Estimation $/m without additional cost

Labor Charges Wage/Manday No. Hours/ day Days/Month Wage/Month Bonus/Year $/hr
Skilled Labour/ Operator 40 1 8 22 880 1760 5.83
Unskilled Labor 20 2 8 22 440 880 5.83
Supervisor 50 1 8 22 1100 2200 7.29
Total Labour Charge per Hour ($/hr) 18.96

Assume driven (m/day) 100


Maximum operating hours per day (hrs/day) 8
Time taken to drive pile in hour (hr/m) 0.08

Total Labor Charge per metre run ($/m) 1.52


Hire Rate inc. fuel &consumables per metre run ($/m) without mobilization 3
Total Labor Charge plus Hire Rate per metre run ($/m) 4.52

Type Dimension Length Working Price Labour Inflation Estimation


Load of & 10% of before
Material Hire Rate Operation adjustment
(mm) (m/pile) (tons) ($/m) ($/m) ($) ($/m)
RC Precast 250x250 9 60 30 4.52 0.45 34.97
RC Precast 300x300 12 80 37 4.52 0.45 41.97
RC Precast 350x350 12 100 48 4.52 0.45 52.97
RC Spun 300 12 84 24 4.52 0.45 28.97
RC Spun 600 12 293 70.35 4.52 0.45 75.32

Note: The above exclude additional factors.


Adjusted cost will include mobilzation of plant, wastage and fillet-weld of pile.
These chiefly depended upon depth of pile work to be done and number of plant hired.
Then only no. of piles can be estimated.

Variable that depends on projects


Standard information (information given)
Functionised do not change
Estimation $/m with additional factors on:
Mobilization & Demobilization of Plant
Fillet-Welding of joint

Essential information:
Cost of fillet-weld per no. ($/no.) 5.00
Assume no of plant (item) 1
Cost of Mobilization ($/item) 2000

Type Dimension Length Working Assumed Qty of Pile Considering


Load Load Safety Factor
Hence take
Whole Qty
(tons/
(mm) (m) no. of pile) (ton) (no. of pile) (no. of pile)
RC Precast 250x250 9 60 500 8.33 9
RC Precast 300x300 12 80 500 6.25 7
RC Precast 350x350 12 100 500 5.00 5
RC Spun 300 12 84 500 5.95 6
RC Spun 600 12 293 500 1.71 2

Adjusted Estimation including Fillet-Weld and Mobilization of Plant (without wastage)


Type Dimension Length Calculated Qty. of Cost Cost Estimation Adjusted Adjusted
Depth pile of of before Estimation Estimation
of including Fillet-Weld Plant adjustment without without
Pile safety Mobilization b/f wastage wastage
Work factor cost per
meter
(mm) (m/pile) (m) (no) ($) ($) ($/m) ($) ($/m)
RC Precast 250x250 9 75.00 9 40 2000 34.97 4662.63 62.17
RC Precast 300x300 12 75.00 7 30 2000 41.97 5177.75 69.04
RC Precast 350x350 12 60.00 5 20 2000 52.97 5198.20 86.64
RC Spun 300 12 71.43 6 25 2000 28.97 4094.29 57.32
RC Spun 600 12 20.48 2 5 2000 75.32 3547.39 173.23
Estimation $/m with additional factors on:
Wastage

Essential Information:
Wastage in metre (m) Calculated below
Wastage is Charge ($/trip) 60
Assumed Trip 1

Type Dimension Length Working Assumed Qty. Considering


Load Load of Safety Factor
Pile Hence take
Whole Qty
(no. of
(mm) (m) (tons/no.) (ton) pile) (no. of pile)
RC Precast 250x250 9 60 500 8.33 9
RC Precast 300x300 12 80 500 6.25 7
RC Precast 350x350 12 100 500 5.00 5
RC Spun 300 12 84 500 5.95 6
RC Spun 600 12 293 500 1.71 2

Final Estimation including Fillet-Weld, Mobilization of Plant and wastage


Type Dimension Length Calculated Qty. of Wastage Wastage Adjusted Final Final
Depth of pile in disposed Estimation Estimation Estimation
Pile Work including metre off-site without with with
Safety wastage wastage wastage
Factor b/f

(mm) (m/pile) (m) (no) (m) ($) ($) ($) ($/m)


RC Precast 250x250 9 75.00 9 6.00 60 4662.75 4722.75 62.97
RC Precast 300x300 12 75.00 7 9.00 60 5177.75 5237.75 69.84
RC Precast 350x350 12 60.00 5 0.00 60 5198.20 5198.20 86.64
RC Spun 300 12 71.43 6 0.57 60 4094.29 4154.29 58.16
RC Spun 600 12 20.48 2 3.52 60 3547.39 3607.39 176.16