Professional Documents
Culture Documents
IN
RIG
the
GULF OF MEXICO
on APRIL
MDL No
Section
2179
20
2010
Applies to
The Honorable
Judge
Barbier
REBUTTAL EXPERT REPORT OF DR FREDERICK GENE BECK ON WELL DESIGN CONTROL DRILLING AND MONITORING
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
TABLE OF CONTENTS
Executive
Summary
For
II
ResDonsibilitv
The
Well
As The
Held
Majority
Of
The
Parties Experts
Ultimate Contrary
And Exercised Responsibility For The Macondo Well Any BP Is Unsupported Suggestion By By The
Agree BP
Evidence
BP
well
all
held
and
preserved
ultimate
responsibility
for the
design
and
operation
of the
Macondo
to
BPs
ultimate
responsibility
extended
operations
conducted
by
Halliburton
and
Sperry
control
In
exercising
over
the
design
and
operation
of the
Macondo
well
BP
repeatedly 13
prioritized cost
Ill
Practice
Failures
BPs
Expert
Is
Wrong
In
To So
16
Suggest
That
BP Complied With
Regulations Written
Its
MMS
And
Regulations Doing
BP
Violated
Federal
Failed
to Follow
Own
30
the
Practices
BP
zone
violated
C.F.R
250.421 hydrocarbon
of
when
it
disregarded
with
M57B
to top
bearing 16
respect
cement
BP
violated
30 C.F.R
safe
250.427 margin
when
it
failed
to maintain
drilling
17
MMS
test
regulations
specifically
250.401
pressure the 19
required
BP
well
to
conduct
negative
as
it
prepared
to temporarily
abandon
Macondo
IV
The
Negative
Pressure Test
As Other
Results
Parties
Experts
Caused
Of
The The To
Blowout
Negative
The
Pressure
And
Proceeding
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
Significantly
Underbalance
Integrity
The
Well
Without
First
Ensuring
Well
20 By Experts Of
For
The
Float
Collar With
As
Explained Sole
The
Other
Parties
The To The
Exception
BP And
Collar
Weatherford
BP
Failed
Float
To
Shut
Its
Valves
Track
Without
Damage
Contrary
Allowing
Occur
For
Any
Suggestion
Is
Experts
BP
And
23
Weatherford
Unsupported
By The Evidence
VI
Unnecessary Heightened
Risks
Alert
In
BP Should
Conducting
Prior
Have The
Been
On
Test
Negative
Pressure Test
Because
To That
Critical
BP Knowingly Designed Drilled And Operated The Macondo Well In An Unnecessarily Risky Manner
For Financial
Reasons
to
27
safe
BP
failed
provide
drilling
margin
that
instead
drilling
an
unstable
well
unnecessarily
necessitated
lower
density
27
BP
zone
incorrectly
suggests
that
it
was
have
free
to
ignore
the
uppermost
it
hydrocarbon-bearing not
because
from
may
royalty
been
This
producible
suggestion
standpoint
shows
29
BP
unreasonably
disregarded
of at least
likely
recommendation
centralizers channeling
twenty-one
causing
thereby
30 chose
risk
BP
imprudently the
long
string
design 34
increasing
of
cement
flow
contamination
fracturing and
annular
BP
unreasonably up
or
to
chose
not
to
circulate
bottoms
adequately
condition increasing
the the
wellbore for
risk
cement placement
of channeling
and contamination
35
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
BP unreasonably
log
canceled
the
cement bond
37
previously scheduled
with Schlumberger
BP chose
plan VII
risky
temporary
abandonment
38
As Other
Is
Parties
Experts
BP
Failure
Not
Halliburton
Responsible
For
Agree Any
42
Of The
Isolation
Primary
Cement Job
To Achieve
Zonal
VIII
Cement
Is
Remediation
The
Of
Only
Failed
Reasonably
Foreseeable Consequence
Cement Job
Did
Cement
Because
Repair
It
Job Which
BP
Not Allow Of
Its
For
Disregarded
The
Results
Negative
Pressure Test
Sperry
final
44
acted reasonably while
IX
Mudloaaina
monitoring the
displacement mudlogger
45
not the
The
crew
Sperry
was
in
same
drilling
position
as
BP and
the
Transocean
46
standpipe
test
is
The
pressure
at best
increase subtle
during
the
sheen
indicator
of well
only
in
50
properly
monitored not
all
him and
would
have
been
expected
to
52
reasonably
that set
Joe
pit
Keith or
could pressure
kick
not have
flow have 54
alarms
would
indicated
Sperry
or
had no say
in
how
the
rig
was plumbed
be run supported
by
how
the displacement
was
to
55
BPs
expert
makes
claims
not
the surviving
mudlogging
data
56 58
Summary
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
LIST
OF FIGURES
shows
that
Figure
BPs OLGAs
was
simulation by the
most
of the
kick
volume
not detectible
mudlogger
interpreted incorrectly
Figure
Sperry
mudlogging data
by
BPs expert
Mr Grace
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
Executive
Summary
and
conclusions
in in
My
opinions
regard
to the
Macondo
parties
well
blowout have
in
are thoroughly
discussed
my October 17 2011
by the opinions support
Opening
Report
involved other
the other
this
and
ascertained
often
that
expressed
by
the
parties
my own opinions which have not changed disagree with certain experts who present opinions that run contrary to my own group comprised mostly of experts retained by BP
most agree
with
and
and
Weatherford addresses
and
find
their suggestions
unsubstantiated
This
rebuttal
report
summarizes
my key
the
this
exception matter
of
certain
in
experts
retained
that
by held
In
BP
and
the
experts
are
for
agreement
BP
and and
exercised
that
in
responsibility
the
Macondo
first
well
exercising over
responsibility
BP
repeatedly
prioritized
cost policy
time
safety
disregard
of
BPs
dollar
more
consistent
with
BPs every
to
mantra
include
Risk-increasing
for
decisions decision
made
to
by
BP
final
save
time and
money
to
example
of
BPs
disregard
Halliburtons production
centralizers
recommendation
casing avoid
In
of placing at least
21 centralizers
on the use
to
the another
of
risk
channeling
to
only
instead
example
at
BP
that
disregard
Halliburtons
circulation
recommendation
prior to
conducting
least
full
bottoms
gelling of
up
pumping
from the
the
cement
so as
so
to
debris the
and
risk
mud
were and
would
be
removed
and
well
reduce
cement
contamination
channeling proceeded
that
And
with
as
operations
on
the
well
concluding
BP
displacement
the
rig
procedure
simultaneous operations
ability
undermined
crews and
kick
mudloggers
to accurately
In prioritizing
for signs of
and
time
ahead
of
safety
as other experts
have
recognized
retained by
BP BP
violated
several
to
MMS
regulations
different
One
of
the
experts
attempts the
suggesting
that
cement
requirements
that
by for example MMS regulations did not require BP to meet top of for the uppermost hydrocarbon zone the M57B
paint picture
zone because
standpoint
zone
may
the
not
have
been
producible
significant
from safety
royalty risk
even
though
the
test
zone
presented
did
and
suggesting negative
that
MMS
do
regulations
its
not
require
BP
to
conduct procedure
test
pressure the
during not
temporary
the
abandonment
because
regulations
use
term negative
pressure
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
expressly even
tested to ensure
further
though
that
it
the
is
regulations
control
clearly at
all
require
that
the
well
be
under
times
The same BP
otherwise
the the
expert
suggests INC
that
despite
drilling
evidence margin
establishing simply
to
BP must
did
have
issue
maintained
safe incident
because
MMS
not
of
an
of
non-compliance
by
BP
during
course
drilling
These
suggestions parties
BPs
The
conclusion
of
other
that
experts
appear caused
failed
to
uniformly explained
agree
with
my
BP and Transocean
pressure the
well test
recklessly
away
by
the
results
the
negative
and
the
the
blowout
significantly
underbalancing time
it
despite
negative
pressure
test
that
At the
it
conducted and
in
the
negative
pressure well
test
BP was
its
well-aware
had
designed
decisions
high-alert
drilled
high-risk
Given
multiple
risk-increasing
regard
to well
design
and operations
caution
BP
should
have
the
been
on
and
test
exercising Instead
extreme
when
at the
conducting other
negative
pressure
part
BPs
conduct
was
extreme
it
when
in
based
upon
explanations
that test
provided the
well
by
Transocean
In
recklessly
away
with
its
indications of the
disregard
results
my
opinion
BPs
move
and
by
its
desire to
temporary abandonment
additional
the
to
well
without
well
incurring
cost
or expending
time
ensure
integrity
control
BPs
negative
acknowledge blowout
the
results
of the
safety
critical
pressure experts
to the that
Nevertheless
in
even
though
results
BP
of
and
the
its
acknowledge blowout
BP
did
fact
misinterpret
the
negative
pressure
for the
test certain
to
experts
retained
by
BP
attempt
to shift
some blame
Halliburtons
with to
cement
work
and
Sperrys
mudlogging operations
disagree attempt
different
BPs
The
work
offer
experts
who
criticize
cement
that
drastically
likely
opinions
none
of
which
In
in
establish
Halliburton
caused caused
the
the
primary
cement
job to
fail
my opinion BP
regard
to
not
Halliburton
of
any
problems
that
existed
the
for
light
performance
cement
downhole
centralize
BP and
the well
BP
alone
decided
relatively
example
weight forego
at least
to
inadequately
leave
drilling
mud
in
the rathole
circulation
adopt
casing
not wait
full
bottoms up
the
prior to of these
cementing
decisions
fail
and
24 hours on the
increased the
float likely
cement Each
risk
individually
and
together convert
that
the
cement
it
job would
BPs
risk
failure to
collar
without
damaging
added
with
to
that
making process
it
even
more
that there
would
be problems
the cementing
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
Furthermore as appear
to
number
the
of experts
including
one
of
of
BPs
failed
experts
primary
to the of
recognize
is
reasonably
repair
foreseeable
result
cement
extent
failed
jobnot Here however cement remediation such was needed BPs disregard any
job pressure
test
cement
blowout
the
negative
precluded
with
its
BP
riser
instead
moved
it
forward
any opportunity for cement repair unsafe temporary abandonment and have
procedure whereby
to
underbalanced
the well
opened up
designed
in
the
well
and
dangerous
plan
hydrocarbons
that
BP
could
left
temporary
state
abandonment
at
all in
would
have
in
instead
the well
balanced
dangerous
next well
to criticize with kick
hydrocarbonsbut
BP
failed to
so
haste to
move on who
for
to the
The
the Sperry
experts
attempt together
improperly
group
the
that
drilling
crew
when
they
kick
assigning Sperry
missing
the
to
the
blowout
the
Although
well
for
and
each
played
role situations
final
monitoring
were
presented
vastly
different
and
opportunities
detection
and
response
during the
the
displacement
Whereas
of
the
Transocean
drilling
drilling
crew and
the Sperry
operations
ongoing
information
limited
that
BP and Transocean
night of the
conveyed
him which
was
exceedingly
on the
Incident displacement
During
the
final
BP and Transocean
to
were
complacent
and
M-l
failed to
communicate key
decisions
pit
information
that
Sperry
to
BP
Transocean and
primary
kick
SWACO made
including
blinded
Sperry
several
indicators
volume
increase
gas
concentration
and
flow-out
flow-
data
out
BP and Transocean
separate
If
access
they
to critical did
Transocean
that
not
make
most
test
Sperry
BP and
in
Transocean
in
had
recognized
after
what sheen
was
substantial
increase
flow-out flow-out
the the
by an increase
data
blowout could
Sperry not
have no
been
prevented
opportunity the ensuing experts
In
BP and Transocean
kick
had have
clear
to
detect
the
and
thus
could
prevented
Several
to criticize
Sperry
to
execute
the
displacement as
Sperry
straightforward
misplaced conducted
final
had
no no
control role
in
over
manner This criticism is how the displacement was amending or approving the BP and Transocean were
M-l
Sperry
played
drafting both by
displacement
the
procedures
whereas
plan
familiar with
displacement
drafted
SWACO
and
approved
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
by
BP
in
BP and Transocean
complicate the
well
knew
at
the
approved
displacement
Sperry
well
procedure sensor
to
would
late
monitoring
by bypassing time
the the
flow-out
likely
displacement
available
when
in
was
be
underbalanced
the
well
Nevertheless
to
the
Sperry
mudlogger accurately
real
monitored
data
him which
well forth control
in
time
contained
no
clear
indications
In
of the
impending
situation
conclusion as set
that
my Opening
Report and
are
herein
it
is
my
opinion
BP and
to
responsible
Macondo
blame support
II
well
consequences
is
thereof
Any
attempt
to
Halliburton
Sperry
improper
and
without
evidentiary
Well As The Majority Of The Parties Experts Agree BP Held And Exercised Ultimate Responsibility For The Macondo Well Any Contrary Suggestion By BP Is Unsupported By The Evidence
Responsibility
For The
BP
held
design
and preserved ultimate responsibility for the and operation of the Macondo well BPs ultimate extended
to
all
operations
conducted by
and Sperry
retained by
BP suggest
disagree
that
that
BP was
not
in
ultimately
for
well
operations
dictates
As
explained
Report
industry of
all
custom
the
well
operator
ownership course
well
procedures
drilling
devices
processes
It
the
of conducting
operations.1
all
is
of the
operations procedures
and
well
meet
or exceed
of parties
all
applicable
in
and
safety
standards
fact2
The
majority
involved
this
recognize
this
including
BP
itself
BPs written
practices
make
clear
Expert
Report
of
Dr
Frederick
Gene
at
Beck
on
Well
Design
Control
Drilling
and
Monitoring
hereinafter Rule
Beck Report
11 20-22
See e.g
20
2010
by the Basis
Opinion
Plaintiffs
M-I
26 Report on BPs Macondo Blowout Re Oil Spill Commencing April Transocean Horizon in the Gulf of Mexico Rig Deepwater Expert of Opinion and Discussion Pritchard Analysis prepared by David
Oil
8/26/2011
hereinafter
Pritchard
Report
at
27
Expert Report
Prepared
at
for 1of
LLC
by George
of
Expert Report
P.E
10/25/2011 10/17/2011
hereinafter
at
Medley Report
Drilling
MOEX
7-8 Expert
Report
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
that at
is all
BP
intends to control
all
aspects
of well
design
in
and
drilling
operations
that
times3 and
BP witnesses have
confirmed
all
their depositions
BP
and conducting
is
well
operations.4
in
BPs
performed
Halliburton
ultimate
authority
particularly Halliburton
clear
regard
to
work
of
by
BPs
The
Unit
contractors
and
for
Sperry
of
division
April
16 2009
Well
Contract Services
Gulf
Mexico
Strategic
Performance Production
Offshore
Between Services
Halliburton
BP
Inc
Exploration hereinafter
and
the
Inc
and
Halliburton
Energy
that
HAL/BP
related
provides provide
and
Sperry and
as
BP
been
all
with
recommendations
to
opinions
the
work
they states
have
that
hired
perform
The
HAL/BP
Agreement
provided by
clearly
recommendations
shall
and/or by
inferred
predictions
Halliburton
and
Sperry
be received
as opinions
by from
only and
no warranty
expressed
or implied shall be
Roger Vernon
Anadarko
10/17/2011
at
Bureau
of
Ocean
at
Oil
Energy
Chief
and EnforcementReport Regarding the Causes Management Regulation JIT 20 2010 Macondo Well Blowout 9/14/2011 hereinafter Report Counsels
Offshore
of the April
Report
Drilling
National
Commission
on the BP
at
Deepwater
Horizon
Spill
and
2011
hereinafter
CCR
30 Transocean
hereinafter
Macondo
Well
Incident
Transocean
at
Investigation
Transocean
Report
Vol
20
4See
Wellsite
e.g
Sepulvado
Depo
has the
5/11/2011
final
at
20713-17
testimony by
6/2/2011
at
BP
Senior
Leader
BP
is
President
that
my
perspective
Lacy Depo and Completions Gulf of Mexico that the operator has the ultimate to responsibility
say
5197-52011
of Drilling
make
or
the
final
decision
and
it
is
not
uncommon
Guide
to
make
5/9/2011
is
decision counter
at
to
an advice testimony
disagreement
on the
day
that
Depo
15722-1 5916
for the well
by
BP
Wells
Team
Leader
MMS Depo
and
regulations
Waltz
that
responsible
pursuant
to
at
7132-19
testimony by
for well
BP
Drilling
Engineer
Team
Leader
at
BP was
by
responsible
4/22/2011
57118-5727
testimony
same
BP
Vice
for
OBryan
Depo
of
7/15/2011
Drilling
60424-60515
President operations
regarding Breazeale
well
site
BPs
various 5/16/2011
responsibilities at
on
the
Macondo
Leader
is
well
the
Depo
leader
is
3746-9
all
testimony by
operations
BP
Wellsite
that
BP
responsible
for at
rig
insofar
as the by
well
concerned
Corser
Depo
that
2/10/2011
15120-1523
testimony
BP
Drilling-Engineering
Manager
BPs
for operations
on the rig
10
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
such
recommendations..
