ELEMENT : WORK BELOW LOWEST FLOOR FINISH

TAKING OFF LIST NO A ITEM Column Bases/Pad footings/ Strip footing/Pile caps 1 2 3 4 5 6 7 1 2 3 1 2 3 4 5 6 1 2 3 4 5 6 7 8 DETAIL MEASUREMENT Excavations Disposal excavated material Filling to excavation Blinding Concrete Formwork Reinforcement Concrete Formwork Reinforcement Excavations Disposal excavated material Blinding Concrete Formwork Reinforcement Excavations (bed) / Filling (slab) Disposal excavated material (bed) Hardcore DPM Blinding Concrete Formwork Reinforcement UNIT M3 M3 M3 M3 M3 M/M2 KG M3 M2 KG M3 M3 M3 M3 M/M2 KG M3 M3 M2/M3 M2 M3 M3 M/M2 KG/M2 REMARKS

Same quantities as per excavation Qty. excavation - qty. concrete

Column Stumps

Ground Beam

Bed/Slab

ITEM NO.
A

ORDER TO TAKING OFF


EXCAVATION

UNIT

DESCRIPTIONS

SMM REF.
Section D General Rules; D.10

REMARKS

Depth classification; Max depth n.ex. 0.25m " 1.00m " 2.00m " 4.00m thereafter in 2.00m stages Starting Level; Ground level, Reduced Level, Formation level or such level which excavation will commence (normally start from Formation level, a level which formed after earthwork has been done) Quantity for excavation is measured from the actual dimension/size as shown on the drawings/plans. Std. Spec C/3.7 & 8

D.11

A.1

Reduced level

M3

Excavating to reduce level, Maximum depth not exceeding ..

D.12.4

area concrete bed (if suspended grd flr slab this item not measured)

A.2

Pits Pile caps Pad footings

M3

Excavating pits to receive .. starting from . level, maximum depth not exceeding (In. no) Excavating pits to receive .. starting from . level, maximum depth not exceeding , both plan dimensions less than 1.25m (In. no)

D.12.6

D.12.6

All pits excavation can grouped together. Starting level normally from formation level. For both plan dimensions (length & width) less than 1.25m measured separately. Stating the number (total number of pits irrespective the size)

ITEM NO.
A A.3

ORDER TO TAKING OFF


EXCAVATION (cont'd) Trench Strip footing Ground beam

UNIT

DESCRIPTIONS

SMM REF.

REMARKS

M3

Excavating trench to receive .. starting from . level, maximum depth not exceeding

D.12.7

All trench excavation can grouped together as foundation, but for purpose of valuation and v.o, it's easier to measure separately.

A4

Extra Over Items Excavating in rock

M3

Extra Over excavation in rock

D.12.2

Also can be measured as an item by itself. ( not as E.O ). Extra Over for each of the various types of excavation (each type of excavation has their own E.O). Quantity can be measure by allow % of the excavation or actual quantity of the rock (depend on engineer's proposal). Std. Spec C/.6.2

Excavating below ground water level

M3

Extra Over Excavating below ground water level

D.12.14

For area which water level is high. E.O to all types of excavation irrespective of depth. of excavation (each type of excavation has their own E.O). Quantity can be measure by allow % of the excavation or actual quantity of the rock (depend on engineer's proposal).

A5

Disposal of water Water in the ground

ITEM

Disposal of water in the ground for keeping the excavations free of ground water

D.16

If there is an item for excavating below ground water level. Std. Spec C/3.9

ITEM NO.
A A6

ORDER TO TAKING OFF


EXCAVATION (cont'd) Disposal of excavated material Disposal on site

UNIT

DESCRIPTIONS

SMM REF.

