Professional Documents
Culture Documents
Tahan
120
100
80
Percent
60
40
20
0
1997 1998 2001
Figure 4. SE/NE equivalent reservoir levels from 1997 to 2001 (Source: ONS)
18 30
16
25
14
12 20
Percent
10
8 15 SE
S/SE
6
N/NE 10
4
2 NE
5
0
1998 2000 2002 2004 2006
0
Year May Jun Jul Aug Sep Oct Nov Dec
Figure 3. Risk of deficit in 1997 (Source: Electrobrás report) Figure 5. Reservoir levels prognosis (Source: ONS)
40
15
30
10
Mean
20
Mean 2001
5
10
2001 Historical Minimum
Historical Minimum
0 0
Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov
shortage. From June to November, consumers had a target to re- Table 3. April 2001 Regional Data
duce their consumption by 20%.
Figure 5 shows that this procedure decreases the risk of a N NE SE S
load shortage even if a water inflow below the mean long-term Peak load (MW) 2,932 7,721 36,342 9,846
average occurs (75% for SE and 56% for NE, in Figure 5). Fig-
Average load (MW) 2,558 6,028 27,824 7,191
ures 6 and Figure 7 compare the water inflow in 2001 to the
long-term mean and the historical minimum. In fact, 2001 is a Reservoir level (%) 75.7 33.7 32.7 82.4
low rain year mainly in the Northeast.
Reservoir full capacity (MW) 10,700 50,000 160,000 14,300
Also note that both in the North and the South the rains were
above the long-term mean, which resulted in a lot of water be-
ing spilled. The excess energy from the North and the South uncertain, there is a concern related to the continuation of the
could not be transferred respectively to the Northeast and to the crisis into the year 2002.
Southeast due to transmission congestion. The energy flows The implementation of the planned gas-fired thermal plants
from South to Southeast through the Itaipu 765 kV ac lines. is very important, but the government is taking other measures
The construction of the third Itaipu ac circuit was delayed due to assure a proper balance of generation and consumption in the
to environmental reasons, and the situation was aggravated by near and long-term future. A new plan was launched on 6 July
a failure in one 765/345 kV, 1500 MVA transformer in the São 2001, aimed at integrating an additional 19.9 GW into the sys-
Paulo area. tem by 2003. Of this, 7.8 GW are from 21 large hydro genera-
There is a concern about the forthcoming situation in 2002. tion units; 6.4 GW will be produced by 15 thermoelectric plants;
The hydro reservoirs are expected to start the year at a very low 2.8 GW will be imports from neighboring countries; 860 MW
level, and, if 2002 is a dry year again, there is a high risk that the from small hydro plants; 960 MW from cogeneration projects;
crisis situation will not be alleviated. Anticipation of the con- and 1,000 MW from wind and solar generation projects.
struction of part of the planned gas-fired thermal plants may par- Many issues are still to be resolved before this plan is com-
tially solve the problem. pletely implemented, such as the guarantee of private invest-
ments, the environmental questions, the currency exchange
Table 3 shows the situation in April 2001 by region. Brazil
issue, increasing tariffs and others. But it seems that the devel-
had a total installed generating capacity of 65,700 MW (59,600
opment of the crisis has brought other variables into the general
MW of Hydro, 4200 MW of conventional thermal and 1,900
scenario (as, for example, better government integration, the
MW nuclear) with a peak load of 56,800 MW at that time.
transparency of the problems to the population, the population
joint effort to solve the crisis) that increase the possibility of this
View of the Future plan being successfully implemented, compared to the previous
Two important factors that have led to the crisis are: Thermoelectricity Priority Plan of 49 thermal plants.
● Delay in generation investment
● Drought. References
The initial public response to the government strategy for “Decenal expansion plan 1997/2008,” Eletrobrás GCPS.
avoiding a shortage has shown a very high level of cooperation Operador Nacional do Sistema Elétrico (ONS) Web site,
from consumers. In May 2001, the total energy consumption http://www.ons.org.br.
was spontaneously reduced by 10%, and in June the reduction “Balanco energetico nacional sinopse 2000” (in Spanish), Brazilian
was around 20%. However, since there is not enough time to Government Energy Secretariat. Available on the Web,
build the necessary generation facilities and the rain behavior is http://www.mme.gov.br/Sen/dadhist/Tsinop_p.htm.