You are on page 1of 3

Certified that the forgoing claim is correct that the necessary measurement ware taken by Mr Surajit Ghosh AM/C in

MB 1172 Page No.1 TO 4.

Dated : JGM/DGM/Civil

Certified that,
1. Measurements recorded in measurement book No-1172 are fully accepted by me and I do not have any other claim against this
bill.
2. The labours employed by me have been paid minimum wages as fixed in similar type of work in the area.
3. All taxes including Royalty charges.cess,etc.due to the Govt.on the materials used for this work have been fully paid and no payment is due to them.
4. All the insurance polices as per previsions of the contract has been taken by me and are valid as on date.
5. I have extended the provident fund benefits to the staff engaged by me and requisites amount of provident fund has been remitted
to the provident fund commissioner.
6.That the statutory formalities and guidelines has been complied with.

Dated :
Contractor

Certified that,
1. The quantity billed is not more than the quantity actually executed at site.
2. No material has been issued to the contractor, for which the cost was to be recovered except such as specifically provided in the agreement/work order.
3. No departmental tools & plants have been issued to the contractor other than those for which hire charges have been recovered in this bill.
4. In case of lump sum payment, approximate quantity billed is not more than the quantity actually executed at site.
5. The work has been executed as per approved drawing and specifications and the method of measurement is correct.
6.That the statutory formalities and guidelines has been complied with.

(Surajit Ghosh)
AM/Civil DGM/ Civil
IRCON INTERNATIONAL LTD
Quazigund Baramulla New Rail Line Project, Srinagar
SUB CONTRACTOR'S RUNNING/FINAL ACCOUNT BILL/CC

RA BILL/Contract Certificate No.:- First


Name of Work:- Conducting field test on completed embankments between km 18.00 to 45.00
Name of Contractor:- AS ASS Consultants, Hawal, Srinagar.
Tender No.:- IRCON/J&K-SGR/1008/CFT/LT/422/16866, DATED: 22-10-2007
Contract Agreement/work order No.:- IRCON/J&K-SGR/1008/CFT/LT/422/17135, DATED: 24-11-2007
Contract value:- Rs. 8,21,100.00
Date of Commencement::- 24-11-2007 Original Date of completion of the work:- 3 months, 23-02-2008
Date of entry: 28-02-2008

BOQ BOQ Quantity upto Quantity Upto Quantity Since Rate Amount Upto Amount Upto Amount Since
Sl no Description of Item Unit
Item No Quantity This Bill Last Bill Last Bill (in Rs.) This Bill Last Bill Last Bill
Drilling of Bore Hole
1 1 150/100 mm dia. Rm 490 331.5 190.5 141 1,500.00 497,250.00 285,750.00 211,500.00

Sieve analysis and


Gradation of
2 2 Blanketing Material Job 50 47 26 21 500.00 23,500.00 13,000.00 10,500.00

Submission of final
3 3 report in trilicate. Job 11 5 3 2 2,000.00 10,000.00 6,000.00 4,000.00

Total: 530,750.00
304,750.00 226,000.00
Add accepted rate 5% above BOQ 26,537.50
15,237.50 11,300.00
Grand Total: 557,287.50
319,987.50 237,300.00
Say: 237,300.00
Amount Payable in this 2nd RA bill is Rupees Two Lakhs Thirty seven Thousand Three Hundred only

(Surajit Ghosh)
AM/Civil

You might also like