You are on page 1of 21

11 - 1

11 - 2

What is capital budgeting?

Steps 1. Estimate CFs (inflows & outflows).

Analysis of potential additions to fixed assets. Long-term decisions; involve large expenditures. Very important to firms future.

2. Assess riskiness of CFs. 3. Determine k = WACC for project. 4. Find NPV and/or IRR. 5. Accept if NPV > 0 and/or IRR > WACC.
Copyright 1999 by The Dryden Press All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 3

11 - 4

Project Types Mutually Exclusive Projects vs Independent Projects Normal CF Projects vs Nonnormal CF Projects
Copyright 1999 by The Dryden Press All rights reserved.

Normal Cash Flow Project: Cost (negative CF) followed by a series of positive cash inflows. One change of signs. Nonnormal Cash Flow Project: Two or more changes of signs. Most common: Cost (negative CF), then string of positive CFs, then cost to close project. Nuclear power plant, strip mine.
Copyright 1999 by The Dryden Press All rights reserved.

11 - 5

11 - 6

What is the payback period?

Strengths of Payback: 1. Provides an indication of a projects risk and liquidity. 2. Easy to calculate and understand. Weaknesses of Payback:

The number of years required to recover a projects cost, or how long does it take to get the businesss money back?

1. Ignores the TVM. 2. Ignores CFs occurring after the payback period.
Copyright 1999 by The Dryden Press All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 7

11 - 8

NPV: Sum of the PVs of inflows and outflows.


NPV
n t 0

Rationale for the NPV Method

1 k t

CFt

NPV = PV inflows - Cost = Net gain in wealth.


Accept project if NPV > 0. Choose between mutually exclusive projects on basis of higher NPV. Adds most value.
All rights reserved. Copyright 1999 by The Dryden Press All rights reserved.

Cost often is CF0 and is negative.


NPV
t 1 n

1 k

CFt

CF0 .

Copyright 1999 by The Dryden Press

11 - 9

11 - 10

Using NPV method, which project(s) should be accepted?


0

Internal Rate of Return: IRR


1 CF1 2 CF2 Inflows 3 CF3

If Projects S and L are mutually exclusive, accept S because NPVs > NPVL . If S & L are independent, accept both; NPV > 0.
Copyright 1999 by The Dryden Press All rights reserved.

CF0 Cost

IRR is the discount rate that forces PV inflows = cost. This is the same as forcing NPV = 0.
Copyright 1999 by The Dryden Press All rights reserved.

11 - 11

11 - 12

NPV: Enter k, solve for NPV.

Rationale for the IRR Method

t 0

1 k t

CFt

NPV .

IRR: Enter NPV = 0, solve for IRR.


CFt t 0. t 0 1 IRR
Copyright 1999 by The Dryden Press All rights reserved.

If IRR > WACC, then the projects rate of return is greater than its cost-- some return is left over to boost stockholders returns.
Example: WACC = 10%, IRR = 15%. Profitable.
Copyright 1999 by The Dryden Press All rights reserved.

11 - 13

11 - 14

IRR Acceptance Criteria

Decisions on Projects S and L per IRR

If IRR > k, accept project.

If S and L are independent, accept both. IRRs > k = 10%. If S and L are mutually exclusive, accept S because IRRS > IRRL .

If IRR < k, reject project.

Copyright 1999 by The Dryden Press

All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 15

11 - 16

Construct NPV Profiles Enter CFs in CFLO and find NPVL and NPVS at different discount rates:
k 0 5 10 15 20
Copyright 1999 by The Dryden Press

NPV ($)
60 50 40 30 20 10 0 0 -1 0 5 10 15 20 2 3 .6

Crossover Point = 8.7%

NPVL 50 33 19 7 (4)

NPVS 40 29 20 12 5
All rights reserved.

k 0 5 10 15 20

NPVL 50 33 19 7 (4)

NPVS 40 29 20 12 5

IRRS = 23.6%

Discount Rate (%)


IRRL = 18.1%

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 17

11 - 18

NPV and IRR always lead to the same accept/reject decision for independent projects:
NPV ($) IRR > k and NPV > 0 Accept. k > IRR and NPV < 0. Reject.

