Professional Documents
Culture Documents
Copy No.
PROJECT IMPLEMENTATION
STATUS REPORT
ON
CENTRAL SECTOR PROJECTS
(COSTING RS.20 CRORES & ABOVE)
JANUARY-MARCH, 2004
CONTENTS
FOREWORD
LIST OF ABBREVIATIONS
i-iv
INTRODUCTION
1-3
PART-I
PART-II
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
OVERVIEW
SECTORAL ANALYSIS AND PROJECT STATUS
4-26
ATOMIC ENERGY
CIVIL AVIATION
COAL
FINANCE
FERTILISERS
INFORMATION & BROADCASTING
MINES
STEEL
PETROCHEMICALS
PETROLEUM & NATURAL GAS
POWER
HEAVY INDUSTRY
HEALTH & FAMILY WELFARE
RAILWAYS
ROAD TRANSPORT & HIGHWAYS
SHIPPING & PORTS
TELECOMMUNICATIONS
URBAN DEVELOPMENT
WATER RESOURCES
27-36
37-40
Appendix-I
Appendix-II
Appendix-III
Appendix-III-A
Appendix-IV
Appendix-IVA
Appendix-V
Appendix-VI
Appendix-VII
Appendix-VIII
Appendix-IX
Appendix-X
Appendix-XI
Appendix-XII
Appendix-XIII
41-67
No project
68-70
71-73
74-76
77-79
No project
80-108
109-134
No project
135-137
138-212
213-243
244-256
257-262
263-271
272-273
274-281
282-290
291-297
298-307
308-314
315-319
320-325
326
327-328
329
330
331-332
333
334
335-342
HIGHLIGHTS
Originally estimated cost of 568
projects
22.7%
6.4%
49.05%
168
59
FOREWORD
The Quarterly Project Implementation Status Report on the Central Sector Projects (costing Rs.20 crore and above) for the quarter January-March,
2004 covers 568 projects. It provides information on 45 mega projects (costing Rs.1,000 crore and above), 258 major projects (costing between Rs.100
crore and Rs. 1,000 crore ) and 265 medium projects (costing between Rs.20 crore and Rs. 100 crore). The anticipated cost of these 568 projects is Rs.
2,47,039 crore. The total expenditure till 31.03.2004 was Rs.96,149 crore, i.e., about 38.92 % of the total estimated cost. Against an approved outlay of
Rs.36,105 crore for the year 2003-04, the expenditure up to the end of the year quarter is Rs.28,546 crore. Major and Mega projects account for about
53.3% of the total number of projects and about 94.7% of the total anticipated cost. At the beginning of the year 2003-04, 168 projects were scheduled to be
completed during the year. In addition, 38 projects were added during the year with dates of completion by March, 2004. Hence out of the 206 projects due
for completion during the year, 59 projects have been completed, 69 projects have slipped beyond March 2004 and for 29 projects, latest status is not
available. Most of the projects in the Railway sector does not have a firm date of commissioning. Part I of the Report gives an overview of implementation
of projects during the quarter. Part II gives a sectoral analysis and the status of individual projects.
2.
The implementation of projects during the quarter ending March, 2004 has been compared with the status in the quarter ending March, 2003. Table
1 and 2 set out the figures with reference to the original and revised schedules.
Table - 1
Status of Projects with reference to the Original Schedule
(Number of projects)
March 2003
March, 2004
Ahead of schedule
45
31
-14
On Schedule
161
152
-9
Delayed
226
211
-15
62
149
87
46
25
-21
Total
540
568
28
8.3
5.5
-2.8
11.5
26.2
14.7
41.9
37.1.0
-4.8
Table 2
Status of Projects with reference to the Latest Approved Schedule
(Number of projects)
Ahead of schedule
45
March,
2004
30
On Schedule
176
162
-14
Delayed
211
202
-9
62
149
87
46
25
-21
Total
540
568
28
8.3
5.3
-3
11.5
26.2
14.7
39.1
35.6
-3.5
March, 2003
Table 1 and 2 show that the performance of implementation of projects during the current quarter has not been satisfactory as compared to that in the same
quarter of last year. There is a decline in the number of projects running on schedule, and ahead of schedule. However, there is a decline in the percentage of
delayed projects. The graph given below depicts the trend in changes in the number of projects on schedule. It may be seen that the number of projects on
schedule has been increasing consistently despite the increasing complexity of the projects under implementation.
o je c ts o n s c h e d u le w .r
.t. rro
o ig in a l s c h e d u le
N o . o f p rro
.r.t.
16
60
0
1
148
140
No.
projects
No.
ofof
projects
140
120
120
148
119
119
100
148
123
108
123
112
108
100
120
112
120
131
131
135
115428
135
88
80
88
80
60
60
40
40
20
20
0
0
1994
1994
1995
1995
1997
1996
1996
1997
1998
1998
1999
1999
y ea
rs
2000
2000
y ears
2001
2001
2002
2002
2003
Dec.2003
Mar. 2004
3.
There are 149 projects on the Monitoring System, for which the latest approved completion schedules or anticipated Date of Completion (DOC)
have not been indicated. Out of these, 132 are in Railways, 4 each in Shipping & Ports and Urban Development, 3 in Coal, 2 each in Water Resources and
Road Transport & Highways and one each in Steel and Health and Family Welfare sectors. The anticipated cost of these projects is Rs. 28,313 crore, as
against the original cost of Rs. 19,518 crore. The total expenditure incurred up to 31-03-2004 on them was about Rs. 5,764 crore. The details of these
projects are given in Appendix IV (A) of the Report. The sector-wise details of the projects covered in Table 3 under various heads are given in the
following statement:
Sector / Month
Atomic Energy
Civil Aviation
Coal
Fertilizers
I&B
Mines
Steel
Petroleum & Natural
Gas
Power
Health & Family
Welfare
Railways
Road Transport &
Highways
Shipping & Ports
Telecommunications
Urban Development
Water Resources
TOTAL
Table-3
Sector wise Implementation Status of Projects with reference to original schedule
(Number of Projects)
Ahead
On schedule
Delayed
Without DOC
DOC not firmed up
03/2003 03/2004 03/2003 03/2004 03/2003 03/2004 03/2003 03/2004 03/2003 03/2004
1
0
1
0
0
0
0
3
1
0
0
0
0
0
0
1
3
0
32
0
0
1
4
15
5
0
41
2
0
1
3
16
2
4
26
1
2
2
3
10
1
2
21
1
1
2
2
13
0
0
0
0
0
0
1
0
0
0
3
0
0
0
1
0
2
1
0
0
1
0
0
3
3
1
0
0
1
0
0
2
4
0
1
0
24
0
29
0
17
2
20
2
0
1
0
1
0
0
0
0
2
33
1
26
29
36
16
17
58
57
42
73
56
0
132
2
23
8
9
1
0
1
0
0
45
1
0
0
0
31
12
1
4
0
161
11
4
7
0
152
26
9
7
0
226
20
7
4
0
211
2
0
0
2
62
4
0
4
2
149
6
2
0
0
46
3
3
2
0
25
4.
A comparative analysis of sector-wise performance with reference to the performance in the preceding period of the last year as indicated in
Table-3 brings out the following:
Performance
Sector
Better
Poorer
No appreciable
change
Mines,
Power,
Steel,
Petroleum,
Shipping
&
Ports
and
Telecommunication
The performance of projects in the Coal, Fertilisers, Telecommunications, Urban Development and Atomic Energy sectors have shown an improvement.
The Statement in Table-2 shows that there are 41 projects in the Coal sector, which are ahead of or on schedule during the current quarter as compared
to 33 in the same period last year. The number of delayed projects have also come down from 26 to 21 in this sector for the corresponding period. In the
Steel sector, the number of projects ahead of or on schedule are 3 in the current quarter as against 4 in the same quarter last year, and the number of
delayed projects are 2 as compared to 3 of last year. In Shipping & Ports sector, also the projects ahead of or on schedule during the current quarter is same
as compared to 12 in the same quarter last year and the number of delayed projects have come down from 26 to 20. On the other hand, performance of
projects in the sectors of Railways and Road Transport & Highways has slipped in 2004 as compared to 2003 for the corresponding quarter. The total
number of delayed projects in these two sectors are same i.e. 115 for the corresponding period of the both years. But , whereas the number of delayed
projects have come down from 58 to 42 in Railway sector, the number of delayed project have gone up to 73 from 57 in Road Transport & Highways sector.
The number of projects which are ahead of or on schedule in these two sectors has declined from 100 to 60. In the remaining sectors, there is no
appreciable change.
5.
Time and cost overruns have been a major problem affecting the central sector projects. An analysis of cost overruns of 211 delayed projects during
the January-March, 2004 quarter shows that 19 projects have contributed more than 90% of the cumulative cost overrun among all the delayed projects.
Similarly, the number of projects with large time overruns is very small. While most of these projects had serious problems in the past, these are now in
fairly advanced stages of completion.
6.
There has been a continuous decline in the extent of time and cost overrun attributable to closer monitoring and system improvements brought about
by the Ministries concerned with the support of the Ministry of Statistics and Programme Implementation. An analysis of cost overrun in the last 13 years
with respect to the originally approved cost shows that the cost overrun has declined from 62% in March, 1991 to 22% in March, 2004 resulting in a
substantial reduction in the potential dissavings of the order of Rs. 1,09,000 crore.
The chart below gives the trend of cost overrun ( with reference to originally approved cost) in Central Sector Projects.
5
T re n d o f C o s t O v e rru n
70
60
30
20
10
% of cost overrun
% of cost overrun
50
5 5 .8
5 5 .1
70
40
T re n d o f C o s t O v e rru n
6 1 .6
60
5 3 .9
4 8 .4
50
5 1 .4
6 1 .6
5 5 .1
5 5 .8
5 7 .5
5 6 .8
5 3 .9
5 6 .8
4 6 .9
5 7 .5
45
5 1 .4
4 8 .4
4 6 .9
4 0 .9
3 7 .3
45
40
3 7 .3
36
36
4 0 .9
36
26
36
30
26
2 2 .3
20
2 2 .3
2 2 .4
2 2 .4
10
0
1 9 808
1989
1988
1990
1989
1991
1990
1992
1991
1992
1993
1993
1994
1994
1995
1995
1996
1996
1997
1997
1998
1998
1999
1999
2000
2000
2001
2001
2002
2002
2003
M ar.
2004
2003
M ar.
2004
Y eYa er sa r s
7.
While the cost overrun due to general inflation cannot be avoided, the escalation on account of delays can be minimised. The Standing Committees
set up to study time and cost overruns and to fix responsibility have to be made more effective. It is hoped that through focussed attention and constant
monitoring by the administrative Ministries/Departments, the declining trend in time and cost overruns in project implementation can be accelerated.
(Adarsh Kishore)
Secretary to the Government of India
Ministry of Statistics and Programme Implementation
ii
ECL
EIL
EMP
EOT
ESP
FCCU
FE
FOIS
FPU
GAIL
GC
GDS
GIS
GT
GTPP
HCU
HEC
HEMM
HEP
HPCL
HRT
HSCL
HVDC
IAAI
ICT
IDC
IFFCO
IMG
IOC
IPCL
KV
L&T
LEP
LOI
LPG
LSTK
MAMC
MFL
MGCL
iii
MIS
MMSCMD
MMT
MOE&F
MT
MTY
MU
MW
NALCO
NBCC
NCL
NEC
NEEPCO
NFL
NH
NHPC
NIRE
NIT
NJPC
NLC
NMDC
NPC
NRL
OB
OC
OECF
ONGC
OPGC
P&M
PERT
PHT
PIB
PSLW
QRC
RAPP
RCE
RCF
ROB
ROH
iv
RTU
SAIL
SCI
SDH
SG
SP
ST
STPS
SSS
SUR
SWSU
TBM
TG
TPA
TPS
TPY
UG
ULDCS
VDU
WHRB
INTRODUCTION
1.
The Ministry of Statistics & Programme Implementation (MOSPI) is the apex-level central monitoring organisation of the Government of India for the
Central Sector Projects costing Rs.20 crores and above.
2.
As an apex institution for monitoring, the Ministry of Statistics & Programme Implementation has initiated several measures to improve the system and
procedures relating to project formulation, implementation and monitoring. The Project Monitoring Division of the MOSPI has strengthened the institution
of MOU system, 3-tier regular monitoring, adoption of network-based monitoring, extensive training of project managers, prioritization of projects
matching with available resources and several project-based interventions. A host of other measures like amendment to Land Acquisition Act and
development of Standard Rehabilitation Package, On-line Computerised Monitoring System (OCMS) etc. are under progress.
3.
Time and cost overruns in projects in the environment of uncertainties, inadequate funding, delay in land acquisition, law and order problems, general
escalation in costs, and high cost of capital cannot be eliminated altogether; but these can be controlled by suitable measures. The measures highlighted
above have definitely brought about improvement in the project implementation scenario. A study carried out by the Ministry shows that the cost overruns
in projects even with respect to original costs have come down from 62% in March, 1991 to 22% in March, 2004. The trend shows a continuous decline in
cost overruns. On an average 500 projects costing Rs.1,60,000 crores have been on the monitor of the Ministry. Assuming 6 to 7 years as average period of
completion of a project, the direct saving over a period of 12 years as a result of decrease in cost overruns of 40.0% is of the order of Rs. 1,09,000 crore (
1,60,000 x 0.40 (% saving in cost) x 1.712 (12 divided by 7)
4.
