated by Hirao,2 company-wide quality man- shown in Table 1, along with the time at which the ob-
agement has become a serious concern for businesses servation on site was carried out.
all over the world. However, in the construction indus- The interviews were carried out through all the
try the application of quality management concepts levels of personnel involved in the QS implementation
and tools has been more dicult due to its reactive processes. A total of 33 persons were interviewed, as
nature and the complexities of the construction pro- shown in Table 2.
cess. As reported by Baden Hellard3, in a study of ex- Figure 1 shows the relationship between the di€erent
periences in 12 countries, the construction industry has participants involved in the QS implementation pro-
lagged behind other industrial sectors in these cesses. Regarding the projects included in the study,
countries. This has also been the case in Chile and the following aspects are interesting to note for clari®-
most of the Latin American countries.4, 5 cation purposes:
317
Quality systems in construction projectsÐthe Chilean case: A Serpell

Table 1 Description of projects studied (adapted from Crovetto6)


Contractor's Previous QS
Project Type Completion term (months) Experience Date of study* (months)
A Civil works and steel structures 12 NO 2.5
B Civil works, piping and steel structures 7 NO 2
C Civil works, piping and steel structures 6 NO 2
D Civil works, piping and steel structures 6 NO 1.5
E Civil works, piping and steel structures 11 YES 10
*Time from the beginning of the project

Table 2 Description of interviewed personnel (adapted from Crovetto6)


Top company Owner's
Project management Site Professionals QA/QC Oce Crew Foremen Site Administratives Representatives

A 2 2 3 2 2 2
B 0 1 2 1 0 1
C 0 2 2 2 0 1
D 1 1 0 1 0 1
E 0 1 1 1 0 1
Totals 3 7 8 7 2 6

. The time between the adjudication of contracts and


the beginning of projects was 45 days and this was
used for the preparation and development phases of
the QS for each project.
. The two contractor companies without experience in
QS, required the services of a consulting company
which had acted as the owner's inspection in a pre-
vious contract.
. The control of the quality system was exercised by
Figure 1 Relationship between projects' participants the owner itself through quality auditors at the site
that were trained during a previous contract.
. Two of the three companies involved did not have The structure of the implementation processes was
previous experience in the application of quality sys- similar for all the projects and it included three
tems in their projects, neither did they possess any sequential phases: preparation, development and im-
knowledge of the ISO 9000 series. plementation, as described in Figure 2. Each phase was