The
contractual
provision
in
question
reads
as
follows
2.3 COIJTRACTOR may give COMPANY
the benelit of
its
pidgment
either
iasd
written
irpr1nQ
or
mforrnaton
niitenal
an
or
fliakin
of
jO4flifldtiQflS
amount
of
or type
oilfield
wvice
01 shall
to
be
provided
by
or
oral
prediction predictions
ruults
riarwithstancling
the foregoing
II
andlor
received be
and
no
warratdy
expressed or
in
or impEed of the
shaD
as opinions
front
such
icammnctioi
of
and
view
rripracticability reliance
knowledge
th
many
variable
the
on
assumptions supporting
which
oiftield
ano
by others
inJreAc.s
of
the
necessity
reIyin
m.asurernent on facts
and and
service3 provided
Depo
industry
Ex 6320
custom
at
BP-HZN-MBI-00022200
of the
HAL/BP
Agreement
provides
of
all
29.3
what
drilling
already
Management
of
Service
MMS now
Energy
looks
reorganized
as the Bureau
Ocean The
Management and
to
the
Safety
and
Environmental
party for the
in is
Enforcement
the
well
well
MMS
regulations
relating clearly
the
drilling
of
wells
that
were and
it
on
directed at the well operator define the well Despite plan and
industry
2010
are
required to
plan.6
seek permission
drill
as
specified
in
that
custom
BPs
for
written
practices
testimony
by
BPs
that
witnesses the
MMS
regulations
establishing
BP was Macondo
exercised
ultimately
procedures
that
undertaken
Halliburton
on
held
the
well
some
for
BPs
over
experts
certain
suggest
well
and
Fred
ultimate
control
operations
BPs
stable
expert
Sabins states
design
example
of
that
Halliburton
to
had
sole responsibility
for the
and
testing
the
foam cement
ensure
foam cement
Depo Ex 6320
at
BP-HZN-MBI-000222000
HAL/BP
Agreement
29.3
emphasis
added
See e.g 30 C.F.R
as having
control or
250.105
Operator means
of operations
the
person
the
lessees
or of the
designates thereof
or
management
lessee
the
on the leased
designated
area agent
portion
An
the
operator holder
may be
of
MMS-approved
rights et
lessees
oil
the
operating
under
an
MMS-approved
forth
operating
for
rights
assignment
drilling
30 C.F.R
in
250.400
Outer
seq
setting
requirements
and
gas
operations
the
Continental
Shelf
11
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
composition.7 responsible
failure of the for
Mr
cement
Sabins
further
suggests and
that
Halliburton
was
solely
execution
job.8
monitoring
reporting
on
the
success
or
disagree
direction including of
Halliburton
as
the
BPs
in
contractor regard
to
acted
all
solely
at
the
BP.9
BP
called
shots
drilling
operations any
than
of
cementing
operations
and
did
was
in
free
to
disregard
Halliburtons
recommendations
This conclusion
is
and
by
in
fact
do so on
more
one
occasion.1
States
of
consistent the
with
of the
United
America team
As
explained
USAs
Glen
Benge
BP
of the
wells
decision both
the final cementing They makers and were empowered to accept or reject the advice
was well-versed
were
BPs
of
internal the
cementing
well
to
expert
the
and
Halliburton
wells
Throughout demonstrated
drilling
Macondo
with lack
BP
team
and
considerable
control
respect
of
cementing
control
design
operations.11
of the
drilling
Halliburtons operations
is
ultimate
over
any
portion
with
industry to
custom
reservoir
dictating
liability
that
as
well
general operator
is in
rule contractors
exposed
The
here
best
in
BP
controls to to
the ownership
and development
of the well
its
and
the not
position position
mitigate
or eliminate risks
whereas
contractors risks
are
be
aware
ofmuch
less
evaluatethose
Thus
Evaluation
of
the
Cementing
on
the
7/8
Production 10/17/2011
at
Casing
String
on the
Macondo Well
at 10
Expert Report
by Fred
Sabins
Report
hereinafter
Sabins
Report
also
Sabins
30 47
Sabins
12 33 36 81
See
Leader
e.g
Sepulvado
Depo
sir
3/10/2011
at
2875-14
to
okay from
involved
it
around
Yes
about
And
well
site
understand leader
there
may
be
other parties
its
but
BP
needs approval
with
from
people
in
Houston
10
his people
cement
Yes
sir.
BP
did
in
fact
disregard
Halliburtons
recommendations
that at least
for the
Macondo
were
well
BP
to
ignored achieve
Halliburtons zonal
its
recommendation and
avoid
21
well
centralizers
needed warning
presented Expert
isolation
channeling
as
as
Halliburtons
well
based on
industry-recognized
SEVERE
Report
gas
flow
potential
BPs
design
of Glen
Benge
in
on Behalf
of
the United
States
8/26/2011
hereinafter
Benge
Report emphasis
original
12
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
contractors stands
well
if
are
not
expected
to
assume
operator
risk
its
The
well
operator
in
to
make
millions
or
to
billions
investment
in
the are
the
drilling
operation
proves successful
their written well
Contractors
the
contrast
compensated
regardless equation
is
pursuant
well
operator
of
whether
the
proves
be
the
profitable
right
The
risk/reward upside
for the
simple
the well
operator
it
holds
to the
potential
the
biggest
operator to contractors
financial
possible
from
financial
standpoint
the
reservoir
the
in
biggest risk
it
Because
the
the
biggest
to
reward
makes
no sense
from
result
standpoint
contractor
share
As
as
contractor perform
such as work
Halliburton
or Sperry customarily
of well
would such
not agree to
any
that
for or
on
the
behalf
operator
BP
if
by
making
agreement
indemnity
this
contractor
of the
reservoir consistent
In
The
with
clause
industry
custom.12
that Halliburton with ultimately controlled
sum
job
any
suggestion
the
cement
practices
cannot
be
by
reconciled
industry
custom
BPs
written
testimony
or the
BPs
BP
witnesses
freely
the
HAL/BP Agreement
Halliburtons held advice
or exercised
MMS
regulations than
fact
that
ignored
that
on more
ultimate
one
occasion any
Any
aspect
suggestion
of
drilling
Sperry
control
over
for the
and
well
completion
operations
controlled
would
be
flawed
all
operations
operator
and
directed
In
Macondo
safety
and operation of the well BP repeatedly prioritized cost and time over
over the design
My
Practice
Opening
Report and
discussed
BPs
Drilling
and
Well
Operations
DWOP
associated
written
Engineering
Technical
for designing
Practices
ETP5
standard
which
drilling
together
provide
framework
recognizes
that
and
conducting
operations.13
Drilling
BPs DWOP
and
to high
Good
drilled
Practices
dictates
many BP wells As
of the
industry
should
be
in
designed
compliance
expert
and completed
relevant laws
and consistent
standards
and
with
12
all
and
regulations.14
explained
by
BPs 19
at
BP-HZN-MBI-00022184-88
HAL/BP
Agreement
13
at at
BP-HZN-BLY00034512 BP-HZN-BLY00034512
14
DWOP DWOP
1.2 1.2
13
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
Morris safety
Burch
BP
considers
the
DWOP
to
be
critical
to
conforming
of
to
management system and achieving BPs goals harm to people and no damage to the environment.15
Significantly
no accidents no
BP
states
well
in
DWOP
operations as
2.3
that
when
planning should
and be
undertaking
prioritized Installation
drilling
and
of
safety
concerns
in
order
importance and
Personnel
Environment
The
Reservoir
that
Integrity
Well
Delivery.16
BPs
written
practices
first
thus
state
safety
personnel
environment
should the
should
be
prioritized
and time
to production written
well delivery
including
be
prioritized last
first
BPs
well
practices
if
safety
directive
of
DWOP
and
for
effective
followed
failed
This
to
was
on the
Macondo
Take
where
BP
repeatedly
comply
own
standards
repeatedly
prioritized time
and
money above
the confirmed
safety
concerns.17
log.18
example
BPs
decision
log
to cancel
Although met
cement
planned
issues
bond
would
have
the
top
or
of
cement
targets
and
determined
requiring
whether
channeling
other
produced
log
result prior to
in
remediation
BP canceled
of the
the
cement bond
that
it
temporary abandonment
its
well
BP suggests
test
was
justified
decision
to to
cancel
the
planned
Halliburton
did
not not
indicate
need
conduct
cement
of
bond
disagree
for testing
BP
the
Halliburton
of the
integrity
and
responsible
the
risk-increasing
decision
not to conduct
in
cement bond
failed to follow
time and
money and
doing
so
safety
BPs
conduct discussed conduct
time
failure to
make
in
safety
its
first
priority
in
whether Rather
pattern
to
cement
at length
bond
log
was
not
an
isolated
as
of
on
the
BP engaged
conduct
prioritized cost
and
ahead
of safety dollar
concerns
This
pattern
BPs every
15
counts
philosophy
and
Report
16
of Morris
Burch
BP
10/17/2011
hereinafter
Report
at
22
Depo Ex
6121
at
at
BP-HZN-BLY00034516
DWOP
2.3
17
23-31 87-88
18
at
19
Report
BP
at
78-80
14
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
high-risk
and
dangerous
well
that
was
described
by
BPs own
engineers
as
nightmare.2
BPs
cost
attributes
expert
at
Dr
the
Kathleen
Sutcliffe of
claims
that that
savings
of
expense
safety
safety
and
strong
culture.21
Similarly
BPs
and
expert
Mr
Burch
opines
that
BPs
the
risk-management
during the
procedures
of
were
applied
planning
design
the
Macondo
pattern of
reasons There
risk
discussed
is in
throughout
in
my Opening money
Report conduct
disagree
that
no question
that
BP engaged
time and the
increased
parties
Other
share on
my opinion
drilling
rig
example
Chief
points
Counsels
to multiple well
Report observes
specific
that
time
money
at
and
decisions saving
by
BP that
increased
risk
the
Macondo
behavior
while
potentially
time.23
Dr
William
Gale
experts
in
retained increased
cite
by the
risk
Plaintiffs
in
conclude
that
BPs
and
resulted
proportion
amount
of time
Macondo well decisions that increased risk but saved time and money.24 And David Pritchard another expert retained by the Plaintiffs found that the final week of the well BP made ten 10
to
exemplary
key
choices and
to
which save
the
were
designed
in
to
save
rig
time costing
it
$1000000
taken
in
day
money
risk
additional
increased
that
of
blowout.25
risk
ways Thus
by
These
decisions
together concluding
of
am
far from
alone
BP
repeatedly
increased
prioritizing
time and
money ahead
safety concerns
20
at
31-101
Sutcliffe
Depo
Ph.D
Ex 126
at
C0N67
82
21
BP
at
22
Burch
Report
at
BP
at vi
BP
at
36-44
23
CCR
245-46
citing
Amendment 126763
Drilling
Contract
No 980249
BP-HZN-BLY 269181
and Guide
125444
Interview
24
BP-HZN-MBI Sims 19
on January
BP-HZN-MBI 2011
225981
BP-HZN-MBI
HAL_10648
interview
February
BP-HZN-CEC22433
2011
BPs
Deepwater Gale
Horizon
Rule
26
Report
Macondo
Blowout
Prepared
by
Dr
Robert
Bea and
Dr
William
Jr
8/26/2011
hereinafter
Bea-Gale Report
BP
25
at xx-xxi
Pritchard
Report
Plaintiffs
at
17-18
15
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
Ill
Practice
Failures
Complied With
Regulations Practices
And
Doing So
Failed
to Follow
Its
Own
Written
BPs
the
expert
Chuck Schoennagel
at least
maintains
MMS
regulatory
BP Macondo
that
fully
complied
with
well.26
disagree
BPs
and
conduct
violated
250.421 30 C.F.R
250.427
30 C.F.R
250.401
violated
BP
30 C.F.R
250.421
when
it
disregarded
the
to
the
MMS
the
regulation
at
30 so
C.F.R
that the
casing
500
above
uppermost
that
hydrocarbon-bearing
misidentified well
zone
the
My
Opening
Report
explained
BP
the
uppermost
highest
hydrocarbon-bearing hydrocarbon-bearing
zone zone
in
the
Macondo
by
claiming
17803 feet even zone was actually much higher though the uppermost hydrocarbon-bearing at 17467 feet the M57B Because BP failed to account for the sand M57B zone BPs designed the top of cement to be at only 17300 feet well plan consequently was designed to place only 167 feet of cement over
located
at approximately
it
was
the
uppermost
27
hydrocarbon-bearing
zone
in
violation
of
30
C.F.R
250.421
BPs
expert
Chuck Schoennagel
because
the the
suggests zone
that
BP
did
this
MMS
at this
regulation
M57B
notes
does
not
as
arrive
MMS
regulatory
regime.28
To
Mr
Schoennagel
that the
MMS
and meets
forth
regulations
do not
that
expressly
hydrocarbon-bearing
zone
that set
reasons
the
in
hydrocarbon-bearing
for
zone must be
royalty
zone
requirements
producibility
from then
standpoint
that
30
C.F.R
not
250.115-116
He
of
concludes
because
the
26
Expert
Report
Chuck
Schoennagel
hereinafter
27
Schoennagel
at
Report
BP
L.L.C at 19-28
MMS
Regulatory
10/17/2011
47-50
28
Report
BP
at
27
16
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
have zone
been
that
producible
in
the
in
royalty
context
with
it
not
be
compliance Although
BPs
expressly the
well industry
wrong
the
it
MMS
is
regulations
do
not
in
define hydrocarbon-bearing
that
zone
seen
at
uniformly understood
feet of
is in
the gas-bearing
zone
17467
volume
the
Macondo
to
In
would
be capable
of delivering
significant
hydrocarbons
fact
the wellbore
i.e hydrocarbon-bearing
of to
No
has
definition
needed
am
not
aware
any
operator
that
or
would
that
define
hydrocarbonfrom
bearing
royalty
testified
zone
that
be
zones
standpoint
if
Indeed
by
asked
gas
bearing
and
feet
capable above
flow
and
asking
you
whether
need
to
cement 500
satisfy
the
MMS
based
that she would have advised them that they had to More important BPs suggestion that an regulation.3
avoid
operator formation
can
selectively
cementing under
safety not
of
hydrocarbon 30
bearing
on
its
producibility
for well
C.F.R
250.115-116
regulation
in
shows
question
complete
disregard
is
The
royalty reflection
MMS
of
250.421
honor
directed suggestion
first
at safety
