Professional Documents
Culture Documents
Introduction
In this project, we are proposing to construct a new hospital in this area. This will be a three story building. But we are keeping provision for future development up to five stories. This hospital is consists of many features that are very useful for the villagers. It is provided with Accident and Emergency treatment unit, X-ray room, Dental unit, Consultant unit, Childrens Ward, Female Ward, Male ward, Mandatory Ward and Delivery section, ICU and Operation Theater. In the design, special care was given to differently able people. They were provided with special Wash rooms with special facilities. These washrooms are present in each floor. Cold water supply system and Hot water supply system are the most critical services in this building. Both above ground and below ground waste water disposal systems were provided. Since this is situated in Hatton, both Air conditioning and heating required for the building. They were provided to the appropriate spaces. Electrical and telephone system is another service present in this building. This building is consists of a wet riser and sprinkler firefighting system. Smoke detectors were used as fire detectors. Refuse chute is also included to the building. Bio-gas system had introduced as an alternative power generation method. Since this area have plenty of water, no need of rain water harvesting. A Roof garden is maintained on the second floor top level. Few service ducts were provided to the building. Service lines were laid along the ceiling. Integrated system was adapted to this building. There are few more services were included in this hospital. Passive concept was taken in to the account in the design and it was design as a green building. Lot of sustainable methods had adapted to this hospital design.
Circulation
Vertical circulation Stair case Two stair cases were provided to this building. Both are identical. This is the main access for the upper floors. Visitors supposed to use stair case. Dimensions and details of the stair case are given below. Floor to floor height = 4500 mm Total width of core Length of the core = 3500 mm = 5000 mm
Length of the landing = 1500 mm Width of stair case Rise Tread = 1750 mm = 175 mm = 290 mm
Lift One lift has provided for this building. It is not for visitors. It is mainly use for the patients and for differently able people. Size of the lift will be 3500 mm 2700 mm. This size was selected because it should be adequate to carry a trolley with a patient. And also Wheel chairs should be able to carry from this lift. Staff can carry their stuff from the lift. Since there is a lift, there is no ramp provided for differently able people. There is a ramp in ground floor to give access to ground floor for differently able people.
3500 mm
2700 mm
Horizontal circulation Corridors and passages were kept in 2.5 m width because they should be adequate to exchange two trolleys or two wheel chairs. In ground floor, a ramp has provided for the differently able people who can use that to enter the ground floor.
Sanitary appliances
Ground floor is consists of several bathrooms for the staff and for the general public. All the wards were provided with Washrooms and adequate number of appliances was provided for them. Each floor is consists with special washroom for differently able people. They were provided with special appliances and special facilities.
Fig.5 Special arrangements for differently able people Following is the calculation to find the required number of sanitary appliances for the hospital staff. Number of beds % of staff required Number of staff required = 105 = 38% = 105 38% = 40 Assumption; Staff is consists of 15 males and 25 females. Therefore; Required number of WCs for females Required number of WCs for males Required number of Wash basins for females Required number of Wash basins for males Required number of Urinals for males =3 =1 =3 =1 =1
In the design, building was provided; One gents washroom at Administration area with 1 WC, 1 Wash basin and 1 Urinal One Ladies washroom at Administration area with 1 WC and 1 Wash basin A washroom for Doctors restroom with two WCs and a Wash basin A washroom for Nurses restroom with two WCs and a wash basin Altogether; 6 WCs, 4 Wash basins and 1 urinal Here, one sink per washrooms was provided for cleaning purpose.
Washrooms were provided for each ward, ICU and Mandatory unit with sufficient sanitary appliances. Hand railings were fixed near the appliances at the washrooms for differently able people. Hygienic effects were taken in to account when arranging the appliances and intervening ventilated space was provided in washrooms. Urinals were not provided to common washrooms in restrooms due to hygienic effect.
