You are on page 1of 5

IRCON International Limited

J&K Rail Project, Srinagar


Date: 01-04-2008
Construction of Miscellaneous External
Development Works at Anantnag Yard, (Package
1 Name of work M-12) on Qazigund - Baramulla Section of New BG
Rail Line Project (J&K)

2 Name of Contractor AN Builders, K.P. Road, Anantnag, J&K

IRCON/ 1008/ J&K -DLI/ Ext Devlp. Works/ M-12/1172


3 LoA No& Date
Date: 31-08-2007

5 Oiginal Contract value Rs. 3,28,55,914.91

6 Revised Contract value NA


Scheduled Date of
7
completion of work:
As per Original contract 31-12-2007
Reference of contractor’s
8 Letter seeking extension of Reference of contractors letter no:ANB
time:
Time Extension
9 31-05-2008
Recommended up to:
10 Present status of work
Financial Rs.1,15,24,651.50
Physical 40%
Expected time required for
11 One months
Completion:
12 Details of time lost due to:
Variation in quantities/ scope
NIL
of work
1. Snow fall-28 days
Snow fall & weather condition.
2. Rainfall-65 days

Law and Order Situation NA

Land Acquisition: NA

TOTAL: 93 Days

a) the work remained suspended due to bad weather


for a long period from in different periods due to
Reasons details for granting Heavy snow/rain fall.
13
time extension: b) There were so many days work has stopped due to
local strikes, holiday etc in the working season.
c)
Delay in completion of work is
14
attributable to :
Contractor Nil

IRCON Nil
Neither to IRCON or
Neither to IRCON or contractor
contractor:
Time extension Recommended
15 31-05-2008
upto:
With or without penalty Without penalty

With or without PVC Without PVC

Submitted for kind approval.

(Surajit Ghosh)
Assistant Manager / Civil

DGM/ Civil

JGM/ Civil

AGM/ Finance

GM/ Srinagar

TIME EXTENSION FILE


EXTENSION RECOMMENDED UP TO: 31-05-2008
Name of work: Construction of Miscellaneous External Development Works
at Anantnag Yard, (Package M-12) on Qazigund - Baramulla Section
of New BG Rail Line Project (J&K)

Approval for execute work by RRM in stead of CRM


IRCON International Limited
J&K Rail Project, Srinagar
Date: 10-08-2008
Construction of Miscellaneous External
Development Works at Anantnag Yard,
1 Name of work (Package M-12) on Qazigund - Baramulla Section
of New BG Rail Line Project (J&K)

2 Name of Contractor AN Builders, K.P. Road, Anantnag, J&K

IRCON/ 1008/ J&K -DLI/ Ext Devlp. Works/ M-12/1172


3 LoA No& Date
Date: 31-08-2007

5 Oiginal Contract value Rs. 3,28,55,914.91

6 Revised Contract value NA

Scheduled Date of
7
completion of work:

As per Original contract 31-12-2007


1st time extension granted up
31-08-2008
to:
Reference of contractor’s
Reference of contractors letter no:ANB /811/M-12/1406
8 Letter seeking extension of
Dated: 25-07-2008
time:
Seeking time Extension up
9 31-08-2008
to:
10 Present status of work

Financial Rs. 1,75,94,506.52

Physical 70%

Expected time required for


11 20 days
Completion:

12 Details of time lost due to:

Variation in quantities/ scope


NIL
of work

Snow fall & weather condition. Rainfall-15 days

Law and Order Situation Bandh due to Shrine board land transfer issue 28 days

Land Acquisition: NA

TOTAL: 43 Days
a) the work remained suspended due to bad weather
for a long period from in different periods due to
Reasons details for granting Heavy snow/rain fall.
13
time extension: b) There were many days work has stopped due to
local strikes in the working season and progress
hampered a lot.
Delay in completion of work is
14
attributable to :
Contractor Nil

IRCON Nil
Neither to IRCON or
Neither to IRCON or contractor
contractor:
Time extension Recommended
15 31-08-2008
upto:
With or without penalty Without penalty

With or without PVC Without PVC

Submitted for kind approval.

(Surajit Ghosh)
Assistant Manager / Civil

DGM/ Civil

JGM/ Civil

AGM/ Finance

GM/ Srinagar

You might also like