Professional Documents
Culture Documents
Cost management is one of the fundamental and yet most challenging tasks for a project manager. Project Cost Management is primarily concerned with the cost of the resources needed to complete schedule activities. Project Cost Management should also consider the effect of project decisions on the cost of using, maintaining, and supporting the product, service, or result of the project. Project cost management should consider the stakeholder requirements for capturing costs, different stakeholders will measure project costs in different ways and at different times.
Life Cycle Costing. Look at manage life cycle costs instead of just project costs.
Level of accuracy. Rounding of the data ( $100, $1000 ) based on the scope of activities and magnitude of the project. Units of measure. For each of the resources ( Staff hours, staff days, lump sum ). Organizational procedures links. Control accounts components of the WBS are assigned a unique codes that links directly to the performing organizations accounting system. Control thresholds. For monitoring cost performance, Agreed-upon amount of variation to be allowed before some action needs to be taken, ( % deviation from baseline ). Rules of performance measurement. Earned value management (EVM) rules of performance measurements are set.
Define WBS points, Techniques ( fixed formula, percent complete), Equations (EAC).
Costs that are directly attributable to more than one Indirect Costs project (overhead) Amount of money needed above the estimate to reduce risk of overruns of project Cost reserves
Developing an approximation of the monetary resources needed to complete project activities. Cost trade-offs and risks must be considered, make or buy, buy or lease, and sharing of resources to achieve optimal costs for the project. The accuracy of project estimates will increase as project progresses through the project life cycle.
In the initiation phase have a rough order of magnitude (ROM) estimate in the range of 50%. Later in the project, as more information is known, estimates could narrow to a range of 10%.
Costs are estimated for all resources that will be charged to the project (labor, materials, equipment, services, and facilities).
Inputs
v Scope Baseline
deliverables, project boundaries, assumptions, and constraints (limited budget, delivery dates, available skilled resources, organizational policies).
Inputs
Project Schedule
Estimate activity resources.
Determine the availability and quantities required of staff and material needed to perform schedule activities.
Risk Register
Risks can be either threats or opportunities. Risk mitigation costs.
Inputs
Organizational Process Assets
Cost estimating policies. Cost estimating templates. Historical information. Lessons learned.
cE = cO + 4cM + cP 6
Cost of Quality (COQ) Project Management Estimating Software Vendor Bid Analysis
The project team examine the price of individual deliverables to drive a cost that supports the final total project cost.
Outputs
Activity Cost Estimates
Quantitative assessments of the probable costs of all resources required to complete project work. labor, materials, equipment, services, facilities, IT, contingency reserves.
Basis of Estimate
Documentation of the basis of estimate. Documentation of all assumptions made. Documentation of any known constraints. Indication of the confidence level of final estimate. Indication of the range of possible estimates ($10.000 (10%)).
Aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. Cost baseline includes all authorized budgets, but excludes management reserves. Project cost performance will be measured against the authorized budget.
Inputs
v Activity Cost Estimates v Basis of Estimates v Scope Baseline
Scope statement. Work Breakdown Structure.
Inputs
Project Schedule
Planed start and finish dates for the projects activities, milestones, work packages, control accounts.
Resource Calendars
Indicate resource costs over the duration of the project.
Contracts
Costs relating to products, services, or results that have been purchased.
Reserve Analysis
Contingency reserves .. Allowances for unplanned but potentially required changes result from realized risks identified in risk register. Management reserves .. Budgets reserved for unplanned changes to project scope or cost, not part of project cost baseline, but included in the total budget.
Expert Judgment
Consultants, stakeholders (include customers). Industry groups, professional associations.
Parameters used in the model are readily quantifiable. Models are scalable, such as work for large project, a small project, and phases of a project.
Outputs
Cost Performance Baseline
Authorized time-phased budget at completion (BAC) used to measure, monitor and control overall cost performance on the project. Developed as a summation of the approved budgets by time period (S-curve). When comparing actual to planned, the cost baseline serves as the planned cost.
Outputs
Project Document Updates
Risk register. Cost estimates. Project schedule.
Monitoring the status of the project to update the project budget and managing changes to the cost baseline. Updating the budget involves recording actual costs spent to date. Analyzing the relationship between the consumption of project funds to the physical work being accomplished for such expenditures.
Inputs
v Project Management Plan
Cost Performance Baseline.
Compared with the actual results to determine if a change, corrective or preventive action is necessary.
Inputs
Work Performance Information
Provide information about project progress. Deliverables that have been completed and those not yet completed. Costs authorized and incurred. Estimates for completing project work.
Planned value .. PV is the budgeted cost for the work scheduled to be completed on an activity or WBS
component, total PV for the project known as Budget At Completion (BAC).
Earned value .. EV is the budgeted amount for the work actually completed on the schedule activity or WBS
component during a given time period, describe the percentage completion of a project, EV cannot be greater than PV.