Water height = 4.8 m There for total capacity of the tank is 120 m3
First floor
Amount Loading total Unit loading units
Second floor
Amount Loading total Unit loading units
Wash basins Sink Bathing cubical (Shower) Bib tap WC Bidet shower Water bath Total
22 5 1
3 5 3
66 25 3
20 2 10
3 5 3
60 10 30
13 4 7
3 5 3
39 20 21
9 13 13 1
5 2 1 10
45 26 13 10
188
10 10 10 1
5 2 1 10
50 20 10 10
190
5 7 7 2
5 2 1 10
25 14 7 20
146
Table.1 Loading units of each floor Calculation to find the flow rate of the urinal as follows; Capacity of the urinal Interval between usage Flow rate = 4.5 l = 20 min = 4.5 60/20 60 60 = 0.0375 l/s
Second floor = 2
Assumptions; Bathing cubical are consist of a shower and a bib tap WC and bidet shower was considered separately PVC pipes were used for cold water supply Water tank is right above the male wards washroom Pipe lines coming from the tank is running through the duct at male wards washroom Pipe has a horizontal length of 0.5 m at the bottom level of the water tank Floor to floor height of the building is 4.5 m Spring water is collected to an underground sump and it is pumped to the overhead tank Showers are at the height of 2 m above from the slab top level and all other appliances are at 1 m height above the slab top level of each floor Water tank is 4.5 m above the top level of the second floor
Except the wash basins in washrooms, few more wash basins and sinks were provided for the places where they are necessary. One wash basin which is at the waiting area of ground floor is for the outside visitors and OPD patient.
Pipe sizing Required pipe sizing for each branch can be calculated and adequate diameter was selected by checking the available head of the appliances at the discharge point. Following is a specimen calculation which was done for the pipe 1 . Assumption :- Inner diameter of 50 mm PVC pipes were used. For ground floor; Total loading units = 188
Flow rate due to loading units= 2.0 l/s Flow rate from 5 urinals = 0.0375 l/s 5 = 0.1875 l/s Total design flow rate = 2.0 + 0.1875 = 2.1875 l/s For first floor; Total loading units Design flow rate For second floor; Total loading units = 146 = 190 = 2.0 l/s
Flow rate due to loading units= 1.7 l/s Flow rate from 2 urinals = 0.0375 l/s 2 = 0.075 l/s Number of; Stop valves Elbows Ts =1 =1 =1
Pipe length
= 404
Flow rate due to loading units= 3.5 l/s From urinals = 0.1875 + 0.075 = 0.2625 l/s Total design flow rate = 3.5 + 0.2625 = 3.7625 l/s Loss of head Head loss due to the pipe = 0.065 m/m run = 0.065 9.5 = 0.6175 m Head loss of stop valve Head loss due to elbows = 1.6 m = 2.3 0.065 = 0.1495 m Head loss due to Ts = 3.5 0.065 = 0.2275 m Total head loss of the pipe 1 = 0.6175 + 0.1495 + 0.2275 = 2.5945 m
Fig.7 Water tank and pumps arrangement Alternative pump has provided to make sure the continuous water supply even in a break down of the main pump. Water which is at under ground sump is pumped to the elevated tank. Key = Stop valve = Pump = Ball valve WC BS = Water closet = Bidet shower BC = Bathing cubical B = Water Bath
WB = Wash basin
Pipe number 1 2 2-1 2-2 2-3 2-4 2-5 3 3-1 4 5 5-1 5-2 5-3 6 6-1 6-2 7 8 8-1 8-2 8-3 9 9-1 9-2 9-3
Table.3 Pipe size estimation for cold water system All the other pipes which are connecting appliances are of 28 mm outer diameter.