is
considerations
Mr
Schonnagels
failure to
contrary
its
another
BPs
continuing
safety
policy casing
at least
BP was
that
required
to set the
and 500
design
feet
in
the
top
of
cement so
uppermost
well
the
casing
was cemented
zone
above
the
the
hydrocarbon-bearing
violated
i.e
the
M57B
do
layer
Macondo
BP
250.421
when
it
failed to
so when
it
BP
violated
drilling
30 C.F.R
250.427
failed
to maintain
safe
Section
related drilling to
margin
of
250.427
drilling
the
MMS
regulations
sets
forth
requirements
that
in
safe
margins
the
Section safest
250.427b
drilling
requires
you
must
maintain
margin
identified
the
approved
this
APD
margin you
the
for Permit
to Drill
drilling
maintain the
safe
must suspend
in
and
remedy
situation
drilling
As
explained
in
margin
safe my Opening Report BP failed to provide Macondo well BPs well design and drilling resulted
29
Schoennagel Douglas
Report
BP
at
27
at
30
Depo
10/11/2011
2672-15
17
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
in
little
or no
to
drilling
margin
its
in
the wellbore
drilling
and
measures
30 C.F.R
remedy
unsafe
margin.31
BP did As
not take
result
available
violated
BP
250.427b.32
United expert
to
The
issue
Its
States
of
Justice
that
agrees
with
me
the
on
this
Dr Alan
opines
multiple
drilling
occasions
BP
failed
maintain
margin under
safe
while
Macondo
well.33
Dr Huffman
concludes
that
his
interpretation
of the
MMS
have
regulations
BPs
failure to maintain
drilling
margin
violated
not only
250.401
opinions
with
250.427a
drilling
and
250.428a.34 agree
with
on the and
margin and
are
consistent
support
my
conclusions
him that BP
as
had
or no
remaining
drilling
margin
and
that
the
Macondo
well
drilled
by
BP was
dangerously
that
it
unstable
with the
BP suggests
safe
drilling
complied
MMS
of
regulations
relating
to
margins because
relating to safe
no
to
INCs
non-compliance
were
issued well.35
to
BP
drilling
disagree discussed
forth
in
BP
above
failed
margin as
well
reasons
and
in
my Opening
expert
well
Report and
the
as
the
of
reasons set
Dr Huffmans
the
report
is
non-issuance
of drilling the
BP
its
was
required
to
maintain
to
if
safest 0.5
drilling
margin
safe
identified
in
Application
for Permit
drilling
Drill
i.e
ppg absent
maintain
that
course
of
and
it
could
not
operations
and
remedy
the situation
BP
repeatedly
violated
250.427b
31
at
31-36 31-36
of
32
at
Report
Dr
Alan
Huffman
Submitted
on
Behalf
of
at
the
United
States
Department
of Justice
8/26/2011
hereinafter
Huffman Report
USA at
Report
filed
BP
it
at
23-24
that
Depo Ex 4021
0.5
BP
represented
its
to the
MMS
and
ppg margin
between
mud
weight
fracture
drilling
the
Macondo
0.5
well
BP
sought
but
at
in
and received
no case did
three waivers
MMS
to
with
less
than
ppg margin
BP
request
to less
than
0.3
ppg
USA
16-21
18
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
when
it
failed to
do
so
250.401 required BP
to to
MMS
regulations specifically
conduct
BPs
at
expert
Mr
1721
Schoennagel
through not
suggests
that
because
the
regulations Temporarily
test
30
C.F.R
30
C.F.R
that
1723 well
of
its
it
covering
Abandoned
conducted conduct procedure
expressly
Wells
do
require
negative
pressure
be
to
when
on
was
not
required
negative
April
as
part
20
2010
in
disagree
pressure test
Although
the
do
not
require
negative
MMS
wells the
regime
well at
all
does contain
operator
to
such
requirement
250.401
to
take necessary precautions times and as discussed below in the necessary precautions
included
keep
of
case
Macondo
test successful
such
negative
pressure
As discussed
pressure
test
in
my Opening
the
it
Report
of the
because
well
negative
that
establishes
ability
is
conditions
run
in
would
normally induce
prior to
flow
the
most
critical
operator negative
removal
test
of the
blowout
preventer.38
Thus
this
in
my
pressure
was
necessary precaution
itself
for
its
keeping
recognizes
own
fact
test
written barriers
independently
to the
pressure
seafloor.39
tested
In
place
along
any
potential
flow path
of
its
had
BP
all
properly
interpreted
the
results of the
negative well
it
pressure
during
that
temporary abandonment
of
its
Macondo
of the
would
have
known
test
expected
barriers
if
for
one
potential
had
failed.4
On
to
the
its
other
hand
BP had
had
not conducted
the
pressure
during
temporary abandonment
it
procedure
as
it
was
not
required
do
would
have
no chance
by
of discovering
that failure
Accordingly
pressure
test
believe that
any suggestion
BPs
expert
that
negative
Schoennagel
38
Report
at
BP
at
25
92
91-92
citing
at
Depo
Ex 6121
at
BP-HZN-BLY00034588
Depo
Ex
184
40
at
2-3
at
Beck Report
93
19
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
during temporary
control
In
is
abandonment
was
not
necessary precaution
for well
disingenuous
in
sum
while
in
my
opinion the
regime above
operating
the
MMS
regulatory
reasons
at least
discussed 30 C.F.R
in
and
my Opening
foregoing
Report
BPs
conduct
violated
250.421 30 C.F.R
violating
its
250.401
Additionally
2.2 shall
the
regulations
BP
of
DWOP
which
provides
in
that
drilling
and
all
operations
be and
planned
and
performed
compliance
with
applicable
legislation
regulations.41
IV
The Negative Pressure Test As Other Parties Experts Agree BP And Transocean Caused The Blowout By Disregarding The
Results Of The Negative
Significantly Integrity
All
Pressure Test
And Proceeding
First
To
Ensuring Well
experts
addressing
the
results
of
the
negative
to
pressure the
test
appear
pressure
to
agree
test
that
BP and Transocean
success42 and
in
were wrong
deem
negative
BP
and
Transocean
expert
previously
that
acknowledged
this
their public
reports.43
No
suggests
BP
41
Depo Ex
6121
at
BP-HZN-BLY00034516
of
DWOP
Grace
should
not
2.2
10/17/2011 hereinafter
42
Expert Report
on Behalf
believe
BP
Robert Test
P.E
Grace
Report
Expert
at
17
of
the Negative
Barnhill
have
been declared 32
success
Control negative Expert
at
Report
Calvin
Macondo
Well
Engineering
Barnhill
integrity
Operations
and Well
Response
testing
9/23/2011
that
revealed
of
the
Transocean Macondo
test
hereinafter lacked
and
Report was
at
The
not
secure
Report 12 Report
test
David negative
Calvert
10/14/2011
pressure
Calvert
Report
of J.J
Azar
Ph.D
BP
by
hereinafter
was
misinterpreted
everyone
Bourgoyne
hard to
of
Adam
Report
of
Bourgoyne
of
10/17/2011 negative
BP
pressure
barrier
hereinafter
test
is
Report
62 the
misinterpretation
the
extremely
McCormack
bottomhole should
not
10/14/2011
Weatherford
never
hereinafter
Gregory
at 21
Report
The
test
was
M-I
at
23
negative
BPs
April
Deepwater
Accident
at
Report
hereinafter
Interview
Bly of
10 31 Transocean
30
citing
BP
Investigation
Team
27 2010
BP-HZN-MB100021406-19
Inc
Hydraulic
Data
of
Engineering
Services
Analysis
2010
Prior to
20
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
and
Transocean
the
test to
were
and
correct
that
in
concluding
that
the
Macondo
thus
well
had
in
passed
BP
and
Transocean
were
justified
proceeding
underbalance
offer
The
pressure negative the
experts
did
different
as
pipe
to
why
critical
the
kill
line
not
increase
test.44
along
is
the
drill
pressure
during
point well
is
the
that
pressure
This
irrelevant
The
significantly
increased
during the
thus
it
integrity
had
established
to
Given
the
to
results of the
was
reckless for
in
proceed
underbalance
the
well
as explained
Report
is
conclusion pressure
to the
as
to
why
to
this
line
did
increase
attribute
in
the
drill in
pipe the
kill
pressure
line
regard valve
experts
who
of flow
if
closed
or hydrostatic
pressure
line
they
are correct
just further
reflects that
should
not have
been
deemed
kill
success
test
line
because this would reflect further errors in the negative pressure test the by BP and Transocean as during the negative pressure valve was supposed to be open and was hydrostatic pressure
to
supposed
Similarly
kill
have
been
is
removed so
that
the well
could
be tested
that
for
leaks
the
irrelevant
BPs
being
Graces
rise.45
suggestion
when
line
is
pressure
was
kill
the well
was
and
with
that
why
the
line
pressure
not
Not only do
that
April
20 2010
the
April with
27 2011
Post-incident
the well
federal
was
likely
in
communication
reach
the formation.
The
at
reports
by
the
same
conclusion
to the
Gulf
Oil
Disaster
government and
See
e.g
Expert Report
that
of
William
lost
Abel
Cameron
restricted
kill
hereinafter
line
Abel
Expert
Report
Report
at 13 opining of
heavy
at
circulation
flow
Donald
Weintritt
Weintritt
P.E
21
LA and
TX Retired
10/17/2011
Halliburton
to
site line
hereinafter
Report
the
kill
useincluding
costslikely valve
is
the Form-A-Set AK
the spacer that BP and MI-SWACO decided and Form-A-Squeeze to avoid hazardous waste
likely
BP
that
at
47 opining
the reason
hydrostatic or
that
kill
closed
kill
BP
that that
line
failed to flow
unknown
line
Medley Report
Barnhill
M-I
at 20-21
at
opining
pressure
hydrostatic
prevented pressure
kill
flow
kill
Report
TO
17
28 opining
plugging
blocked
line
flow
BP
at
In my
opinion
the well
was
not
underbalanced
during
Line
was monitored
21
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
Mr Grace
reflect that
but the
more
test
importantly
if
he were and
correct not
this
would been
well
also further
was
as
failure
should the
have
the
deemed was
for to
success
46
because
BP
designed
test could
be
underbalanced
be checked
leaks
Again the
did
critical
point
is
that the
results of the
negative
pressure
test
not
establish
well
integrity
and
to
thus
BP and
had
Transocean
well
absolutely
resulting
should
not
is
have
proceeded
proof test
underbalance
well
integrity
the not
The
blowout
conclusive pressure
that
been
established
by
the negative
46
Given
the
way BP
the with
designed
the
if
pressure
test
BP
sought
to underbalance
the well
during
test
Thus
was
not
underbalanced
failed not to
during
suggestion
correctly to
which
test
and
extent
the
BP
and
Transocean
failure the well
perform
success
not state of
Furthermore
during the
the
Mr
Grace
test
trying
to
suggest
that
was
flowing
negative
flow
into
strongly
disagree
is
The
underbalanced pieces
of the well
and the
the high
reflected
by several
evidence
significant to
pressure
of
readings
that
drill
shown
on the
drill
pipe pressure
off
gauge
is
the
quantities
seawater
that
were repeatedly
pipe pressure
of
bled
to bring
the
fact
the as
1400 psi
expect noted
result
pressure
of
formation
when
underbalancing Report
at
well
as
by
another
drill
one
BPs
reports
Bourgoyne
pore increase
63
calculating
with effect
expected
pipe
pressure
that
based 1400
measured
pressure
disagree U-tube
Mr
of
Graces
spacer
psi
suggestion
with
lost
the
circulation
material
LCM
BOP
of the
fill
improbable
spacer annulus
with
1400
lost
pressure
differential
would
height
require that
over
feet
16 ppg
feet
circulation
material
3300
of
between
the
drill
pipe and
that
if
the
casing
below the
of
BOP
am
unaware
in
concluded
this
amount
spacer
remained
the
who
has
BOP
it
Moreover
pressure
the
well
was
not
merely
hydrostatically
out of
drill
balance
negative as
did
test
would
expect
pressure
on
the
pipe to build
up gradually
between stopped
pressure reservoir
800 PM
response
If
and 832
PM
BOP
was
annular
The gradual
build-up
pipe pressure
if
between
800
in
that
would
be expected
in
the well
communication
condition
the
well
was
merely
hydrostatically
if
imbalanced
the pressure
not instantaneous Regardless Mr Graces response would be much more sudden do not in BP and Transoceans the attempted explanations declaring any way justify to underbalance the well The success and proceeding negative pressure test pressure the well
justify
required that
they not
relied
proceed
with
underbalancing
not
upon during the test do not success and thus underbalancing the
establishes
this
well
The
the blowout
occurred
indisputably
22
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
Lastly negative
while
BPs
test47
experts
acknowledge
that
BP
misinterpreted
the
some of BPs experts appear to suggest that the test was not the direct cause of the catastrophe negative pressure blowout was known or reasonably foreseeable risk strongly disagree of reckless disregard of the negative pressure test On the other hand that there would be reckless disregard of the negative test was not pressure
pressure reasonably foreseeable
direct to contractors of the loss
like
Halliburton control
The which
test
cause
of well
and
reckless disregard
fully
in
of the
negative
pressure
discussed
more
to
is
Section
VI
below and
well
despite
the failed
their
proceeding
underbalance
important
to
the note
per
BPs
that
in
temporary
abandonment
have
well
in
plan
It
also safer
again
here plan
BP
be
well
of
could the
shut-
designed would
not be
to
much
left in
temporary abandonment
state
which
an underbalanced
risk
balanced
in
avoid
the
of
hydrocarbons
coming
up
the
As
well
well
explained
including
the
my Opening Macondo
Report
well
temporary abandonment
not
require
does
leaving
the
underbalanced.48
As Explained By Experts For The Other Of BP And Weatherford BP Parties With The Sole Exception Failed To Convert The Float Collar To Shut Its Valves To The Shoe Track Without Damage Allowing The Blowout To Occur Any Contrary Suggestion By Experts For BP And Weatherford Unsupported By The Evidence