Mutually Exclusive Projects


NPV
L

k < 8.7: NPVL> NPVS , IRRS > IRRL CONFLICT k > 8.7: NPVS> NPVL , IRRS > IRRL NO CONFLICT

S k (%) IRR
Copyright 1999 by The Dryden Press All rights reserved.

IRRS

8.7

%
IRRL
All rights reserved.

Copyright 1999 by The Dryden Press

11 - 19

11 - 20

Two Reasons NPV Profiles Cross 1. Size (scale) differences. Smaller project frees up funds at t = 0 for investment. The higher the opportunity cost, the more valuable these funds, so high k favors small projects. 2. Timing differences. Project with faster payback provides more CF in early years for reinvestment. If k is high, early CF especially good, NPVS > NPVL.
Copyright 1999 by The Dryden Press All rights reserved.

Reinvestment Rate Assumptions

NPV assumes reinvest at k (opportunity cost of capital).

IRR assumes reinvest at IRR.


Reinvest at opportunity cost, k, is more realistic, so NPV method is best. NPV should be used to choose between mutually exclusive projects.
Copyright 1999 by The Dryden Press All rights reserved.

11 - 21

11 - 22

Managers like rates--prefer IRR to NPV comparisons. Can we give them a better IRR? Yes, MIRR is the discount rate which causes the PV of a projects terminal value (TV) to equal the PV of costs. TV is found by compounding inflows at WACC. Thus, MIRR assumes cash inflows are reinvested at WACC.
Copyright 1999 by The Dryden Press All rights reserved.

MIRR for Project L (k = 10%)


0
10%

1
10.0
10%

2
60.0
10%

3
80.0 66.0 12.1 158.1 TV inflows

-100.0

-100.0 PV outflows

$158.1 $100 = (1+MIRRL)3 MIRRL = 16.5%

MIRR = 16.5%

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 23

11 - 24

Why use MIRR versus IRR?

When there are nonnormal CFs and more than one IRR, use MIRR:
0 -800,000 1 5,000,000 2 -5,000,000

MIRR correctly assumes reinvestment at opportunity cost = WACC. MIRR also avoids the problem of multiple IRRs. Managers like rate of return comparisons, and MIRR is better for this than IRR.
Copyright 1999 by The Dryden Press All rights reserved.

PV outflows @ 10% = -4,932,231.40. TV inflows @ 10% = 5,500,000.00. MIRR = 5.6%


Copyright 1999 by The Dryden Press All rights reserved.

11 - 25

11 - 26

Accept Project P?

Incremental Cash Flow

NO. Reject because MIRR = 5.6% < k = 10%. Also, if MIRR < k, NPV will be negative: NPV = -$386,777.

= Corporate cash flow with project minus Corporate cash flow without project
Copyright 1999 by The Dryden Press All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 27

11 - 28

Should CFs include interest expense? Dividends?

Suppose $100,000 had been spent last year to improve the production line site. Should this cost be included in the analysis?

NO. The costs of capital are already incorporated in the analysis since we use them in discounting. If we included them as cash flows, we would be double counting capital costs.
Copyright 1999 by The Dryden Press All rights reserved.

NO. This is a sunk cost. Focus on incremental investment and operating cash flows.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 29

11 - 30

Suppose the plant space could be leased out for $25,000 a year. Would this affect the analysis? Yes. Accepting the project means we will not receive the $25,000. This is an opportunity cost and it should be charged to the project. A.T. opportunity cost = $25,000 (1 - T) = $15,000 annual cost.
Copyright 1999 by The Dryden Press All rights reserved.

If the new product line would decrease sales of the firms other products by $50,000 per year, would this affect the analysis? Yes. The effects on the other projects CFs are externalities. Net CF loss per year on other lines would be a cost to this project. Externalities will be positive if new projects are complements to existing assets, negative if substitutes.
All rights reserved.

Copyright 1999 by The Dryden Press

11 - 31

11 - 32

What if you terminate a project before the asset is fully depreciated?

Example: If Sold After 3 Years (000s)

Cash flow from sale = Sale proceeds - taxes paid. Taxes are based on difference between sales price and tax basis, where: Basis = Original basis - Accum. deprec.
Copyright 1999 by The Dryden Press All rights reserved.

