Scheron SEPCOS-SCM Stray Current Monitoring System

SEPCOS-SCM Presentation

Scheron SCMS Stray Current Monitoring System Characteristics


Based on potential measure avoiding any interference with the stray current collecting system Continuous monitoring of the tracks potential during operation Representation and archiving of potential values in a central unit Analysis and automatic localization of insulation deficiencies Monitored data available in real time over SCADA Recommended according to EN50122-2:2011

SEPCOS-SCM Stray current principle

Due to insulation of rails the potential of the track-earth is floating (in time and location) Stray current appears in case of insulation deterioration (dirt, premature ageing and wear insufficient maintenance) Corrosion of metallic structure in soil and close of tracks happens

SEPCOS-SCM Potential of rails

A healthy systems presents a specific voltage profile called reference or imprint A deficiency of insulation between the rail and the earth will modify this voltage distribution The track potential can be used to ensure the healthy of the system and determine a modification in behavior of the stray current by comparison with the reference curves
26/08/2011 4

SEPCOS-SCM Comply with specifications

Proposed system is in compliance with BMRCL EP1-CC chapter 18.2.6.6 (taking into account Addendum 1) Proposed system fulfill the request from DDC document chapter 9 (Stray current monitoring) The proposed software will include more functionallity than requested - measurement of the current when the SCD in closed - log file of the SCD closing and taking into account in the analyse

26/08/2011

SEPCOS-SCM Reference values


Monitoring to establish background levels used for the comparison with the measured values
80 60 40 20
U [V]

Maximum of average values monitored

0 -20 -40 -60 -80

Minimum of average values monitored

ST AT IO N ST 1 AT IO N ST 2 AT IO N ST 3 AT IO N ST 4 AT IO N ST 5 AT IO N ST 6 AT IO N ST 7 AT IO N ST 8 AT IO N ST 9 AT IO N ST 10 AT IO N ST 11 AT IO N ST 12 AT IO N ST 13 AT IO N ST 14 AT IO N ST 15 AT IO N 16

26/08/2011

SEPCOS-SCM Potential of rails


Typical characteristic of a track potential in function of time for a metro
40.00

30.00

20.00

U [V]

10.00

0.00

-10.00

-20.00 0 100 200 300 400 500 600

Time [s]

SEPCOS-SCM Architecture

Scheron Sepcos- SCM collects the voltages between the return line and the structure earth via the measuring system integrated in the overvoltage device (SCD) along the tracks. The transmission of the measured values from the SCD to the central unit is done via a communication network: Ethernet, TCP/IP, MODBUS TCP, IEC61850, IEC60870-5-104 and DNP3 Existing network can be used as from the RTU The central unit archives, analyses and depicts the potential of the tracks via an HMI interface executable
8

SEPCOS-SCM Example of communication network

SCADA

RTU

SEPCOS -NG SCD


Short circuiting device) Track (rail) to earth (MET) Measuring voltage

26/08/2011

SEPCOS-SCM Bangalore TSS communication network

STRAY CURRENT Monitoring software

MAIN SCADA (ABB)

IEC 60870-5-104

RTU 560

SCD with Track (Rails) to Earth (MET) voltage measurement


Modb us-TCP Gateway for IEC 61850

SWITCH

IEC 61850
SEPCOS FEEDER SEPCOS FEEDER SEPCOS FEEDER SEPCOS FEEDER

Display

SEPCOS PLC NEGATIVE

Display NEGATIVE LBS RECTIFIER INCOMING

Display

Display

Display

26/08/2011

10

SEPCOS-SCM Bangalore ASS communication network

STRAY CURRENT Monitoring system

MAIN SCADA (ABB)

IEC 60870-5-104

RTU 560

SWITCH

IEC 61850
SCD with Track (Rails) to Earth (MET) voltage measurement

26/08/2011

11

SEPCOS-SCM Central Unit Hardware Software

26/08/2011

12

SEPCOS-SCM Central Unit (in OCC ctrl room) Hardware Specifications

Industrial Computer CPU board Intel Atom Fan-less, HD PCI-Raid Systems SATA 2x250 GB 19 display for table or panel mounting Touchscreen display HMI licence software included IEC60870-5-104 protocol installed (server) Raid Technology: - Dual disk data archive - Data Mirroring