The
Float
Collar
Is
All
the
parties
float
whose
collar
experts
have
considered
BPs
attempted
the by the fact
conversion
float
of the
share
it.49
my
This
BP
is
failed to convert
collar without
damaging
supported
Grace Report
48
BP
at
at
17 Azar
Report
BP
at
47
Bourgoyne Report
BP
at
62
Beck Report
Barnhill
90-91
Report
Transocean
Cementation
at at
13 18-19
19-20
Operation by
Macondo
of Ian
Engineering the
Operations 9-7/8
and
Well
Control
Response
Frigaard
09/23/11
Review
Macondo
10/17/11 Kevin
Production hereinafter
Casing
Frigaard
of
Cameron
10/17/2011
Report
at
16 29
at
Expert
Report
Trahan
at
Cameron
Report
at of
hereinafter
Trahan Report
17-19
Benge
Report Hughett
USA
26-28
Expert
John
Hughett
P.E
10/17/2011
hereinafter
Report
Halliburton
34
23
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
that
BPs
track
failed negative
pressure
that
test
showed
path This
the well
of the
was
is
leaking and
by the
the
prevailing
view
to
date
float
the
flow
blowout
was up
shoe
through
the
collar.5
conclusion
further
its
supported
conversion
by evidence showing
attempts.51
that
during
Only
the
float
BP and
the
float
collar
Weatherford
suggest
that
collar of
converted
or
may have
after
converted.52 the
disagree.53
The
of
absence
that
observed backflow
valves experts experts
pumping
without
cement does
as
not
not establish
the
float
converted
damage
path
some
Weatherfords Weatherfords
through the
acknowledge.54 can
reconcile
Moreover
flow
BPs
or
up the
track
float
and
float
collar with
in
non-damaged
Report served as and
collar
in
As Macondo
fluid
explained
well
if
my Opening
have
collar barrier
installed
the
would
temporary
and
the
held
float
back
collar
flow not
properly converted
to act
undamaged.55
barrier
Although
the
was
that
intended by
as
permanent
for both
post-blowout
testing
performed
if
Stress
Engineering
BP and Transocean
it
confirmed acted
properly
converted
and
undamaged
would
have
as
50
While
the prevailing by
view
kill
to
date
is
that
is
the
flow
path
recorded
BP
during
operations
inconclusive
flow
at
2179MDL01591521
through
flow
BP modeled
the casing
paths two up
feet
casing
and one
breach
fit
in
near
12487
None
of these to
assumed
been
that
paths
the
observed
data
no
additional
modeling
appears
it
have
conducted
to
determine possible
an exact
path
long
Id
string
Nevertheless
in
BP
in
acknowledged
the casing
51
damage
to the
modeling
flow
breach
Depo Ex 2584
Expert Report
at of
BP-HZN-MBIOO1
Brent
Lirette
29068
Transocean
of
Report
at
52
10/17/2011
at
52
on Behalf
U.S L.P
of
hereinafter
Lirette
Report
at
at
48
3-4
57
13-17
Calvert Expert
at
Weatherford
Marion Report
McCormack
10/14/2011 worth
Report
Weatherford
Woolie
Weatherford
noting that not
hereinafter
Woolie Report
retained
12
Sabins
BP
merely
at
84
that
It
is
all
of the experts
by
BP and
Weatherford
Calvert at
insist
the
that
float
collar
must have
converted
Weatherfords expert
Calvert Report
David
says
conversion
may
have occurred
at
Weatherford
Report
10
at
Calvert
Report
at
Weatherford
10 see
also
McCormack
Weatherford
18
Beck Report
79
24
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
temporary
the
barrier
by
preventing
flow at the
in
differential
pressures the
seen
in
Macondo
test
well.56 for
Additionally
the
way BP
float
configured
collar
negative
pressure
the
in
Macondo
combination
well
with
the the
was
tested
as
in
temporary Opening
barrier
cement as
explained
my
Report.57
Also
as
discussed
published ignored
in
my Opening
and
Report
instead
of
following
Weatherfords
float
instructions
real time
guidance used
high
regarding brute
the
collar
BP
Weatherfords
the
float
advice
and
nine
force
attempts
likely
to try to convert
collar.58
These
have
attempts
auto-fill
damaged
The
with
the
float
collar parties
possibly
ejecting
the
ball
tube.59
majority
of
whose
point.60
experts
considered
this
issue
agree
my
conclusion
on
this
Certain the
ball
experts ejected
retained
by
Weatherford
fail
discount
the
was
tube
to
account which
for the
obstructions
auto-fill
such
in
as
barite
or
other
debris
could
have
by
held
the
place
acknowledge
valves
to to help
the
experts the
retained
collar
Weatherford
hold
float
to
open
its
for debris to
enter
and
BPs
collar
high
pressure prevented
attempts
it
clear
such debris as
it
likely
damaged
if
it
the
float
and
from performing
would
float
have
had
been
properly
converted
and
undamaged
to
The
failure
auto-fill
collar
is
mechanical
device
and
thus
susceptible
and
damage On
the other
hand
in
the following
photograph
of
an
the
auto-fill float
float
collar
like
the
one
used
the
Macondo
at
well
shows
at
that
collars
two
56
Lirette
Report
Weatherford
at
42-44
Beck Report
79
Beck Report
58
93
67-72
the crew that psi
the
ball
Beck Report
Weatherford
at
advised
could
at
pressure
of
around 1300
This advice
for
was
confirmed
the mechanical
at
testing
conducted
60
by Stress Engineering
Transocean
Beck Report
70 73-74 18 see
also Barnhill
Frigaard Report
61
Report
Cameron
at
at
29 Trahan
Report
Cameron
at
Transocean
Report
19
at
Lirette
Weatherford
at 9-11
19
Calvert
Report
Weatherford
at
at
McCormack
Report
Weatherford
Woolie
Report
Weatherford
12
25
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
check
valves
are
stout
piece
of
equipment
in
for holding
back
fluid
flow
if
and
not
damaged
the conversion
process
Lirette
Report Weatherford
test
at
Fig
5B
It
is
not
surprising
float
that
the
backpressure
withstand
In
conducted
by
BP
established
that
the
collar
could
very
high pressures
designed.62
sum
as discussed
convert the
in
Report
safest
BP
time
first
failed to safely
and
properly the
float
and
to
next
failed
to
repair
damaged
pressure
float
collar
when
do
so These
of
unreasonable
negative
actions
by
BP
followed
reckless
disregard
the
62 Lirette
Report
Weatherford
at
at
43
Beck Report
at
79
63
Beck Report
79
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
VI
BP Should Have Been On Heightened Alert In Conducting The Negative Pressure Test Because Prior To That Critical Test BP Knowingly Designed Drilled And Operated The Macondo Well In An Unnecessarily Risky Manner For Financial Reasons BP
failed
Unnecessary Risks
to provide
safe
drilling
margin instead
necessitated
drilling
lower
As discussed
were
well while
its
my Opening
are
attributable
problems
those
with
the downhole
problems
not
to decisions
it
made
if
by
BP.64
Further
am
cementing
expert
it
is
my
opinion that
BP had managed
for
drilling
margin more
effectively
could
have
to lower
the
cement
it
density
and
if
BP had
not created
cement
density
well
would design
not necessarily
have
for well
cement
narrow
drilling
BPs
margins
in
which
called
the open
shoe
design
necessitated
density
of
cement which
margins
in
accomplished caused
by nitrogen
foaming
The narrow
drilling
the well
densities created
BP to be concerned about the equivalent circulating when heavy mud was pumped out of the reamer shoe
Specifically
and
up the annulus
the
high the
pump
would
pressures
would
be required and
to place
cement and
mud
at the
into
annulus between
in
the
casing
which
turn
apply
pressures
bottom
of the
hole
view
of the
narrow margins
the
in
the
Macondo
well
it
was BPs
risky
well
design
that
created density
need
for lower
equivalent
circulating
densities
and thus
to
lower the
cement
e.g
foamed cement
of the
The
foam
cement reduced
circulating
in
the
density
cement
thereby
the equivalent
density
my Opening
to repair level steel
Report
the
prudent
course
of action
by
margin
Extra
to
safe
cement
pay
zones
cement and
would
have
isolated
and
reinforced
64
Beck Report
at
79-85
see also
VII
below
27
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
certain
zones and
of
liner
then
lighter
mud weights
been
to
that to
produced
to the
lower
equivalent
circulating
densities could
have
used
drill
The use
the allowed cement.65
as opposed
the
long
string
would
equivalent the
circulating of
densities
well to
These
safer
alternatives with
bottom
be cemented
standard
unfoamed
The
alternative
Plaintiffs
expert
Mr
Pritchard
agrees
that
with
my
opinion
of
that
that
designs
were
available the
and
BPs
use
improperly
balanced
mud
When
weights
set
its
placed
cement
job at risk
1000
ft
BP
g-7/s
inch casing of
approximately
loss circulation
above
the
reservoir
BP then
pumped
copiou
its
amounts cement
LCM
and
purposefully
job to avoid
casing
additional
BP should
of the
have
chosen to
plug1
set
run another
for
liner
above
top
new cement
balanced
which
BP to re-enter
days of
rig
the
reservoir with
proper
mud weight
another liner
would
have
required hole
timer cost
more money1
provided
and
required
further condition
reduced
to
size
but
also
would
have
safe
at-balance
welibore
conduct
Instead
logging
casing save
running the
and
non-compromised
cementing
risk
operations
BP chose to
time and
money and
took the
to
its
cement
job
Pritchard
Report
at 12
highlighting
alternatives
in
added
available well
Although
the
safer
were
BP chose
This
led circulating
not to
to
its
remedy
use
of
narrow
drilling
margins
the
Macondo
light
foamed cement
slurry to
reduce equivalent
densities and
at
potential
damage
of the well BP chose
the long
to
the
sensitive
hydrocarbon-bearing
formations
the
bottom
Again
me
determined
that using BP $7liner
to use
string
it
MOC
to
BP
9-5/8
casing
opposed
would save
of circulation
problem during
the
cementing1
cement cement
to
reduce
density and
ECD
It
chose to save
morey and
to
its
job
65
Beck
Report
at
36-38
e.g
and
16-17
Expert
Report
of
Sam
Lewis
Ph.D on Cement
Halliburton the
risk
Chemistry
hereinafter
fracturing
Formulation Lewis
Laboratory
Testing
10/17/2011
Report
while
BPs
use
of
foam cement
of long
reduce
of
the
formation
allowing
the use
string
production
casing
string
28
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
Pritchard
Report
at iv
highlighting here
is
added
not to
The obvious
drilling
question the
why BP chose
answer
in is
margins
in
well
The
that
doing
have would
liners
be set
and would
each
cost
of the
have
required
separate
cement job
BP
both
time and
well that moneyresources that BP was likely unwilling to part with for was already millions of dollars over-budget and behind significantly schedule.66 BP chose the riskiest path in the interest of Consequently
saving
time and
money
incorrectly
BP
suggests
that
it
was
uppermost hydrocarbon-bearing zone because may not have been producible from This royalty standpoint
suggestion
shows
As discussed
achieve proper zonal must ensure the because zone
in
in
my Opening
BPs
well
design proper
failed
to
isolationwhich
critical
because
well
design
isolation
of hydrocarbon-bearing
zones
Section
III
BP
the
misidentified well
uppermost zone
in
hydrocarbon-bearing
in
the M57B
that
royalty
zone.67
the
Now
M57B
as discussed
above BP
is
BP suggests
in
because
context
in is
may
the
not
have
the
been
zone.68
in
producible
the
BP was
Section directed
justified
III
ignoring
wrong As
also discussed
above
MMS
regulation
question
30 C.F.R
250.42
at safety
not producibility
from
royalty standpoint
many
factors
that
control
the producibility
of
one
in
of
them
being
thickness
yet
producible
other
significant
such
as
porosity
saturation
delivering
Thinner zones
significant
such
of
as
the
M57B
zone
to
can
be
volumes
for safety
hydrocarbon
to
well
bore
short
period of
time and
need
be cemented
and
isolated
just the
same as
BP-HZN
66
BP-HZN-MBI-OO1
25958
to
BP-HZN-MBIOO1
MB100192559 247
67
According
CCR
92552
that
time
CCR
at
at
47-51
at
68
Report
27
29
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
producible
of the
welibore from
By
in
ignoring
the existence
of saving
in
increased
risk
the
interest
Identification
hydrocarbon
important option
of
bearing
for
formations safety
open
sections
with
critically
managing
the
but
of
BP
the
went
riskier
less
costly
ignoring
existence
disregarded
Halliburtons
centralizers
of at least twenty-one
causing
other
channeling
opinions
points
reviewing
the
expert
regarding
in
centralization
Vll.B of
have
determined
that
the
in
following
discussed
my
Opening
dispute69
in
Inadequate
centralization
70
the
Macondo
well
increased
the
risk
of
Halliburton
recommended
Halliburtons flown
at least
twenty-one
centralizers
fifteen
to
BP
additional
Based on
centralizers
recommendation
to the
rig
overnight
total
of twenty-
one
centralizers
available for
use
in
BP
placed
the
well
69
at 53-60
VII.B 23-25
against
70
Report
also
Depo
Transocean at 19-20 Frigaard Report Cameron at Beirute Ex 4842 at cementing expert Dr Robert cautioning
run just
see
not
running
Pritchard
71
centralizers
few
otherwise Report
at
it
would
result at
in
poor cement
job
Report
Plaintiffs
at
19 Trahan
71-72
Cameron
25
61327 HAL_10604
Plaintiffs
Sabins
Report
BP BP
at
CCR
Report
83
BP-HZN-BLY
at
HAL_10608
HAL_10713
Frigaard
at
Cameron
Pritchard
Report
19 Trahan Report
72
Cameron
at
25
Sabins
Report
of
71-72
CCR
at
at
83-84
Bly
BP-HZN-BLY
Report
at
61327
64
Tr
of
Telephone
as
Interview
Gagliano 6/11/2010
that
50-52
BP
The
investigation
team determined
result of the
centralizers
was made
OptiCemTM
modeling
on
April
15 2010.