In this hospital, only the necessary appliances are provided with hot water. Mainly the selected wash basins, selected sinks, bathing cubicles and water baths were connected to hot water supply system. (i.e. wash basins in ward washrooms, washrooms in other important units, sinks in operation theater and ICU.etc.) Ground floors public washrooms were not connected to the hot water system because they may not use in night time when the environment is cold. It is not necessary and also uneconomical. (This hospital is situated in Hatton where the night temperature is low) Hot water will generate using boilers. These boilers will be function with bio-gas. Detail of the bio-gas supply unit will be discussed later. Electrical backup system for the boilers were connected to keep continuation of hot water supply is low or dropped down. Per person hot water demand Hot water cylinder capacity = 35 l/day = 35 105 = 3675 l/day = 3.675 m3 /day We cannot store the amount of total hot water demand in a cylinder because it will cause a massive energy loss while storage and the water will not in adequate temperature all over the day. So we are planning to do the boiling throughout the day. So we do not need cylinder of 16.8 m3. So, about 4 m3 cylinder will be adequate.
Vent pipe
Cylinder
In this case, solar water heaters were come in to the seen as an alternative. But doing it in large scale is expensive. Hatton area is not much experience lot of solar heat. So it is not economically feasible. Bio-gas can reduce the cost because we can get it free. And it also gives solution for the solid waste disposal.
Required flow rate (Hot water) for several appliances Wash basin Water bath Shower Sink = 0.08 l/s = 0.15 l/s = 0.20 l/s = 0.15 l/s
Cold water supply for the heating was taken from the main water tank. Insulated copper pipes were used for the system. Total amount of loading units at; Ground floor First floor Second floor Total loading units = 32.5 = 91 = 68 = 191.5
Assumption:- For hot water system, loading units were assumed as follows; Wash basin Water bath Sink Shower Bib tap = 1.5 = 10 =3 =3 =3
Outer diameter 42 28 28 35 35 35 35 42 22
Outer diameter of 22 mm pipes were used for the other part of the pipe network. They were used to connect appliances to the main pipe lines.
= WC = 14 =S = 14
= WB = 2 =B = 18
= SH = 2 = BT = 2
Assumption :- Bathing cubical (BC) is consists of a shower and a bib tap. Therefore discharge unit of a bathing cubical is 4.
D1-1
D1-10
D1-11
Fig.11 Gray water disposal pipe line system through duct 1 (D1)
Pipe number
42 = 8 414= 42 = 56 8
181= 18
32 = 6 12 = 2
32 = 6 12 = 2
20 86 20+86 = 106
214= 210= 28 20 22 = 4
82 = 16 -
82 = 16 -
80 4
76 50
84+106 = 89 190
52 = 10 52 = 10 514= 22 = 70 4
52 = 10
50 50 76 89 100
D2-1
D2-3
D2-4
D2-6
D2-8
D2-9
From D3
D2-10
Fig.12 Gray water disposal pipe line system through duct 2 (D2)
Pipe number
23 = 6 21 = 2
22 = 4 22 = 4
6 10 6+10 = 16
23= 6 22 = 4
22 = 4
22 = 4
6 12 18+16 = 34
50 63 76
22 = 4
50 76 50
32 = 6 32 = 6
89
D3-1
D3-3
D3-6
D3-7
D3-8 D3-9
Fig.13 Gray water disposal pipe line system through duct 3 (D3)
Pipe number
22 = 4
118= 18 -
21 = 2
21 = 2
18 8 18+8 = 26
21 = 2
118= 18 -
21 = 2
21 = 2
18 6 24+26= 50
63 50 76
118= 18
18 18+50= 68 8+68 = 76
50 76 76
22 = 4
21 = 2
21 = 2
Higher provision for discharge pipes were given so that to avoid blocks and to increase the efficiency of flow.