The MOSPI has been monitoring projects of 16 different sectors of the economy. A two-tier system of monitoring is adopted. While all projects are
monitored on quarterly basis, the major projects (costing between Rs.100 crores and Rs.1000 crores) and mega projects (costing over Rs.1000 crores) are
monitored on a monthly basis. The projects costing between Rs.20 crores and Rs.100 crores are defined as medium projects. Based on the computerised
data base and comments furnished by the project authorities/administrative Ministries and in-house analysis, the Project Monitoring Division (PMD) of the
Ministry prepares Monthly Flash and Exception Reports in respect of the major and mega projects and Quarterly Status Reports in respect of all the
projects. The present report presents macro analysis of the projects on the monitor of the MOSPI during the period January-March 2004.
5.
The other activities of the PMD during the period January-March 2004 were as follows:
A.
(i)
Examined the NHDP packages at the site in north Karnataka nad Goa and the report was submitted for necessary action by project authorities.
(ii)
The officers of the PMD attended the Quarterly Progress Review/Standing Committee Meetings for the following:-
i.
Pre-PIB meeting in respect of Transmission system associated with Kahalgaon STPP, Stage II (phase I) , NTPC, National Hydro Electric
Corporation, Nathpa Jhakri Hydel Project of the Ministry of Power and also department of Atomic Energy.
Tala and Kurichu Hydro project in Bhutan funded by Govt. of India.
PIB meetings in respect of Phase expansion of NALCO integrated Aluminium Complex in the M/o Mines and Setting of joint venture power
project of Nabi Nagar in the M/o Power.
Meeting of the re-Engineering group set up by M/o of Power for bringing reforms in the Extant Procedured for formulation and appraisal of
projects.
M/o of water Resources, Health and Family Welfare and Deptt. of Fertilisers to fix the responsibility for time and cost overruns for their respective
projects.
ii.
iii.
iv.
v.
vi.
vii.
viii.
Negotiation meetings on the proposal of the Ministry under Indo- German Coopration held in New Delhi.
Air India in M/o Civil Aviation and Hotel Corporation of India.
MOU meetings of NTPC &NHPC in M/o Power, NLC in M/o Coal, SAIL in M/o Steel , Coal India Limited, Indian Oil Corporation.
B.
i)
Being the central monitoring agency of the Govt. of India, it has been able to document problems faced by project authorities and experiences of
problem solving gained in different sectors. The Infrastructure and Project Monitoring Division (IPMD) of the MOSPI has been suggesting, from
time to time, various remedial measures to be adopted by the Administrative Ministries and project authorities for better implementation of
projects. The Division is engaged in examining the causes of time and cost overrun and identifying the bottlenecks during the implementation of
projects. It also examines specific projects with a view to fixing responsibilities for time and cost overrun. The major contributions of the Division
have been in creating awareness for bringing in qualitative change in the system of project management and implementation.
ii)
The PMD is assisting the Standing Committee of Secretaries and Group of Secretaries to bring second stage reforms on extant procedures and
approval of projects in public and private sector.
C.
(i)
Ministry of Coal initiated an exercise of prioritisation of projects based on the recommendations made by the MOSPI. As a result of this, six
projects in the coal sector were dropped.
As a result of the follow-up at the Ministers level, the Govt. of UP identified land for afforestation and released the forest land for Dudhichua and
Khadia coal projects.
In case of Varanasi-Ramnagar-Mughal Sarai By-pass project, the MOSPI with its vigorous follow-up at the highest level revived the
implementation of the project and facilitated getting the Bank Guarantee to the extent of Rs.4 crores encashed in favour of the Government.
In the past, Railway projects were being sanctioned by the Ministry of Railways without external appraisal and CCEA approval. As a result,
projects were often sanctioned at a conceptual stage without due regard to need, viability and availability of fund. Such projects remained under
implementation for a long time. For nearly 2 decades, after the creation of the PIB (for non-Railway projects), the government had been trying
to change the institutional arrangements. On the basis of the DPI's analysis carried out during 1992-93 highlighting the shortcomings in the
system of formulation, appraisal, sanction and implementation of the Railway projects, the Department of Expenditure prepared a note for the
CCEA recommending change in the system. The CCEA accepted the recommendation and ordered that the Railway projects costing Rs.50 crores
and above should be subjected to external appraisal and the Secretaries of the Planning Commission, Departments of Expenditure and
Programme Implementation should be associated with the Railway Board extended board for appraisal of Railway Projects for the consideration of
such projects, which would also require the CCEA approval.
The MOSPI has been drawing the attention of the authorities to a number of projects in various sectors which have made little progress or no
progress since their approval by the Government. It has also been emphasising that these projects which are 'frozen' should be dropped from
the list of active projects under implementation.
The problem of supplies by Bharat Heavy Plates and vessels Ltd. (BHPV) to 3 major projects, namely Revamp project of HFC and two refinery
projects at Digboi and Barauni of Indian Oil Corporation has been resolved through the intervention meeting taken by Secretary (S&PI) Secretary
(P & NG) and Secretary (HI). M/s. BHPV has been provided soft loan of Rs.20 crores by IOCL to resolve the Financial crisis of M/s. BHPV
coming in the way of timely supplies to the refinery projects.
(ii)
(iii)
iv)
v)
vi)
6.
Policy issues relating to Amendment of Land Acquisition Act of 1894 have been drawn up after examination of all the relevant issues on the subject and a
Bill to modify the Land Acquisition Act has been prepared by the Ministry of Rural Development for approval of both the Houses of Parliament.
In order to sort out the related rehabilitation and resettlement problems, a National Policy on Resettlement and Rehabilitation has also been evolved and
suitable initiative has been taken to incorporate the policy into a suitable legislative framework.
(ii)
The policy issues relating to standardisation of contract documents have been examined by the MOSPI, particularly in the light of constraints in award of
contracts, reasons for failure of contracts, poor contract management, etc., and a proposal for standardisation of contract management system has been
prepared. Standard Contract Management System consisting of (i) Standard Contract Clauses and (ii) Standard General conditions of contract has been
approved as guideline for adoption at the National level. The document has already been released. Efforts are being made to remove other weaknesses in
the Contract Management System in India.
(iii)
At the end of the year 2003-04, out of 206 delayed projects with respect to the original schedule, only 19 projects accounted for more than 90% of the total
cost overrun. More intensive monitoring of these projects would be undertaken with a view to expediting corrective actions by the agencies concerned.
Inter-ministerial issues, if any, relating to these projects will be taken up with the authorities concerned.
(iv)
Standing Committees
The institution of Standing Committees to review the time and cost overruns in projects and to fix responsibility therefor has been made more effective by
introducing a system of furnishing an action taken report on the recommendations of these Committees while recommending proposals for Revised Cost
Estimates for approval of the PIB/CCEA.
(v)
The Ministry carried out a detailed study on the various types of clearances (103 types), analysed their relevance in the present environment and made the
findings available to High Level Committee headed by Shri Govindrajan. The ministry assisted the Committee in bringing out its report in two volumes on
Extant Procedures for Project Formulation, Appraisal, Implementation and Monitoring. The recommendations have been accepted by the Government and
these are under implementation by all the agencies concerned. Ministry of Statistics & Programme Implementation is in the process of taking up postevaluation of completed projects which is one of the recommendations of the Committee.
7.
The macro analysis of 5682 Projects under implementation as on 31.03.2004 is given in Part-I.
TOTAL EXPENDITURE IN
Rs. Crores
% OF TOTAL COST
5%
45
5,005
32%
31,128
265
258
60,017
63%
MEGA
MAJOR
MEDIUM
MEGA
MAJOR
MEDIUM
MEGA
MAJOR
MEDIUM
OVERVIEW
1.
The report presents an overview of the projects under implementation, indicating sector-wise analysis of time/cost over run, with respect to approved schedule
and incremental time/cost over-run reported during the quarter January-March,2004, factors of delay, gestation period, fund requirement, etc. The overview
also includes analysis of projects due for commissioning and those actually commissioned.
2.
During the period April,2003-March,2004, in all 59 projects were completed. The list of these 59 projects completed till March,2004 is given in Appendix-I.
As on 1.4.2003, 168 projects were expected to be completed in various sectors during the year 2003-2004. In addition, during the period April,2003 to
March,2003, 38 more projects were reported for completion by 3/2004. Out of a total of 206 projects, 59 projects have already been completed, 69 projects
have slipped beyond 3/2004 and for 29 projects latest status is not available. The status of these projects is given in Appendix-II. The list of 33 frozen and 43
dropped projects upto 03/2004 is given in Appendix-III and III-A respectively.
3.
As on 31-03-2004 there were 568 projects involving anticipated cost of Rs.247,039.20 crore on the monitor of MOSPI. The classification of these Projects
into Mega (costing Rs.1000 crs. and above), Major (costing between Rs.100 crs. and Rs.1000 crs.), and Medium (costing between Rs.20 crs. and Rs.100 crs.)
categories is given in Table-1 set out below: The 45 mega and 258 major projects involve anticipated cost of Rs.2,33,966.38 crores (94.70% of total cost).
Out of these 303 Mega & Major projects. 286 projects are covered under the Flash Report/Exeption Report system of monitoring and remaining 17 projects
are yet to be brought under Flash Report monitoring system.
TABLE-1
Anticipated Cost
No. of Projects
WATER RESOURCES
URBAN DEVELOPMENT
TELECOMMUNICATION
RAILWAYS
HEALTH & FW
POWER
PETROLEUM
STEEL
MINES
I&B
FERTILISERS
COAL
CIVIL AVIATION
ATOMIC ENERGY
60.0
200
50.0
150
40.0
30.0
100
20.0
50
0.0
NO. OF PROJECTS
CHART-2
70.0
10.0
4.
5.
Table-2 presents sector-wise break up of the projects on the monitoring system at the end of March,2004. The graphic presentation of the frequency
distribution of projects among various sectors is shown in Chart-2.
TABLE-2
6.
There were 540 projects on the monitoring system at the end of March,2003. 23 new projects were taken on the monitoring system and 44 projects were dropped
during the period April-June,2003. Leaving 519 projects on the monitoring system at the end of June,2003. In the second quarter 31 new projects were added on the
monitoring system and 22 projects were dropped. Thus at the end of September,2003 there were 528 projects on the monitoring system. During the 3rd quarter of the
year, 14 projects were added and 10 were dropped from the monitoring, resulting a total of 532 projects on the monitoring at the end of December,2003. In the forth
quarter 50 new projects were added and 14 projects were dropped leaving 568 projects on the monitor of the Ministry at the end of March,2004. The sector wise and
quarter wise no. of projects dropped and added are given in table 3. The list of projects added/dropped is given in Appendix- IV.
TABLE-3
RUNNING SUMMARY OF PROJECTS ADDED/DROPPED, SECTOR-WISE IN VARIOUS QUARTERS
-------------------------------------------------------------------------------------------------------------------SR. NAME OF THE
QR. I
QR. II
QR. III
QR. IV
NO. SECTOR
NO. OF PROJECTS
NO. OF PROJECTS
NO. OF PROJECTS
NO. OF PROJECTS
------------------------ ------------------- -------------------- ------------------3/03 ADDED DROPPED 6/03 ADDED DROPPED 9/03 ADDED DROPPED 12/03 ADDED DROPPED 3/04
-------------------------------------------------------------------------------------------------------------------1. ATOMIC ENERGY
8
0
0
8
0
0
8
2
0
10
0
0
10
2. CIVIL AVIATION
5
0
1
4
0
1
3
0
0
3
0
0
3
3. COAL
59
6
8
57
4
1
60
1
1
60
5
0
65
4. FINANCE
0
0
0
0
0
0
0
0
0
0
0
0
0
5. FERTILISERS
1
0
0
1
1
0
2
0
0
2
1
0
3
6. I & B
3
0
0
3
0
1
2
0
0
2
0
0
2
7. MINES
3
0
0
3
0
0
3
0
0
3
0
0
3
8. STEEL
8
0
0
8
0
1
7
0
0
7
0
1
6
9. PETROCHEMICALS
0
0
0
0
0
0
0
0
0
0
0
0
0
10. PETROLEUM
31
4
5
30
3
2
31
2
2
31
3
2
32
11. POWER
45
3
3
45
4
3
46
1
0
47
5
2
50
12. HEAVY INDUSTRY
0
0
0
0
0
0
0
0
0
0
0
0
0
13. HEALTH & FW
3
0
0
3
0
0
3
0
0
3
0
0
3
14. RAILWAYS
168
0
5
163
11
6
168
7
2
173
27
0
200
15. ROAD TRANSPORT & HIGHWAYS 134
0
12
122
0
0
122
0
1
121
5
7
119
16. SHIPPING & PORTS
46
6
7
45
0
5
40
0
1
39
2
2
39
17. TELECOMMUNICATION
13
3
3
13
2
2
13
1
2
12
2
0
14
18. URBAN DEVELOPMENT
11
1
0
12
6
0
18
0
1
17
0
0
17
19. WATER RESOURCES
2
0
0
2
0
0
2
0
0
2
0
0
2
-------------------------------------------------------------------------------------------------------------------TOTAL
540
23
44
519
31
22
528
14
10
532
50
14
568
--------------------------------------------------------------------------------------------------------------------
7.
The names of 45 Mega projects under monitoring system as on 31.03.2004 are given in table-4 below:-
TABLE-4
Sl.
No.
--1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
Anticipated Date of
Project
Agency
Cost(Rs.Crs) Comm.
---------------------- -------- -------------- -------TARAPUR ATO-MIC POWER
(NPCIL ) Rs.
6525.00 01/2007
KAIGA 3 & 4 UNITS
(NPC
) Rs.