30
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
BP
in
did
not consult
to
its
Halliburton
or Weatherford
its
centralizer
in
supplier
regard
did
decision to place
the
well
model
in
BP
not
ask
Halliburton
generate
an
OptiCemTM
predicting
with
the
well
Halliburton channeling placed only using
its
OptiCemTM
gas
in
software
potential
predicted
in
risk
of
and
SEVERE
centralizers
flow the
the
event
that of
BP
this
well
and
informed
BP
prediction
and
its its
BP
in
did
not follow
with
internal
management
regarding
of
change
MOC process
of the well.77 to
connection
decisions
centralization
Two
of
BPs
experts
nonetheless
attempt
to
seek
to justify
BPs
decision
They
do so based
on three unsupported
claims
CCR
Coast
Marine
at
86
Bly
Report
at
63 BP-HZN-BLY
Service
61225
Marine Sinking
Tr
of
the of
Joint
United
States
into
Guard
Minerals
Management
Loss
of Life
Board
Investigation
the Unit
Casualty
Explosion
Fire Pollution
in
and
of Mobile
Offshore
April
Drilling
2010
hereinafter Report
USCG/MMS Cameron at
Beck
Report by
Investigation
Pritchard
7/22/10
at
Guide
Testimony
at
at
374
Frigaard
Report
19 Trahan
Fred Sabins
Report
25
to justify
at
56 BPs
to
expert
attempts
BPs
use
of
only
six
centralizers
citing
various
testimonies Report
by
at
BPs
72
contractors But
including
is
Halliburton
irrelevant
Dril-Quip
and
Weatherford
to
Sabins
six
such testimony
without
BPs
decision
use
only
centralizers of the
was
fifteen
unilateral additional
involving also
contractors
BPs
overnight
delivery
centralizers
BP deemed
additional
centralizers
necessary
Beck Report
76
at
56
Report
of
at
CCR
at
86
Bly
64 BP-HZN-MBI
128708-756
at
at
BP-HZN-MBI
Trahan
of the
128739
Report
at
Tr
of
Telephone
Interview
My
flow
Opening Report
41 44-45
existence
25
to
the
M57B
note
zone
Halliburton
potential
Halliburtons OptiCemTM
for the
effort
simulation would
to
its
have
predicted potential
pertinent
CRITICAL
that
gas
well
as
opposed
or justify at
SEVERE
withholding
gas
flow
BP
has made no
to explain
of such
well
information
from Halliburton
Beck Report
57
Bly
Report
at
64 Depo Ex 6291
31
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
First of
BPs
fifteen
experts
Fred
Sabins and
J.J
that
BPs
that
in
use
the the
six centralizers
was an
acceptable
engineering
by
and
additional well
centralizers
recommended
only
Halliburton
for
use
were
not necessary
or suitable.79
disagree
To
start
in
BPs
BP
so-called
engineering procurement
timely
decision
decision
to
use
six centralizers
in
was
reality
poor
failed to
As discussed
quantity
my Opening
Regarding
Report
well
procure
of
sufficient centralizers
of centralizers
rig.80
for the
leading to the
fifteen
shortage
additional
on
the
whether
fail
centralizers
were
if
necessary
that
BPs
the
experts
to
provide
any
explanation procured
as
to at
why
the the
is
was
not
case
BP went
at the
ahead and
them
last
minute
based
on
Halliburtons procured
that
in
advice
last
BPs
minute Report
in
experts were
claim that
fifteen
centralizers
BP
not suitable
that
similarly inexplicable
fifteen
given
BPs own
question
Bly
concludes
the
additional
well.81
centralizers
were
fact
for the
Second recommended
centralizers.82
BPs
that
expert
Mr
Sabins
with
suggests
that
Halliburton
BP
proceed
the
to
cement
place
job
using
only
in
six
disagree
The
before
decision
six centralizers
the
Macondo
this
well
clear
when he
the
USCG/BOEM
78
BPs
not
expert Sabins
Mr
Sabins
references
at
Displace
3D
it
modeling
conducted
after the
is
after
the
it
blowout
could
to
Report
BP
BPs
was
this
73-74
Because
was conducted
centralizers
blowout
relevant
have informed
that
and thus
not to
whether
not
decision
when made
modeling
Mr
Sabins
appears
agree
as
he does
assert that
post-blowout
that
influenced
BP
pre-blowout consistent
with
Azar Report
BP
at
at
38 opining
BPs
use
of six centralizers
is
sound engineering
80
principles
Report
BP
at
72
Beck Report
Bly
54-55
81
Report
at
64
82
Sabins
Report
BP
at
34 omitting OptiCemTM
flown
events
on
April
Gagliano
conducted
additional
multiple
simulations with
to
have
fifteen
centralizers
the rig
32
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
our
we
dx-
BECK
Sir
The You
we
we
had that
plans had
in
place
centralizers
available oftentimes
know
have
to
the
role of
hung
between ccmpany weiqh
riot
make
judgments from
one to
recommendations other
10 11 12 13 14 15
risks
good
set
We
for of
have one
out
whats
another
may
be
better
criteria
that were
so
rrtade
assessment
incurring we
we
other
those
to
when to
realigned Because
centralizers
get
Ti
of
USCG/MMS
Halliburton
Investigation
10/7/2010
in
AM
WaIz
Testimony
in
at
18720-18815
informed
Additionally
of
its
as discussed
to
my Opening
Report
BP never
the well
subject.83
decision
six centralizers
and
ignored
an email from
learned
of
Halliburtons
When Gagliano
frustrated
BPs
that
decision to use
he
was
Walz
the
and he
concerned
the cement
that
job
require
remedial
work84
confirmed
risk
but
this
knew
that
was
job
decision.85
BPs
and due
Gregg accepted
when he
and
that
testified
BP was
be
fully
aware
that
remedial
cement
would
required
in
to
inadequate
centralization
BP had contingency
Dr Azar
asserts
plans
place.86 did
Third
BPs
expert
that
Jesse Gagliano
not warn
in
BP
of
inadequate Report
centralization.87
Again
disagree
Brett
As discussed
Cocales and
my
Opening
83
BP
Operations
Engineer
Drilling
Beck
Report
at
56 2596-9
at
Tr
of
Walz
Investigation
at
8/24/2010
Gagliano
at
18116-1827
CCR
106 BP-HZN
Telephone Telephone Tr
of
interview
of
6/11/2010 6/11/2010
at
85
interview
of
at
41 95
at
86
USCG/MMS
Investigation
10/7/2010
to
AM
realign
Walz Testimony
to the six
18321-1847
had
18710-19
When
we went
in
to the direction
in
the contingency
87
plans
place
the
event
something went
wrong.
Azar Report
BP
at
37-38
33
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
Engineering 18 email
reviewed
and
considered
an
April report
from
of the
Gagliano
with
that
included
the
OptiCemTM
Halliburton
warning
ignored
risks associated
using
But both
the warnings
to
Rather
perform
based
on
would
have
an opportunity
they
remedial
cementing
if
the
primary
cement
job channeled
decided
that
BPs
poor
centralization
would
probably
be
fine.89 with
Dr Azars
to
suggestion
that of
the
inadequate
zonal creates
was
up and
irrelevant
the
blowout.90 causing
Lack
annular
through
inadequate
centralization
channeling
prevailing
of flow
that
the flow
down the annulus and under the was down the annulus and up the shoe
not conduct
sufficient
view
did
to date
track
likely
enable
the blowout
BP
timely
did
itself
as
prudent
to of
well
operator
when
it
failed to
procure
centralizers
properly
at least
centralize
the
casing
ignored
Halliburtons
recommendation
twenty-one
centralizers
and
installed
BP imprudently chose long string design increasing the risk of cement contamination fracturing and annular flow Some
production casing might
of
BPs
experts
suggest
that
BPs
use
long
of string
long
string
casing
disagree
wells
in
production
for the for the
the Gulf of
that
Mexico but
the
reasons discussed
88
my Opening
Report
was
not
case
Beck Report
at
89
BP
engineers
of
channeling as
April
and and
at
gas
flow
potential
as the
result
inadequate
centralization
as
early
15
accordingly
ordered
additional
15 centralizers
See
Cocales
Depo
04/26/11
68815-19
and
85810-
14
Depo
to
Ex
1517
at
BP-HZN-2179MDL00033080
Testimony
six at
Tr
of
USCG/MMS
Investigation
10/7/2010
direction
AM
realign
Walz
to
18321-1847
18710-19
When
we went
plans
in
to the
in
the
place
the event
90
something went
wrong.
Azar Report
BP
Review
at
lack
91
of centralization
39 opining that any failure relating to eccentricity caused by would have resulted in flow up the annulus not the shoe track
of the
See
at
e.g 69
Production
Casing
at
Design
for the
Macondo Well
at
Expert Report
Report
by David
Lewis
10/17/2011
BP
Azar Report
BP
34-35
Sabins
BP
34
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
Macondo
liner
well.92
BP
on
selected
its
the
risky that
long
string
design
over
in
the
safer best
design
based
conclusion
doing
so would
again
result
the
of that
economic
case
for the
Macondo
not alone placed
well93
in
once
prioritizing
economics
long
ahead
string
of safety
am
of
my
the
conclusions
that at
BPs
risk
use
instead
liner
cement The
job
and
BPs
motivation
for doing
so
was money
Plaintiffs
expert
Mr
Pritchard
agrees
with
me on
both issues.94
BP unreasonably
adequately increasing the
chose
not to circulate
bottoms up or
to
cement placement
have adhered
of channeling
and contamination
should
to the
As discussed
widely recognized cementing.95
in
my Opening
practice of
Report
of
BP
good
majority
circulating
bottoms
also
The
the
experts
who have
at least Calvin Barnhill Transocean agree with my conclusion including Dr Robert Bea and Dr William Gale Jr Plaintiffs Glen Benge Ian
USA
Frigaard
Cameron
prior to the
David
Pritchard
Plaintiffs
in
and
that
Kevin
Trahan
Cameron.96 BP appears
circulation
to stand
alone
suggesting
bottoms up
cement
job
was
not necessary.97
that
BPs
April
expert
Dr Azar suggests
days
prior to
BPs
bottoms job
up
circulation sufficient
on
16
2010
at
three
the
cement
was
92
Beck Report
39-46
at
Depo Ex 2659
Pritchard
BP-HZN-MB100143259
Plaintiffs at iv
Report
VII.G
Barnhill
Report bottoms
Transocean
up volume up
at prior to
at for
20
the
The
well
job
volume
of
SBM..
Report
.did
not
xviii
total
up
to to
complete
circulate
Bea-Gale
is
at of
Refusing
full
bottoms
cement
pre-job
one
the failures
Benge
Report
USA
did not at
22
The
circulation
volume
on
the
approach
better
bottoms
up
the
Frigaard
Report
for
Cameron
More
Pritchard
would have
18
conditioned choice
drilling
mud
displacement
circulation at
Report
Plaintiffs that
BPs
volume
to forego
bottoms Report
to
it
up
increased
the
to
likelihood circulate
the cement
job would
fail Trahan
Cameron
prior to
20 Failure
cbottoms
the
risk
up
the
or anywhere
close
pumping
cement
increased Sabins
risk
of
Report
BP
at
70-71
BP
at
35
35
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
disagree up
Dr Azars
is
suggestion
presumes
cuttings circulating of
that the
circulation
in is
to
remove
for
from
drilling
But
as
explained
my Opening
prudent
in
Report
the
full
volume
prior to
likely
number
over
reasons
three-day
gelled
mud
the
wellbore
the
period between
April
16
19 and mud
is
bottoms up
prior to
circulation
would
have
cementing and as
lost
reducing
of
cement
up were
This
contamination
circulation
channeling
circulation
Second
here
bottoms
important
when
into
was
the
case
hydrocarbons
observed
fact
to
be seeping
that
alone
dictated
the well
have
not
been
fully
circulated
prior to for
cementing.99
BPs
expert
Dr
Azar
did
address
these
purposes
remains unchanged
to properly
that
BP
should the
clean
and
condition
cement job
BPs
decision
to
expert forego
Mr
that
Halliburton prior to
was
involved
in
the
bottoms
circulation indicates
the
cement job
prior least to at
The
the
full
evidence
that
have
otherwise
namely
lower 18
cement job
be
Halliburtons
Nathaniel by
Chaisson
site
suggested
one
bottoms up but
was
told
BP
well
leader that
in
volume
log
would
the the
pumped
and
Also
Mr
Chaisson
listed
noted
his
April
job
that that
up.101
volumes
pump
rates
were
as
would
of
per
co
man
reflecting
bottoms
event
is
preclude
full
circulation
of the
cementing
loss
circulation
BPs
during
experts the
do
not
suggest
circulation
there
was any
the should
lost
circulation
event
bottoms
prior to that
cement job
have
and
accordingly
to the
my
opinion
up remains
unchanged
98
BP
adhered
good
practice
of circulating
BP-HZN-2179MDL3541-45
at
BP-HZN-2179MDL3543
Depo
Ex
3188
at
BP-HZN
at
77
Chaisson
CCR
to
at
91
this
Depo
at this
03/17/11
rate
at
70411-70514
by
at
definitely
were Tr
of
going
pump
volume
as
dictated
Bob
Kaluza
USCG/MMS
101
Investigation
8/24/2010
Chaisson Testimony Tr
of
4373-4388
8/24/2010
CCR
at
91
Chaisson Testimony
USCG/MMS
Investigation
36
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
bottoms up
prior to cementing.102
BP unreasonably
scheduled
with
canceled
the
cement bond
log previously
Schlumberger
Report
log
As discussed
cement
as bond
log accurately
to
in
my Opening
cement
of
BP
should
have
conducted
bond
would
have
permitted
BP
to
the
the
in
achieved
to
cement
accurate
of
placement assessment
conducting
This would
of the
have
turn
permitted
BP
make
more
flow
annular
cement as
log
potential
barrier to
Instead
cement bond
to
however
the
crew
conduct
experts
the
Schlumberger
testing
early.103
of the
who have
bond
log
also considered
whether
BP
should
including
have
at
conducted
least
cement
Barnhill Ian
agree
with
Calvin
Transocean
Frigaard
Dr
William
Gale
and
in
Jr
Plaintiffs
Cameron
Plaintiffs
Kevin
Trahan
that
be alone
suggesting
Additionally suggestion
that
it
as discussed
Section
II
above
disagree
log
with
BPs
was
justified
canceling
the
cement bond
because
102
Note
that
the
pre-cementing the
bottoms
for
up
circulation
discussed
here which
serves from
isolate
to the
condition circulation
and
prepare
wellbore
the
cement
job
is
distinguishable
of spacer
and other
fluids during
the cement
this
in
serves
to
the
cement
expert
from
possible
to
contaminants
Displace
Given
distinction to
reference
is
by
to
BPs
pre
Mr
Sabins
3D
modeling
regard
spacer
irrelevant
cement
103
bottoms
up
at
circulation
Beck Report
Barnhill
87-88
104
Report
the cement
21
been
able
to
see
if
the
general
quality
of the
cement
cement
to run
the
float
collar Bea-Gale
knowing
these
failures
it
failure
cement
bond
one 29
of the
all
BP Macondo
cement
team
Frigaard
to evaluate
Cameron
job
at
For
with
reasons
would have
been advisable
the cement
further
some
form of logging
at
in all
e.g
Report
bond log before proceeding Pritchard Report Plaintiffs 10/17/11 at 29 CBL been at either point run Cameron Had would have been prevented.