Original basis = $240. After 3 years = $17 remaining. Sales price Tax on sale Cash flow
Copyright 1999 by The Dryden Press

= $25. = 0.4($25-$17) = $3.2. = $25-$3.2=$21.7.


All rights reserved.

11 - 33

11 - 34

If this were a replacement rather than a new project, would the analysis change? Yes. The old equipment would be sold and the incremental CFs would be the changes from the old to the new situation.

Revenues. Costs. The relevant depreciation would be the change with the new equipment. Also, if the firm sold the old machine now, it would not receive the salvage value at the end of the machines life.
Copyright 1999 by The Dryden Press All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 35

11 - 36

What is cash flow estimation bias? CFs are estimated for many future periods. If company has many projects and errors are random and unbiased, errors will cancel out (aggregate NPV estimate will be OK). Studies show that forecasts often are biased (overly optimistic revenues, underestimated costs).
Copyright 1999 by The Dryden Press All rights reserved.

What is option value?

Investment in a project may lead to other valuable opportunities. Investment now may extinguish opportunity to undertake same project in the future. True project NPV = NPV + value of options.
Copyright 1999 by The Dryden Press All rights reserved.

11 - 37

11 - 38

If 5% inflation is expected over the next 5 years, are the firms cash flow estimates accurate?

Real vs. Nominal Cash flows In DCF analysis, k includes an estimate of inflation. If cash flow estimates are not adjusted for inflation (i.e., are in todays dollars), this will bias the NPV downward. This bias may offset the optimistic bias of management.
Copyright 1999 by The Dryden Press All rights reserved.

No. Net revenues are assumed to be constant over the 4-year project life, so inflation effects have not been incorporated into the cash flows.
Copyright 1999 by The Dryden Press All rights reserved.

11 - 39

11 - 40

S and L are mutually exclusive and will be repeated. k = 10%. Which is better? (000s) 0 1 2 3 4

CF0 CF1 Nj I NPV

S -100,000 60,000 2 10 4,132

L -100,000 33,500 4 10 6,190

Project S: (100) 60 Project L: (100) 33.5


Copyright 1999 by The Dryden Press

60 33.5 33.5 33.5 NPVL > NPVS. But is L better? Cant say yet. Need to perform common life analysis.
Copyright 1999 by The Dryden Press All rights reserved.

All rights reserved.

11 - 41

11 - 42

Replacement Chain Approach (000s)


Note that Project S could be repeated after 2 years to generate additional profits. Can use either replacement chain or equivalent annual annuity analysis to make decision. Project S with Replication: 0 1 2 3 4

Project S: (100) 60 (100) 60

60 (100) (40)

60 60

60 60

NPV = $7,547.
Copyright 1999 by The Dryden Press All rights reserved. Copyright 1999 by The Dryden Press All rights reserved.

11 - 43

11 - 44

Or, use NPVs: 0 4,132 3,415 7,547 1 10% 2 4,132 3 4

Equivalent Annual Annuity (EAA) Approach

Finds the constant annuity payment whose PV is equal to the projects raw NPV over its original life.

Compare to Project L NPV = $6,190.


Copyright 1999 by The Dryden Press All rights reserved. Copyright 1999 by The Dryden Press All rights reserved.

11 - 45

11 - 46

EAA Calculator Solution


Project S PV = Raw NPV = $4,132. n = Original project life = 2. k = 10%. Solve for PMT = EAAS = $2,381. Project L PV = $6,190; n = 4; k = 10%.
Copyright 1999 by The Dryden Press

The project, in effect, provides an annuity of EAA. EAAS > EAAL so pick S. Replacement chains and EAA always lead to the same decision if cash flows are expected to stay the same.

Solve for PMT = EAAL = $1,953.

All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 47

11 - 48

If the cost to repeat S in two years rises to $105,000, which is best? (000s)
0 1 2 3 4

Types of Abandonment

Project S: (100) 60

60 (105) (45)

Sale to another party who can obtain greater cash flows, e.g., IBM sold typewriter division. Abandon because losing money, e.g., smokeless cigarette.
Copyright 1999 by The Dryden Press All rights reserved.

60

60

NPVS = $3,415 < NPVL = $6,190. Now choose L.