Figure 2 Description of the phases of the implementation process

318
Quality systems in construction projectsÐthe Chilean case: A Serpell

considered concluded when speci®c planned objectives . An intensive all-level training program at work was
were reached. Then it was possible to continue with developed, with the objective of reducing the lack of
the development of the next phase. knowledge and experience in the use of the concepts
and techniques that sustain the application of a QS.
. A permanent evaluation of the learning and progress
of participants was performed, and a periodical
Characteristics of the implementation process evaluation of the training program was carried out.
The QS implementation introduced changes in di€er- . Knowledge matrixes were developed, in which each
ent aspects of the organisations involved in the pro- member of the organisation was associated to the
cess. Interviews served to analyse the impact of this needed quality knowledge and abilities.
changes and to identify ideas for improving future im- It is also important to underline that the results
plementations. In the next sections of this paper, the obtained by one contractor that extended the training
main issues observed are discussed. programs to direct labour levels were not better than
those which only trained down to foremen level. This
Characteristics associated with the organisational situation was basically due to the lack of workers'
structure of the work interest, to the work pressure produced by the short
construction time allowed, and to the lack of appropri-
Concerning their organisational structure on site, con- ate incentives.
tractors had to incorporate a Quality Assurance and
Control Oce (QA/QC), which was directly under the
control of Project Management. Contractors' site or-
ganisations were quite similar, but di€erences were Barriers or limitations
found in their support towards the QA/QC oce
which depended on the magnitude of the project and At the beginning of the QS implementation processes,
on each contractor's commitment to the QS. both cultural and operational barriers were observed,
The principal novelty for the owner's organisation, some of which could not be surpassed and notably
was the inclusion of site quality auditors in charge of a€ected the success of the processes. The most import-
assuring the e€ectiveness of the contractors' quality ant faced by the contractors were as follows:
systems. Due to the lack of experience of contractors . Lack of knowledge of the concepts and tools of QS
and indeed of their own, they had to be very ¯exible systems.
and appeal to the good faith of contractors to achieve . De®cient communication of objectives to personnel.
this purpose. . Unlinked implementation processes between the
main oce and the site.
. Improper organisation of the company, not ade-
Characteristics related to incentives quate for the implementation process.
In order to motivate and achieve the workers' commit- . Lack of real commitment, leadership and interest of
ment to the system, the contractors took some of the the company's top management.
following actions: . Problems with the de®nition of the QS project scope
. Key implementation processes personnel received due to inexperience in the topic.
monetary and non-monetary incentives. . Lack of interest and commitment of site personnel.
. There was a permanent presence of management on Furthermore, particular barriers faced by project
site to show commitment to the quality system. managers at the construction sites were as follows:
. Supervisors were consulted about operating pro-
cedures and they participated in the elaboration of . Lack of knowledge about the company's quality
manual and procedures.
procedures associated with their jobs.
. Short project completion times.
. Objectives pursued through the implementation of
. Lack of participation in the elaboration of oper-
QS were communicated in a clear and precise way
ational and administrative procedures.
to site personnel.
. Insucient knowledge of project documents, a fact
. Personnel were convinced that training on QS would
that produced an inadequate handling of changes
provide them with better quali®cations for future
and supplies as well as late detection of design qual-
jobs.
ity problems.
The main incentive given by the owner to contrac- . Bad attitudes in front of the system's application.
tors, was the promise to incorporate them into a `short . Lack of knowledge and expertise in the construction
list' for future projects. In spite of this incentive, con- market, in order to involve designers, suppliers and
tractors were not very convinced of the bene®ts of QS subcontractors in the process.
and the system was only seen as an owner's contrac- . Natural rejection of the system due to the extra
tual requirement. As a direct consequence of this, none e€orts that its implementation implied.
of the construction companies was able to maintain . Lack of quali®ed personnel on quality and quality
the application of the system beyond the time speci®ed systems in the construction market at all levels.
by the contract.
The owner's sta€ also faced several important bar-
riers which are mentioned below:
Characteristics related to training . Rejection of the QS by owner personnel.
The contractors took several actions to confront the . Insucient management of changes and supplies
training needs of personnel, as follows: that a€ected the owner/contractor relationship.
319
Quality systems in construction projectsÐthe Chilean case: A Serpell

Table 3 Problems mentioned by contractors' personnel (adapted from Crovetto6)


Projects
Problems A B C D E
Lack of knowledge and expertise of site personnel q q q q q
Lack of performance parameters to evaluate the implementation process q q q q q
Rejection to the system by site personnel q q q q q
Diculties associated with system documents q q q q q
Rotation of site personnel (foremen and workers) q q q
Diculties in the design and implementation of the ®les required by the system q q q
Objectives con¯icts between production area and the QS q q q
Diculties in management and consolidation of the QA/QC oce at work q q q
Lack of presence and motivation in site of companies' top management q q q
Mistakes and diculties in the training program q q q
Diculties in the integration of professionals to the implementation process q q q
No prior knowledge about the system q q q q q
Negative reaction and bad initial attitude q q q q q
Diculties associated with training and communication of the system at the site q q q q q
Lack of relationship between the new system and bene®ts that workers could receive q q

