Land Acquisition: NA
TOTAL: 93 Days
IRCON Nil
Neither to IRCON or
Neither to IRCON or contractor
contractor:
Time extension Recommended
15 31-05-2008
upto:
With or without penalty Without penalty
(Surajit Ghosh)
Assistant Manager / Civil
DGM/ Civil
JGM/ Civil
AGM/ Finance
GM/ Srinagar
Scheduled Date of
7
completion of work:
Physical 70%
Law and Order Situation Bandh due to Shrine board land transfer issue 28 days
Land Acquisition: NA
TOTAL: 43 Days
a) the work remained suspended due to bad weather
for a long period from in different periods due to
Reasons details for granting Heavy snow/rain fall.
13
time extension: b) There were many days work has stopped due to
local strikes in the working season and progress
hampered a lot.
Delay in completion of work is
14
attributable to :
Contractor Nil
IRCON Nil
Neither to IRCON or
Neither to IRCON or contractor
contractor:
Time extension Recommended
15 31-08-2008
upto:
With or without penalty Without penalty
(Surajit Ghosh)
Assistant Manager / Civil
DGM/ Civil
JGM/ Civil
AGM/ Finance
GM/ Srinagar