Copyright 1999 by The Dryden Press All rights reserved.

11 - 49

11 - 50

Consider another project with a 3-year life. If abandoned prior to Year 3, the machinery will have positive abandonment value. Year 0 1 2 3 CF ($5,000) 2,100 2,000 1,750 Abandonment Value $5,000 3,100 2,000 0
All rights reserved.

CFs Under Each Alternative (000s)

0 1. No abandonment (5) 2. Abandon 2 years 3. Abandon 1 year (5) (5)

1 2.1 2.1 5.2

2 2 4

3 1.75

Copyright 1999 by The Dryden Press

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 51

11 - 52

Assuming a 10% cost of capital, what is the projects optimal life?

Conclusions The project is acceptable only if operated for 2 years. A projects engineering life does not always equal its economic life. The ability to abandon a project may make an otherwise unattractive project acceptable. Abandonment possibilities will be very important when we get to risk.

NPV(no) = -$123. NPV(2) = $215. NPV(1) = -$273.

Copyright 1999 by The Dryden Press

All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 53

11 - 54

What does risk mean in capital budgeting?

Is risk analysis based on historical data or subjective judgment?

Uncertainty about a projects future profitability.


Measured by sNPV, sIRR, beta. Will taking on the project increase the firms and stockholders risk?
Copyright 1999 by The Dryden Press All rights reserved.

Can sometimes use historical data, but generally cannot.


So risk analysis in capital budgeting is usually based on subjective judgments.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 55

11 - 56

What three types of risk are relevant in capital budgeting?

How is each type of risk measured, and how do they relate to one another? 1. Stand-Alone Risk: The projects risk if it were the firms only asset and there were no shareholders. Ignores both firm and shareholder diversification. Measured by the s or CV of NPV, IRR, or MIRR.

Stand-alone risk Corporate risk

Market (or beta) risk

Copyright 1999 by The Dryden Press

All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 57

11 - 58

Probability Density
Flatter distribution, larger s, larger stand-alone risk.

2. Corporate Risk:
Reflects the projects effect on corporate earnings stability. Considers firms other assets (diversification within firm). Depends on:
projects s, and

E(NPV)

NPV

its correlation with returns on firms other assets.

Such graphics are increasingly used by corporations.


Copyright 1999 by The Dryden Press All rights reserved.

Measured by the projects corporate beta.


Copyright 1999 by The Dryden Press All rights reserved.

11 - 59

11 - 60

Profitability Project X Total Firm Rest of Firm

3. Market Risk:
Reflects the projects effect on a welldiversified stock portfolio. Takes account of stockholders other assets. Depends on projects s and correlation with the stock market. Measured by the projects market beta.

Years

1. Project X is negatively correlated to firms other assets. 2. If r < 1.0, some diversification benefits. 3. If r = 1.0, no diversification effects.
Copyright 1999 by The Dryden Press All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

10

11 - 61

11 - 62

How is each type of risk used? Market risk is theoretically best in most situations. However, creditors, customers, suppliers, and employees are more affected by corporate risk. Therefore, corporate risk is also relevant.
Copyright 1999 by The Dryden Press All rights reserved.

Stand-alone risk is easiest to measure, more intuitive. Core projects are highly correlated with other assets, so stand-alone risk generally reflects corporate risk. If the project is highly correlated with the economy, stand-alone risk also reflects market risk.
Copyright 1999 by The Dryden Press All rights reserved.

11 - 63

11 - 64

What is sensitivity analysis? Shows how changes in a variable such as unit sales affect NPV or IRR. Each variable is fixed except one. Change this one variable to see the effect on NPV or IRR. Answers what if questions, e.g. What if sales decline by 30%?
Copyright 1999 by The Dryden Press All rights reserved.

Illustration
Change from Base Level Resulting NPV (000s) Unit Sales Salvage k

-30% -20 -10 0 +10 +20 +30

$ 10 35 58 82 105 129 153

$78 80 81 82 83 84 85

$105 97 89 82 74 67 61
All rights reserved.