. Improper training of the contract administration . Once the system was put under way and accepted, it
team. increased the order and the speed in the projects
. Insucient control of the main parameters of pro- progress.
ject management: quality, time and cost. . Trust between the hierarchic levels on site increased
. Divergence of objectives inside the owner's team. considerably.
. Weaknesses in the creation of owner/contractor . A re-evaluation of workers' responsibility, image,
teams. and ethics by professionals was achieved.
. The disappearance of the classic antagonistic point
of view about work inspection for workers and fore-
men was encouraged.
Particular problems of the implementation Bene®ts perceived by the owner's sta€ from the im-
processes plementation of QS's are mentioned below:
The principal problems as identi®ed by contractors' . The relationship owner/contractor shifted to an
personnel are shown in detail in Table 3. The answers issue of mutual trust.
have been individualised by each project. . The combination of the QS with the organisational
According to the owner's personnel, the following structure of the owner reduced the `work dead
problems were associated with the contractors' per- times', due to better decision making on site.
formance: . Re-work was reduced due to the fact that the per-
. Diculty for generating commitment of site person- sonnel became conscious of a greater responsibility
nel to the system. on the quality of their assigned tasks.
. Contractors demonstrated severe diculties in the . The management of changes and/or modi®cations
management of system documentation and in the was improved.
maintenance of the system ®les. . The completion of tasks was documented and regis-
. Lack of initiative of contractors to begin with the tered in detail, reducing the possibility of subjective
implementation process, that ampli®ed the impact of interpretations.
the short construction completion time.

Success factors
Bene®ts of the system The processes were also supported by success factors
The most relevant bene®ts as perceived by contractors' or positive aspects found in the cultural characteristics
professionals are shown in Table 4. Foremen also of the members of the construction companies, which
added the following bene®ts: should be taking into account for future QS implemen-

Table 4 Bene®ts mentioned by contractors' professionals (adapted from Crovetto6)


Projects
Bene®ts A B C D E

Relationship with the owner improved ostensibly q q q q q


System provided order, control and planning to site works q q q
System favoured quick treatment of doubts and/or work
modi®cations q q q
System increased the participation and communication at site q q q
System improved team working of personnel q q
Implementation processes allowed to spread companies and
projects objectives q q
Implementation processes improved the leadership conditions of
people in charge of workers q q

320
Quality systems in construction projectsÐthe Chilean case: A Serpell

tation processes. Among the most important factors . To promote by incentive, ISO certi®cation of sup-
mentioned are the following: pliers and service companies, as well as the involve-
ment of designers and subcontractors.
. Local companies showed high levels of personal
involvement in their human relationships. Their re-
lationships with owners, suppliers, and personnel
were based on seriousness and honesty.
. There were adequate levels of self-examination Related to training
between the professional and management levels. Contractors developed several training activities:
. Many workers felt very identi®ed with their compa-
. To increase the quality of persons in charge of the
nies, a fact that was used for motivation purposes.
training program.
. To continue with training at all levels, given the fact
that the fundamental limitations for the implemen-
tation processes were the lack of knowledge and
expertise of site engineers and personnel on the
Recommendations topic.
The analysis of the research results provided several . Construction companies should keep applying
recommendations for future improvement of QS im- quality systems in their projects even if it is not a
plementation processes. These are discussed in the next contractual requirement, to learn and acquire exper-
sections of this paper. tise on it.
. To use quality circles as a better and quicker way to
acquire knowledge, expertise and search of sol-
Regarding the contractors' organisation of the work utions.
Owners should foresee realistic periods between
. To assure that company and project organisational contract adjudication and the beginning of the con-
structures are ®tted to the proposed projects objec- struction project, to allow proper planning and im-
tives. plementation of the QS by contractors, and in this
. To adequately structure and support the QA/QC way, to avoid the contractor's dilemma of attending to
oce at the site, according to the tasks that it must the system or to the production.
ful®l.
. To reduce the hierarchies and delegate decision mak- Conclusions
ing at site level, in order to achieve a greater ¯exi-
bility and decrease `work dead times'. The introduction of the modern concepts of quality
. To provide the necessary training and abilities to systems is not an easy task in environments where the
QA/QC oces members. lack of knowledge and experience create particular
. To establish means for improving communication limitations or barriers to implementation processes.
among di€erent levels. This exploratory study allowed us to know the limi-
. To assure the use of a clear and common language tations and the most important characteristics which
to avoid distortion of QS concepts and terminology, were present in di€erent QS implementation processes.
specially at the lower organisational levels. Also some bene®ts produced by a QS were identi®ed.
Furthermore, an e€ort was made to transform the in-
formation obtained into useful recommendations.
These recommendations are directed to prevent foreign
For owners and local companies which want to implement a QS
basing it on external experience, without taking into
. To introduce the contractors at early stages of the account the particular characteristics of the local con-
project in order that they can better understand struction market.
owner's requirements. It is stressed, ®nally, the need of creating a `domino
. To consider the possibility of `partnering' with pro- e€ect' in the market towards quality systems, in order
jects participants. to convince construction companies about the advan-
tages of its application and in this way to induce their
use by their own initiative and not as an owner's con-
tractual requirement. Also, this initiative should be
Regarding incentives extended to suppliers, designers, subcontractors and
Contractors can use the following recommendations: other organisations in the construction industry.
Regarding construction procurement, the main con-
. To develop statistical tools to measure the achieved
clusion is that quality systems can provide a suitable
results and communicate them in order to increase
mechanism to improve the relationships between an
the commitment to, and trust in the system.
owner and its contractors. The main advantages
. To stipulate adequate incentive plans for critical im-
o€ered by this approach are as follows:
plementation personnel.
. It establishes a common goal for all parties
Owners can also play an important role:
involved.
. To establish actions for increasing QS knowledge . It performance depends on the creation of a team
and expertise in the construction market, by requir- spirit between the contractor and the owner, and it
ing their use within their procurement processes. favours partnering.
321
Quality systems in construction projectsÐthe Chilean case: A Serpell