3282.00 09/2007
ATOMIC POWER PROJECT
(NPC
) Rs. 13171.00 12/2008
RAPP 5&6
(NPCIL ) Rs.
3072.00 02/2008
FAST BREEDER REACTOR PR. (BHAVNI) Rs.
3492.00 10/2009
DUDHICHUA OC PHASE-I
(NCL
) Rs.
1281.39 03/2004
NIGAHI EXPN. OC
(NCL
) Rs.
1846.49 03/2004
EXP.OF CAP. SMELTER-CPP (NALCO ) Rs.
2061.98 04/2004
REF.MODERNI-SATION
(BPCL ) Rs.
1831.00 10/2004
UPGRADATION-HBJ PIPELINE (GAIL ) Rs.
2444.54 04/2004
DAHEJ-HAZIRA-URAN PIPELN (GAIL ) Rs.
1416.00 12/2005
GREEN FUELS&EMISSION CTL (HPCL ) Rs.
1152.00 12/2005
INTEGERATED PARAXYLENE
(IOCL ) Rs.
5104.00 08/2005
PANIPAT REF.EXPANSION
(IOCL ) Rs.
4177.00 04/2005
LINEAR ALKYL BENLENE
(IOCL ) Rs.
1317.00 08/2004
MS QUALITY UPGRADATION (IOCL ) Rs.
1755.00 12/2004
MUMBAI HIGH NORTH DEV
(ONGCL ) Rs.
2929.40 12/2005
MUMBAI HIGH SOUTH DEV.
(ONGCL ) Rs.
5255.97 07/2007
HIGH-URAN
TRUNK P.LINE (ONGC ) Rs.
2792.50 05/2005
REFIN.EXPN. CUM.MOD.
(CPCL ) Rs.
2360.38 06/2004
DULHASTI HEP
(NHPC ) Rs.
4227.92 11/2004
DHAULIGANGA H.E.P.-I
(NHPC ) Rs.
1578.31 03/2005
CHAMERA H.E.PROJECT
(NHPC ) Rs.
1684.02 05/2004
Expenditure
(Rs. Crores)
-----------Rs. 4203.00
Rs.
775.00
Rs. 2780.00
Rs.
378.00
Rs.
0.00
Rs. 1233.43
Rs. 1369.45
Rs. 1593.05
Rs. 1157.00
Rs. 2007.87
Rs.
2.53
Rs.
14.85
Rs.
966.92
Rs. 1064.88
Rs.
709.71
Rs.
658.91
Rs. 1293.86
Rs.
235.29
Rs.
1.21
Rs. 1975.96
Rs. 4034.40
Rs. 1281.55
Rs. 1899.80
Sl.
No.
--24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
Project
-----------------------TEESTA HE
PROJ.ST-V
PARBATI HEP ST.-II
SUBANSIRI
LOWER HEP
TEHRI DAM
H.P.P.
KOTESHWAR
HEP
NATHPA JHKRI H.E.P.
TALCHER STPP ST-II
RIHAND STPP ST-II
RAMAGUNDAM STPP ST-III
KOL DAM HEP
VINDHYACHAL STPP-III
KAHALGAON
STPP ST-II
RIHAND-II
TRANSMISSION
TR.SYSTEM
WITH TALAHEP
B'PUTRA BR, BOGIBIL&LINK
LUMDINGSILCHAR
UDHAMPUR-S'-NGR-B'MULLA,
GODRA-INDOREDEWAS-MAKSI
KODERMARANCHI(BARKNA
DIPU TO
KARONG,NEFR
DELHI METRO RAPID SYS-I
PAGLADIYES DAM PROJECT
Agency
-------(NHPC )
(NHPC )
(NHPC )
(THDCL )
(THDCL )
(SJVNL )
(NTPC )
(NTPC )
(NTPC )
(NTPC )
(NTPC )
(NTPC )
(P.GRID)
(P.GRID)
(B&S
)
(GC
)
(NL
)
(NL
)
(NL
)
(NL
)
(DMRC )
(
)
Anticipated
Cost(Rs.Crs.)
------------Rs.
2198.04
Rs.
3919.59
Rs.
6285.33
Rs.
5209.10
Rs.
1301.56
Rs.
8656.61
Rs.
7682.00
Rs.
4044.53
Rs.
2072.45
Rs.
5340.07
Rs.
4201.50
Rs.
4002.28
Rs.
1044.44
Rs.
1980.70
Rs.
1767.00
Rs.
1491.61
Rs.
3564.00
Rs.
1007.14
Rs.
1028.00
Rs.
1600.00
Rs. 10571.00
Rs.
1030.00
Date of
Comm.
------02/2007
09/2009
09/2010
03/2004
03/2006
07/2004
02/2006
05/2006
08/2005
04/2009
08/2007
05/2007
12/2005
06/2006
04/2008
-N.A.08/2007
-N.A.03/2006
-N.A.09/2005
-N.A.-
Expenditure
(Rs. Crores)
-----------Rs.
975.44
Rs.
682.31
Rs.
260.99
Rs. 5328.37
Rs.
167.59
Rs. 7958.83
Rs. 3936.11
Rs. 1392.69
Rs.
989.54
Rs.
526.80
Rs.
394.66
Rs.
218.43
Rs.
360.26
Rs.
12.56
Rs.
130.24
Rs.
241.91
Rs. 1291.60
Rs.
62.21
Rs.
149.35
Rs.
0.02
Rs. 5299.95
Rs.
0.00
WATER RESOURCES
URBAN
DEVELOPMENT
TELECOMMUNICATION
1,222.00
3,859.18
7,147.05
244.38
682.29
880.30
2,420.50
8,473.32
17,871.80
11,558.07
20,000.00
RAILWAYS
132.02
648.84
36,108.72
48,192.53
50,000.00
HEALTH & FW
26,231.85
35,308.09
40,000.00
POWER
4,631.01
61.66
841.09
STEEL
PETROLEUM
1,846.57
752.19
123.53
17.24
354.00
264.45
3,480.54
3,406.77
MINES
I&B
FERTILISERS
COAL
31.88
149.80
24,402.07
30,000.00
CIVIL AVIATION
5,695.46
10,000.00
ATOMIC ENERGY
(Rs. CRORES)
CHART-3
60,000.00
8.
Table-5 below presents an analysis of investments and expenditure in projects under implementation in each of the sixteen sectors. The graphic presentation of
the analysis of planned investment and balance expenditure of the projects is shown in Chart-3.
TABLE-5
ANALYSIS OF PLANNED AND BALANCE EXPENDITURE (SECTOR WISE)
-------------------------------------------------------------------------------------------------------------S.No. SECTOR
NUMBER OF NOW ANT- % OF
CUM.EXP.
EXP.UPTO
OUTLAY (RS.CR.)
BALANCE
PROJECTS
ICIPATED TOTAL 03/2003
THE END
------------------ EXPENDITURE
COST OF
(RS.CR.)
OF QTR.
2003-2004 % DISTR.
PROJECT
(RS.CR.)
-------------------------------------------------------------------------------------------------------------(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
-------------------------------------------------------------------------------------------------------------1. ATOMIC ENERGY
10
30097.53
12.18
5695.46
8255.46
3304.00
9.15
24402.07
2. CIVIL AVIATION
3
181.68
0.07
31.88
66.58
33.00
0.09
149.80
3. COAL
65
6887.31
2.79
3480.54
3786.55
608.63
1.69
3406.77
4. FERTILISERS
3
618.45
0.25
354.00
439.45
149.92
0.42
264.45
5. I & B
2
140.77
0.06
123.53
132.93
21.32
0.06
17.24
6. MINES
3
2598.76
1.05
1846.57
1911.20
0.00
0.00
752.19
7. STEEL
6
902.75
0.37
61.66
257.77
400.77
1.11
841.09
8. PETROLEUM
32
39939.10
16.17
4631.01
11562.19
7376.28
20.43
35308.09
9. POWER
50
74424.38
30.13
26231.85
33595.55
7676.36
21.26
48192.53
10. HEALTH & FW
3
780.86
0.32
132.02
253.10
90.10
0.25
648.84
11. RAILWAYS
200
47666.79
19.30
11558.07
14741.46
2686.89
7.44
36108.72
12. ROAD TRANSPORT & HIGHWAYS 119
26345.12
10.66
8473.32
13821.82
10218.19
28.30
17871.80
13. SHIPPING & PORTS
39
3300.80
1.34
880.30
1514.27
845.21
2.34
2420.50
14. TELECOMMUNICATION
14
926.67
0.38
244.38
360.45
295.63
0.82
682.29
15. URBAN DEVELOPMENT
17
11006.23
4.46
3859.18
5450.55
2398.63
6.64
7147.05
16. WATER RESOURCES
2
1222.00
0.49
0.00
0.00
0.00
0.00
1222.00
-------------------------------------------------------------------------------------------------------------TOTAL
568
247039.20 100.0
67603.77
96149.33
36104.93
100.0
179435.43
--------------------------------------------------------------------------------------------------------------
9.
Out of 568 projects, 31 projects are ahead of schedule, 152 are on schedule, 211 projects are delayed w.r.t. the original schedule, for 149 projects, the date of
commissioning is not available and for 25 projects, date of commissioning has not been firmed up. An analysis of time and cost-overrun of all the 568 projects with
respect to the original approved schedule and cost is presented in the Table-6 below:
TABLE-6
EXTENT OF TIME / COST OVERRUN IN PROJECTS WITH RESPECT TO ORIGINAL SCHEDULE
-------------------------------------------------------------------------------------------------------------------------------------------S.No.
SECTOR
NO.OF
TOTAL COST (RS. CRS)
PROJ-------------------------ECTS
ORIGANTIC_
COST
PROJ. WITH COST OVER RUN
PROJ. WITH TIME OVER RUN
INAL
IPATED
OVER
-------------------------------------------------------------------COST
RUN(%) NO.
ORGI.
ANTIC- %INCR
NO.
ORIG.
ANTICRANGE
COST
IPATED BASE
COST
IPATED
(NO)
COST
COST
-------------------------------------------------------------------------------------------------------------------------------------------(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
-------------------------------------------------------------------------------------------------------------------------------------------1. ATOMIC ENERGY
10
27950.6
30097.5
7.7
1
3447.1
6525.0
89.3
1
28.0
28.0
81- 81
2. CIVIL AVIATION
3
161.2
181.7
12.7
3
161.2
181.7
12.7
2
103.3
111.7
13- 13
3. COAL
65
6309.1
6887.3
9.2
8
1237.8
1909.7
54.3
21
2058.0
2648.6
3- 240
4. FERTILISERS
3
459.1
618.5
34.7
1
350.0
509.4
45.5
1
350.0
509.4
36- 36
5. I & B
2
93.3
140.8
50.8
1
34.2
81.6 138.9
1
34.2
81.6
171- 171
6. MINES
3
2598.8
2598.8
0.0
0
0.0
0.0
0.0
2
2118.8
2118.8
23- 52
7. STEEL
6
895.1
902.8
0.9
1
42.9
50.5
17.9
2
387.8
387.8
18- 20
8. PETROLEUM
32
38099.0
39939.1
4.8
8
13237.8
15637.4
18.1
13
14836.4
16242.7
3- 15
9. POWER
50
56845.9
74424.4
30.9
15
27205.3
44824.3
64.8
20
9473.2
24181.8
2- 168
10. HEALTH & FW
3
159.9
780.9 388.2
3
159.9
780.9 388.2
2
140.9
691.8
72- 78
11. RAILWAYS
200
32385.6
47666.8
47.2 132
22091.6
37683.5
70.6
42
9315.1
14217.2
3- 168
12. ROAD TRANSPORT & HIGHWAYS 119
25539.5
26345.1
3.2
5
1065.4
1876.3
76.1
73
13637.5
14443.1
2- 147
13. SHIPPING & PORTS
39
3168.4
3300.8
4.2
12
469.6
653.3
39.1
20
1326.4
1438.3
3- 63
14. TELECOMMUNICATION
14
907.3
926.7
2.1
3
130.4
149.8
14.9
7
430.3
447.1
3- 67
15. URBAN DEVELOPMENT
17
5280.1
11006.2 108.4
4
4942.8
10718.4 116.8
4
4942.4
10665.7
6- 60
16. WATER RESOURCES
2
409.3
1222.0 198.5
2
409.3
1222.0 198.5
0
0.0
0.0
00
-------------------------------------------------------------------------------------------------------------------------------------------TOTAL
568
201262.3
247039.2
22.7 199
74985.1
122803.7
63.8 211
59182.3
88213.5
--------------------------------------------------------------------------------------------------------------------------------------------
WATER RESOURCES
URBAN
DEVELOPMENT
TELECOMMUNICATION
1,383
1,438
447
447
10,632
10,644
18,518
15,875
16,243
14,475
14,443
10,000
2,119
2,119
15,000
11,247
14,169
HEALTH & FW
POWER
388
388
82
82
509
509
20,000
PETROLEUM
STEEL
MINES
I&B
FERTILISERS
1,313
1,243
5,000
COAL
22,603
25,000
RAILWAYS
103
112
28
28
CIVIL AVIATION
ATOMIC ENERGY
CHART-4
10.
An analysis of time and cost over-run of all the 568 projects on the monitoring system with respect to the latest schedule and cost approved by the Government
is given in the Table-7. The graphic presentation of the sector-wise anticipated cost vis-a-vis approved cost of delayed projects at the end of March,2004 is
shown in Chart-4.
TABLE-7
EXTENT OF TIME / COST OVERRUN IN PROJECTS WITH RESPECT TO LATEST SCHEDULE
----------------------------------------------------------------------------------------------------------------------------------------S.No.