Copyright 1999 by The Dryden Press

11 - 65
NPV (000s) Unit Sales

11 - 66

Results of Sensitivity Analysis

82 k

Salvage

Steeper sensitivity lines show greater risk. Small changes result in large declines in NPV.
Unit sales line is steeper than salvage value or k, so for this project, should worry most about accuracy of sales forecast.
Copyright 1999 by The Dryden Press All rights reserved.

-30

-20

-10 Base 10 Value

20

30
All rights reserved.

Copyright 1999 by The Dryden Press

11

11 - 67

11 - 68

What are the weaknesses of sensitivity analysis? Does not reflect diversification. Says nothing about the likelihood of change in a variable, i.e. a steep sales line is not a problem if sales wont fall. Ignores relationships among variables.
Copyright 1999 by The Dryden Press All rights reserved.

Why is sensitivity analysis useful?

Gives some idea of stand-alone risk. Identifies dangerous variables. Gives some breakeven information.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 69

11 - 70

What is scenario analysis?

Assume we know with certainty all variables except unit sales, which could range from 900 to 1,600. Scenario Worst Base Best Probability 0.25 0.50 0.25 NPV(000) $ 15 82 148

Examines several possible situations, usually worst case, most likely case, and best case. Provides a range of possible outcomes.

E(NPV) = $ 82 47 CV(NPV) = s(NPV)/E(NPV) = 0.57

s(NPV) =

Copyright 1999 by The Dryden Press

All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 71

11 - 72

If the firms average project has a CV of 0.2 to 0.4, is this a high-risk project? What type of risk is being measured?

Would a project in a firms core business likely be highly correlated with the firms other assets? Yes. Economy and customer demand would affect all core products. But each product would be more or less successful, so correlation < +1.0. Core projects probably have correlations within a range of +0.5 to +0.9.
Copyright 1999 by The Dryden Press All rights reserved.

Since CV = 0.57 > 0.4, this project has high risk. CV measures a projects standalone risk. It does not reflect firm or stockholder diversification.
Copyright 1999 by The Dryden Press All rights reserved.

12

11 - 73

11 - 74

How do correlation and s affect a projects contribution to corporate risk? If sP is relatively high, then projects corporate risk will be high unless diversification benefits are significant. If project cash flows are highly correlated with the firms aggregate cash flows, then the projects corporate risk will be high if sP is high.
Copyright 1999 by The Dryden Press All rights reserved.

Would correlation with the economy affect market risk?

Yes.

High correlation increases market risk (beta). Low correlation lowers it.
Copyright 1999 by The Dryden Press All rights reserved.

11 - 75

11 - 76

Should subjective risk factors be considered?

Are there any problems with scenario analysis?


Only considers a few possible outcomes. Assumes that inputs are perfectly correlated--all bad values occur together and all good values occur together. Focuses on stand-alone risk, although subjective adjustments can be made.
Copyright 1999 by The Dryden Press All rights reserved.

Yes. A numerical analysis may not capture all of the risk factors inherent in the project. For example, if the project has the potential for bringing on harmful lawsuits, then it might be riskier than a standard analysis would indicate.
Copyright 1999 by The Dryden Press All rights reserved.

11 - 77

11 - 78

What is a simulation analysis? NPV and IRR are calculated. A computerized version of scenario analysis which uses continuous probability distributions. Computer selects values for each variable based on given probability distributions.
(More...)
Copyright 1999 by The Dryden Press All rights reserved. Copyright 1999 by The Dryden Press All rights reserved.

Process is repeated many times (1,000 or more). End result: Probability distribution of NPV and IRR based on sample of simulated values. Generally shown graphically.

13

11 - 79

11 - 80

Probability Density

What are the advantages of simulation analysis?

xxxx x xxxxxx xx xxxxxx x xxx xxxxxx xx xxxxxxxxxxx xxxx xxxxxxxxxxxxxxxxxxxxxxxxx

Reflects the probability distributions of each input.


Shows range of NPVs, the expected NPV, sNPV, and CVNPV. Gives an intuitive graph of the risk situation.
Copyright 1999 by The Dryden Press All rights reserved.

E(NPV)

NPV

Also gives sNPV, CVNPV, probability of NPV > 0.


Copyright 1999 by The Dryden Press All rights reserved.