Report
19 Trahan
likelihood
the blowout
105
Sabins
BP
at
78-80
Azar Report
BP
at
39-40
37
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE was
BECK
Halliburton
did
not
indicate
that
it
needed.106
As BP was
the
itself
correctly for
acknowledges
making bond
this
BP
in
specifically
fact
its
drilling
engineers
to
responsible
and
did
make
as
not
for
the
decision
cancel
log.107
Halliburton
BPs
part
cementing
of
contractor
decision
and no
was
BPs
decision
other than
tree.108
its
As
to
have save
log
it
ascertained approximately
is
basis
BPs
of
rig
decision
desire
eight
hours
the
in
cement bond
interest
apparent
that
BP decided
again
at the
not to conduct
the
of saving
time and
money
expense
of safety.109
BP chose As
similarly risky
risky
temporary abandonment
Report have
plan
explained
in
my Opening
plan for the
BP
could
have
at least
designed and
less
temporary abandonment
Calvin
Barnhill
procedure
including
William Abel
Cameron111
Transocean2
Dr Robert Bea
Dr
106
Sabins
Report
BP
at
at
79-80 see
also that at Sepulvado Depo 3/10/11 even BPs own well site leader
107
Azar
Report
39
that
14617-14916
does
that not
testimony by
the discretion
BP
to
Well
Site
Leader
call
have
make
the cement
bond
log
unless
its
within
decision
tree
108
CCR
at
94
citing
BP-HZN-MBI 143304
it
and BP-HZN-CEC
experts
21665
mention
of
109
find that
notable
that
BPs
log the
make no
run
in all
BPs
where
written top of
cement
feet of
bond
should
be
instances
cement
5.3.1
less
than
1000
above
shallowest
to follow
hydrocarbon these
10-60
it
and
533109
explained
at
or
BPs
bond
failure
internal
when
standards
canceled
the planned
is
cement
in
log
BPs
failure to follow
these
and others
110
my
Opening Report
See
20-31
Beck Report
Abel Report
12-13
opining
that
at 8-11
BP
failed
to
set
second
that
barrier
hydrostatic
control
during
to
temporary
abandonment
and
BP
apparently which
was more
drill
use the
feet
DWH
the
that
to set
the wellhead
packoff
required
.Yet
pipe
8367
for
plug
and
is
abandonment
considered
to
procedure..
no
consideration
if
was
given
to the fact
8367
feet
be
poor
position
38
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
David
Pritchard
Plaintiffs.114
The
last
safer alternative
in its
to
BPs
to
plan to set
the
lock
down
casing
sleeve
as the
to set
step
lock
temporary abandonment
sleeve
first
procedure would
against the the
have
been hanger
issue
the
down
guard
during
seal
assembly
becoming Most
unseated
experts
temporary
this
abandonment agree
plan to
procedure.115
including
who
to stand
have
considered
William Abel
Cameron116 and
alone
TransoceanY7
that
BPs
112
expert
Dr Azar appears
suggesting
BPs
Barnhill
Report
Transocean
un-necessarily
to set
at
22-26
the
42 stating
that at
risk
net
effect
BPs
was
using
to
place
Macondo
in
Well
during
the
TA
and
BPs
and
under
If
plan
plug
water pipe
coupled
with
LDS
last
the
already
back
drill
morphed
procedure
the
TA
procedure
not
into
higher
risk
that
BPs
level
did
have
to at
be 25 an
fact
conducted
opining overview
that
the
of risk within to
was
BP
less
Barnhill
Report
Transocean
and
considered
with the
that
someone
barriers
had
stepped
back
situation
include
the history
flow
coupled
not
adequate
much
with
redundant
that
had
been
to
to
tested
nor out
confirmed
further
coupled
the fact
the
the
TA
well
operations
about
it
be carried
would deeper
potentially
significantly
by displacing
significantly
depth
than
normal
could
have
been
explored
that
would
have
significantly
113
reduced
the risk.
at xi
its
Bea-Gale
Report
Plaintiffs for
xviii
xxiii
58 73
opining
that
BP
and
did that
is
not
have
risk
management
install
process
temporary
abandonment
temporary
procedure
to
additional failures of
physical
barriers
during
abandonment
one
of
the
knowing
114
BP on Macondo
Plaintiffs for at
Pritchard
Report
details
86
BPs
procedures
testing or
were
woefully
inadequate
negative
identified
pressure
risk
displacement
and
managing
those
115
known
and previously
at
of uncontrolled
blowout
Beck Report
Abel Report
91
at 8-1 to
116
Cameron
the
feet for the that
opining
set
that
BP
apparently which
decided
required..
it
was more
drill
to use
DWH
8367
the wellhead
packoff
pipe
8367
plug and
feet
is
abandonment
considered
to
procedure..
no consideration
if
was
given
to the fact
be
poor position..
the
well
were
to kick..
117
Barnhill
Report
to
un-necessarily
to
Transocean at 22-26 42 The net place the Macondo Well at risk during
plug
drill in
effect
BPs
set
decisions
that
last
was
the
TA
to
into
and opining
the
BPs
using
plan
set
the cement
water
coupled
with
the
desire
LDS
back
pipe morphed
the
TA
procedure
higher
risk
39
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
set the
that
lock
down
sleeve
BPs
decision could
operations
He instead suggests was not more risky.118 was made out of concern for the potential that the down sleeve.119 As stated in damage the LDS
last
my Opening
lifting
Report
during
however
the the
the
risk
associated
test
with far
the
casing
hanger any
risk
off-seat with
negative
pressure
outweighs
cost
to well
associated
damaging
lock-down
is
sleeve
as the
to
repair control
damaged
incident
In
120
lock-down
sleeve
marginal
compared
addition
to
setting
the
lock
down
state
sleeve
first
BP
to
also could
have
much
been
abandonment
plan
under which
the well
balanced
placing
as
opposed would
underbalancing
BP did
while
second
Under
set
this first
much
safer by
the
lock
down
setting
sleeve by
been
well
integrity
conducting
positive barrier
and
pressure
and then
cement
from
taking well
plug as
riser
prior to
removing
of the
balancing
further
drilling
mud
by the
the the
BP
then
could
prior
have
to
shown
appropriate
caution
filling
additional
step
setting
the
cement
float
plug
of
with
heavy
mud from
the
well
the
seafloor to the
fluid
collar
which would
drilling
riser
without
left in
underbalancing
welli.e
would
have
balanced
state.121
BPs
at
Dr Azar suggests
feet
that
BPs
did
is
plan not
to set the
cement
the
plug
of
about
3000
below
the This
mudline
suggestion
increase
to
risk
underbalancing
the well.122 by
contrary
my view and
the
feet
the
view expressed
the surface
most
of the
experts
to set the
who have
cement
considered plug
issue of
plug.123
BPs
40 43
plan
3000
below the
118
Azar Report Azar Report Beck Report Beck Report Azar Report
Abel Report
BP BP
at
at
119
at
120
91 88
at
121
at
122
BP
42
at
123
Cameron
Barnhill
8-1
opining
that at
8367
feet
is
considered
to
be
that
poor
position...
Report
Transocean
22-26
than
42
opining
BPs
the
abandonment
well
operations.. would
potentially
significantly
underbalance
by displacing
it
to
significantly
deeper depth
normal..
40
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
mudline exposed
with
displacement
well of to
all
the
way
down
degree chance
to
there
of
with
seawater
the
the
much
were
higher greater
underbalance
failing
consequences
inducing kick
which
of
barrier
and
also disagree
its
with
Dr Azars
plan
opinion124
that
BPs
well
temporary abandonment
of
for the
Macondo
In
until
20
the
day
the
blowout
was reasonable
because
time and
my
opinion
to
BPs
been
at the
last-minute motivated
changes
solely
were
unreasonable
desire to save
to
they
appear
have
by
BPs
In
expense
of
safety.125 selectively
attempting
suggest
to
its
otherwise
plan
Dr Azar appears
to focus
on
BPs
revisions
15 2010
April 15 that
without
addressing
the
multiple
revisions
and
BP
in
revised
Moreover although Dr Azar suggests temporary abandonment plan between April 12 and April
information acquired
of
15
response and
to
by
BP
the
during
drilling
he
fails
to
provide
initial
any explanation
final
whatsoever have
how
differences
between
gained should should
BPs
from
plans
If
could
resulted results
all
from
new knowledge
operations operations
anything the
alert
of logging
have have as
BP on
heightened
to
and
risk
subsequent
been
designed
reduce the
3.3.1.127
to
as
low
as reasonably
by
practical
clearly to
required by massively
DWOP
thick
if
The
well
logs obtained
with
BP
show
high given
high-porosity placed
in
reservoir
the
potential
deliver
volume
flow
an
underbalanced
to offer
condition
credible
Accordingly
justification for
BPs
before
and
Dr
Azars
to
failure
its
any
BPs
just
multiple
revisions
temporary abandonment
plan
in
the
of
days
the
blowout
and
ignoring that
requirements 20
to finalize
its
BPs
change
until
April
124
Azar Report
In
BP
to
at
40
several substantive plan
deficiencies that
125
addition
the
and
deficient
other This
experts
is
have
noted
BPs
temporary
list
abandonment
was
procedurally
evidenced
by the two
in page my Opening Report all of which were made by BP without following its internal management of change process Beck BP does not disagree that the management of change process was Report at 26-28 not followed for BPs various decisions in the temporary abandonment procedure
of last-minute
changes
set forth
126
Azar Report
BP
at
40
127
Depo
Ex 6121
at
BP-HZN-BLY00034519
DWOP
3.3.1
41
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
VII
The Cement
Halliburton
Job As
Is
Other
Agree BP
Not
Responsible
Any
Failure
Of The Primary
Isolation Halliburtons
offer
experts
who
the the
have
criticized well
cement
to
design
and
work
on
Macondo
cement
this
drastically failed
different
how
In
job
supposedly
lack
of
provide
my
opinion
an
accepted
cohesive
opinion that
undermines
their respective
views and
supports
with
my own
problems associated
well
the downhole
performance caused
by
cement on
or
the
Macondo
any such
problems were
by
likely
one
more
of the following
decisions
made
BP
the well
BPs
of
decision
to inadequately single
centralize
and
its
decision
not
to perform
even
bottoms-up which
circulation
prior to the
pumping
in
the
cement
both
of
likely
caused
channeling
the
annulus BPs
the decision
to
use
production
casing
which
increased
risk
of contaminating to
cement
weight
drilling
BPs
risked
decision roping
leave
mud
in
the
rathole
which
the
where
in
the the
light
weight
track
to the
mud
migrates
up
through
in
heavier
cement
from
shoe
forming
channels
float
the
unset
cement
up
unconverted
collar
128
BP
at
because
Frigaard
could
as flow
paths
for
hydrocarbons
channeling
Cameron
and was
flow
at not
20-28
fully
cement
Calvert
was
contaminated
by
and
fluid
swapping
created
set
at
Report
channels
through
at 14-20 hydrocarbons Weatherford cement as the cement was setting and to pinpoint the
Trahan cement
Report
failure
Cameron
but failure
10
19-29
impossible
to
exact
rate
cause
of
was
likely
due
low cement
volume
of the
the low
at which
the cement
129
was pumped
at
contamination
and/or
movement
cement
as
it
set
53 77 39 82
130
at
131
at
42
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
BPs
decision
cement
the
rig
industry
accepted
twenty-four
hours
performing
as other parties
agree
to
risked
its
interfering
the
BPs
with
decision
cancel
planned have
cement
put
bond
which
of
as
recognized the
BP on
notice
problems
cement
job and
pressures
far
in
BPs
decision to apply
excess
of those
recommended
collar
by the manufacturer
when
the
attempting
to convert track to
the
float
which
float
may have
collar
All
caused
entire
shoe
separate
from
the
at risk.134
of the foregoing of
at risk
resulted Hall
any one or more of which put the cement job BP alone Any consequences that failing were made by BP and from these decisions are thus due to BP and not attributable to
burton
Lastly
in
addition
to
BPs
decisions
listed
it
above
also the
in
BPs
float
failure
to
convert
the
float
equipment
without
damaging
to
could
have
caused
problems
without
with
the
cement
allowed
job.135
equipment have
damage
is
u-tubing
for the
occur
track
which
turn
would
shoe
cement
to set.136
My
opinion
this
regard
shared by
Camerons
expert
Mr
Trahan.137
132
Beck
Report
at
85
test of
Pritchard only
Report hours
Plaintiffs after
at
33
BPs
decision
to
perform
the
positive
pressure the
risk
10
increased
plug
recklessly at 14
Cameron
of
an
unconverted
float
can
prevent Report
at
cement
up because
Expert Report
at
ongoing
of
movement
Bolado
133
see
also
Lewis
Halliburton Hughett
45-47
David
10/17/2011
Halliburton
38-41
Report
at
Halliburton
35-39
Beck
Report
at
87
Pritchard
Report
Plaintiffs
33 Trahan
Report
Cameron
at
29
134
at
83-85
135
at
62
Halliburton
136
Sam
Lewis
if
cement
expert
that set
the cement
at at
Halliburton
left
undisturbed
of the well
likely
would
Lewis
the
time
pumped by BP and
Transocean
137
lost
control
Report
Halliburton
45
Cameron
at
14
43
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
VIII
Cement Remediation
The Only Reasonably Foreseeable Failed Cement Job Is Cement Repair Job Consequence Of Which BP Did Not Allow For Because The Results Disregarded
It
Of
If
Its
Negative
Pressure Test
interpreted that
BP had
would zones
correctly
the
results
of
the
of
negative the
pressure
test
it
have had
zonal
isolation that
hydrocarbon
steps
bearing
been
the
achieved
and
corrective
were
necessary would
At that
complete
the
have
been
need
cement
remediation
e.g
squeeze
job
whereby
additional
As
job would
by other experts138
need
site
for
such
cement
repair that
been
surprise
BPs
well
cement
remediation
management of
If
may have
been
BPs
losses
cement
job
rossible
cement
prior to
evaluation
includinci
remedial
cement
will
orerations
disrensations and/or
performing
MMS
arovals
to
be
than
required required
TA
the
in
operations
due
lower
Top
of
Cement
left
in
annulus
Possible
hydrocarbon
zones
could
be
exposed
single
hanger seal as
decision
tree
the
barrier
the
TA
to
The
add
addresses
operation
these could
options
perf
attached
and
sgueeze
in
be
performed
second
barrier
the
annulus
138
See
Sabins issues
Report
BP
be
at
73
by
potential
channeling
that
causes
Calvert
long
term
isolation
can
13
failed
addressed
remedial
failure
cementing
of
in
Report
test
this
Weatherford
demonstrates
situation
at
In
my
opinion casing
the
the
the
negative
pressure
production
cement
job
Macondo Two
Well
In
industry actions
standards
require
to
and
prudent
well
operator
should possible
insist
that
remediation
actions
be undertaken
establish or set
integrity
remediation
were
to perform
squeeze job
bridge
Trahan
Report
Cameron at
the
29
The
test
information
gained
by the
BP
to take to test
remedial the
actions
of
Even
subsequent job BP
in all
used
integrity
Macondo cement
run
at
to run
the
CBL Had
CBL been
either point
likelihood
44
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
Depo Ex 2659
failed
at
BP-HZN-MB100143259
test
well
emphasis
have
added
the
Following
its
negative
to
pressure the
BP
should
displaced
mud back
into
the
well
return
to
balance
pressure
to
and
fracture
i.e mud weight above the pore BP then could have proceeded gradient