SECTOR
NO.OF
TOTAL COST (RS. CRS)
PROJ-------------------------ECTS
LATEST
ANTIC_
COST
PROJ. WITH COST OVER RUN
PROJ. WITH TIME OVER RUN
APPROVED
IPATED
OVER
----------------------------------------------------------------COST
RUN(%) NO. LATEST
ANTIC- %INCR
NO. LATEST
ANTICRANGE
APPROVED
IPATED BASE
APPROVED
IPATED
(MO)
COST
COST
----------------------------------------------------------------------------------------------------------------------------------------(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
----------------------------------------------------------------------------------------------------------------------------------------1. ATOMIC ENERGY
10
29993.5
30097.5
0.3
1
6421.0
6525.0
1.6
1
28.0
28.0
8181
2. CIVIL AVIATION
3
161.2
181.7
12.7
3
161.2
181.7
12.7
2
103.3
111.7
1313
3. COAL
65
6955.4
6887.3
-1.0
3
96.3
104.2
8.2
17
1312.5
1243.4
3- 108
4. FERTILISERS
3
618.5
618.5
0.0
0
0.0
0.0
0.0
1
509.4
509.4
2727
5. I & B
2
140.8
140.8
0.0
0
0.0
0.0
0.0
1
81.6
81.6
6363
6. MINES
3
2598.8
2598.8
0.0
0
0.0
0.0
0.0
2
2118.8
2118.8
2352
7. STEEL
6
895.1
902.8
0.9
1
42.9
50.5
17.9
2
387.8
387.8
1820
8. PETROLEUM
32
40013.3
39939.1
-0.2
6
8217.1
8702.4
5.9
13
15874.7
16242.7
315
9. POWER
50
67468.8
74424.4
10.3
14
36249.9
43246.0
19.3
19
18517.8
22603.4
260
10. HEALTH & FW
3
710.9
780.9
9.8
1
19.0
89.0 368.0
0
0.0
0.0
00
11. RAILWAYS
200
39885.7
47666.8
19.5 101
21520.4
30227.4
40.5
41
11247.3
14169.4
3- 156
12. ROAD TRANSPORT & HIGHWAYS 119
26377.3
26345.1
-0.1
3
836.6
890.0
6.4
73
14475.2
14443.1
265
13. SHIPPING & PORTS
39
3231.7
3300.8
2.1
8
398.7
519.1
30.2
20
1383.4
1438.3
363
14. TELECOMMUNICATION
14
924.0
926.7
0.3
2
50.4
53.1
5.3
7
447.1
447.1
324
15. URBAN DEVELOPMENT
17
11034.3
11006.2
-0.3
2
48.9
70.3
43.8
3
10631.9
10644.2
638
16. WATER RESOURCES
2
1222.0
1222.0
0.0
0
0.0
0.0
0.0
0
0.0
0.0
00
-------------------------------------------------------------------------------------------------------------------------------------------TOTAL
568
232231.2
247039.2
6.4 145
74062.4
90658.6
22.4 202
77118.7
84468.9
--------------------------------------------------------------------------------------------------------------------------------------------
11.
It may be noted that the cost of 568 projects on the monitor has escalated from the latest approved cost of Rs.2,32,231.2 crores to Rs.2,47,039.2 crores by as
much as 6.4%. Of the total cost increase of Rs.14,808 crores, Rs.7,350.2 crores is accounted by the 202 delayed projects.
12.
There are 74 projects reporting both time and cost overrun to the extent of 97.66% from the original cost and time overrun ranging from 3 to 240 months. The sector
wise details and extent of time overrun and cost overrun are given in Table-8 below.
TABLE-8
EXTENT OF TIME & COST OVERRUN IN PROJECTS WITH RESPECT TO ORIGINAL SCHEDULE
--------------------------------------------------------------------------------------------------------S.No.
SECTOR
NO.OF
TOTAL COST (RS. CRS)
PROJ-------------------------ECTS
ORIGANTIC_
COST
PROJ. WITH TIME & COST OVER RUN
INAL
IPATED
OVER
---------------------------------COST
RUN(%) NO.
ORGI.
ANTICRANGE
COST
IPATED
(MO)
COST
--------------------------------------------------------------------------------------------------------(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
--------------------------------------------------------------------------------------------------------1. ATOMIC ENERGY
10
27950.6
30097.5
7.7
0
0.0
0.0
00
2. CIVIL AVIATION
3
161.2
181.7
12.7
2
103.3
111.7
13- 13
3. COAL
65
6309.1
6887.3
9.2
7
1189.6
1860.5
3- 240
4. FERTILISERS
3
459.1
618.5
34.7
1
350.0
509.4
36- 36
5. I & B
2
93.3
140.8
50.8
1
34.2
81.6
171- 171
6. MINES
3
2598.8
2598.8
0.0
0
0.0
0.0
00
7. STEEL
6
895.1
902.8
0.9
0
0.0
0.0
00
8. PETROLEUM
32
38099.0
39939.1
4.8
5
8298.1
9772.5
3- 13
9. POWER
50
56845.9
74424.4
30.9
9
6641.6
21385.7
8- 168
10. HEALTH & FW
3
159.9
780.9 388.2
2
140.9
691.8
72- 78
11. RAILWAYS
200
32385.6
47666.8
47.2
31
6957.7
12013.3
8- 168
12. ROAD TRANSPORT & HIGHWAYS 119
25539.5
26345.1
3.2
5
1065.4
1876.3
6- 147
13. SHIPPING & PORTS
39
3168.4
3300.8
4.2
8
368.1
517.5
6- 63
14. TELECOMMUNICATION
14
907.3
926.7
2.1
1
80.0
96.7
67- 67
15. URBAN DEVELOPMENT
17
5280.1
11006.2 108.4
2
4885.8
10609.0
6- 38
16. WATER RESOURCES
2
409.3
1222.0 198.5
0
0.0
0.0
00
--------------------------------------------------------------------------------------------------------TOTAL
568
201262.3
247039.2
22.7
74
30114.6
59526.0
---------------------------------------------------------------------------------------------------------
The analysis of 568 projects on the monitor indicates that there were 43 projects which completed 60% or more of the gestation period but actual expenditure is
less than 20% with reference to the anticipated time and cost. It may be seen that out of 43 projects making little progress despite 60% or more of the gestation
period over being 12 are major projects (6 in Railways, 4 in Road Transport & Highways, 1 in Steel and 1 in Shipping & Ports Sector). It may however, be clarified
that the rate of financial expenditure may not indicate the correct position of the physical progress of the projects. The details of 43 projects are given in AppendixV. To check time and cost overruns, it is essential that the projects make physical and financial progress from the beginning. The sector-wise details of number of
projects having completed 60% or more of anticipated gestation period and have spent upto 50% of the anticipated cost as on 31-03-2004 (category-wise) is given
in table-9 below:-
TABLE-9
-------------------------------------------------------------------------------------------EXPENDITURE
---------------------------------------------------TOTAL
S.NO.
SECTOR
LESS THAN
NO. OF
5%
5-10%
10-20%
20-30%
30-40% 40-50%
PROJECTS
-------------------------------------------------------------------------------------------1. ATOMIC ENERGY
0
0
0
1
0
0
1
2. CIVIL AVIATION
0
0
0
0
0
1
1
3. COAL
8
3
3
3
3
3
23
4. FERTILISERS
0
0
0
0
0
0
0
5. I & B
0
0
0
0
0
0
0
6. MINES
0
0
0
0
0
0
0
7. STEEL
0
1
0
1
0
0
2
8. PETROLEUM
0
0
1
3
2
1
7
9. POWER
0
0
1
2
2
3
8
10. HEALTH & FW
0
0
0
1
0
1
2
11. RAILWAYS
2
3
7
5
8
2
27
12. ROAD TRANSPORT & HIGHWAYS
2
0
2
9
12
22
47
13. SHIPPING & PORTS
5
1
0
0
1
2
9
14. TELECOMMUNICATION
0
1
0
1
1
1
4
15. URBAN DEVELOPMENT
1
0
2
1
2
1
7
16. WATER RESOURCES
0
0
0
0
0
0
0
-------------------------------------------------------------------------------------------TOTAL
18
9
16
27
31
37
138
--------------------------------------------------------------------------------------------
14.
The analysis of various factors of time and cost overrun shows that further delay is taking place with respect to the latest revised schedules even in those projects
which have already been delayed with reference to their original schedule. The main factors and the number of projects in various sectors, the progress of which is
being affected adversely are summarised in Appendix-VI (It may be noted that the projects affected by more than one factor appear under more than one head).
15.
It may be observed from Appendix-VI that in 15 projects, the main reason identified has been the delay in civil work mainly in Railways (10). In 11 projects the
main reason identified has been the slow progress of works. In 36 projects fund contraints has also been causing delay.
16.
The other important factor affecting the implementation of projects (14) has been award of contracts.
17.
The delay in land acquisition and related matters has been affecting mostly in the Railway (23), Coal (6) and Power (2) sectors (Total 31 projects). Another
important factor of delay is the delay in supply of equipment (6 projects).
18.
The other factors affecting the progress are law & order problem and adverse geomining conditions, court cases etc.
19.
The cost overrun is mainly on account of time overrun besides, price rise, exchange rate variation, increase in levies and change in scope of project parameters
during implementation. The impact of these factors becomes more serious with the time overrun of the projects.
During the quarter under review, 30 projects reported additional delays of 6 months or more for the periods ranging from 6 months to 36 months. The Table-10
below presents sector-wise data on incremental time overrun, no. of delayed projects, incremental delay in scheduled date of commissioning during the quarter.
Main Sectors reporting delay are 8 in Road Transport & Highways, 3 in Shipping & Ports, 6 each in Railway and Petroleum, 4 in Power, 1 in Steel and 2 in
Telecommunication sector. Details of the projects are given in Appendix-VII.
TABLE-10
---------------------------------------------------------------------------------------------------------------S.NO. NAME OF THE SECTOR
APR-JUN(1 st QTR)
JUL-SEP(2 nd QTR)
OCT-DEC(3 rd QTR)
JAN-MAR(4 th QTR)
----------------------------------------------------------------NO.
RANGE
NO.
RANGE
NO.
RANGE
NO.
RANGE
OF DELAY
OF DELAY
OF DELAY
OF DELAY
---------------------------------------------------------------------------------------------------------------1. ATOMIC ENERGY
0
0- 0
0
0- 0
0
0- 0
0
0- 0
2. CIVIL AVIATION
0
0- 0
0
0- 0
1
6- 6
0
0- 0
3. COAL
1
12-12
3
6-12
0
0- 0
0
0- 0
4. FERTILISERS
0
0- 0
0
0- 0
0
0- 0
0
0- 0
5. I & B
0
0- 0
0
0- 0
1
6- 6
0
0- 0
6. MINES
0
0- 0
1
6- 6
0
0- 0
0
0- 0
7. STEEL
1
6- 6
0
0- 0
0
0- 0
1
14-14
8. PETROLEUM
0
0- 0
4
6-36
1
11-11
6
8-36
9. POWER
2
6- 7
0
0- 0
3
7- 9
4
6-24
10. HEALTH & FW
0
0- 0
0
0- 0
0
0- 0
0
0- 0
11. RAILWAYS
7
9-21
4
6-24
2
6-48
6
6-21
12. ROAD TRANSPORT & HIGHWAYS
12
6- 9
4
7-12
9
6- 9
8
7-10
13. SHIPPING & PORTS
2
8-12
1
8- 8
5
6-23
3
7-12
14. TELECOMMUNICATION
1
14-14
1
6- 6
1
9- 9
2
12-15
15. URBAN DEVELOPMENT
0
0- 0
0
0- 0
0
0- 0
0
0- 0
16. WATER RESOURCES
0
0- 0
0
0- 0
0
0- 0
0
0- 0
---------------------------------------------------------------------------------------------------------------TOTAL
26
18
23
30
----------------------------------------------------------------------------------------------------------------
21.
From Table-11 it may be seen that in all 2 projects (i.e. 1 each in Railway and Shipping & Ports sector) reported major cost overruns of 20% or more during the
quarter ending March,2004. Strict cost control measures are required in this sector to check further increase in cost. The total cost overrun during the quarter
ending March,2004 accounts for Rs.31.60 crore by 2 projects. The details of the projects are given in Appendix-VIII.
TABLE-11
SECTORWISE ANALYSIS OF PROJECTS SHOWING ADDITIONAL COST OVERRUN IN VARIOUS QUARTERS OF 2003-2004
------------------------------------------------------------------------------------------------S.No.