11 - 81

11 - 82

What are the disadvantages of simulation? Difficult to specify probability distributions and correlations. If inputs are bad, output will be bad: Garbage in, garbage out. May look more accurate than it really is.
(More...)
Copyright 1999 by The Dryden Press All rights reserved.

Sensitivity, scenario, and simulation analyses do not provide a decision rule. They do not indicate whether a projects expected return is sufficient to compensate for its risk. Sensitivity, scenario, and simulation analyses all ignore diversification. Thus they measure only stand-alone risk, which may not be the most relevant risk in capital budgeting.
Copyright 1999 by The Dryden Press All rights reserved.

11 - 83

11 - 84

How does the projects market risk compare with the firms overall market risk?

Is the projects relative market risk consistent with its stand-alone risk?

Project k = 12.2% versus companys k = 10%. Indicates that projects market risk is greater than firms average project.
Copyright 1999 by The Dryden Press All rights reserved.

Yes. Project CV = 0.57 versus 0.3 for an average project, which is consistent with projects higher market risk.

Copyright 1999 by The Dryden Press

All rights reserved.

14

11 - 85

11 - 86

Methods for estimating a projects beta Accounting beta. Run regression between projects ROA and S&P index ROA. Accounting betas are correlated (0.5-0.6) with market betas. But normally cant get data on new projects ROAs before the capital budgeting decision has been made.
Copyright 1999 by The Dryden Press All rights reserved.

Pure play. Find several publicly traded companies exclusively in projects business. Use average of their betas as proxy for projects beta.
Hard to find such companies.
Copyright 1999 by The Dryden Press All rights reserved.

11 - 87

11 - 88

Advantages and disadvantages of applying the CAPM in capital budgeting Disadvantages: Advantages: A projects market risk is the most relevant risk to stockholders, hence to determine the effect of the project on stock price.

It is virtually impossible to estimate betas for many projects.


People sometimes focus on market risk to the exclusion of corporate risk, and this may be a mistake.

It results in a definite hurdle rate for use in evaluating the project.


Copyright 1999 by The Dryden Press All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 89

11 - 90

Divisional Costs of Capital Debt Cost of Capacity Capital Low Avg. High 14% 10% 8%

Project Risk Adjustments

Division Heirloom Maple School

Beta High Avg. Low

Crockett Furniture classifies each project within a division as high risk, average risk, and low risk. Crockett adjusts divisional costs of capital by:
Adding 2% for high risk project No adjustment for average risk project Subtracting 1% for low risk project
Copyright 1999 by The Dryden Press All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

15

11 - 91

11 - 92

Evaluating Our Project

Evaluating Risky Outflows Company is evaluating two alternative production processes. Plan W requires more workers but less capital. Plan C requires more capital but fewer workers. Both systems have 3-year lives. The choice will have no impact on revenues, so the decision will be based on relative costs.
All rights reserved. Copyright 1999 by The Dryden Press All rights reserved.

Our project is a high risk project in the Heirloom division.

Project cost of capital = 16%


NPV = $42 thousand

Copyright 1999 by The Dryden Press

11 - 93

11 - 94

Year 0 1 2 3

Plan W ($500) (500) (500) (500)

Plan C ($1,000) (300) (300) (300)

Now suppose Plan W is riskier than Plan C because future wage rates are difficult to forecast. Would this affect the choice? If we add a 3% risk adjustment to the 10% to get kW = 13%, new PV would be: PVCOSTS-W = -$1,681 which is < old PVCOSTS-W = -$1,743. W now looks even better.
Copyright 1999 by The Dryden Press All rights reserved.

The two systems are of average risk, so k = 10%. Which to accept? PVCOSTS-W = -$1,743. PVCOSTS-C = -$1,746.

Ws costs are slightly lower so pick W.


Copyright 1999 by The Dryden Press All rights reserved.

11 - 95

11 - 96

Plan W now looks better, but since it is riskier, it should look worse! When costs are being discounted, we must use a lower discount rate to reflect higher risk. Thus, the appropriate discount rate would be 10% - 3% = 7%, making PVCOSTS-W = -$1,812 > old -$1,743.

Note that neither plan has an IRR. IRR is the discount rate that equates the PV (inflows) to the PV (outflows). Since there are only outflows, there can be no IRR (or MIRR). Similarly, a meaningful NPV can only be calculated if a project has both inflows and outflows.