. It creates communication channels between owner Sjoholt, editor. Quality Management in Building and
and contractors, as required by the QS. Construction. Norwegian Building Research Institute, 1994;
41±48.
. It requires a formal and rigorous handling of docu- 4. De Solminihac, H., Serpell, A. and Figari, C., Quality in the
mentation and the creation of records that help to Chilean construction industry: a general diagnosis (in Spanish).
solve problems. BoletõÂn de InformacioÂn TecnoloÂgica BIT, 1996, 3(6), 27±30.
. Because of its nature, a QS requires the attendance 5. Covelo Silva M. A. A Modernizacao do Macrocomplexo da
Construcao Civil: O Posicionamento Competitivo na
to problems and con¯icts in the short-term. Contribuicao ao Desenvolvimento do PaõÂ s. Seminario
However all these advantages can also be sources of Internacional, Sao Paulo, Brazil, 5±6 December, 1994: 5±13.
6. Crovetto A. Quality Improvement Program for Construction
problems if the QS is not well applied and if there is a Companies. Master Thesis, Department of Construction
high level of distrust between the parties. This fact Engineering and Management, Ponti®cia Universidad CatoÂlica
makes it necessary to teach contractors and owners to de Chile, 1995.
work under this scheme.

Acknowledgements
Alfredo Serpell is Associate
The author expresses his gratefulness to CorporacioÂn Professor of Construction Engin-
eering and Management at the
de InvestigacioÂn de la ConstruccioÂn and to Ponti®cia Universidad CatoÂlica de
FONDECYT, for the ®nancial support granted that Chile. He teaches project manage-
made possible this research through the Project ment, construction productivity
1940609. improvement, construction quality
management and construction pro-
curement. His current research
interests include quality manage-
References ment, productivity improvement,
1. Serpell A., AlarcoÂn L. F. Inspection of Construction Projects in lean construction and construction
Chile, Real Behavioural Analysis. Research Report ICC-II-1, procurement practices in Chile.
Ponti®cia Universidad CatoÂlica de Chile, 1986. Since 1990 he has directed and
2. Hirao S. Management and QualityÐas the basis of continuous managed a consulting group that
improvement of the competitiveness of Takenata Corporation. provides services to the Chilean
In: Odd Sjoholt, editor. Quality Management in Building and construction industry and has been involved in the promotion of
Constructios. Norwegian Building Research Institute, 1994: 20± continuous improvement of this sector. He obtained a Civil
28. Engineering Degree from the Ponti®cia Universidad CatoÂlica de
3. Baden Hellard R. Quality Management in ConstructionÐA Chile, an MSc. in Architectural Engineering and a Ph.D. in Civil
State of the Art Report on a Worldwide Canvass. In: Odd Engineering, both from the University of Texas at Austin, USA.

322

You might also like