SECTOR
QR.I
QR.II
QR.III
QR.IV
--------------- -------------- --------------------------NO. TOTAL COST NO. TOTAL COST NO. TOTAL COST
NO. TOTAL COST
OVERRUN
OVERRUN
OVERRUN
OVERRUN
------------------------------------------------------------------------------------------------1. ATOMIC ENERGY
0
0.00
0
0.00
0
0.00
0
0.00
2. CIVIL AVIATION
0
0.00
0
0.00
0
0.00
0
0.00
3. COAL
0
0.00
0
0.00
0
0.00
0
0.00
4. FERTILISERS
0
0.00
0
0.00
0
0.00
0
0.00
5. I & B
0
0.00
0
0.00
0
0.00
0
0.00
6. MINES
0
0.00
0
0.00
0
0.00
0
0.00
7. STEEL
0
0.00
0
0.00
0
0.00
0
0.00
8. PETROLEUM
0
0.00
0
0.00
0
0.00
0
0.00
9. POWER
0
0.00
0
0.00
1
59.15
0
0.00
10. HEALTH & FW
0
0.00
0
0.00
0
0.00
0
0.00
11. RAILWAYS
5
649.88
2
21.08
1
91.66
1
10.00
12. ROAD TRANSPORT & HIGHWAYS
0
0.00
0
0.00
0
0.00
0
0.00
13. SHIPPING & PORTS
0
0.00
0
0.00
2
24.00
1
21.60
14. TELECOMMUNICATION
0
0.00
0
0.00
0
0.00
0
0.00
15. URBAN DEVELOPMENT
0
0.00
0
0.00
0
0.00
0
0.00
16. WATER RESOURCES
0
0.00
0
0.00
1
780.00
0
0.00
-------------------------------------------------------------------------------------------TOTAL
5
649.88
2
21.08
5
954.81
2
31.60
--------------------------------------------------------------------------------------------
It may be noted that as many as 145 (17 Mega, 74 Major, 54 Medium) of the 568 projects on the monitoring system require review/sanction of the cost estimates as
their anticipated costs have gone up over and above the latest approved cost. It may be noted from the Table below that in 51 (4 Mega, 19 Major, 28 Medium)
projects, the actual expenditure upto March,2004 had already exceeded the latest sanctioned cost. The excercise for the review of cost is required for 145 projects
and in the case of 51 projects, RCE needs to be approved by PIB/CCEA. The sector-wise picture is presented in Table-12 below :-
TABLE-12
SECTOR-WISE DISTRIBUTION OF PROJECTS REQUIRING REVIEW/SANCTION OF RCE
(NUMBER OF PROJECTS)
----------------------------------------------------------------------------------------------Sl. SECTOR
TOTAL
MEGA
MAJOR
MEDIUM
TOTAL
No.
No. of
------------------------------------------PROJECTS
APP.COST
APP.COST
APP.COST
APP.COST
LESS THAN
LESS THAN
LESS THAN
LESS THAN
NAC | EXP.
NAC | EXP.
NAC | EXP.
NAC | EXP.
----------------------------------------------------------------------------------------------1. ATOMIC ENERGY
10
1
0
0
0
0
0
1
0
2. CIVIL AVIATION
3
0
0
0
0
3
0
3
0
3. COAL
65
0
0
0
0
3
1
3
1
4. FERTILISERS
3
0
0
0
0
0
0
0
0
5. I & B
2
0
0
0
0
0
0
0
0
6. MINES
3
0
0
0
0
0
0
0
0
7. STEEL
6
0
0
0
0
1
0
1
0
8. PETROLEUM
32
3
0
3
0
0
0
6
0
9. POWER
50
8
4
5
1
1
0
14
5
10. HEALTH & FW
3
0
0
0
0
1
0
1
0
11. RAILWAYS
200
5
0
63
15
33
15
101
30
12. ROAD TRANSPORT & HIGHWAYS 119
0
0
2
3
1
4
3
7
13. SHIPPING & PORTS
39
0
0
1
0
7
5
8
5
14. TELECOMMUNICATION
14
0
0
0
0
2
2
2
2
15. URBAN DEVELOPMENT
17
0
0
0
0
2
1
2
1
16. WATER RESOURCES
2
0
0
0
0
0
0
0
0
----------------------------------------------------------------------------------------------TOTAL :
568
17
4
74
19
54
28
145
51
-----------------------------------------------------------------------------------------------
23.
It may be seen that the maximum number of projects, which require review of the sanctioned cost are in the Railways (101), Power (14), Shipping & Port (8),
Petroleum (6) , Civil Aviation (3), Road Transport & Highways (3), Urban Development (2), Coal (3), Steel (1), Atomic Energy (1) and Health & Family
Welfare (1) and Telecommunication (2) sectors.
24.
Factors
No. of Projects
1.
Fund Constraints
2.
Land Problems
3.
4.
5.
11 (8 Railways and 1 each in Power, Road Transport & Highways and Urban
Development)
6.
In addition, the following reasons have also been contributing to time and cost overruns:
Reasons for Time Overruns:
(i)
(ii)
delay in finalisation of detailed engineering, release of drawings and delay in availability of fronts,
(iii)
changes in scope,
(iv)
(v)
(vi)
(vii)
(viii)
geological surprises.
Time overruns,
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
In view of the huge investments of the order of Rs.2,47,039.20 crore made in the Central Sector Projects and also their contributions to the overall infrastructural
development of the country, it is important that these are completed within the time and costs approved for them. If the single most important factor, that of time
overrun, could be controlled, a major part of cost overrun including general escalation and interest during construction could also be contained. The individual sectoral
chapters in the Report provide details of the status and constraints faced by each project. The administrative Ministries/Departments/Project Authorities would do well
to initiate corrective action in regard to them.
Revisions of costs and schedules continue to plague the scenario. At the very least these should provide an occasion for a detailed examination of the constraints, pace of
work, cost of execution, and using the experience gained for bringing improvements in future.
8
6
54
2003-04
60
2002-03
2001-02
35
2000-01
29
1999-00
1998-99
40
1997-98
1996-97
40
1995-96
1994-95
1993-94
1989-90
6
1992-93
1991-92
1990-91
1988-89
1986-87
0
4
1985-86
1987-88
20
1979-85
NO. OF PROJECTS
CHART-5
180
162
160
140
120
100
80
67
44
50
30
The distribution of projects sanctioned in different years of various plan periods and different sectors is given in Appendix-IX. The graphic presentation of the
number of projects sanctioned prior to 1985 and 1985-86 onwards shown in Chart-5.
26.
As on 31-03-2004, there were 48 projects which have been under implementation for more than a decade. A sector-wise list of projects is given in Appendix X.
These include 30 projects in the Railways, 5 each in the Coal and Power, 3 in Health & Family Welfare, 2 in Urban Development and one each in the Atomic
Energy, I & B, Road Transport & Highways sectors.
27.
Out of 5 projects in the Coal Sector, 3 are underground (2 major and 1 medium), 1 open cast (mega) and one for shifting of railway line (medium). Out of 5
projects, 4 projects have suffered time overrun and no projects with cost overrun. The underground coal projects are making slow progress because of geo-mining
and technology related problems.
28.
Out of 5 projects in the Power Sector 4 are hydel (all mega) projects. All the four projects namely Dulhasti, Nathpa Jhakri and Dhauliganga H.E. projects have
slipped to 10th plan.
29.
Out of 30 projects in the Railways Sector, 11 are for new lines (1 mega, 8 major and 2 medium), 7 for Gauge Conversion (6 major and 1 medium), 4 for doubling (1
major, 3 medium), 3 for WS & PU (1 major, 2 medium), one each for S & T (medium), MTP (major), TF (medium), RE (major) and Freight Operation Information
System (major).
30.
One project in the Road Transport & Highways (major) sector is also under implementation for more than 10 years.
31.
Tarapur Atomic Power Projects (mega) in the Atomic Energy sector is under implementation for more then 10 years. The likely commissioning date of this project is
January,2007.
32.
Two Projects in Urban Development sector namely construction of Library Bhasa Bhawan and IGNOU Campus, New Delhi are also under implementation for more
than 10 years.
33.
One project in I & B (DD Bhawan Delhi) is also under implementation for more than 10 years.
34.
Out of three projects in Health & Family Welfare sector, two projects are scheduled to be completed by 3/2005 & regarding one project, DOC is yet to be fixed by the
project authorities.
Out of 568 projects on the monitor and as per the imformation available in MOSPI, 7 projects have external assistance in the form of loan and other credit facilities
provided by world bank (2 projects) and bilateral (5 projects). Out of 7 projects, 5 projects are financed through external assistance in Power and 2 in Coal sectors.
The details are given in table-13 below. Out of 7 externally assisted projects, 5 projects have both time and cost overrun. In view of heavy commitment charges
being paid for unutilised portion of aid and the policy of the World Bank to withdraw aid in the event of delay, these projects need special attention. The project
wise details are given in Appendix XI & XII.
TABLE-13
---------------------------------------------------------------------------------------------------TIME OVERRUN
COST OVERRUN
---------------------- ----------------------Sl.No.
SECTOR
W.B.
ADB
BIL TOTAL W.B.
ADB
BIL TOTAL W.B.
ADB
BIL TOTAL
---------------------------------------------------------------------------------------------------1. ATOMIC ENERGY
0
0
0
0
0
0
0
0
0
0
0
0
2. CIVIL AVIATION
0
0
0
0
0
0
0
0
0
0
0
0
3. COAL
1
0
1
2
1
0
1
2
1
0
1
2
4. FERTILISERS
0
0
0
0
0
0
0
0
0
0
0
0
5. I & B
0
0
0
0
0
0
0
0
0
0
0
0
6. MINES
0
0
0
0
0
0
0
0
0
0
0
0
7. STEEL
0
0
0
0
0
0
0
0
0
0
0
0
8. PETROLEUM
0
0
0
0
0
0
0
0
0
0
0
0
9. POWER
1
0
4
5
1
0
2
3
1
0
2
3
10. HEALTH & FW
0
0
0
0
0
0
0
0
0
0
0
0
11. RAILWAYS
0
0
0
0
0
0
0
0
0
0
0
0
12. ROAD TRANSPORT & HIGHWAYS 0
0
0
0
0
0
0
0
0
0
0
0
13. SHIPPING & PORTS
0
0
0
0
0
0
0
0
0
0
0
0
14. TELECOMMUNICATION
0
0
0
0
0
0
0
0
0
0
0
0
15. URBAN DEVELOPMENT
0
0
0
0
0
0
0
0
0
0
0
0
16. WATER RESOURCES
0
0
0
0
0
0
0
0
0
0
0
0
---------------------------------------------------------------------------------------------------TOTAL
2
0
5
7
2
0
3
5
2
0
3
5
----------------------------------------------------------------------------------------------------
The list of projects included in the Report is not exhaustive. Only those projects which are reported by the Companies/Departments are included in the Report.
Particularly some of the projects with capital cost between Rs.20 crores to 50 crores which are sanctioned within the delegated powers of the Companies are not
reported by the Companies/Departments. Some of the projects where the anticipated cost had exceeded the sanctioned cost and crossed Rs.20 crore had also been
left out. In many such cases data has been taken out from the Annual Plan Reports or draft of MOUs which are sent to the Ministry for comments. This has also
been brought to the notice of some administative departments so that they may advise companies to send complete and regular details on projects approved by their
Boards. Projects which are sanctioned recently by the Government where the execution work had not yet started would be included in the subsequent reports.
37.
The project-wise outlay of all the projects covered in the Report is not the same as approved by the Planning Commission particularly for the projects with a capital
cost between Rs.20 crores and Rs.50 crores. The outlays for such projects is generally fixed within the Company depending upon the availability of resources. The
expenditure figures shown against each project are provisional and at times do not include the reappropriation of funds within the projects. The committed
expenditure for a particular project is not covered. The ratio of expenditure commitment for various activities as against the total cost of the project gives the extent
to which the progress is made towards its implementation.
38.
The anticipated date of commissioning and anticipated cost of the projects do not reflect the exact assessment of the project authorities at the time of reporting. This
needs to be reviewed taking the progress in the master network of the project. This will reveal the true status.
39.
The project authorities are not furnishing the complete and accurate data in time. This is one of the main reasons for delay in bringing out the Status Report. The
project authorities are also not reporting the exact status of progress of the projects. In most of the projects the physical progress of the project is not reported.
Repetitively they are giving the same objective parameters without changing for several quarters continuously.
I. ATOMIC ENERGY
Project Review:
1.1
There are 10 projects under implementation on the QPISR monitoring system at the end of 4th
Generation Projects in the Mega Project category.
1.2
The overall status of the projects w.r.t the original schedules are as follows:
Status of Projects as on 31.03.2004
-------------------------------------------------------WITHIN
WITHIN
TIME
COST
WITH
BUT
BUT
TIME
WITH
WITH
&
TOTAL
WITHIN
COST
TIME
COST
CATNO. OF
TIME &
OVEROVEROVEREGORY
PROJECTS
COST
RUNS
RUNS
RUNS
-------------------------------------------------------1
2
3
4
5
6
-------------------------------------------------------MEGA
5
4
1
0
0
MAJOR
1
1
0
0
0
MEDIUM
4
3
0
1
0
-------------------------------------------------------TOTAL
10
8
1
1
0
-------------------------------------------------------1.3
The anticipated cost of the 10 projects as at the quarter ending March,2004 was Rs.30,097.73 crores forming 12.18% of all investment in the Central Sector projects
(568 projects costing Rs.2,47,039.20 crores) of all the central sector projects on the MOS&PI's monitor. Of this, the anticipated cost of the 5 nuclear power project
belonging to NPCIL and BHAVINI, is Rs. 29,542 crores. Expenditure incurred on all 10 projects upto the end of 4th quarter, against an outlay of 3304 crores is
Rs.2560 crores and cumulative expenditure is Rs.8259.40 crores. Outlay for Atomic power programme in 2003-04 is Rs.2841 crores forming 9.15% of the outlay on all
16 sectors being monitored. Bulk of this outlay is for Nuclear Power Generation Projects. Cost overrun of projects under implementation is 7.7% with respect to the
original cost (Rs.27,950.6 Crores).
1.4
Year-wise availability of capacity of nuclear power upto 2006-07 (end of 10th Plan) and 2008-09 (2nd year of 11th Plan) are given below. These are based on the installed
capacities and likely streaming in of projects under implementation .
Project Status
1.5
The implementation status of each of the project is given in the following paragraphs.
1.