REMARKS

M3

Disposal of excavated material within site in permenent spoil heaps, ..meter from the excavation. Remove excavated material within site in m distance from the excavation. Spread within site excavated material Disposal of excavated material off site at contractor own source

D.18

All types of excavation can be grouped together To be save allow both types of disposal

M3

D.18

M3 Disposal off site M3

D.18 D.19

A7

Filling Filling to excavations

M3

Filling to excavations, material arising from the excavation Filling to excavations, material to be obtained off site at contractor own source Filling to excavations, material .. deposited and compacted in layers, *mm maximum thickness. Filling to make up levels over 250mm thk, material arising from the excavation Filling to make up levels n.ex 250mm thk, material to be obtained off site, hardcore as specified, average thickness mm.

M3

D.23 & 25 Filling materials: a. Material arising from the excavation b. Ditto to be selected and treated D.23 & 25 c. Material to be obtained off site Filling to all types of excavation can be D.23 & 25 grouped together D.27 Std. Spec C/4.12 D.23 & D.26

M3

Filling to make up levels

M3

M2

D.23 & D.26

A8

Surface treatment

M2

Applying anti-termite treatment as specified

D.30.2

Std. Spec - apply to area ground slab (C/4.13)

ITEM NO.
B B.1

ORDER TO TAKING OFF


CONCRETE WORKS IN-SITU CONCRETE

UNIT

DESCRIPTIONS

SMM REF.
F.1 Generally

REMARKS

Plain in-situ concrete / Reinforced in-situ concrete Grade concrete F.2.1 Thickness categories: Not exceeding 100mm 100mm - 150mm 150mm - 300mm exceeding 300mm

F.3

Concrete Categories: 1. Foundations in trenches 2. Isolated foundation bases 3. Ground Beam 4. Pile caps 5. Beds 6. Suspended slabs 7. Isolated columns

Plain concrete (blinding)

M3

Plain in-situ concrete grade . blinding bed; laid on earth or hardcore; not exceeding..thick.

All blinding works can grouped together under one item.

Reinforced concrete

M3

Reinforced in-situ concrete grade . in.

In Follow concrete categories. Column stump is under isolated column.

ITEM NO.
B B.2

ORDER TO TAKING OFF


CONCRETE WORKS (CONT'D)

UNIT

DESCRIPTIONS

SMM REF.

REMARKS

F.8.4 REINFORCEMENT KG ..mm Diameter mild steel bar as links, stirrups, binders and the like in foundation

Classification: In foundation (bases, grd beam & pile cap) In ground slabs (beds) In Isolated column (stump)

KG

..mm Diameter high tensile deformed bar as straight and bend bars in ground beam. F.8.5 Categories: Straight and bend bars Curved bars Links,stirrups, binders and the like Spacers and chairs Curved bar Bar required to be formed to radius not exceeding the critical radius. If not, it will consider as straight bar. Size () 6 8 10 12 16 20 25 Critical Radius (mm) 2500 2750 3500 5000 7500 14000 30000

KG

High tensile deformed bar in foundation; ..mm diameter, straight and bent.

Allowance for bend and hook shall follow BS 4466:1989

ITEM NO.
B B.2

ORDER TO TAKING OFF


CONCRETE WORKS (CONT'D) REINFORCEMENT (cont'd)

UNIT

DESCRIPTIONS

SMM REF.

REMARKS

M2

Fabric reinforcement ; In ground slab; reference

F.9.2

Classification follows as bar reinforcement Quantity measured as the area covered.

Fabric reinforcement ; strip ...mm width; in ground slab; reference

F.9.4

B.3

FORMWORK

F.10.1

Categories; Foundations and beds (footings, pile caps bases, ground beams) Isolated features (stumps)

F.11.1

Height categories; (for height n.ex. 1m) Not exceeding 250mm high 250mm-500mm high 500mm-1.00m high

M2

Formwork to edges and faces of foundations Formwork to ground beam; 250mm500mm high.

WATEPROOFING AND ASPHALT WORK

Classfication; A layer of polythene sheet as specified damp proof membrane; .mm thick; laid on blinding. Damp proofing and tanking