You are on page 1of 9

CEB STANDARD 066 : 1998 Revised - September 1998

Specification for

GALVANIZED IRON PIPES FOR SERVICE CONNECTIONS

CEB Standard 066 : 1998

CEYLON ELECTRICITY BOARD

No. 50, Sir Chittampalam A. Gardiner Mawatha, Colombo 2. Sri Lanka


Telephone: 24471-8 Telex : 21368 CE Facsimile: 94-1-449572 E-mail : cedp@mega.lk

AMMENDMENT TO CE STANDARD 066 : 1998 1 SPECIFICATION FOR GALVANIZED IRON PIPES FOR SERVICE CONNECTIONS TENDER FOR THE SUPPLY AND DELIVERY OF GALANIZED IRON PIPES FOR SERVICE CONNECTIONS
(Revised September 98)

CEB STANDARD 066 : 1998 Revised - September 1998

TENDER NO : MMP/T/D/98/42

REVISED TEXT 1. Clause No. 5.8 Galvanizing The first word in the last raw of the paragraph copper should be read as Zinc. The word in the last raw of the paragraph less than should be read as not less than 2. Clause No. 8.0 INFORMATIION TO BE SUPPLIED WITH THE OFFER The word in the third sub clause conforming should be read as conforming. 3. The Drawing No. DS&S-66/1/98 wherever mentioned in the Specification should be amended as Drawing No. CEB/DS&S/66-2/1998

CEB STANDARD 066 : 1998 Revised - September 1998

CONTENTS

PAGE NO.

1. 2. 3. 4. 5.. 6. 7. 8. 9. 10. 11.

General Design Loadings Standards And Codes Of Practice Materials Construction Minimum Technical Requirements Additional Requirements Information To Be Supplied With The Offer Inspection And Testing Sample Annex 4 2

2 2

2 3

5 5 5 6 6

CEB STANDARD 066 : 1998 Revised - September 1998

SPECIFICATION FOR GALVANIZED IRON PIPES FOR SERVICE CONNECTIONS

1.0

GENERAL This Specification covers fabrication, galvanizing and testing of Iron Pipes used as Tubular Service Connection Poles.

2.0

DESIGN LOADINGS The Fabricated Tubular Iron Pole shall be able to withstand a load of 50 kgf (Tension) as the Pole Top loading in all directions, applied at a distance of 0.6 Metres from the top of the pole.

3.0

STANDARDS AND CODES OF PRACTICE Unless otherwise specified, the materials and workmanship specified under this Specification shall conform to the latest version of the appropriate British Standards. In particular to : BS 3601 - Part 1 : 1987- Seamless Welded Tubes Hot finished structural hollow section Hot Dip Galvanised Coating on Iron & Steel Article

BSEN 10216-1 BS 4.0 MATERIALS 729 - 1991

The tubular pole shall be constructed with steel of grade S 235 JRH or any other higher grade of steel used in the fabrication of hollow structures. The flat iron used in the fabrication of "D" bracket shall conform to BS 7613-1994 and BS 7668 - 1994 or any other hitherto. The chemical properties and mechanical properties of steel shall be in accordance with BSEN 10216-1 and BS 729 - 1991 or any other standard hitherto.

CEB STANDARD 066 : 1998 Revised - September 1998

5.0

CONSTRUCTION 5.1. Tubular Pole The steel used in the manufacture of tubes shall be of grade S 235 JRH or any other higher grade conforming to the British Standards given in Clause 3.0 of this specification. The tubes used in the construction of service poles shall be seamless. However, spirally or longitudinally welded tubes are also acceptable. The tubular pole and its components shall be constructed as per Drawing No. DS&S - 66-1/98 given in Annex B, using steel of grade S 235 JRH. The Steel used shall satisfy all the requirements under BSEN 10216. No welding or threading arrangements with unions to maintain the length of the pole is acceptable. The full length of the pipe inclusive of the end seal, given in 5.2 below, may also be of either centrifugal casting or produced by extrusion from the parent metal. 5.2 End Seal

The top end of the pole shall be sealed from ingress of moisture by completely welding to size with a sheet steel of same grade as that of the pole or any other suitable arrangement, using metal. Usage of PVC or any other non-metal component to seal the top end of the pole is not acceptable. Refer Drawing No. DS&S-66-1/98 given in annex - B of this Specification, for constructional features. 5.3 "D" Bracket

This is constructed as per Drawing No. DS&S - 66-1/98 given in Annex B using flat iron specified under BS 7613 - 1994 and BS 7668 - 1994. 5.4 Anchoring Device

This is constructed as per Drawing No. DS&S - 66-1/98 given in Annex B. M.S. Bar used for Anchoring shall be welded to the Pipe in the same plane as that of the "D" Bracket.