Tarapur Atomic Power Project 3 & 4 - 2 X 500 MWe, Tarapur, Maharashtra (NPC) :
The financial sanction for the project by GOI was given in January 1991 and at that time they had also obtained permission for making advance procurements of critical
equipment and other long delivery items like Calandrias for both units, Reactor headers, PHT pumps and motors, TG equipment for one unit etc.,As against the original
sanctioned cost of Rs. 3447.06 crores, RCE of Rs. 6421 crores at 1996 prices has been approved by the Government in December 1997. Start of project work did not
take place due to financial crunch till December, 1997. No work other than procurement activity took place at site. Site clearance and environmental clearances were
obtained. The site infrastructure is now fully developed. Gestation period for the first unit is 7 years for criticality. Certain critical and long delivery items such as
Calandria, Pressurisers, Reactor headers for both units, PHT pumps (for one unit) have been procured.
Scheduled
Activity
Scheduled
Date
Achieved/Expected
Date
March'98
31/08/98
April'99
08/03/2000
Date of criticality of
TAPP-4
TAPP-3
October 2005
July,2006
October'2005
July,2006
Milestones Achieved
April June, 2003
Pert Event No.
Description of Milestone
T4-037
T4-040
T3-026
T4-024
T4-041
T4-036
T3-022
T3-018
Date of
Achievement
April,2003
April,2003
April,2003
May,2003
May,2003
May,2003
May,2003
May,2003
July - September,2003
PERT Event No.
Description of milestone
T4-033
T4-046
T4-036
T4-039
Date of
Achievement
September,2003
September,2003
August,2003
August,2003
October December,2003
PERT Event No.
Description of milestone
T3-024
T3-021
T3-019
Complete IC dome
Delivery of FM Bridge & Column
Delivery of D20 vapour recovery
system equipment
FM head manufacture & delivery
T4-027
Date of
Achievement
October,2003
November,2003
November,2003
December,2003
Description of milestone
T3-017
T4-043
T4-045
T4-048
T3-030
Date of
Achievement
January,2004
February,2004
March,2004
March,2004
March,2004
Cumulative progress till date is 85.4% as against 81.1% last quarter. (65% weightage given for procurement and 20% for site construction).
2.
Kaiga Atomic Power Project 3 & 4 Units, Kaiga, Uttara Kannada Distt.,Karnataka (NPCIL)
Background
A project to set up 2 x 220 Mwe nuclear power stations (Unit 3 & 4) at Kaiga, in Uttara Kannada district in Karnataka, has been taken up at a sanctioned cost of Rs.4213
crore at current rupee value including escalations. The scheduled dates of criticality are April 2008 (Kaiga 3) and April 2009 (Kaiga 4) respectively. The total cost of
the project (Kaiga 3 & 4) at March,1999 constant rupee value was Rs.2856 crore, comprising of Rs.2400 crore base cost and Rs.456 Interest During Construction (IDC).
The total cost of completion with provision towards escalation @ 8% works out to Rs.4213 crore at current rupee value (Rs.3679 crore base cost and Rs.534 crore IDC),
with a Debt/Equity ratio of 1:1, with equity flowing initially from Government through budgetary support and the balance to be raised from the capital market. As Mega
Project status has now been given to nuclear power projects, they will become eligible for fiscal concessions towards Excise Duty/Customs Duty etc. The completion
schedule for the project is also being shortened. A proposal for the revision of cost estimates/completion schedule of Kaiga 3&4 is being submitted to the CCEA,
proposing to use the resultant savings to set up 2x220 Mwe power plants at Rajasthan Atomic Power Project (RAPP 5&6), keeping a debt/equity ratio of 2:1 for both the
projects. Environmental clearance from the State and Union Government and clearance from the Atomic Energy Regulatroy Board have been obtained.
Sanctioned Cost:
GROUP
ED
PD
Base value total
IDC
Total
As on March'99
Rupee Value
1608.00
792.00
2400.00
456.00
2856.00
Rupee Value
escalated upto 2009
2391.00
1288.00
3679.00
534.00
4213.00
REVISED
SANCTIONED COST
Rupee value escalated
upto 2007
1869.32
862.68
2727.00
555.00
3282.00
Scheduled Completion
7.2.02
Package-2
Construction of Safety related
buildings
Primary Piping Package
Electrical Main Plant Works
Turbo Generators and
auxiliaries(Delivery)
Secondary Cycle Piping
255 cr.
22.9.01
30.11.05
Anticipated completion
Area released for RB-3 raft. For
RB-4, expected by end
February,02.
30.11.05
165 cr.
112 Cr.
215 Cr.
30.8.02
30.12.02
30.11.02
30.9.06
31.7.06
30.11.05
30.9.06
31.7.06
30.11.05
30 Cr.
28.2.03
30.9.06
30.9.06
Unit
Kaiga-3
Kaiga-4
Kaiga-3
Kaiga-4
Month /year
October-2008
October-2009
March-2007
September,2007
Date of approval
18.5.2001
12.4.2002
Unit
KK-1
KK-2
KK-1
KK-2
Month /year
Dec.-07
Dec.-08
Dec.-07
Dec.-08
Date of approval
7.12.2001
-do-
Status
Following milestones have been achieved in the order of importance:
PERT Event No.
60
53
134
770
242
420
580
248
239
780
Description of milestones
Signing of contract for designer's supervision at site.
Signing of contract for equipment delivery
Issue of LOI/WO for hydro technical structures
Construction of foundation slab of Reactor Building-2
Release of technical specification/tender drawings for
NSSS & auxiliary system erection
Construction of fundamental section of Reactor
Building-1
Construction of Turbine building upto 0.00 MEL
Release of tech specs/tender drawings for ventilation
system erection
Release of tech specs / tender drawings for
instrumentation works
Construction of fundamental section (upto +5.4 M EL
slab) in Reactor building-2
Date of Achievement
August,2002
August,2002
September,2002
September,2002
March,2003
September,2003
October,2003
October,2003
October,2003
December,2003
Rajasthan Atomic Power Project Unit 5&6, Rawat Bhata, Distt. Kota, Rajasthan (NPCIL)
Background
Government approved the proposal in April,2002 for setting up 2 units of 220 Mwe each at the existing site in Rajasthan. The estimated cost of Rs.3072 crores (base
cost of Rs.2700 crores + IDC of Rs.372 crores ) which scheduled dates of commercial operation of RAPP Unit-5 by August,2007 and RAPP Unit-6 by February,2008.
Foreign Exchange component of the project is put at Rs.247.9 crores. Major project components along with their estimated cost and completion dates is given below:
Major Packages
Package-1
Main Plant excavation
Package-2
Construction of safety related buildings
Primary Piping Package
Electrical Main Plant Works
Turbo Generators and auxiliaries
(Delivery)
Secondary Cycle Piping
Packages cost /
Estimated cost (in crore)
12.25
Scheduled
Completion
14-6-02
238
26-3-02
25-2-06
Anticipated
Completion
Aug-02
(Excavation
of RB-5
completed)
25-2-06
120
114
215
15-7-02
30-12-02
30-11-02
30-8-06
30-6-06
30-11-05
30-8-06
30-6-06
30-11-05
37
28-2-03
31-8-06
31-8-06
Unit
RAPP-5
RAPP-6
Month /year
Aug-07
Feb-08
Date of approval
12-04-02
Description of milestones
First pour of concrete in RB-5
Completion of RB-5 Raft
Completion of RB-6 raft
Complete 100 M floor of RAB-5
Complete 100 M slab for RB-5
Complete 100 M floor for RAB-6
Date of
Achievement
September,2002
December,2002
March,2003
December,2003
February,2004
March,2004
6.
7.
Stage A Phase-I of Prototype Fast Breeder Reactor, IGCAR, Madras (TN) (IGCAR DAE)
This project assists in the development of prototype fast breeder reactor programme. As against an approved cost of Rs.95 crores, expenditure till March, 2002 is
Rs.Rs.82.58 crores. Cumulative Physical progress is 36% as against 34% achieved till the end of December,99.
Action to be taken
Expediting works at BHEL(Trichi). Due to embargo problem, there is delay in procurement of micro focal x-ray machine. This machine is required to evaluate tube to
tube sheet welding joints of Reheater & evaporator. (Same as reported last five quarters).
8.
Development of Site Infrastructure for Prototype Fast Breeder Reactor Stage A,Phase II, IGCAR, Madras (TB) (IGCAR DAE)
This project was approved in March,1997 at a cost of Rs.28 crores. Expenditure incurred is Rs.1.5 crores till 31st March,2000 as against Rs.1.2 crore expenditure till
31st December,1999. Its objective is to develop infrastructure for developing PFBR of 500 Mwe capacity. Cumulative progress till date is 6%.
9.
Development of Site Infrastructure and Materials Procurement, Prototype Fast Breeder Reactor Phase I Stage I, Madras TN (IGCAR DAE)
This project is to develop infrastructure for setting up PFBR. Expenditure till date is Rs.84 Lakhs against a total cost of the project of Rs.28.2 crores. The infrastructure
development is expected to be completed by March,2002.
10.
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------NUCLEAR POWER CORPORATION OF INDIA LIMITED
-----------------------------------------1. TARAPUR ATO- MW
1991/01 2007/01 2007/01
0
0
0
3447.06
6525.00
89 3166.00
991.00
1037.00
4203.00
85.40
MIC POWER
2X400
1997/12
0
0
6421.00
2
1091.00
TARAPUR
MAHARASHTRA
2. KAIGA 3 & 4
UNITS
KANUR
KARNATAKA
MW
2X220
2001/05
2002/04
2009/10
2007/09
-25
-25
-25
-25
4213.00
3282.00
3282.00
-22
0
627.00
375.00
243.00
148.00
775.00
41.10
3. ATOMIC POWER
PROJECT
KUDANKULAM
TAMIL NADU
MW
2X1000
2001/12
2008/12
2008/12
0
0
0
0
13171.00
13171.00
0
0
1539.00
1150.00
1750.00
1241.00
2780.00
27.40
4. RAPP 5&6
MWE
2X220
2002/04
2008/02
2008/02
0
0
0
0
3072.00
3072.00
0
0
244.00
325.00
220.00
134.00
378.00
32.20
1999/03
N.R.
2003/04
N.A.
N.A.
N.A.
N.A.
N.A.
61.07
61.07
0
0
35.14
35.14
2006/06
2006/06
0
0
0
0
343.26
343.26
0
0
N.R.
2002/12
N.A.
N.A.
N.A.
N.A.
N.A.
95.00
95.00
0
0
74.45
74.45
65.00
RAJASTHAN
URANIUM CORPORATION OF INDIA LIMITED
-----------------------------------5. 3RD SHAFT
1998/12
SINKING
JADUGUDA
JHARKHAND
6. NEW URANIUM
ORE PRO.MILL
BANDUHURANG
JHARKHAND
2003/09
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------8. PFBR-STAGE
1997/03 1998/06 2005/03
81
0
81
28.00
28.00
0
5.61
5.61
28.00
A PHASE-II
540
540
0
CHINGLEPUT
TAMIL NADU
9. PFBR PH I ST
A SITE INFR.
CHINGLEPUT
TAMIL NADU
BHAVINI LIMITED
--------------10. FAST BREEDER
REACTOR PR.
KALPAKKAM
TAMIL NADU
1999/01
2002/03
N.R.
2002/03
N.A.
N.A.
N.A.
N.A.
N.A.
28.20
28.20
0
0
4.26
4.26
2003/09
2009/10
2009/10
0
0
0
0
3492.00
3492.00
0
0
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
1.
1. Ext. of Runway
Jaipur (01/2004)
2.
Intregrated Cargo
Trml,Chennai(2003/01)
Completed
2. Dev of Amritsar
Airport (03/2004)
3.
3. Prov. Dedicated
Satellite (DOC-NA)
4.
Agartala Airport
Modification (2002/10)
Completed
5.
There were 4 projects on the monitoring system in the beginning of the year 2003-04. Out of these 4 projects the project namely ' New International terminal Complex
Phase-II, Chennai, Tamil Nadu was completed during the 1st quarter of the year. Thus there are only 3 projects at present on the monitor. All the three Projects are
being executed by the Airports Authority of India (AAI).
The implementation status of each of the project and statistical details of cost and time schedules, original, revised and anticipated, are given in the succeeding section.
AIR PORTS AUTHORITY OF INDIA
1.
2.
3.
Development of Airport
Perimeter road.
Boundary wall and
Terminal Building etc.
The project was approved on 8/2000 at a cost of Rs.79.27 crores with the DOC November,2003. The revised cost is Rs. 82.81 crore. The work is delayed due to delay in
land acquisition in the past for construction of approach for runway and remaining portion of perimeter road. Civil work for runway, taxi track and apron has been
completed. The work on the main approach road and car park area has been completed. Construction of compound wall and perimeter has been completed. Structural
portion of technical building is completed. Work of control tower is in progress. Civil and electrical work of the fire station has been completed. Civil work of cargo
complex has been completed and the electrical work is in progress. Fresh tenders are being processed for the building portion of the terminal building. The revised cost
of additional Rs.3.54 crores is for additional passenger facilities equipment as per approval sought for MOCA. The cumulative physical progress up to 03/2004 was
62%. The new DOC of the project is December, 2004.
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------AIRPORT AUTHORITY OF INDIA LIMITED
---------------------------------1. PROV.DEDICA1999/03 2001/03
N.R.
N.A.
N.A.
N.A.
57.93
70.00
21
4.45
4.45
40.00
TED SATELITE
2002/03
N.A.
N.A.