26/08/2011

13

SEPCOS-SCM Central Unit (in OCC ctrl room) Main Technical data
No 1 2 3 description Maximum number of measuring points Communication protocol Frequency of acquisition Data Min. 60 for one system IEC60870-5-104 (for this project) 2 sec Parameterization possible by software: from 2 to 60 min for short-term mode from 1 to 7 days for long-term mode 10 most relevant measurements All points for 16 weeks Mean values saved for 10 years 250 GB (with integrated RAID backup technology) English, French, Spanish

Time lag mean time calculation

5 6

Number of acquisition for the reference profile Number of acquisition (global)

7 8

Total memory size Available languages

26/08/2011

14

SEPCOS-SCM Supervision

Supervision of status of Short Circuiting devices at all stations and giving an alarm if the device has operated.
26/08/2011 15

SEPCOS-SCM Representation instantaneous

possibility to represent the instantaneous values with time window adjustable


16

SEPCOS-SCM Representation in function of time

Possibility to depict the max. and min reference threshold Average values Average values of the absolute Time window adjustable for long (days) and short (hours) analysis Adjustment of calculation step 160 min for short time 17 days for long time

26/08/2011

17

SEPCOS-SCM Representation in function of location

Possibility to depict the max. and min reference threshold Average values Average values of the absolute Time window adjustable for long (days) and short (hours) analysis Adjustment of calculation step 160 min for short time 17 days for long time

26/08/2011

18

SEPCOS-SCM Analysis detection of insulation fault

Above the upper reference

Below the lower reference

Detection of an isolation deficiencies

26/08/2011

19

SEPCOS-SCM Analysis detection of insulation fault


140.00

U [V]
120.00

Rise of the voltage due to the substation out of service.

100.00

80.00

60.00

40.00

20.00

0.00 0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00

-20.00

-40.00

-60.00

Reference in normal operation Substation out

-80.00

The algorithm can differentiate the abnormal change in operating conditions from the rail-to-earth faults because the effects on the line are different.
26/08/2011 20

SEPCOS-SCM Analysis detection of insulation fault


100.00
U[V]

80.00

Decrease of voltage due to the insulation fault.

60.00

40.00

20.00

0.00 0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00

-20.00

-40.00

Reference in normal operation

-60.00

-80.00

Insulation fault

The algorithm can differentiate the abnormal change in operating conditions from the rail-to-earth faults because the effects on the line are different.
26/08/2011 21

SEPCOS-SCM Reference
Stray currents measurement by direct current measuring (SCD): - 1998 Taiwan Taipei Blue & Tucheng Line - 2007 Taiwan Taipei Orange & SX Line - 2008 Singapore CCL - 2000 Iran Tehran TURSC Line 1 HMI interfaces (using same software): - since 2005 Switzerland Basel/Bern/Luzern Tramway - 2010 Germany Leipzig Tramway - since 2005 Belgium Train line - 2011 Venezuela Caracas metro L1 - 2008 Venezuela Barquisimeto trolleybus - 2011 Georgia Train line - 2010 Azerbaijan Baku metro Stray currents measurement by rail-to-earth potential measurement: - since 2007 Iran Tehran Line 3,4 & Isphan metro - 2007 China Beijing L1/L2/L10 - 2009 China Chengdu L1, Xian L1 - 2010 Brazil Sao Paulo Train (CPTM)
26/08/2011 22

SEPCOS-SCM

Benefit for the BMRCL Bangalore Metro


Stray current monitoring in accordance with the actual EN50122-2 standards Data acquisition system already in place (with delivered SCD) Communication layout installed, data acquisition already tested and ability to receive the data at the ASS level confirmed Experience and practice with IEC61850 and IEC60870-5-104 protocol, as well as HMI interfaces Know how in running rail to earth network behaviour Long Experience in Railways stray currents detection Benefit of Secheron specialists in network simulation and calculation

26/08/2011

23

SEPCOS-SCM

Secheron Offer
As a complete DC system provider for BMRCL (including SCD devices) we have necessary expertise in measurement of Stary current monitoring and fully comply the contractual conditions. We are glad to offer 3 years of warantee to give more confidence including visit of our expert every year.