5.6

Welding of "D" Bracket to service Pole

This is constructed as given in Drawing No. DS&S - 66-1/98 given in Annex B.

CEB STANDARD 066 : 1998 Revised - September 1998

The "D" bracket so fabricated as in Clause 5.2 above shall be welded to the Tubular Pipe in the same plane as that of the M.S. Bar used for Anchoring of the Tubular Pole. The welding shall have a good finish to prevent accumulation of water between the welding and the metal interfaces. Strength of welding shall be able to hold the "D" bracket to the constructed tubular pole without detaching from same for a load greater than 200kgf. The structure so fabricated as above shall be first cleaned by sand blasting, necessary holes drilled, cut into required size and necessary sheet metal working welding etc. carried out before galvanizing. 5.7 Finish

All components shall be smooth, with corners rounded and free from sharp edges. All burrs shall be removed after shearing, drilling or punching. The galvanizing on all items shall be smooth, continuous, uniform and free from flux stains. Holes shall be free from nodules of pelter. 5.8 Galvanizing

The complete fabricated structure shall be hot dip galvanized conforming to BS 729, and treated with Sodium Dichromate or Pelter W20 Solution immediately after galvanizing to prevent the formation of white rust. The preparation for galvanizing itself shall not distort the mechanical properties of material. All components shall be effectively galvanized to give a uniform Zinc coating of not less than 610 grams of copper per square meter of surface ie uniform thickness less than 0.086mm. 5.9 Design Drawings

The design and dimension of the structure and relevant components are as shown in the Drawing No. DS&S - 66/1/98 given in Annex B of this text. 6.0 MINIMUM TECHNICAL REQUIREMENTS Quality of steel for pipe Length of pipe External diameter Wall thickness S 235 JRH 5.8 M 76.1 mm not less than 3.4 mm.

The grade and chemical composition of steel shall be S 235 JRH which is accordance with BSEN 10210-1 (1994) and BS 7668 - 1994. Accordingly the minimum tensile strength of steel shall be 389 Newton per mm. 7.0 ADDITIONAL REQUIREMENTS 1. Marking

CEB STANDARD 066 : 1998 Revised - September 1998

Manufactures identification mark and the letter CEB shall be impressed on the finished product (tubular pole) at a height not less than 3.0 m from the Anchored end of the Pole. 2. Packing The complete galvanized structure shall be bundled together using GS wire, each bundle having 100 Nos. of items. A label indicating the name and quantity of the item shall be fixed to each bundle. 8.0 INFORMATION TO BE SUPPLIED WITH THE OFFER 1) 2) 3) 4) 5) Test certificate for the steel used in the fabrication of items offered conforming to BS 7613 - 1994; BS 7668 - 1994. Test certificate for galvanizing conforming to GS 729 from an independent testing authority acceptable to CEB. Test Certificate conforming the strength of welding The constructional drawings and details of Section A and B as shown in Drawing No. DS&S - 66/1/98 given in Annex B of this text. Sample as per Clause No. 11 of this Specification. Failure to furnish the above particulars will result in this offer being rejected. 9.0 INSPECTION AND TESTING The selected tenderer shall make necessary arrangements for inspection by an Engineer appointed by the CEB for carrying out the following tests in his presence a) b) c) Visual inspection as per clause 9 and 12.3, tensile test as per clause 8.1, 12.2 and 13.1, flattening test or bend test as per clause 8.1, 12.2 and 13.2 of BS 3602 Part 1 - 1987. Elongation Galvanizing

and to check the Dimensions, Tolerance, Finish and formation of White Rust.

10.0

SAMPLE One sample (non returnable) shall be supplied. The length of the sample shall be of any length not less than 0.5 m so as to include the "D" bracket welded portion of the Tubular Pole. Late sample shall not be acceptable.
7

CEB STANDARD 066 : 1998 Revised - September 1998

11.0

Annex Schedule of Particulars Constructional features (Annex A) Drwg. No. DS&S - 66/1/98 (Annex B)

CEB STANDARD 066 : 1998 Revised - September 1998

Annexure - A SCHEDULE OF PARTICULARS 1. 2. Grade of Steel Mechanical Properties of steel a) b) c) 3. 4. Minimum Tensile strength Minimum Yield strength Minimum Elongation -

Whether the grit blast facilities available for rust freeing the steel sections Galvanizing a) b) Thickness of galvanized coating in any area Weight of galvanized coating per square meters -

5. 6. 7. 8.

Country of Origin for Steel Hardware Components

Chemical Composition of the Steel used (furnish mills certificate) Thickness of the Pipe Diameter of the Pipe a) Internal b) External

9. 10.

Whether the Top End Seal is provided Detailed Dimensional Drawing of the Pipe