21
ALL INDIA
2. EXT.OF RUNWA
Y JAIPUR AIR
JAIPUR
RAJASTHAN
2000/08
2003/02
2004/03
13
43
13
43
24.03
28.87
20
20
3.80
13.00
-
18.10
21.90
82.00
3. DEVELOPMENT
AMRITSAR AIR
AMRITSAR
PUNJAB
2000/01
2003/11
2004/12
13
28
13
28
79.27
82.81
4
4
23.63
20.00
-
16.60
40.23
62.00
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
III. COAL
Project Review:
3.1
At the end of the forth quarter ending March, 2004 there where 60 projects on MOS&PI monitor in the Coal Sector.
Status of Projects as on 31.03.2004
-------------------------------------------------------WITHIN
WITHIN
TIME
COST
WITH
BUT
BUT
TIME
WITH
WITH
&
TOTAL
WITHIN
COST
TIME
COST
CATNO. OF
TIME &
OVEROVEROVEREGORY
PROJECTS
COST
RUNS
RUNS
RUNS
-------------------------------------------------------1
2
3
4
5
6
-------------------------------------------------------MEGA
2
1
0
0
1
MAJOR
4
2
0
1
1
MEDIUM
59
40
1
13
5
-------------------------------------------------------TOTAL
65
43
1
14
7
--------------------------------------------------------
3.2
These 60 projects are being executed by various Central Sector Undertakings as given below:
CPSU
BCCL
CCL
SECL
ECL
NCL
MCL
WCL
NLC
SCCL
Total
3.3
No. of Projects as in
the last quarter
1
3
15
2
2
6
10
1
20
60
No. of projects as in
December, 2003
1
3
15
2
2
6
10
1
20
60
The latest anticipated cost of 60 projects is Rs.6664 crore showing an escalation of about 9.5% with respect to the original approved cost of Rs.6085.7 crore.
Expenditure till date on these projects is Rs. 3736.72 crore. Outlay in 2003-04 on these projects is Rs 608.63 crore out of which Rs.256.18 crore has been spent during
the first three quarters.
No. of Projects
% of Total Cost
2.3
BCCL
1 3
2.6
9.4
CCL
20
SECL
15
18
ECL
BCCL
8.2
CCL
5.6
ECL
NCL
1
10
NCL
MCL
MCL
7.5
WCL
SECL
6.8
NLC
WCL
39.6
SCCL
NLC
SCCL
152
171 155
154
413
1186
BCCL
CCL
SECL
ECL
NCL
120
MCL
WCL
NLC
2491
SCCL
The accompanying pie charts show the pictorial representation of number of projects being executed by various CPSUs and the anticipated investment/expendiure made
in each of the 9 companies.
3 projects are with cost overrun, the increase in cost being 8.2%, and 17 projects are with time overrun ranging from 3-108 months with respect to the original
schedule and with respect to the latest approved cost and schedule There are 7 projects with cost overrun. The time and cost overrun is mainly due to problems
encountered in execution of UG projects. Many of these projects are under execution for many years and once these projects are completed , the cost and time overrun
would be contained in Coal sector to a greater extent. There are 5 projects which have been under implementation for more than a decade. The reason for the delay in
most of these projects being fund constraints due to delay in tying up fund, problems of fire, gas etc. All these projects are now likely to be completed during the next 12 years.
3.4
Out of the 60 projects, 21 projects are for the development of additional coal production capacity through opencast mines and 36 projects are underground projects, 3
projects are non-mining projects such as Power Plant, Workshops and other allied facilities required for existing and new mines. It has been observed that the time
overrun is much higher in underground mines as compared to the opencast mines.
Project Status
3.5
The implementation status of each of the projects and the statistical details of cost and time schedules, original, revised and anticipated, are given in the succeeding
paras.
COAL INDIA LIMITED (CIL)
BHARAT COKING COAL LTD. (BCCL) (1 Project) , Jharkhand
1.
2.
line (7.13 Km) involves construction of road over-bridges, and re-location of schools and colleges. Out of 83.40 Ha of land, 81.40 Ha has been in the possession. For
balance land, action needs to be expedited. Work on various sections is in progress. The present status of work is as follows:
For the purpose of smooth implementation of the rail diversion project the whole length of 7.425 Km. has been divided into five sections namely section. The likely
DOC of the project is March, 2005. Expenditure incurred over the project so far has been of the order of Rs. 61.26 crore.
In Dhori village, there is a case in Supreme Court and land acquisition was very difficult so a revised alignment was suggested by Railway. Now work in revised
alignment is under implementation.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
During the course of draft discussion and finalisation of Seetaldhara RPR with SECL and CMPDI, it was decided to amalgamate Seetaldhara UG project with the
existing Kurja UG project. Accordingly a Re-organisation PR for combined Seetaldhara & Kurja was prepared (0.88 MTY) for a capital of Rs.98.98 crore which was
approved by SECL Board in its meeting held on 21.7.1999.
The re-organisation project for a production taget of 0.88 MTY at a capital investment of Rs.98.98 crore was approved in the ESC meeting of CIL Board held on
23.5.2000.
As the new re-organisation project for Seetaldhara & Kurja is under implementation after amalgamation of Seetaldhara and Kurja project, implementation of
Seetaldhara & Kurja projects separately, as sanctioned earlier, stands withdrawn. Seetaldhara UG project has, therefore, been put in the list of dropped projects.26.9 Ha
Tenancy land and 16.88 Ha Government land has already been acquired. EMP has been submitted to MOEF in April, 02 and public hearing completed. Main incline
has been completed. Action for ordering HEMM is in progress. Production during 2003-04 (upto December, 2003) is 0.11 MT. Shaft sinking for both shafts
completed.. The project is on schedule. The DOC of the project is May, 2006.
14.
15.
16.
17.
Kanchan OC, M. P.
The project is located in the Umaria district of MP. It has been approved by the Government in March, 2001 for a production capacity of 0.32 MTY at an estimated cost
of Rs.23.92 crore. The production is to start from the 3rd year of land acquisition. The activities on the project are yet to start. EMP has been submitted in April, 02.
Land acquisition is in progress.
18.
19.
Chirimiri Collieries is proposed to be shifted. For CHP. the tenders for the coal bunkers have been issued. 46.4 m and 63.8 m drivage in Incline 1 & 2 has already
been completed out of 175 m each, till December, '03.
20.
21.
22.
23.
Procurement of longwall spares from CIS countries. The proposal was approved by CIL Board on 29.12.1997.
Supply of extensible belt conveyors from MAMC.
Installation of 4th longwall set from Churcha project after refurbishing etc.
Reduced budget allocation in 9th Plan.
Though the project cost is presently estimated same as approved Rs.403.9 crore,
March, 2004.
the cost is likely to go up with the additional delay of 6 years from March 1998 to
It appears, the target production of 2MTY under Phase-I is not possible due to existing old longwall equipment attracting DGMS restrictions. Of the total land
requirement of 1322.95 Ha for both the phases, 1308.85 Ha of land has been acquired till December, 2003.
24.
25.
26.
commissioned. Coal production during 2002-03 was 7.59 MT against targeted production level of of 6.50 MT, and during 2003-04 it was 6.77MT against targeted
production level of 9.00MT till December, '03.
MAHANADI COALFIELDS LTD.(M.C.L.) (6 projects)
27.
Natraj UG,Orissa
The project was approved in January, 2001 for production capacity of 0.64 MTY at estimated cost of Rs.92.11 crore. Out of a total of 270.4 Ha of land requirement,
17.94 Ha of tenancy land is in the physical possession of the Company. For acquiring 216.6 Ha of forest land, application to DFO, Angul for diversion of forest land
has been submitted and the DFO has already carried out the inspection. EMP forwarded to MOEF on 1.5.02. Site verification has been completed and public hearing
held on 03.04.03. NOC was issued in November,'03. Work order related to starting of drivage for incline is being issued to M/s MECL. The likely DOC of the project
is March, 2008.
28.
29.
30.
31.
32.
33.
35.
36.
37.
38.
39.
40.
41.
42.
43.
45.
46.
The project is essential as the company has to supply C grade coal to cement and textile industries in the South and also to accommodate the surplus manpower from
other closing mines of the company. First stage clearance for diversion of 431.85 Ha of forest land has since been obtained.
KTK-3 Incline UG (0.3 MTY), Andhra Pradesh
The project was sanctioned in August, 1996 at estimated cost of Rs.37.50 crore with completion schedule of March, 2003. Land required for initial developmental
activities acquired. Drivage of main tunnels is in progress. 2HS drills deployed in KTK-3A incline so far.
47.
48.
49.
50.
51.
52.
53.
Chennur-2 Incline
The project was estimates approved in June 2002, at estimated cost of Rs. 28.33 crore for a capacity of 0.312 MTPA with completion schedule of March, 2006.
Out of a total land requirement of 85.62 Ha private land, 30.98Ha has been acquired and another 17 Ha is under acquisition . Balance is not critical now.
The project has attained a built - up capacity of 3- HS drills against a total of 6 -Drills. Air shaft sinking and service building construction have started. Inter seam
tunneling is in progress.
54.
KTK 2 Incline
The project was approved in June, 2002 at estimated of Rs.35.35 crore for a production capacity of 0.416 MTPA with completion schedule of March, 2005.
The requirement of land for the present has already been acquired and the balance land is not critical at this stage and the acquisition will be processed as per the need.
The project has attained a built-up of 8 - HS drills so far.
55.
KTK-5 Incline:
The project was sanctioned in June, 2002 at an estimated cost of Rs.40.19 crore for a production capacity of 0.41 with completion schedule of March, 2004.
Most of the land - private as well as forest land, has been acquired. The project has attained a built-up capacity of 8-drills at KTK-5 incline.
56.
KTK-6 Incline
The project was approved in June, 2002 an estimated cost of Rs.29.9 crore with a production capacity of 0.312 MTPA The project is scheduled for completion during
2004-05
About 36 Ha private land has already been acquired and the balance land is not critical now. The project has attained a built up capacity of 3-drills against a total of 6
drills. After completion of the inter seam tunneling, further drill will be added.
57.
58.
59.
60.
61.
62.
63.
64.
65.
SECTOR: COAL
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------BHARAT COKING COAL LIMITED
-------------------------1. POOTKEE
3.00
1983/12 1994/03 2004/03
120
0
48
199.87
182.60
-9
170.94
0.98
171.92
BALIHARI UG
1997/04 2000/03
98
25
199.87
-9
DHANBAD
JHARKHAND
MTY
CENTRAL COAL FIELDS LIMITED
--------------------------2. J.P.RLY LINE
1982/02
1991/03
1985/03
1997/06
2005/03
240
649
93
51
15.93
48.78
48.78
206
0
61.27
0.06
61.33
0.80
MTY
1995/07
2000/03
2005/03
60
107
60
107
46.78
46.78
0
0
38.68
3.31
41.99
1.0
MTY
1998/10
2004/03
2004/03
0
0
0
0
110.89
110.89
0
0
44.70
12.41
-
17.76
62.46
2000/03
2004/03
48
107
48
107
41.95
41.95
0
0
9.69
0.39
-
9.68
19.37
BOKARO
JHARKHAND
3. BOKARO OC
BOKARO
JHARKHAND
4. JHARKHAND OC
JHARKHAND
1998/03
2003/03
2004/03
12
20
12
20
49.93
49.93
0
0
6.52
2.44
-
0.15
6.67
7. VINDHYA UG
AUG.
1998/03
2003/03
2004/03
12
20
12
20
49.90
49.90
0
0
3.29
2.52
-
0.41
3.70
0.585
MTY
MADHYA PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: COAL
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------8. REHAR UG RPR 0.31
1998/12 2003/12 2004/03
3
0
3
26.30
29.91
14
10.69
5.57
0.11
10.80
MTY
5
5
14
SHABOL
MADHYA PRADESH
9. GAYATRI UG
0.31
RPR
MTY
SURGUJA
MADHYA PRADESH
1998/12
2003/12
2004/03
3
5
3
5
26.30
26.30
0
0
5.94
3.35
-
0.34
6.28
1999/07
2004/07
2004/07
0
0
0
0
48.54
48.54
0
0
3.22
5.22
-
1.11
4.33
1999/07
2004/07
2005/03
8
13
8
13
45.26
45.26
0
0
35.35
3.40
-
35.35
12. BAGDEVA UG
0.405
RPR
MTY
KORBA
MADHYA PRADESH
1999/07
2004/07
2005/07
12
20
12
20
38.46
38.46
0
0
16.50
3.39
-
2.24
18.74
2000/05
2006/05
2006/05
0
0
0
0
98.98
98.98
0
0
36.48
3.18
-
1.06
37.54
14. DAMNI UG
2000/04
2005/04
2005/04
0
0
0
0
39.32
39.32
0
0
0.04
-
0.22
0.22
0.48
MTY
SHAHDOL
MADHYA PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: COAL
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------15. JHIRIA UG
0.33
2000/10 2006/03 2006/03
0
0
0
32.07
32.07
0
0.33
3.84
0.33
MTY
0
0
0
SHAHDOL
MADHYA PRADESH
16. NAWAPARA OC
RPR
SURGUJA
CHHATISGARH
0.36
MTY
2000/10
2006/03
2006/03
0
0
0
0
42.55
42.55
0
0
8.77
0.19
-
0.24
9.01
17. KANCHAN OC
0.32
MTY
2001/03
2004/03
2004/03
0
0
0
0
23.92
23.92
0
0
2002/07
2005/07
2005/07
0
0
0
0
41.69
41.69
0
0
1.59
-
2002/12
2009/03
2009/03
0
0
0
0
49.29
49.29
0
0
1.000
MTY
2003/05
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
28.02
28.02
0
0
1.400
MTY
2003/02
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
22.82
22.82
0
0
UMARIA
MADHYA PRADESH
18. AMERA OC
1.0
MTY
MADHYA PRADESH
19. SEAM-V NCPH
UG
0.405
MTY
MADHYA PRADESH
20. BAROUD OC
EXPANSION
CHHATISGARH
21. SARAIPALI OC
CHHATISGARH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: COAL
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------22. KHAIRAHA UG
0.585
2003/09
N.A.
