You are on page 1of 19

MD 021 - Operations Management Capacity Planning and Decision Theory

Measures of capacity Bottlenecks Capacity strategies A systematic approach to capacity decisions Make or Buy problem Decision making under uncertainty and risk

Capacity Planning

Capacity is the maximum rate of output for a facility. Capacity planning considers questions such as:

Should we have one large facility or several small ones? Should we expand capacity before the demand is there or wait until demand is more certain? Should we invest in flexible or non-flexible capacity?

Measuring Capacity Measurement Type: Output measure for product focus Input measure for process focus

Actual Output Utilization = Design Capacity

Actual Output Efficiency = Effective Capacity


Effective Capacity = Design Capacity (maximum output rate) Allowances (e.g. personal time, maintenance, and scrap)

Sizing Capacity Cushion


Cushion: the amount of the reserved capacity that a firm maintains to handle sudden increase in demand or temporary losses of production capacity. Capacity cushion =1 - Utilization

Pressures for Large Cushion Uneven demand Uncertain demand Changing product mix Capacity comes in large increments Uncertain supply

Pressure for Small Cushion Capital costs

Links with Other Areas

Other Choice Faster delivery times Smaller yield losses Higher capital intensity Less worker flexibility Lower inventories More stable schedules

Cushion Larger Smaller Smaller Larger Larger Smaller

Optimal Capacity Level


Average cost per unit

Optimal rate

Rate of output

Two Capacity Strategies


Forecast of capacity required Forecast of capacity required

Capacity

Capacity

Planned unused capacity

Planned use of short-term options

Capacity increment Time between increments

Capacity increment Time between increments

Time (a) Expansionist Strategy

Time (b) Wait-and-see Strategy

Large economies of scale Cost of lost sales is high Increases in demand are fairly certain Most capital intensive businesses shy away from expansionist strategy

Short-term options available Customers accept backorders Cost of over-capacity is high Technology becomes obsolete quickly

Bottleneck
A mortgage review process:
20/hr
Step 1 Accept mortgage applications

5/hr
Step 2 Review applications and verify information

10/hr
Step 3 Decisions (and fund transfer if approved)

What is the capacity of this process?

Bottleneck operation: An operation in a sequence of operations whose capacity is lower than that of the other operations. The capacity of a process is the capacity of the bottleneck operation.

A Systematic Approach to Capacity Decisions

1. 2. 3. 4.

Estimate capacity requirements Identify gaps Develop alternatives Evaluate the alternatives

10

Estimate Capacity Requirements 1. One type of product


Numbers of machines required = Processing hours required for year's demand hours available from one machine per year, after the desired cushion deducted

M =

Dp N (1 C )

where D = number of units (customers) forecast per year p = processing time (in hours per unit or customer) N = total number of hours per year during which the process operates C = desired capacity cushion rate (%)

11

2. More than one type of product: n types of products


Numbers of machines required = Processing and setup hours required for year' s demand, sumed over all products hours available from one machine per year, after the desired cushion deducted

M =

[ Dp + ( D / Q ) s ] product 1 + [ Dp + ( D / Q ) s ] product 2 + ... + [ Dp + ( D / Q ) s ] product n N (1 C )

Q = number of units in each lot s = setup time (in hours) per lot Note: Always round up the fractional part for the number of machines required.

12

Capacity Planning Problem You have been asked to put together a capacity plan for a critical bottleneck operation at the Surefoot Sandal Company. Your capacity measure is number of machines. Three products (mens, womens, and kids sandals) are manufactured. The time standards (processing and setup), lot sizes, and demand forecasts are given in the following table. The firm operates two 8-hour shifts, 5 days per week, 50 weeks per year. Experience shows that a capacity cushion of 5 percent is sufficient.
Time Standards Processing Setup Lot Size (hr/pair) (hr/lot) (pairs/lot) 0.05 0.5 240 0.10 2.2 180 0.02 3.8 360 Demand Forecast (pairs/yr) 80,000 60,000 120,000

Product Mens sandals Womens sandals Kids sandals

a. How many machines are needed at the bottleneck? b. If the operation currently has two machines, what is the capacity gap? c. If the operation can not buy any more machines, which products can be made? d. If the operation currently has five machines, what is the utilization?
13

Capacity Planning Problem Solution Total time available per machine per year: (2 shifts/day)(8 hours/shift)(5 days/week)(50 weeks/year) = 4000 hours/machine/year With a 5% capacity cushion, the hours/machine/year that are available are: 4000(1-0.05) = 3800 hours/machine/year Total time to produce the yearly demand of each product: (This is equal to the processing time plus the setup time.) Mens =(0.05)(80,000)+(80,000/240)(0.5)= 4167 hrs Womens =(0.10)(60,000)+(60,000/180)(2.2)= 6733 hrs Kids =(0.02)(120,000)+(120,000/360)(3.8)= 3667 hrs

Total time for all products =4167+6733+3667= 14567 hrs

14

a. Machines needed = (14,567/3800) = 3.83 = 4 machines

b. Capacity gap is 4 - 2 = 2 machines

c. With two machines, we have (3800)(2) = 7600 hours of machine capacity. We can make all of the womens sandals (6733 hours) and some of the mens sandals, for example.

d. With five machines, (5)(4000) = 20,000 machine-hours/yr are available. The total number of machine-hours/yr needed for production is 14,567. Utilization = (14,567/20,000)(100%) = 73%. Thus, the capacity cushion is (100% - 73%) = 27%.

15

Vertical Integration Problem: Make or Buy


Hahn Manufacturing has been purchasing a key component of one of its products from a local supplier. The current purchase price is $1,500 per unit. Efforts to standardize parts have succeeded to the point that this same component can now be used in five different products. Annual component usage should increase from 150 to 750 units. Management wonders whether it is time to make the component in-house, rather than to continue buying it from the supplier. Fixed costs would increase by about $40,000 per year for the new equipment and tooling needed. The cost of raw materials and variable overhead would be about $1,100 per unit, and labor costs would go up by another $300 per unit produced. a. Should Hahn make rather than buy?

b. What is the break-even quantity?

c. What other considerations might be important?

16

Decision Making Under Uncertainty Decision Rules

Maximin: Choose the alternative that is the best of the worst. Maximax: Choose the alternative that is the best of the best. Laplace: Choose the alternative with the best weighted payoff. Minimax regret: Choose the alternative with the best worst regret (i.e., opportunity losses).

17

Decision Making Under Uncertainty Profits Event 1 (Low demand) Event 2 (High demand) Alternative 1 (Small facility) $300 $200 Alternative 2 (Large facility) $50 $400

Decision rules: Maximin: Maximax: Laplace: Minimax regret:

18

Decision Making Under Risk

Profits Event 1 (Low demand) Event 2 (High demand) Probability = 0.3 Probability = 0.7 Alternative 1 (Small facility) Alternative 2 (Large facility) $300 $50 $200 $400

Use the expected value decision rule:

19

You might also like