Professional Documents
Culture Documents
A schedule is the conversion of the project action plan into an operating timetable The schedule are typically based on the WBS (work breakdown structure); as breaking down the job in to sub jobs followed by tasks. The basic approach of all scheduling techniques is to form a network of activity and event relationship that graphically portrays the sequential relations between the tasks in the project. Making network has following benefits for projects: 1. Consistent~ framework for (planning, monitoring, and controlling) 2. Illustrates~ interdependence of all (task, work packages and work elements) 3. Illustrates~ which task must be coordinated to avoid resource or timing conflicts 4. Illustrates~ which tasks (may be, must be run in parallel to achieve the predetermined project completion date) 5. Determine~ expected project completion date 6. Determine~ date on which (task may or must be started) 7. Identifies so-called critical activities (that cannot be delayed) 8. Identifies activities with slack (that can be delayed) 9. Provide proper communication
Basic Terminologies: Activity: A specified task or set of tasks that are required by the project, use up resources and take time to complete. Event: The results of completing one or more activities. An identifiable end state occurring at a particular time, events use no resources. Network: The arrangement of all activities (and, in some cases, events) in a project arrayed in their logical sequence and represented by arcs and nodes. This arrangement defines predecessors and successor relationship
Predecessors: Past activities that have been completed previously. Successor: Future activities that have no yet being completed. Measured on a event An activity can be any of these conditions: p It may have successor but no predecessor p It may have predecessor but no successor p It may have both predecessor and successor
Path: The series of connected activities (or intermediate events) between any two events in a net work. Critical: Activities, events, or paths which, if delayed, will delay the completion of the project. A project s critical path is understood to mean that sequence of critical activities ( and critical events) that connects the project s start event to its finish event and which cannot be delayed without delaying the project.
Two Approaches are: AON (activity on node) AOA (activity on arrow) AON (activity on node)
As shown in figure 1.1: Example of AON
Explanation of activities: As starting from one side a, b and c has no predecessors (as starting point of the project is a, b, c) other d to j has their predecessors.
As In Figure 1.3: AON Net-Work from Table 1
Explanation of times: As shown in table 1 that two extremes are used, are taken by PM (project manager) as optimistic (time required by an activity 99% equals to a or greater than 99%) and pessimistic (time required by an activity 99% equals to b or 99% less) in between the most likely time exist, as project manager is estimating off and on having results off and on (it may due to past experience or some other related aspects). Note that some managers or workers may feel uncomfortable in making estimations with such level of precisions, on the way we do not deal with this problem Remember that these estimates are an expression of the risk associated with the time required for each activity.
Table 2:
Expected Activity Times (TE), Variance ( ) and Standard Deviation ( )
Activity
a b c d e f g h i j
Expected Time(TE)
20 20 10 15 10 14 4 11 18 8
Variance ( )
4 0 4 25 4 4 0 5.4 28.5 4
Standard Deviation ( )
2 0 2 5 2 2 0 2.32 5.33 2
Determining Time
Taking TE (expected time) along with variance ( network. ) we can map out AON
As in figure1.5: The AON Network from Table 2 showing activity durations and variance
Time is expected and designated to every activity in project map but the question arises is how much time a project takes to complete, means in mapping the highest time taken by an Activity Path as shown in figure j taking 43 days followed by 20 + 15 + 8 so completion time=43 days.
Explanation: From start the ES is on day 0 and EF will be the day an activity takes maximum time/ days to complete. Here we use the word maximum; mean if an activity has more than 2 predecessor than both predecessors should be necessarily completed within their highest range rather than lowest. As e has 2 two predecessors one take 20 other takes 10 days to complete, mean 20 days both activities will be completed. And so on. As in figure 1.5: Showing Network Mapping and Critical Path