You are on page 1of 4

J.A. Jardini, D.S. Ramos, J.S.C. Martini, L.B. Reis, C.M.V.

Tahan

Brazilian Energy Crisis


W ith deregulation and the privat-
ization processes in progress,
there were high expectations that the
Two important factors led
to the crisis: a delay in
ins’ seasonal characteristics. Oil, coal,
and nuclear plants provide thermal gen-
eration. The use of natural gas, most of it
private sector would invest in genera- coming from Bolivia, for producing
tion and transmission, but this did not
occur. The shortage of generation was
generation investment electricity is just beginning. So far, its
use has been implemented primarily to
exacerbated by drought conditions that and drought conditions produce electricity, reducing the imbal-
deteriorated reservoir levels. These cir- ance between generation and consump-
cumstances led to an increase of the risk tion resulting from the lack of
of an energy shortage. investments in the last decade.
Plans are now being implemented that take measures to as- After 1995, the energy business began restructuring with
sure a proper balance of generation and consumption in the near deverticalization, privatization, and the creation of regulatory
and long-term future. agencies (ANEEL for electricity, and ANP for petroleum and
natural gas).
Brazil and Its Regional Characteristics
The Federative Republic of Brazil is situated in northeastern Electricity Business Before Deregulation
South America. Administratively, the country is divided into 27 Under Eletrobrás, the federal holding company, there were four
federal units (states and DC) and the capital is Brasilia. For the regional companies: Furnas (SE), CHESF (NE), Eletronorte
purpose of this analysis we shall address the four main regions: (N), and Eletrosul (S); these companies were responsible for
North (N), Northeast (NE), Southeast (SE), and South (S), with electricity generation and transmission, except that Eletronorte
their specific characteristics. was also responsible for distribution in the Amazon’s isolated
The Southeast is the most developed area, followed by the systems.
South, the Northeast, and the North. Table 1 shows the country’s The Brazilian states owned most of the distribution compa-
population, electrical generation, and energy consumption by nies. Very few were private. The state distribution companies of
region. São Paulo and Minas Gerais in the Southeast and of Paraná in
In 1999, the participation of the fuels in the Brazilian energy the South also had generation and transmission activities.
matrix was: oil (22.8%), natural gas (2.4%), electricity (39.5%), Eletrobras supervised the centralized power system opera-
mineral coal (4.1%), firewood (7.5%), and alcohol and others tion as well as the expansion planning activities.
(23.7%). Oil production is lower than demand, resulting in some
dependence on importation. The country’s mineral coal presents New Electricity Business Structure
a low standard quality level, and it is, therefore, more used in the
The new structure includes:
metallurgy sector than for electricity production, which is
● ANEEL, the regulatory agency
mainly based on hydro plants.
● ONS, the independent system operator (ISO)
Figure 1 shows the Brazilian regions, with their main cities,
● MAE, the wholesale market
river basins, and hydroelectric plants. The North region, where
● Deverticalized companies (generation, transmission, and
the Amazon River and the rain forest are located, is the largest
area with the lowest population density. The largest Brazilian distribution)
● Free competition and free customers (depending on size
cities are São Paulo/SP, Rio de Janeiro/RJ, Belo Horizonte/MG
in the Southeast; Curitiba/PR and Porto Alegre/RS in the South; and according to a time schedule)
Recife/PE and Salvador/BA in the Northeast; and Belém/PA, ● Expansion planning retained by the government, under the

São Luiz/MR, and Manaus/AM in the North. Federal Energy Secretariat.


Conceptually, the generation and distribution companies un-
Energy Business dergo privatization, whereas the transmission companies remain
Until 1995, energy was mainly a state business controlled by the governmental. At present, most distribution companies have
government: Petrobrás in the oil sector and Eletrobrás, a federal been privatized, except for the states of MG and PR; however,
holding company, in the electricity sector. In 1997, 94% of the the latter is in the process of privatization.
electricity consumption was provided by hydropower (87% in To date, very few generation companies have been privat-
1999). Transmission interconnections play an important role to ized. Eletrosul is one. São Paulo state generation has been di-
ensure a better use of water, due to the differences in the river bas- vided in three companies, two already privatized and the largest
scheduled to be privatized by the end of 2002. A major percent-
J.A. Jardini, D.S. Ramos, J.S.C. Martini, L.B. Reis, and C.M.V. Tahan are with age of the Brazilian generation plants (Furnas, CHESF,
São Paulo University, São Paulo, Brazil. Eletronorte) are behind in the privatization process, leading to
IEEE Power Engineering Review, April 2002 0272-1724/02/$17.00©2002 IEEE 21
Table1. Brazil and its regions at a glance (1997) Generation is allocated in this timeframe
based on a 5% energy risk criteria, meaning
Region that the probability of generation not supply-
Indicator Total Brazil SE (%) S (%) NE (%) N (%) ing any amount of load (generation firm
power) is 5%.
Population 161 million 49 15 29 7