The
the
well
evaluate
the
cement job
control
would
have
could
been have
kept
balanced prevented
pressure
and
hence
under
and
blowout
the
been
Instead test
BP
imprudently
to
disregarded
results of the
negative
proceeded
underbalance
the
well
and
the
blowout
occurred
IX
final
reviewing
alters
the
reports
of that
the
other
April
parties
to
this
action by
see
nothing
that
my
opinion
on
20
2010
decisions
BP
non
any
set
Transocean and
standard
M-I
SWACO
during the
that
to
conduct
multiple
simultaneous and
frustrated
operations
final
Macondo displacement
Joe
Keith
reasonable
the kick
of
opportunity
had
to identify
As many of
these
was
second
eyes monitoring the well and he had access to far less information than the BP company man and the Transocean crew because of drilling decisions made by BP Transocean and M-I SWACO
Other
drilling
experts
improperly
lump
Keith
Joe
Keith
in
with
the
of
Transocean ongoing
rig
crew
even and
April by
though
the the
Mr
was
kept
test
uninformed
operations
time
the
sheen
909 PM on
20
M-I
Sperry
flow-out
and
SWACOs
sensor
approved
while the
drilling
flow-out
remained
available
Transocean
and
BP
Mr
is
Keith
could
that
clear
It not per BPs instructions access the Hitec flow-out data BP and Transocean knew the limitations of the mudloggers
monitoring involved
designed gas
to
and
displacement
flow-out could
that
bypassing
sensor
with allow
sensor been
for
while agreeing
me
Joe
have
closed system
to shift
monitor the
to
well
the responsibility
authority
for the or
configuration for
Sperry
the
pits
however
configured
has no
or
over
responsibility
how
how
the
displacement
was
conducted
The
139
Depo
Ex 967 see
also
Depo Ex 607
45
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
responsibility
for those
decisions
falls
squarely on
BPs
Transoceans
and
M-l
SWACOs
shoulders
position
The Sperry mud logger was not in the same and the Transocean drilling crew
as
BP
common
reports
is
mischaracterization
position
throughout Sperry
the
other
parties
relative
expert
to the to
in
the comparative
drilling
of the
in
mudlogger
crew
into
BPs
Sperry
experts
particular
improperly
attempt
outlined
individuals
single
category.14
However as
the
my Opening
crew were
better
Report
the
mudlogger and
the
fully
and
Transocean
drilling
not on equal
footing
on the evening
well
of April
rig
20
Transocean
In
had
information
operations
of
rig
particular at
all
not only
was
the Transocean
after all
drilling
crew and
aware
operations
timestheywere
they could
directing
conducting
those
operationsbut
diverting Keith
in
when
they
began
overboard
not.141
as
it
appears the
control
well of
started
kicking also
The
drill
crews
to
operations
of
them To
hands-on mudlogger
rig
position
sits
in
be
aware
ongoing
the
operations
floor
whereas
stay abreast
drilling
small
drill
crew
April
Joe
Keith
on
20
2010.142
specialist
Nor
or of
did
the
BP
well
leader
the
M-l
to
SWACO
keep
the
drilling
fluids
engineer
decisions
attempt
In
informed
ability
any
ongoing
to
operations
addition regarding
or
the
rig
mudlogger
or
authority
make
configuration
activate
control
this
actions
is
displacement
reserved are
all
procedure
whether
to
the
BOP
authority
for the
the
in
Transocean
well
drilling
crew
who
required by regulation
be
certified
control
140
Report
at
20
141
BP
by
BP
at
10 and
64-66
Grace Report
BP
at
and
18-
11 44-45
experts that
of at
and
50
Keith
Any
is
implication belied
BPs
Joe
had access
to
Transoceans
Bly
flow-out at
data
by
BPs own
investigative
team
Report
42
E-mail
Robinson
relating to
Depo
34825-34923
concluding
see
also
TRN-INV-01824082
sensor
Transoceans overboard
investigation but
the
Sperry
was
bypassed
when
142
diverting
the Transocean
Keith
paddle
sensor
was
not
at
Tr
of
USCG/MMS
Investigation
testimony 12/7/2010
19311-15
46
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
As
described
drilling
in
Appendix
shut
to
my Opening pumps
Sperry
to
Report conduct
at
908 PM
sheen Joe
the test
Transocean
crew
down
later
the the
the
one
minute and
mudlogger
Sperry yet
Keith
flow check
visually
well
decrease
data.143 or
stop
This
is
confirmed
by
flow-out
either
stopped
because
the
was
returns
not
underbalanced
before
because sheen
Transocean
test
improperly
If
diverted
well
returns
overboard
diverted
this well
the
was
only
conducted
the
drilling
were
overboard
the Sperry
prematurely mudlogger
having
just
crew have
would
have
known
the gold
would passed
reasonably
concluded
flow
that
was secure
in
successful
after
checkthe
had
confirmed
standard
kick
detection
Accordingly he had
Joe
to
Keith
was
static at
909
PM
no reason
believe any
kick or at
mudlogging need
collected
and
observed up
to that
time indicated
for well
control the
When
returns were
lost
the
resumed
at the
914
line
PM
after
sheen
test
routed
bypass
to dispose
of the
weighted
circulation to
material
this
When
sensor
BP
it
Transocean
did
and
M-l
that
SWACO
it
decided bypass
dump
overboard
so knowing
would
pit
both
Sperrys
and
the
Deepwater
Horizons
system
kick
effectively
blinding
the Sperry
flow
flow-out
sensor
and
were
bypassed sensor
and
unavailable
still
to monitor well
Hitec flow-out
was
have
able
to
monitor the
rate to
well.145
mudlogger
had
access
some Transocean
data
not
143
Exhibit
604
that
144
understand
Transocean
that
and
flow-out
moved
See e.g Depo at 5428-5438 Gisclair Depo Depo 4/15/2011 Clark Depo 7/29/2011 at 2094-2106
Keith
145
Transocean
BP had and BP
to
could
for the
Sperry
the
sensor
be
3/28/2011 3/14/2011
1755-17615 10320-10515
Gray and
See
e.g
at
Sepulvado
Depo
5/11/2011
at
3/10/2011
flow-out
26311-26424
should
Tiano accurately
Depo
65
8/25/2011
sensor
have
Report
transmitted flow
on
April
20
2010
flow-out that
and
Bourgoyne
BP
at
When
was
pumping
passing
Sperry-Sun
flow
meter
part
was bypassed
of the rig sensor
However
flow
through
second
meter
was
package
47
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
access
to the
Transocean
drilling
flow-out data
even did
though the
BP company man
crew
certainly
As
the
described
in
my Opening
to
if
Report
BP
told
Sperrys mudloggers
on
Horizon vast by
flow-out sensor
kick
majority
of the
occurred
returns
BP and Transocean As
the could
rate147
out of the
well
mudloggers
increased
flow and
gas
capability
after the
sheen
BP and Transocean
in
have which
and
is
should
classic
have
kick
seen
indicator
significant
increase
that
the
flow-out
The
fact
the
Transocean
drilling
crewand
is in
the
BP Company
reflection
Mandid
on the job
drilling
not
that
indicator
no
way
the
especially
given the
Transocean
crews
well.148
As
far
as Joe and
Keith
was
he
concerned he had
confirmed
the well
was
not flowing
nothing
saw
would
that
have
reasonably experts
cite
telling
BPs
do
from the
the
OLGA
and
simulations
for well
flow149
rather
than
surviving
in
Sperry
data
They
no
clear
so
because
as
described
in
my Opening
Sperry data
there are
Keith
indications
of well
flow
the actual
Joe
was
monitoring
The
volume
OLGA model
actually
however
by
does Joe
18
not Keith
of
accurately
illustrate
in
what
figure
was
detectable
As shown
Emilsen
the
below which
146
was
BPs
and
Report5
Keith
only
See
for it
e.g Appendix
at
to
Beck
get
Report
their
at
see also
Depo
you
3/28/2011
1807-22
We
dont
but
ask
147
We
did
at
one time
--we dont get their flowout didnt want us to use it.. they
5/11/2011 Tiano
at
Could
See
e.g
at
Sepulvado
Depo
and
3/10/2011
148
26311-26424
at 102-1
Depo
8/25/2011
Depo
07
149
See
e.g
Grace
Report
at
BP
67
best
at
and
18 Azar
pits
Report Sperry
BP
600
in
at
and
50
and were
is
Bourgoyne
Report
the
BP
kick
because
10
the
pit
the
and
flow-out
sensor
pit
bypassed when
misleading
occurred
at
Dr Bourgoynes
barrel
pit pit
barrel
pits
gain
as there
was
the
prior to
the
sheen
test
This would
have
been
as
only
gain
The
rest of
mud was
diverted
overboard
150
gain.
Horizon Incident
at
Summary
Deepwater
prepared
by
Morton
Emilsen 10/17/2011
BP hereinafter
Emilsen
Report
48
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
small percentage
rig
of
BPs
By
simulated
pit
gain would
have
out
of
even
the
reached
the
before
flow-out
was
diverted basing
that
overboard
their
and
mudloggers
data
monitoring experts
after
fail
capability
to
arguments
could
on
simulated
BPs
gain
were
acknowledge
Joe
Keith
of this
pits
910
PM
when
the
drill
Sperry
flow-out
sensor
and
the
in
bypassed
to actually
Only the
TO
crew and
majority
position
observe the
vast
flow out
of the
well
since the
rig
only
prior to
negligible
amount
of the
simulated
flow ostensibly
reached
diversion overboard
BPs OLGA
volume was
simulation
simulation
shows
that
most
of
not detectible
by the mudlogger
BPs OLGA
predicted fixed
is
also
likely
overestimates
even
the
small
gain prior to 910 PM By BPs own admission OLGA assumed net pay from the reservoir even though BP acknowledged that
that
initially
possible
only the
small
channels
If
in
the
cement
used
flow
If
were
this
open
latter
between
reservoir
and
wellbore.5 concedes
in
OLGA
initial
assumption
significantly
however
less
BP
that
that figure
the
would
then
be even
than
shown
the
above.152
so
151
Emilsen Emilsen
Report Report
at at
14 see 14 see
also also
Bly Bly
page page
vii
152
vii
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
this
corrected
been
virtually
undetectable
by the
Sperry
mudlogger and
data
that
line
with
my
analysis 10 bbls
based
entered
upon
the
the
well
volume sheen
indicates
at
most
before
the
test.153
The
simple truth
is
there were
no
clear
indicators
of
kick
lost
in
the data
mudlogger
before
BP
discharged
the
circulation
spacer
overboard
Such
did
indications
were
likely
present
in
Transoceans
Horizon and
Hitec but
data monitored
that
drilling
crew and
BP
company man
data
sinking
of the
Deepwater
made
test
in
is
best
subtle
indicator
of well
hindsight
As
expert154
noted the
in
my Opening
Report
M-l
and
confirmed operations
by
Camerons
at the of subtle
simultaneous and
non-standard
conducted
detection
behest
kick
of
BP
Transocean and
any were
to
SWACO
well
prevented the
indicatorsif
presentbefore
monitor flow
sheen
test
Because
available
in
the
was unable
after the that
once
kick
returns were
indicator
diverted
to
sheen
other
the the
have
cited
is
the
increase
standpipe
pressure
during subtle
sheen
of
This
in
parameter
real-time
would
is
have
notable
been
only
at
in
best
indicator
well
flow
and
hindsight
The 200
alerted
psi pressure
increase
that visual
during the
kick
sheen
test
would
not have
reasonable
did
mud logger
after
was ongoing
that with
especially the
of well
coming
as
it
immediately
confirmation
was
not
flowing.156
Joe Keith
seasoned
mud logger
years
experience as
153
Beck Report
Abel Report
at
114
154
Cameron at 14
Grace
at
155
See
e.g
Report
Report
BP
at
at
18
and
of
Report
Barnhill
Cameron
prepared
at
14-15
Expert Report
BP
at
66
Abel
Cameron at
United States of
Transocean
by
34-35
BP-Macondo P.Eng
America
Richard
Heenan
8/31/2011
hereinafter
Heenan
Report
156
21
at
113-114
50
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
Horizon
for
and
18 years
in
the
Gulf of
Mexico
to
was
not
abnormal
the
the
Transocean and
that
off.157
drilling
crew expect an
leave
slight
trapped pressure
pressure
rise
on
standpipe reasonable
he
would
after the
pumps were
shut
When
could
using
excessive
typical
amount
pressure
of
mud logger
expect such
Further standpipe
are kick
not
trained
to
associate
in
increases
in
pressure standard
in
As
described are
my Opening
taught
to
Expert
is
Report decrease
indicator
mudloggers
likely
expect
pump pressurenot an
psi
if
increase.158
On Joe
be
difficult
5000
Even
to
pressure
200
psi
increase
would
the
at
to detect
he had
normally
increase
because
pressure
appeared
the
behave
once
the
displacement
resumed
914
PM
reasonable mudlogger
during
may have
By
the
discounted time
anomaly
sheen
test
more
pressure
around
with
930
Drilling
PM
the Transocean
halted
crew had
At
for
problems
the well
and crew
point
the
to the
Transocean
had
responding operations
not participate
well
control
he merely
monitoring.161
As
several
thoroughly
of
discussed
parties
my Opening
the
is
Report
driller
and has
supported
primary set of
by
well
the
other
experts162
monitoring
responsibility
drilling
and
the
mudlogger
traditionally
just
second
more
eyes
on
the
well
crew
has
training
than
157
Keith
Depo
drill
3/28/2011
at
10316-25
90 percent
of the
off
158
crew do shut the pumps off they do not bleed the stand pipe pressure and sometimes the pressure will come up little bit and then level out. See
also
HAL0051030
Surface
Data
Logging
Core
Fundamentals
at
159
SeeJ
Gisclair
Depo
114
3/14/2011
at
691-12
160
Beck Report
at
161
590
162
Well
Control
Handbook
Section
Subsection
5.15
Exhibit
at
103-107
BP
at
11 and
Grace
Report
BP
at
51
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
mudlogger
data not
activities
drilling
has
higher
to
certification
requirements such
arise
and
is
able
of
to
access
rig
available
the
mudlogger
an anomaly
is
as knowledge
in
ongoing data
Also
not
should the
the
mudlogging
action to
the
crew
mudlogger
able
to
take
diagnose
and
Joe
Keith
properly monitored
all
data available
to
him and
to stop the
that
if
displacement
mudlogger
BPs
not aware
expert
of
all
Dr Azar appears
parameters
at
to
all
suggest
the
was
well
times he should
with
have
stopped the
that the with
is
displacement.163
While
to
do not disagree
continuously
the general
assertion
is
required
that
do disagree
data
that
implication to
the
mudlogger
is
monitor
not
him
BP
Transocean
that
and
SWACO
total
knowingly
to
designed
of his
executed
kick
displacement
indicators164
blinded
that
the
pit
mudlogger
some
traditional
and
not
knew
be
to
gas concentration
they discharged the
and
the not
to
Sperry
flow-out
data
would
available the
when
he
As
all
backup
driller165
mudlogger would be
was
stop
operations
simply
because
unable
monitor each
well
site
and
every
BPs Macondo
BP and
M-l
material
leader
has
confirmed
Indeed
the
because
lost
SWACO
appeared
it
determined
is in
to that
discharge
circulation
by the mudlogger any concern raised any change to the overboard discharge procedures
that
doubtful
simultaneous operations
are
part
of drilling
do not disagree
and 44
However when
contemplating
Azar Report
BP
it
at 11
164
See e.g
is
Sepulvado
isolates
Depo
flow
5/11/2011
at
37424-37620
Sepulvado
that
dump
3225-
valve
open
swing
pretty
their
flowmeter
shows
over
will
Depo
crane
3/10/2011
at
3410
and 53322-5348
the crane quick
The
with
change
the
operations
make them
change
volume
well
165
in
load
the side
thing
And
thats the
same
30-barrel increase in you may get see when kick out of the you you get
the
well.
