Professional Documents
Culture Documents
Kong
32
2004 E E E International Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong Kong
n. MARKETSIMULATION MODELS for transmission limit violations. The cost term for unserved
loads provides cost account for emergency load shedding in
GridView is a market simulation program that is able to case of supply shortage or import transmission limitations.
GridView Database for US regional power market is utilized to
perform transmissionkecurity constrained unit commitment
build the market model for the study system.
and economic dispatch. Detailed transmission network model
Gridview’s unit commitment and economic dispatch process
is included to ensure physical feasibility of power flows [ 11-[2]. is capable of modeling emission constraints and adequate in
The simulation program requires data from the following maximizing the emission compliance.
major categories:
0 Supply - generating capacity location, heat rates, fuel m.
METHODOLOGY DESCRIPTION
cost, operation constraints, and bidding information
0 Demand - spatial load distribution over time A . Problem description
0 Ancillary service requirements
Each group of units are assigned a certain amount of
0 Transmission - load flow model, interface limitations,
emission allowance within one year or in a specified season
transmission nomogram, and security constraints
such as from June to September. The emission types include
Other data categories may include market scenarios, market
rules, reliability performance data, and environmental S02, NOx, C02, etc. Additional emission allowances can be
constraint data. purchased from open emission markets at the market credit
The simulation program mimics the operation of open price [3]-[SI.
electricity markets by performing transmission security Without emission constraints, the system can be operated
constrained unit commitment and economic dispatch. This is at an optimal point with the lowest production cost determined
done sequentially in chronological order for a period from a by the unit commitment and economic dispatch process.
week to a few years, depending on the objective of the However, some cheaper units may be dirty, and discharge
application. Typical outputs include: undesirable emission output. If the total emission outputs
Locational market clearing prices exceed the available allowance, costs will be incurred due to
0 Generation utilization - dispatch hours, total generation, purchasing additional allowance from open market. The
production cost, and revenues problem is how to consider emission constraints in the unit
0 Environmental impacts commitment and economic dispatch process to economically
0 Transmission utilization - maximum loading, loading maximize the emission compliance, such that the production
factor cost plus emission allowance purchase cost is minimized when
0 Transmission bottlenecks - hours of congestion,
the economic equilibrium is reached.
economic value of expansion
The data related to emission analysis that can be used as
Reliability indices and other market performance
inputs include:
measures
Emission rate for each type of emission for each unit
A salient feature of GridView is the transmission security
Emission allowance for each type of emission for each
constrained unit commitment. This procedure determines the
group of units
startup, shutdown schedules and dispatch levels of generators
Market trading price for each type of emission
to minimize the total system cost while satisfying the various
generation and transmission constraints. The unit commitment allowance
is performed using the following information: Main output related to emission analysis include:
Day-ahead (or week-ahead) load forecast Emission output for each unit and unit group
0 Emission constraint 0 Marginal emission rate for specified horizon
Maintenance scheduling
0 Average full load production cost Emission output is a function of generation level that is
0 Generation operation constraint determined by energy demand and other market requirements
Start-up cost such as reserves. Change in energy demand is likely to lead to
Load plus various reserve requirements such as change in emission output. Marginal Emission Rate (MER) is a
regulation down, regulation up, spinning reserve, non- value measuring how the total emission output changes as a
spinning reserve and replacement reserve result of an infinitesimal increment in energy demand [6].
0 Transmission constraint and contingencies
33
2004 IEEE Intemational Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong Kong
an operating point with optimal production cost, and the current unit generation output by using (1) and ( 2 ) . If stopping
generation production cost may go up due to out-of-merit criteria are met, the program stops and otherwise continues as
operations. On the other hand, the cost for purchasing follows. Based on the shortfall of emission allowance, obtained
additional emission allowances is reduced, and the reduction as difference between actual emission output Eaclual-~
and
goes faster than the increase in production cost before an
equilibrium point is reached. And thus the production cost allowance EallOw
-
ki , the emission cost adjustment for unit
plus the allowance purchase cost is reduced in the process. groups can be calculated. This cost adjustment will be
The process iterates until an economic equilibrium or its accumulated in each iteration. The larger the shortfall of
proximity is reached that results in the lowest total cost. allowance, the larger the cost adjustment will be. When the
shortfall approaches zero, the cost adjustment will also
The following notations will be used: approach zero. These characteristics are conducive to a fast
Eaclual-~ : actual total emission output (lbs) for unit group k Commit and dispatch units I
for emission type j I
~~
The emission output for unit i for emission type j for all Calculate marginal emission rate
simulation hours is calculated as:
N
In the figure, Initial unit commitment and dispatch Then, unit commitment and dispatch cost is adjusted by
scheduling obtains the generator commitment status and using the calculated unit cumulative emission cost adjustment,
energy output without considering the emission constraints and the process of unit commitment and dispatch is carried out
for the simulation horizon. The approach proceeds as follows to obtain the generation outputs. Next the emission outputs
in the emission iteration loop. The program calculates the can be calculated again and checked with given allowance
emission outputs for units and unit groups based on the limit. The above process is iterated until convergence criteria
34
2004 WEE International Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DRPT2004) April 2004 Hong Kong
TABLE I
EMISSION ALLOWANCE AND MARKET PRICE OF ALLOWANCE
CREDIT
so2 NOx
Allowance (Ton) 36,000.00 35,000.0C
Allowance Trading Price
:%Lb) 0.0635 0.4
35
2004 E E E International Conference on Electric Utility Deregulation,Restructuringand Power Technologies (DRPT2004) April 2004 Hong Kong
TABLE V
GENERATION LEVEL, COST, REVENUE FOR SELECTED
AREAS
1 2 3 4 5 6 7 8 9101112
lteration
Generation
Fig. 2. Generation production cost and emission credit cost Revenue($) 158,998,432.0 48,096,408.0 27,519.010.0 10.950.563.ONo
Generation
Revenue ($) 164,301,776.0 58,916.416.0 19,232,356.0 11,677,182.OYes
36
2004 IEEE Intemational Conference on Electric Utility Deregulation, Restructuring and Power Technologies (DWT2004) April 2004 Hong Kong
50 - I-- - - - - - Without EM1 Mukerji, “An integrated electrical power system and market
analysis tool for asset utilization assessment”, IEEE PES Summer
Meeting, Chicago, July 2002.
45
[2] X. Feng, J. Pan, L. Tang, H. Chao. and J. Yang, “Economic
40
35 .. I I
evaluation of transmission congestion relief based on power market
simulations”, IEEE PES General Meeting, 2002.U.S.
30
131 Environmental Protection Agency, “EPA Acid Rain Program,
25 1 I t 2001 Progress Report”, November 2002.
n 20 [4] U.S. Environmental Protection Agency, Ozone Transport
f 15
10
i
t
I I
i l
Commission NOx Budget Program,
http:!iwww .epa.gov:airmarkets:otc/index.li tml.
web site:
Jiuping Pan (M’97) received his B.S.E.E and M.S.E.E. from Shandong
v. CONCLUSIONS University of Technology, China, and then his Ph.D. in electrical
An emission compliance approach is described in this engineering from Virginia Tech, USA. He is currently a principal
paper, which was implemented in a power market simulation consulting R&D engineer at ABB Corporate Research US. His main
program GridView. This approach maximizes the emission working experiences and research interests include generation and
transmission planning, power system reliability assessment, network
compliance by iteratively adjusting the unit commitment and assessment management, and competitive market simulation studies.
37