Income per capita 5,000 USS$/yr Crisis in 2001


The Brazilian system was mainly developed
Electrical engery consumption 290 TWh/yr 64 15 16 5
in the 1960s and 1970s. In the 1980s, impor-
Per capita consumption 1,800 kWh/yr tant hydro plants were completed. At that
1 2 1 time, the economic growth was smaller than
Total electricity installed capacity 57 GW 40 36 16 8
the planning forecasts, so that the electricity
1
Includes Itaipu (A Brazil-Paraguay joint enterprise installed capacity was sufficient to start the
2
Hydro 53.5 GW; thermal 3.5 GW 1990s without a shortage and with minimal
investment.
With deregulation and the privatization
doubts about the process itself. Discussions are being held, and processes in progress in the mid-1990s, the Brazilian govern-
other alternatives are being implemented, even in the Brazilian ment essentially did not invest in generation and transmission,
Congress, which approved the present privatization process. which was compliant with their policy of economic stabilization
and nonacquisition of external debts. There were high expecta-
Electrical System tions that the private sector would invest in these areas. This did
The hydro generation locations and the major river basins of not occur for many reasons, such as: strong opposition to the
Brazil appear in Figure 1. Respective installed capacity figures changes and the privatization process, conflict between the nat-
are shown in Table 2. The hydro system is cascade operated, op- ural gas price (bought in US$ from Bolivia) and the electricity
timizing the water flow into the power plants. A set of historical tariffs (in Reais, the Brazilian currency), the price escalation
reservoir water inflow data is used to avoid the risk of deficit. policy, lack of clear rules for the transition to the new model, dif-
Up until now, thermal generation complementation to hydro ficulties in getting long-term contracts for selling electricity to
has been very low (< 15%). As large hydro plants demand a long guarantee project financing, and enforcement of environmental
time to be built, from 5 to 10 years, the recent lack of invest- requirements.
ments has created a scenario requiring alternative solutions with This has led to an increase of the risk of an energy short-
lower construction time, such as gas-fired plants. Add to this the age, which has already been detected in the electric sector
increasing attention being given to the environmental and social planning process, as can be seen in Figure 3. This figure, from
problems attributed to large hydro plants. In Brazil, the delay in which Eletrobrás evaluated the risk of deficit in 1997, clearly
investing in alternative solutions is one of the reasons for the shows that from 1998 to 2001 the risk was greater than the de-
present crisis. sign criteria.
Within this context, the transmission interconnections play Recognizing that the construction of new hydro plants in a
an important role, since they allow the optimum use of hydro for short period of time is not feasible, a thermal generation plan,
producing electricity, taking into account the seasonal diversity the Thermoelectricity Priority Plan, using natural gas imported
of river basins. Transmission interconnection bottlenecks, on from Bolivia, was conceived and launched in the beginning of
the other hand, can result in undue water spilling, which some- 2000. This plan initially called for the construction of 49 plants,
times occurred, during the last periods.
Energy imports of neighbor countries are also part of this
scenario; besides the Bolivian natural gas imported to fuel the
new planned thermal plants, electricity is directly bought from
Paraguay (Itaipu 50 Hz machines ) and Argentina.
Figure 2 shows the high voltage transmission system of 345
kV, 440 kV, 500 kV, 765 kV ac lines and dc bipoles of ±600 kV
(from Itaipu).
Prior to 1998, the integrated N-NE system was not connected
to the S-SE system. Now they are interconnected through one
500 kV transmission line with controlled series compensation.
Duplication of this facility is scheduled for the end of 2002.
Many new 500 kV lines are scheduled for 2002 and their con-
cession was adjudicated to private companies by a bidding pro-
cess. In 1997, the total length of high voltage transmission lines
was about 120,000 km.

System Planning General Criteria


The (n-1) criteria are used for transmission line and transformer
planning. For load growth, three scenarios are established: the
reference (5.8% per year from 1998 to 2007), the high (6.5% per
year), and the low (5.3% per year), based on hypothetic eco-
nomic and population growth. Figure 1. Regions, cities, and rivers

22 IEEE Power Engineering Review, April 2002


comprising a total of around 12 GW, to be built by the end of tion added an extra delaying force to investments in generation,
2003. because the fuel is bought in US$ whereas consumer tariffs are
There were many reasons for delaying private investments in regulated by ANEEL in R$. Within this scenario, the govern-
the electricity sector. Some of the problems were caused by the ment had to count on its company Petrobrás. Basically, only the
international crisis (1999) and the devaluation of the Brazilian projects in which this company was involved as a partner were
currency (R$). The risk of a Brazilian currency maxi-devalua- carried out. This government procedure, to a certain extent
forced by current circumstances, has been seen as a contradic-
Table 2. Installed capacity in the river basins (1997) tion within the context of the privatization plan.
River Installed Capacity (MW) But another important factor must be considered to better un-
derstand the present electricity crisis: the behavior of hydro gen-
Tocantins 4,2000 eration. Figure 4 shows the SE/NE equivalent reservoir levels in
Sao Francisco 9,3000 the period 1997-2001. A continuous reduction in the average
reservoir levels due to the lack of supplementary generation, the
Paranaiba 4,000 reduction in the annual precipitation rates, and the growth in
Grande 5,900 load can be observed.
In 1999, although the level of hydro reservoirs had decreased
Paranaiba 4,9000
significantly, the load could be supplied but with little safety
Paranaiba (Itaipu) 12,6000 margins. The same occurred in the year 2000. In the last rain pe-
riod (November 2000 to January 2001), the SE/NE reservoir
South 6,700
levels were in a little better situation compared to the previous
year.
But by February 2001, the SE/NE reservoir levels were
worse (lower levels) than at the same period in 2000. In addition,
the weather forecast in February 2001 indicated less rain for the
March to May period. This led to a government strategy of es-
tablishing a plan to reduce consumption in order to avoid a