Size of the discharge pipe of each appliance (inner diameter) Wash basin Sink Water bath Bathing cubical = 38 mm = 50 mm = 63 mm = 63 mm
Total discharge units of main discharge pipe = 294+126+76 = 496 Therefore proposed pipe size = 125 mm
Assumption:- 85% of consumption will be discharge as gray water. Consume will be take place in 18 hrs duration per day. Discharge = 99.43585% /186060 = 1.30410-3m3/s = 1.304 l/s From Chezzys equation; V = Cmi Considering half-filled conditions and assuming the self-cleansing velocity is 1.1 m/s
Assume the peak flow is 6 time higher than average flow: Peak flow = 1.304 6 = 7.824 l/s Considering; Q 7.82410-3 d = AV = (d/2)20.9 = 0.1488 m
Therefore d = 125 mm pipe is not adequate. So we can use d = 150 mm pipe as the main horizontal discharge pipe.
Considering; V = Cmi , C = 55 1.1 i = 550.0375i = 4/374 = 0.01067 Can use the slope of the pipe as 1: 90
Gray water treatment and disposal This gray water was directed to a treatment plant and after treating they will be discharge to a soakage pit.
D1-1B
D1-2B
D1-9B
Pipe Second floor D1-1B D1-2B D1-3B First floor D1-4B D1-5B D1-6B Ground floor D1-7B D1-8B D1-9B
Urinal 22 = 4 -
314 = 42 414 = 56
42 56 42+56+60=158
89 89 100
914 = 126
24 = 8 -
50 100 150
D2-1B
D2-2B
D2-4B
D2-5B
D2-6B D2-7B
Pipe Second floor D2-1B D2-2B First floor D2-3B D2-4B Ground floor D2-5B D2-6B From D3 D2-7B
Urinal -
214 = 28
28 28+28 = 56
89 89
28 28 42 56+56+42=164
89 89 125
D3-1B
D3-2B
D4-1B
D3-5B D3-6B
Pipe Second floor D3-1B D3-2B First floor D3-3B D3-4B Ground floor D3-5B D3-6B
Urinal -
114 = 14
14 14+14 = 28
89 89
14 14 =28 = 42
89 100
Higher provisions were allowed for diameter of the pipes to make sure that solids will not block the pipes and to obtain the half fill condition. It also increases the efficiency of the flow.
= 292+42+112 = 446
Therefore, 150 mm diameter pipe was provided as the main black water disposal pipe. This is laid on the ground. Assumptions : Total amount of the black water discharge per day is equal to 15% of the usage Pipes are in half filled condition Self-cleansing velocity of the black water is 0.9 m/s Water demand will be occur during 18 hr period per day Peak demand is six times the average demand
Peak discharge
= 2.30210-4 6 = 1.381210-3m3/s
Therefore d=150 mm pipe is adequate. Considering, m = A/; m = d/4 =0.15/4 m From Chezzys equation, 0.9 i = 0.0375 m V = Cmi , C=55 = 550.0375i = 7.93410-4
Provided slope for the pipe is 1:125 This pipe was directed to bio-gas unit.
Below ground gray water disposal system All the Gray water was directed to a gray water treatment plant. After treating, they will be discharge to the ground. This system will be acting as the below ground gray water disposal system.
Further details of the bio-gas unit and water treatment plant will be discussed later.
Fire detecting system We have provided heat detectors as the fire detectors. Since this area has less temperature, smoke detectors will be more effective over heat detectors. They were connected to fire alarms.
Fig.18 Smoke detectors Fire alarms were installed in wards and other necessary areas. If smoke enters the unit, particles attach to the ions slowing their movement. This reduction in current flow actuates an electronic relay circuit to operate an alarm.
A wet riser was provided to the building. Plumbing for wet riser was laid through service ducts. Hoses were provided in each floor. Except the wet riser, portable fire fighters (Foam) were installed at necessary places. Especially we provided them for small fire and for the places where using water is not much appropriate.
Security Camera system Security cameras were mounted in the entrance, wards and other necessary positions in the hospital for security purpose. Control unit was situated in administration area. Cables for this system were laid through service ducts.