at 103-1
Beck Report
07
leader
flow-out
166
BPs Macondo
inform
well
site
Ronnie Sepulvado
sensor
would
not
expect
the mudlogger
to
him
at
if
the Sperry
was bypassed
See
Sepulvado
Depo
3/10/2011
1263-1276
52
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
simultaneous
impact
until
it
operations
safety
is
the
operator
or else
must
ensure
that
any
adverse
on can
rig
mitigated
be
conducted
require
safely
that
This
specified
in
BPs own
of or field
written
practices operations
to identify
which and
the
risk
assessment on each
simultaneous
in
threats
shall
be performed
facility
order
risks across
the complete
range
of well
activities.167 prior to
have
the
final
seen
no evidence
such
an
assessment
was conducted
Macondo
Further
relied
influx
in
some
pit
of
BPs
and
is
experts
that to
BP
reasonably
if
on Sperry and
Sun
to monitor
levels
flow rates
determine
an
of formation
fluids
had
occurred169
drafting
approved
opinion
the displacement
difficult
is
BP made
assisted
pit
level
and
flow rate
In
monitoring
before
910 PM and
by
impossible
after that
time.7
for
its
my
this
BP
to shift the
blame
own poor
decisions to one
contractors
all
Nevertheless evidenced
by the
Joe
four
Keith
monitored
data
available
to
him as
the
final
anomalies
data
of
he
communicated
none
the well
during
displacement.171 indicators
The
Keith
available
exhibited
of the
traditional
until
kick after
Joe
had
no
way
knowing
was
kicking
167
Depo Ex 1575 BPs ETP GP 10-75Simultaneous Operations see also Depo Ex 6121 at BPHZN-BLY00034593 2197MDL00408287
and
Well Operations
shall
at
BP-HZN
Drilling
BPs
place
Practice
Major Depo
Accident
Hazards
mitigations
as
result
of
Simultaneous
in
be identified so that
controls
and
at
can be
put
before
takes
place
transfers
and
Ex
590
TRN-MDL-00286819
in
Control
Handbook
pit
noting
to the
individuals
involved
rig
activity critical
should
treatment
168
and
absolute
minimum during
sections of the
See
Bellow
Depo
05/03/11
at
6274-16
and 63422-63519
169
Grace Report
BP
Billon
at
170
Depo
6/24/2011
at
36521-36711
9/14-15/2011
at
Keith
Depo
3/28/2011
at
1363-7 2439-24421
at
Lindner
Depo
12523-1307
3/10/2011
at
23110-17
and 4495-14
Sepulvado
Depo
476-481
110
53
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
the
Transocean
drilling
crew
had
already
recognized
an
anomaly
and
stopped the
BPs
control
drilling
conclude
kick
that
reason
in
for the
loss
of well
was
crew
the the
was
not
detected
time
by
the
Transocean
kick
and
in
Sperry
mudlogger.173
partially
agreethe
of
not detected
time by Transocean
and
BP
not
with
was them
after
The
to
Sperry
mudlogger
that
had
no data
steps
clearly
indicative
Moreover
well
the
extent
proper
were
taken
to
shut
the
930 PM
and Joe
and
blowout
shoulders
ensued
that
responsibility
falls
squarely
on
Transoceans
had the
Keith
because
they were
aware
of the
pressure
anomaly
ability
and
the responsibility
to activate
the
blowout preventer
had neither
Joe
Keith
could
have
indicated should
alerted
Some
his InSite
in
experts
have
Keith
set alarms
to
in
monitoring
well
software
would
did
have have
any
the not
slight
change
alerted
status.174
Joe no
fact
alarms
that
to of
is
monitor
the
displacement
there
to
is
indication
that
however
any
It
alarms always
Mr
to
Keith
the
the
well kick
was
flowing For
possible
indicators
example
pit
pit
when
will
pumping
constantly
into
from
an
unmonitored
set
to
sea
chest
slight
volume
gain
increase sound
An
final
alarm the
detect are
would
continuously
because
pits
continuously
of flow-out
gaining
mud
at over
displacement
If
the rate
peaked
to
1200
172
gallons
per
minute.76
Joe
Keith
had
set an
alarm
monitor for
Some
Keith
have suggested
took
that
an 8-10 minute
Joe
some
at
time between
830
PM
break
restroom coffee and cigarette break that and 900 PM was improper See e.g Abel
Report
entirely
Cameron
reasonably
implication
44
completely restroom
is
disagree
When
April
working
12
hour
shift
it
is
to take
provided
proper safeguards
Mr
Abels
otherwise
the
disingenuous
driller
On
20
Joe
Keith
took
proper
safeguards 3/28/2011
173
by
at
alerting
assistant
he was
taking
break
Depo
15117-1 5217
Report
and 23616-22
at
BP BP
at
BP
65
at
66-67
174
Report
at 12
BP
at
175
Depo
Ex 620
3/28/2011
33119-24
176
Depo
54
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
excessive
displacement and
the
he would
in
have
at
set
it
higher than
1200
gallons
minute
increase
flow
908
PM177 which
his
kick indicator would not have some have cited as this flow was less than 1200 gallons per minute to reset flow-out nor common practice practical
triggered
It
alarm as been
the time
would
not have
alarm every
the
Transocean
drilling
crew
is
changed
of
pump speed
exhibited
during
displacement
the
final
The
same
thing
true
standpipe
pressure
frequent
During
standpipe
it
pressure
and
significant
fluctuations
for
would
to set
have
been
impractical
under
the
Joe
Keith
alarms which
would
be meaningless only
Moreover
Opening
values
to
without the
schedule
as described have
in
my
Report78 use
not necessarily
known what
when
setting
alarms during
in
complex
displacement
how
the
rig
was
to be
run
agree
that closed-pit
As
is
described
in
my Opening
of
Report conducted
expert
system
that
the
preferred
method have
operating
displacement
in
and
the
displacement
closed Sperry
pit
could
been
manner which
utilized
system.179
to
Camerons
in
alleges that
and
pit
failed
maintain
material
to
balance180meaning
system as described
Appendix
is
my Opening
manner
in
which
the
rig
plumbed
during
177
Note
result of
it
is
not
clear
in
flow-out
was due
to or
flowing
well
was
by
rig
the
trip
tank
dump
which
began
around
959
at
PM
was caused
movement and
178
crane
operations
at
Report
110-112
5/11/2011
at
See Beck
Report
113
See also
Sepulvado
Depo
would
2098-25
and
2131-6
179
Note
Sperry
alternate
routings online at
available
that
have
at
least
allowed
the
flow
remain
while
displacing
overboard
See
5125
180
US
e.g
Depo
Ex
18
Abel
Cameron at 14
55
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
decision.181
BP
the
fluid
in
Transocean
and
and
M-l
SWACO made
to divert active
the
decisions
to
pump
from
unmonitored
into
sea
chest
overboard
pits.182
and
Sperry
to
move
no Joe
additional
had
these
which
simply
well
monitoring
situation
Sperry
with
mudlogger
the
he
was
presented
using
the sensors
made
him
by the surviving
BPs
In
expert
mudlogging
his
opening
report
in
BPs
expert
Robert
Grace
identified
three
anomalies
that
do not see
stated
the Sperry
data
Mr
drill
Grace
852
remained
PM
the
the
string
pressure This
constant
time
the
well
was
seems to imply the pressure response was caused by when in fact the reduction in pump rate was on the booster
is
pump
the
which
not connected
In
to the
standpipe the
and
thus
has no
effect
on
pressure
in is
truth
when
PM
the
well
in
also
decreased
did
not
remain
constant
shown
the data
below
181
Billon
Depo
6/24/2011
at
36521-36711
9/14-15/2011
at
Keith
Depo
3/28/2011
at
1363-7
Lindner
Depo
4425-4511
14924-1504
47215-21
of
USCG/MMS
of
is
and 47921-4806 at 476-481 Sepulvado Depo 3/10/2011 Guide testimony 7/22/2010 at 161 24-1624 Investigation
USCG/MMS
Transocean
certain
Investigation that
it
operates are
this
Guide testimony 7/22/2010 at 161 24and BP that makes the decision as rig
to
to
not that
operations That
is
going
be performed
Billon
and
when
at
they
are
performed
correct
36711
15/2011
Keith at
Depo
3/28/2011
at
correct 857-887
Depo
6/24/2011
36521-
12523-1307
23110-17
at
and
Sepulvado
183
Depo
3/10/2011
at
476-481
Grace Report
BP
18
56
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
LU
9r
-I\
rfl
.1
.1
rTJ
.1
FT
rTl
cc
cc
Q_
TI Fl
211511
21
1111
2i
ii
2i
Figure
incorrectly
by
BPs
expert
Mr Grace
Mr
to
Grace
also stated
roughly
drill
859
PM
to
the
pumps were
The
analysis
further
on the
this
string
184
began Again
increase
well
is
had
not
at
time
data
Mr Graces
consistent
with
mudlogging decreased
reveals
is
When
the
859
of the
this
PM
the
pressure data
as would
be expected
beginning
analysis
surviving
pressure
increase
900
of
PM
but
pressure detected
increase
in
not
something
especially
including well
reasonable
given the the
pits
mudlogger
would
several
have
real
time
simultaneous
the then
trip
pit
fluid
transfers switching
in
dumping
emptying
pit
tanks
and
returns from
Report.185
to
and
as discussed
my Opening
what
Finally
Mr
Grace
identified
he believes
the
is
an
inconsistency
that
drill
sheen
periods
of constant
pump
then
it
pressure
until
about
926
were
PM
and
began he
is
to decrease.186 referring
am
periods
the
of constant
pump rates
the
to
During
this
drillers
staggering
pumps and ramping them up gradually as can be seen in the data above According to Joe Keith this was abnormal behavior and Mr Keith called to Between 914 PM and 926 PM there are no periods where investigate.187
184
Grace Report
BP BP
at
18
to the
185
Beck Report
at
35-39
186
19
187
at
110
57
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
the
pump
rates
steady
to
draw
any conclusions
the
rate
about
well
flowing
from the
is
response.188
Rather
observed increases
in
response
generally
as one
would
expect
as
total
pump
increases
Once pumps
is
level
off
pressure
the well
displaced
by lighter seawater
Summary
My
of
opinions
and
In
conclusions
as set
forth
in
my Opening
conduct
Report
remain unchanged
the well
my
opinion
BPs
did
and
to
lesser extent
Transoceans
not
in
caused and
are
the not
blowout
Halliburton
and
Sperry
any
way cause
thereof
responsible
consequences
188
C.f
Heenan
rig
Report
US
is
at
23 Noting
from
that
pressure
to
particularly to
in
real
personnel
difficult
2115
2130 due
changes
in
pump rate.
58
CONFIDENTIAL
REBUTTAL
EXPERT
REPORT
OF
DR
FREDERICK
GENE
BECK
reserve
additional
the
right
to
modify
this
report
and
in
to
supplement
to
my
opinions
if
data
becomes
available
and
response
reports served
by
other parties
Dated
Frederick
Eug
ne Beck
59
CONFIDENTIAL
MDL NO
In
2179
the Gulf of
re
Oil Spill
by the
Oil Rig
Mexico on
April
20 2010
DR FREDERICK
RELIANCE APPENDIX
BP-HZN-21 79MDL00269659-269673
HAL_0048974
BP-HZN-MBIOO1
28708-128756
BP-HZN-21 79MDL03082878-30831
51
IBP-HZN-21
79MDLO1
591 521-1591535
of
Pages
TRN-INV-01
747442-1
747659
6/20/2011
Macondo
Application E-mail
Well Incident
for
Transocean
to Drill to
Investigation
Report
Volume
Permit
Hafle
New
Well Subject
from Mark
Brian
Morel
Macondo
9-78
LOT
FIT Worksheet.xls
marked
BP-HZN-MBI
00125958
4242 4842
4/12/2010
April
12 2010 Macondo
string
from David
Sims
to
Brian
Morel
from
Brian
Morel
to
David
Sims
times
marked
job
as Confidential
Presentation
re designing
cement
5125
6121 6291 6320 6321 60071
9/30/2010
string
among
Well
Drilling
Wesley
Bell
et
al
practice for
BP
3/31/2009
Drilling
and
Practice
EP
Defined Operating
GP
10-00
of
Completions marked as
DC
Recommended
Practice
Management
31 2009
of
CONFIDENTIAL
Mexico
to
BP-HZN-2179MDL00032979-32981
from
Mr
Daly
Mr
Inglis
Benge
Lewis
USA
before
60079 60080
60081
6/11/2010 10/17/2011 10/17/201 10/17/2011 4/16/2010 8/31/2011 10/7/2010 8/24/2010 12/7/2010 9/23/2011 11/8/2010
Jesse
Gagliano
US House
of
Representatives
Expert Report of
Sam
Halliburton
Drilling
and
Monitoring
Hughett
Halliburton
BP
Daily
Operations
Report
Partners
Completion
USA
USCG/BOEM USCG/BOEM USCG/BOEM
Investigation Investigation Investigation
60124
TO
BP Deepwater
30
Part
HAL 0506948-507095
The 60504
National
Commission on
Horizon
Oil
Spill
and
Offshore
Drilling
Hearing
Transcript
Code
60521
of
Title
250
Oil
and
Gas and
Sulphur Operations
in
the
Outer
Continental
30
PIs
CFR
08-26-1
250
08-26-1
8/26/201 8/26/201
David
Pritchard
PIs
Dr Alan Huffman
Submitted
on
States
Department
of
8/26/201 Justice
7/22/2010 8/27/2010
Testimony
of Joint
60815
Investigation
of
Pages
BP-HZN-BLY00061
224-61227
5/1
1/2010
Handwritten
Halliburton
Notes
7/8
Production
Casing
Initiate et
BP BP BP BP
Drilling
Completions Cocales
to
MOC
Email from
Walz
for
al
re
Cement Procedure
Supplemental
Authorization
Authorization
for
Expenditure
Macondo
4/15/2010 01/00/2001 9/16/2010 5/11/2010 3/8/2010 4/16/2010 10/25/201 10/17/2011
10/1 7/20
Production
7/8
Production Logging
Morel
Core
to
824082
TSC
of
Conrols
Flow
Line
Sensor Committee
Senate
Energy
and
Natural
Resources
Data Data
for
M-l
LLC by George
Medley
Jr P.E
MOEX
Anadarko 7/8
Production Casing String on the
Evaluation
of the
Macondo
10/17/2011
3/10/201 10/1 7/20
Well
Sepulvado
Report
Ronald Burch
Deposition
Transcript
of Morris
BP
Sutcliffe
Ph.D
Chuck Schoennagel
Behalf of
L.L.C
MMS
Regulatory
Regime
Expert Report on
BP
Robert
Grace
P.E
Calvert
Weatherford
Azar Ph.D
BP BP
VVeatherford
Adam
\Nilliam
Bourgoyne
McCormack
Abel
Cameron
P.E LA and
10/17/201 10/17/2011
Weintritt
TX Retired
Casing Cementation Operation by Ian
Macondo
9-7/8
Production
Cameron
Trahan
Lirette
Cameron
on Behalf of Weatherford
U.S
L.P
Marion
Woolie
Deposition
Weatherford
Transcript
Walz
Gregory Stephen
of
Pages
_________
4/22/201
Walz
Review
Gregory Stephen
of the
Deposition
Transcript
Production
Casing Design
Transcript Transcript
forthe Macondo
Well
Lewis
Chaisson Sepulvado
Nathaniel
Deposition
Murry Deposition
Deposition Deposition
Tiano Robert
Keith Joseph
Transcript Transcript
Summary and
Conclusions
Deepwater
Horizon Incident
prepared
by Morton
Emilsen
BP
Cameron
Deposition
Transcript Transcript
Deposition
Lindner Lindner
Thomas Thomas
Deposition Deposition
Transcript Transcript
Lacy
Kevin
Deposition Deposition
Guide John
5/20
OBryan
Breazeale Corser
Patrick Martin
Deposition Deposition
5/16/2011
2/10/201 10/1 1/201
Ken
Deposition
Transcript Transcript
Deposition
4/26/201
Brett Deposition
Transcript
10/17/2011
4/15/201 7/29/201 5/3/201
Bolado
Transcript Transcript Transcript simulation
Gray
Kelly
Deposition
Deposition
Beck
Rebuttal
Figure
BPs OLGAs
shows
that
most
of the
kick
volume
was
not
detectible
Beck Grace
Rebuttal
Sperry
mudlogging
data interpreted
incorrectly
by
BPs
expert
Mr
of
Pages