120

100

80
Percent

60

40

20

0
1997 1998 2001

Figure 4. SE/NE equivalent reservoir levels from 1997 to 2001 (Source: ONS)

Figure 2. Transmission lines in 2000 (Source: ANEEL) 35


%

18 30

16
25
14
12 20
Percent

10
8 15 SE
S/SE
6
N/NE 10
4
2 NE
5
0
1998 2000 2002 2004 2006
0
Year May Jun Jul Aug Sep Oct Nov Dec

Figure 3. Risk of deficit in 1997 (Source: Electrobrás report) Figure 5. Reservoir levels prognosis (Source: ONS)

IEEE Power Engineering Review, April 2002 23


GW avr GW avr
20 50

40
15

30

10
Mean
20

Mean 2001
5
10
2001 Historical Minimum

Historical Minimum
0 0
Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov

Figure 6. NE inflow (Source: ONS) Figure 7. SE inflow (Source: ONS)

shortage. From June to November, consumers had a target to re- Table 3. April 2001 Regional Data
duce their consumption by 20%.
Figure 5 shows that this procedure decreases the risk of a N NE SE S
load shortage even if a water inflow below the mean long-term Peak load (MW) 2,932 7,721 36,342 9,846
average occurs (75% for SE and 56% for NE, in Figure 5). Fig-
Average load (MW) 2,558 6,028 27,824 7,191
ures 6 and Figure 7 compare the water inflow in 2001 to the
long-term mean and the historical minimum. In fact, 2001 is a Reservoir level (%) 75.7 33.7 32.7 82.4
low rain year mainly in the Northeast.
Reservoir full capacity (MW) 10,700 50,000 160,000 14,300
Also note that both in the North and the South the rains were
above the long-term mean, which resulted in a lot of water be-
ing spilled. The excess energy from the North and the South uncertain, there is a concern related to the continuation of the
could not be transferred respectively to the Northeast and to the crisis into the year 2002.
Southeast due to transmission congestion. The energy flows The implementation of the planned gas-fired thermal plants
from South to Southeast through the Itaipu 765 kV ac lines. is very important, but the government is taking other measures
The construction of the third Itaipu ac circuit was delayed due to assure a proper balance of generation and consumption in the
to environmental reasons, and the situation was aggravated by near and long-term future. A new plan was launched on 6 July
a failure in one 765/345 kV, 1500 MVA transformer in the São 2001, aimed at integrating an additional 19.9 GW into the sys-
Paulo area. tem by 2003. Of this, 7.8 GW are from 21 large hydro genera-
There is a concern about the forthcoming situation in 2002. tion units; 6.4 GW will be produced by 15 thermoelectric plants;
The hydro reservoirs are expected to start the year at a very low 2.8 GW will be imports from neighboring countries; 860 MW
level, and, if 2002 is a dry year again, there is a high risk that the from small hydro plants; 960 MW from cogeneration projects;
crisis situation will not be alleviated. Anticipation of the con- and 1,000 MW from wind and solar generation projects.
struction of part of the planned gas-fired thermal plants may par- Many issues are still to be resolved before this plan is com-
tially solve the problem. pletely implemented, such as the guarantee of private invest-
ments, the environmental questions, the currency exchange
Table 3 shows the situation in April 2001 by region. Brazil
issue, increasing tariffs and others. But it seems that the devel-
had a total installed generating capacity of 65,700 MW (59,600
opment of the crisis has brought other variables into the general
MW of Hydro, 4200 MW of conventional thermal and 1,900
scenario (as, for example, better government integration, the
MW nuclear) with a peak load of 56,800 MW at that time.
transparency of the problems to the population, the population
joint effort to solve the crisis) that increase the possibility of this
View of the Future plan being successfully implemented, compared to the previous
Two important factors that have led to the crisis are: Thermoelectricity Priority Plan of 49 thermal plants.
● Delay in generation investment

● Drought. References
The initial public response to the government strategy for “Decenal expansion plan 1997/2008,” Eletrobrás GCPS.
avoiding a shortage has shown a very high level of cooperation Operador Nacional do Sistema Elétrico (ONS) Web site,
from consumers. In May 2001, the total energy consumption http://www.ons.org.br.
was spontaneously reduced by 10%, and in June the reduction “Balanco energetico nacional sinopse 2000” (in Spanish), Brazilian
was around 20%. However, since there is not enough time to Government Energy Secretariat. Available on the Web,
build the necessary generation facilities and the rain behavior is http://www.mme.gov.br/Sen/dadhist/Tsinop_p.htm.

24 IEEE Power Engineering Review, April 2002

You might also like