Lighting system
Illumination level and required lamps Lighting is another critical service of a hospital. Adequate light with appropriate Illumination level should be provided. Followings are the required Illumination levels according to EN 12464-1 (2002)
Area
Corridor 200 washrooms 200 Store room 100 Office 500 Staff room 300 Wards 300 Delivery room General lighting 300 Examination area 1000 Emergency treatment unit 500 Operation theater Theater 1000 Recovery area 500 ICU general 300 Examination and treatment area 1000 Dental unit General 500 At the patient 1000 Pharmacy 500 Table.10 Illumination level of different areas
Assumption:- use 80 W Fluorescent lamp which has 7375 luminous. Number of lamps Where; E A F U M = Illumination level = Area = luminous per lamp = Utilization factor = Maintenance factor = EA/ FUM
Here, U = 0.5 and M = 0.8 Specimen calculation to find the required number of lamps for front lobby, stair case and lobby in the ground floor as follow; Area = 737.5 = 248.5 m2 Illumination level Required number of lamps = 200 lx = EA/FUM = 200248.5/73750.50.8 = 16.85 17 lamps were required.
Assumption:Average illumination level at, Delivery room = (1000 + 300)/2 = 650 lx ICU = (1000 + 300)/2 = 650 lx Dental unit = (1000 + 500) = 750 lx
Area (m2)
Number of lamps 17 4 12 6 7 2 3 10 4 2 1 7 4 8 9 96
Ground floor Front lobby, Stair case and lift 200 Corridors 200 Administration area 500 Rest rooms 300 Washrooms and cleaning room 200 Services room and store room 100 Consultant room 300 Emergency treatment unit 500 OPD 500 Medical record room 300 Pharmacy 500 Back lobby and stair case 200 X-ray room 300 Dental unit 750 Around the hospital 100 Total number of lamps required for ground floor First floor Corridors, lobbies, lift and staircase 200 Children ward 300 Female ward 300 Washrooms 200 Mandatory ward 300 Delivery section 650 Total number of lamps required for First floor
15 12 22 6 8 14 77
Second floor Corridors, lobbies, lift and staircase 200 135.25 Male ward 300 115 General ward 300 131.5 Operation theater 1000 40 Recovery area and lobby 500 25 Washrooms 200 70 ICU 650 112 Store room 100 48 Total number of lamps required for First floor Table.12 Estimation of number of lamps per several areas
10 12 14 14 5 5 25 2 87
= 96 + 77 + 87 = 260
= 260 80 W = 20.8 kW
In hospitals, special kind of lamps and lightings are using in Operation theaters, ICU and Dental units. High intensity lighting systems are useful for examine patients in operation theaters and dental units.
(i)
(ii)
Alternative lighting method- LED lighting system LED lamps are proposed to use in this hospital as alternative energy conservation method.
Advantages of LED lighting system long service life low maintenance costs low power consumption minimum operating costs vibration and impact-proof compact size high colour stability efficient control thanks to simple control system low heat generation
Energy Consumption
Equipment Energy (kW) MI (Cyclotron) 100 Cathlab 105 MRI 75 CT 64 PET & PET CT 72 Surgery mobile C arm 8 CSSD (Central Sterilization supply dept.) 96 OT equipment 1.6 ICCU equipment 1.6 X-ray (Radiography, Fluoroscopy) 52 Mammography 12 Ultra sound 4 Healthcare IT work station 1.6 Table.13 Energy consumption for equipment
Assuming the energy requirement for lighting is 15% of the total energy consumption; Energy requirement for lighting Energy requirement for Cooking = 20.8 kW = 20.85.6/15 = 7.77 kW Energy requirement for refrigeration = 20.82.2/15 = 3.05 kW Energy requirement for office equipment = 20.86/15 = 8.32 kW Energy requirement for miscellaneous = 20.813.4/15 = 18.58 kW Energy requirement for ventilation = 20.82.6/15 = 3.61 kW