With risk adjustment, PVCOSTS-W > PVCOSTS-C, so now choose Plan C.


Copyright 1999 by The Dryden Press All rights reserved.

If CFs all have the same sign, the result is a PV, not an NPV.
Copyright 1999 by The Dryden Press All rights reserved.

16

11 - 97

11 - 98

Real Options Real options occur when managers have the opportunity to influence the cash flows of a project after the project has been implemented. Real options also are called:

How do real options increase the value of a project? Real options allow managers to avoid negative project cash flows or magnify positive project cash flows.

Managerial options. Strategic options.


Copyright 1999 by The Dryden Press All rights reserved.

Increases size of expected cash flows. Decreases risk of expected cash flows.
All rights reserved.

Copyright 1999 by The Dryden Press

11 - 99

11 - 100

How is the DCF method affected? (1) Its easy to quantify the increase in the size of the expected cash flows. (2) Its very hard to quantify the decrease in the risk of the expected cash flows.

Types of Real Options Flexibility options Abandonment options Options to contract or temporarily suspend operations Options to expand volume of product Options to expand into new geographic areas
Copyright 1999 by The Dryden Press

(3) The correct cost of capital cannot be identified, so the DCF method doesnt work very well.
Copyright 1999 by The Dryden Press All rights reserved.

(More...)
All rights reserved.

11 - 101

11 - 102

What attributes increase the value of real options? Options to add complementary products Options to add successive generations of the same product Options to delay

All real options have a positive value.


Even if its not possible to determine a quantitative estimate of a real options value, its better to have a qualitative estimate than to ignore the real option.
(More...)
Copyright 1999 by The Dryden Press All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

17

11 - 103

11 - 104

Choosing the Optimal Capital Budget Real options are more valuable if:

They have a long time until you must exercise them. The underlying source of risk is very volatile. Interest rates are high.

Finance theory says to accept all positive NPV projects. Two problems can occur when there is not enough internally generated cash to fund all positive NPV projects:

An increasing marginal cost of capital. Capital rationing


All rights reserved. Copyright 1999 by The Dryden Press All rights reserved.

Copyright 1999 by The Dryden Press

11 - 105

11 - 106

Increasing Marginal Cost of Capital If external funds will be raised, then the NPV of all projects should be estimated using this higher marginal cost of capital.

Externally raised capital can have large flotation costs, which increase the cost of capital. Investors often perceive large capital budgets as being risky, which drives up the cost of capital.
(More...)
Copyright 1999 by The Dryden Press All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 107

11 - 108

Capital Rationing Capital rationing occurs when a company chooses not to fund all positive NPV projects. The company typically sets an upper limit on the total amount of capital expenditures that it will make in the upcoming year.
(More...)
Copyright 1999 by The Dryden Press All rights reserved. Copyright 1999 by The Dryden Press

Reason: Companies want to avoid the direct costs (i.e., flotation costs) and the indirect costs of issuing new capital. Solution: Increase the cost of capital by enough to reflect all of these costs, and then accept all projects that still have a positive NPV with the higher cost of capital.
(More...)
All rights reserved.

18

11 - 109

11 - 110

Reason: Companies dont have enough managerial, marketing, or engineering staff to implement all positive NPV projects. Solution: Use linear programming to maximize NPV subject to not exceeding the constraints on staffing.
(More...)
Copyright 1999 by The Dryden Press All rights reserved.

Reason: Companies believe that the projects managers forecast unreasonably high cash flow estimates, so companies filter out the worst projects by limiting the total amount of projects that can be accepted. Solution: Implement a post-audit process and tie the managers compensation to the subsequent performance of the project.
Copyright 1999 by The Dryden Press All rights reserved.

11 - 111

11 - 112

Blum Industries has 5 potential projects:

Weve seen how to evaluate projects. We need cost of capital for evaluation. But corporate cost of capital depends on size of capital budget. Must combine WACC and capital budget analysis.