Actual cost .. AC is the total cost incurred in accomplishing work on the schedule activity or WBS component
during a given time period, AC have no upper limit.
Indication Good if 0 Good if 0 Good if 1 Good if 1 Budgeted rate Actual cost CPI , SPI How much more spent
Term Schedule Variance Cost Variance Schedule Performance Index Cost Performance Index
EAC = AC + BAC EV EAC = BAC / CPI Estimate at Completion EAC = AC + ((BAC EV)/(CPI * SPI)) ETC = EAC - AC Estimate to Complete
TCPI =
It answers the question of : In order to stay within budget, What rate must we meet for the remaining work? Consider risks, schedule, and technical performance.
Earned value performance .. Compares the baseline plan to actual schedule and cost performance.
Variance Analysis
Cost performance measurements (CV, CPI) are used to assess the magnitude of variation to the original cost baseline. Determine the cause and degree of variance relative to the cost performance baseline. Deciding whether corrective or preventive action is required.
Outputs
Budget Forecasts
The calculated EAC value is documented and communicated to stakeholders.
Outputs
Change Requests
Preventive or corrective action. Processed for review and disposition through the Perform Integrated Change Control process.
Question
A cost performance index (CPI) of 0.89 means: A. At this time, we expect the total project to cost 89 percent more than planned. B. When the project is completed we will have spent 89 percent more than planned. C. The project is only progressing at 89 percent of the rate planned. D. The project is only getting 89 cents out of every dollar invested. Answer: D
Question
You provide a project cost estimate for the project to the project sponsor. He is unhappy with the estimate, because he thinks the price should be lower. He asks you to cut 15 percent off the project estimate. What should you do? A. Start the project and constantly look for cost savings. B. Tell all the team members to cut 15 percent from their estimates. C. Inform the sponsor of the activities to be cut. D. Add additional resources with low hourly rates. Answer: C
Question
Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following should you do? A. Eliminate risks in estimates and re-estimate. B. Meet with the sponsor to find out what work can be done sooner. C. Cut quality. D. Decrease scope. Answer: A
Question
A manufacturing project has a schedule performance index (SPI) of 0.89 and a cost performance index (CPI) of 0.91. Generally what is the BEST explanation for why this occurred? A. The scope was changed. B. A supplier went out of business and a new one needed to be found. C. Additional equipment needed to be purchased. D. A critical path activity took longer and needed more labor hours to complete. Answer: D
Question
Although the stakeholders thought there was enough money in the budget, halfway through the project the cost performance index (CPI) is 0.7. To determine the root cause, several stakeholders audit the project and discover the project cost budget was estimated analogously. Although the activity estimates add up to the project estimate, the stakeholders think something was missing in how the estimates was completed. Which of the following describes what was missing? A. Estimated costs should be used to measure CPI. B. SPI should be used, not CPI. C. Bottom-up estimating should have been used. D. Past history was not taken into account. Answer: C
Question
You are about to take over a project from another project manager and find out the following information about the project. Activity Z has an early start (ES) of day 15 and a late start (LS) of day 20. Activity Z is a difficult activity. The cost performance index (CPI) is 1.1. The schedule performance index (SPI) is 0.8. There are 11 stakeholders on the project. Based on this information, which of the following would you be the MOST concerned about? A. Schedule. B. Float. C. Cost. D. The number of available resources. Answer: A
Question
The difference between the cost baseline and the cost budget can be BEST described as: A. The management reserve. B. The contingency reserve. C. The project cost estimate. D. The cost account. Answer: A
Question
A project manager needs to analyze the project costs to find ways to decrease costs. It would be BEST if the project manager looks at: A. Variable costs and fixed costs. B. Fixed costs and indirect costs. C. Direct costs and variable costs. D. Indirect costs and direct costs. Answer: C
Question
Estimate at completion (EAC) is a periodic evaluation of: A. The cast of work completed. B. The value of work performed. C. The anticipated total cost at project completion. D. What it will cost to finish the job. Answer: C
Question
If earned value (EV) = 350, actual cost (AC) = 400, planned value (PV)= 350, what is cost variance (CV)? A. 350. B. -75. C. 400. D. -50. Answer: D
Question
All the following are outputs of the Estimate Costs process EXCEPT: A. An understanding of the cost risk in the work that has been estimated. B. The prevention of inappropriate changes from being included in the cost baseline. C. An indication of the range of possible costs for the project. D. Documentation of any assumptions made during the Estimate Costs process. Answer: B
Question
The cost contingency reserve should be: A. Hidden to prevent management from disallowing the reserve. B. Added to each activity to provide the customer with a shorter critical path. C. Maintained by management to cover cost overruns. D. Added to the base costs of the project to account for risks. Answer: D
Thank you