Project Cost CF Life (N) IRR A $400,000 $119,326 5 15% B 200,000 56,863 5 13 B* 200,000 35,397 10 12 C 100,000 27,057 5 11 D 300,000 79,139 5 10 Projects B & B* are mutually exclusive, the others are independent. Neither B nor B* will be repeated.
Copyright 1999 by The Dryden Press All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 113

11 - 114

Additional Information
Interest rate on new debt Tax rate Debt ratio Current stock price, P0 Last dividend, D0 Expected growth rate, g Flotation cost on CS, F Expected addition to RE (NI = $500,000, Payout = 60%.) 8.0% 40.0% 60.0% $20.00 $2.00 6.0% 19.0% $200,000

Calculate WACC, then plot IOS and MCC schedules. Step 1: Estimate the cost of equity
D0(1 + g) + g = $2(1.06) + 6% = 16.6%. P0 $20 D1 $2(1.06) + 6% ke = +g= P0(1 - F) $20(1 - 0.19) ks = = $2.12 + 6% = 19.1%. $16.2
All rights reserved.

For differential project risk, add or subtract 2% to WACC.


Copyright 1999 by The Dryden Press All rights reserved.

Copyright 1999 by The Dryden Press

19

11 - 115

11 - 116

Step 2: Estimate the WACCs


WACC1 = w dkd(1 - T) + w ceks = (0.6)(8%)(0.6) + 0.4(16.6%) = 9.5%.

Step 3: Estimate the RE break point BPRE = Retained earnings Equity fraction $200,000 = $500,000. 0.4

=
WACC2 = w dkd(1 - T) + w ceke = (0.6)(8%)(0.6) + 0.4(19.1%) = 10.5%.

Each dollar up to $500,000 has $0.40 of RE at cost of 16.6%, then WACC rises. Only 1 compensating cost increase, so only 1 break point.
Copyright 1999 by The Dryden Press All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 117 % 16 15 14 13 12 11 10 9 8 7 500 700 New Capital (000s)


All rights reserved. Copyright 1999 by The Dryden Press

11 - 118

FIGURE 1
A
B

The IOS schedule plots projects in descending order of IRR.


C WACC2 = 10.5%
MCC IOS

B*

Two potential IOS schedules--one with A, B, C, and D and another with A, B*, C, and D.

WACC1 = 9.5%

The WACC has a break point at $500,000 of new capital.

Copyright 1999 by The Dryden Press

All rights reserved.

11 - 119

11 - 120

What MCC do we use for capital budgeting, i.e., for calculating NPV?

If all 5 projects are average risk, whats the optimal capital budget? MCC = 10.5%.

MCC: WACC that exists where IOS and MCC schedules intersect. In this case, MCC = 10.5%.

IRR and NPV lead to same decisions for independent projects. Thus, all independent projects with IRRs above 10.5% should be accepted. Therefore, accept A and C, reject D, and accept B or B*.

Copyright 1999 by The Dryden Press

All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

20

11 - 121

11 - 122

NPV and IRR can conflict for mutually exclusive projects.

Suppose you arent sure of WACC. At what WACC would B and B* have the same NPV? Get differences: CF0 = 200,000 - 200,000 CF1- 5 = 56,863 - 35,397 CF6-10 = 0 - 35,397
Copyright 1999 by The Dryden Press

NPV method is better, so choose between B and B* based on NPV at WACC = 10.5%.
NPVB* = $12,905 > NPVB = $12,830, so choose B* over B.

= 0 = 21,466 = -35,397

Indifference WACC = IRR = 10.52%.


Copyright 1999 by The Dryden Press All rights reserved. All rights reserved.

11 - 123

11 - 124

The risk-adjusted rates are as follows: WACC = 10.5% 2% Risk-Adjusted Hurdle Rate 8.5% 10.5 12.5
A B B* C D

IRR 15% 13 12 11 10

Hurdle Rate 12.5% 10.5 10.5 8.5 8.5 Accept Accept Accept Accept Accept
one

Project Risk Low: C, D Average: B, B* High: A

Now the optimal capital budget consists of A, B (or B*), C, and D, for a total of $1,000,000. Corporate k is still = 10.5%, so NPVB* still larger than NPVB.
Copyright 1999 by The Dryden Press All rights reserved.

Copyright 1999 by The Dryden Press

All rights reserved.

21

You might also like