N.A.
N.A.
N.A.
N.A.
88.33
88.33
0
MTY
N.A.
N.A.
0
MADHYA PRADESH
EASTERN COAL FIELDS LIMITED
--------------------------23. JHANJRA UG
3.50
2.00
BURDWAN
MTY
WEST BENGAL
1982/12
1995/08
1994/03
1998/03
2004/03
120
89
72
39
184.55
403.96
386.44
109
-4
363.69
9.33
-
0.40
364.09
24. J.K.NAGAR UG
1991/02
1995/03
2004/03
108
220
108
220
95.28
54.15
-43
-43
48.64
2.12
-
0.07
48.71
1998/03
1998/03
2004/03
2004/03
72
107
0
0
868.93
1281.39
1281.39
47
0
1135.21
120.82
-
98.22
1233.43
2004/03
2004/03
0
0
0
0
1846.49
1846.49
0
0
1229.65
287.39
-
139.80
1369.45
2004/01
2004/01
0
0
0
0
92.11
92.11
0
0
1.82
3.49
-
0.04
1.86
2010/03
2010/03
0
0
0
0
80.75
80.75
0
0
0.49
5.45
-
0.49
BURDWAN
WEST BENGAL
0.87
0.65
MTY
0.435
1997/07
0.67
MTY
2002/03
ORISSA
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: COAL
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------29. TALCHER(W)
0.52
2003/02 2010/03 2010/03
0
0
0
85.05
85.05
0
UG
MTY
0
0
0
ORISSA
30. LINGARAJ OC
5.0
MTY
2003/02
2007/03
2007/03
0
0
0
0
98.89
98.89
0
0
2.0
MTY
2003/02
2005/03
2005/03
0
0
0
0
87.10
87.10
0
0
6.0
MTY
2003/06
2006/06
2006/06
0
0
0
0
95.87
95.87
0
0
MTY
2.4
2003/10
2007/10
2007/10
0
0
0
0
176.55
176.55
0
0
1996/06
2003/03
2004/03
12
15
12
15
46.17
46.17
0
0
23.34
5.11
-
0.26
23.60
1998/12
2002/07
2004/03
2005/03
2005/03
12
19
0
0
56.90
34.91
34.91
-39
0
17.15
6.21
-
2.67
19.82
ORISSA
31. HINGULA-II
OC EXPN
ORISSA
32. BHARATUR OCP
ORISSA
33. BASUNDHRA
(WEST)O.C.P
ORISSA
WESTERN COAL FIELDS LIMITED
--------------------------34. NAHARIA UG
0.36
MT
CHINDWAR
MADHYA PRADESH
35. KUMBHARHKANI
UG
YEOTMAL
MAHARASHTRA
0.36
MTY
0.30
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: COAL
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------36. CONV.KAMPTEE 0.65
2000/05 2007/03 2007/03
0
0
0
88.39
88.39
0
24.97
15.84
6.68
31.65
UG TO OCP
MTY
0
0
0
NAGPUR
MAHARASHTRA
37. ADASA UG
MTY
0.21
2000/12
2005/03
2006/03
12
24
12
24
39.87
39.87
0
0
1.12
3.82
-
0.46
1.58
0.55
MTY
2001/08
2006/03
2007/03
12
22
12
22
62.74
62.74
0
0
5.36
4.93
-
1.06
6.42
0.59
MTY
2001/07
2004/03
2005/03
12
38
12
38
69.06
69.06
0
0
10.65
8.20
-
0.12
10.77
0.4
MTY
2001/08
2006/03
2006/03
0
0
0
0
74.97
74.97
0
0
0.62
2.03
-
0.86
1.48
41. GAURI-DEEP
OC
BALLARPUR
MAHARASHTRA
0.4
MTY
2001/11
2010/03
2010/03
0
0
0
0
86.21
86.21
0
0
0.25
1.68
-
0.25
0.5
MTY
2002/05
2006/03
2006/03
0
0
0
0
43.50
43.50
0
0
3.54
4.65
-
0.06
3.60
NAGPUR
MAHARASHTRA
38. DHURWASA OC
WARDHA
MAHARASHTRA
39. TANDSI UG
EXPN.
MADHYA PRADESH
40. KALGAON OC
MAHARASHTRA
PENCH
MADHYA PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: COAL
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------43. MAKARDHOKRA- 0.5
2003/01 2005/03 2005/03
0
0
0
44.62
44.62
0
20.08
1.76
0.27
20.35
II OC
MTY
0
0
0
UMRER
MADHYA PRADESH
SINGARENI COLLIERIES COMPANY LIMITED
-----------------------------------44. KTK-8 INCL
0.27
1995/12
UG
MTY
2002/06
WARANGAL
0.416
ANDHRA PRADESH MTY
2002/01
2008/03
2008/03
74
101
0
0
34.51
41.54
41.54
20
0
0.16
3.55
-
0.16
1996/08
2005/03
2005/03
0
0
0
0
43.41
43.41
0
0
0.18
0.05
-
0.18
1996/08
2002/06
2003/03
2007/03
2007/03
48
61
0
0
37.50
47.33
47.33
26
0
16.10
5.40
-
4.25
20.35
2000/02
2004/03
2004/03
0
0
0
0
27.05
27.05
0
0
5.35
0.55
5.90
48. KOYAGUDEM
1.0
OCP
MTY
KHAMMAM
ANDHRA PRADESH
2000/11
2001/09
2004/03
2004/03
0
0
0
0
39.14
25.84
25.84
-34
0
6.54
0.70
-
1.40
7.94
2001/02
2005/03
2005/03
0
0
0
0
21.95
21.95
0
0
2.06
1.25
-
0.26
2.32
0.285
MTY
KHAMMAM
ANDHRA PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: COAL
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------50. VK-7 CONTIN- 0.4
2001/08 2004/03 2004/03
0
0
0
49.51
49.51
0
25.00
3.30
3.30
UOUS MINER
MTY
0
0
0
KHAMMAM
ANDHRA PRADESH
51. KHAIRAGURA
0.72
OC
MTY
ADILABAD
ANDHRA PRADESH
2001/09
2005/03
2005/03
0
0
0
0
47.46
47.46
0
0
0.75
0.22
0.97
2002/06
2005/03
2005/03
0
0
0
0
34.94
34.94
0
0
25.94
0.21
3.10
0.85
26.79
2002/06
2006/03
2006/03
0
0
0
0
28.33
28.33
0
0
8.82
0.16
9.00
0.62
9.44
2002/06
2005/03
2005/03
0
0
0
0
35.35
35.35
0
0
27.91
0.27
-
2.35
30.26
2002/06
2004/03
2004/03
0
0
0
0
40.19
40.19
0
0
28.91
0.35
3.80
2.25
31.16
2002/06
2005/03
2005/03
0
0
0
0
29.90
29.90
0
0
18.54
0.12
3.75
0.65
19.19
0.416
MTY
ANDHRA PRADESH
53. CHENNUR 2
INC
0.312
MTY
ANDHRA PRADESH
54. KTK-2 INC
0.416
MTY
ANDHRA PRADESH
55. KTK-5 INC
0.41
MTY
ANDHRA PRADESH
56. KTK-6 INC
0.312
MTY
ANDHRA PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: COAL
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------57. KTK-7 INC
0.312
2002/06 2008/03 2008/03
0
0
0
33.01
33.01
0
0.08
0.75
0.03
0.11
MTY
0
0
0
ANDHRA PRADESH
58. KASIPET OC
0.60
MTY
2001/11
2005/03
2005/03
0
0
0
0
47.29
47.29
0
0
10.00
-
59. RAMAGUNDAM
1.50
OC-I(LEP)
MTY
RAMAGUNDAM
ANDHRA PRADESH
2002/09
2006/03
2006/03
0
0
0
0
48.18
49.18
2
2
3.00
-
0.45
0.45
60. SATTUPALLI
OCP
2002/12
2008/03
2008/03
0
0
0
0
43.44
43.44
0
0
0.25
1.30
-
0.15
0.40
2003/07
2008/03
2008/03
0
0
0
0
48.93
48.93
0
0
3.30
-
62. MANUGURU OC
0.50
III
MTY
KHAMMAM
ANDHRA PRADESH
2003/07
2005/03
2007/03
24
120
24
120
21.85
25.10
15
15
0.75
-
0.04
0.04
2003/07
2005/03
2005/03
0
0
0
0
21.85
21.85
0
0
3.30
-
ANDHRA PRADESH
0.7
MTY
ANDHRA PRADESH
61. SRP OCP-I
0.60
MTY
ADILABAD
ANDHRA PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: COAL
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------64. BPA CC-II
0.400
2003/12 2006/03 2006/03
0
0
0
35.51
35.51
0
EXTN.
MTY
0
0
0
ADILABAD
ANDHRA PRADESH
65. DORLI OCP-I
0.700
MTY
2003/12
2006/03
2006/03
0
0
0
0
48.68
48.68
0
0
ADILABAD
ANDHRA PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
V. FERTILISERS
Project Review
5.1
During the quarter April-June, 2003, there was 1 project on the monitoring system. During the 2nd quarter one more project has been added. The overall status of these
2 project as on 31.12.2003 is summarised below:
Status of Projects as on 31.03.2004
-------------------------------------------------------WITHIN
WITHIN
TIME
COST
WITH
BUT
BUT
TIME
WITH
WITH
&
TOTAL
WITHIN
COST
TIME
COST
CATNO. OF
TIME &
OVEROVEROVEREGORY
PROJECTS
COST
RUNS
RUNS
RUNS
-------------------------------------------------------1
2
3
4
5
6
-------------------------------------------------------MEGA
0
0
0
0
0
MAJOR
1
0
0
0
1
MEDIUM
2
2
0
0
0
-------------------------------------------------------TOTAL
3
2
0
0
1
--------------------------------------------------------
Project Status
5.2.
The implementation status of each of the project and the statistical details of cost and time schedules are given in the attached statements. Brief details of the project is
given below:
1.
ready for commissioning. The project has been scheduled for completion by mid of May 2004 and the commercial production is likely to start thereafter. The delay in
the commissioning of the plant is due to following reasons;
Slow progress of erection by M/s Stewarts & Lloyds.
Delay in supply of critical spares for overhauling of compressors by M/s BHEL.
Non- arrangement of heavy duty crane for erection of Ammonia Converter Shell by M/s S & L. and
Law & order problem at Namrup and its surrounding in the month of November,2003 due to ethnic problem & its consequential effects.
2.
3.
SECTOR: FERTILISERS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------BRAHMAPUTRA VALLY FERTILISER CORPORATION
---------------------------------------1. NAMRUP PLANT UREA
1997/10 2001/05 2004/05
36
0
27
350.00
509.40
46
354.00
124.88
75.31
429.31
92.30
REVAMP
555000
2001/09 2002/02
84
52
509.40
0
NAMRUP
MTPY
ASSAM
RASHTRIYA CHEMICALS & FERTILISERS LTD.
--------------------------------------2. NTRIC ACID
2003/05 2005/01
PLANT UPGRAD
TROMBAY
MAHARASHTRA
3. METHYLAMINES
EXPAN.PROJ.
2003/07
2005/03
2005/01
0
0
0
0
85.00
85.00
0
0
10.00
-
9.51
9.51
69.00
2005/03
0
0
0
0
24.05
24.05
0
0
15.04
-
0.63
0.63
37.00
MAHARASHTRA
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
Project Review :
There are total 2 projects (1 number of AIR and 1 Doordarshan) on the monitoring system during the quarter. The overall status of project was as under:
Status of Projects as on 31.03.2004
-------------------------------------------------------WITHIN
WITHIN
TIME
COST
WITH
BUT
BUT
TIME
WITH
WITH
&
TOTAL
WITHIN
COST
TIME
COST
CATNO. OF
TIME &
OVEROVEROVEREGORY
PROJECTS
COST
RUNS
RUNS
RUNS
-------------------------------------------------------1
2
3
4
5
6
-------------------------------------------------------MEGA
0
0
0
0
0
MAJOR
0
0
0
0
0
MEDIUM
2
1
0
0
1
-------------------------------------------------------TOTAL
2
1
0
0
1
-------------------------------------------------------Project Status:
6.12
The implementation status of each of these projects and statistical details of cost and time schedules, original, revised and anticipated, are given in the succeeding
paras:ALL INDIA RADIO (AIR):
1.
Present Status:
1.
Studio Block:
(a)
(b)
(c)
(d)
(2)
Civil Works in the studio technical area complete. Stone column & cladding work in progress.
Equipment installed. Testing & training in progress.
Power supply connection obtained.
Staff sanction for operation of the new set up is awaited.
Office Block: Building work complete. Computer net working in progress wiring work for EPABX in progress. Finishing and fire hydrant work completed.
DOORDARSHAN (DD)
2.
Brief description of the project : The project envisages setting up of a large Studio Complex comprising eight studios of size varying from 36 Sq mts. To 593
Sq. mts. Area along with associated technical areas and an administrative block. The project was originally approved in April, 87 at a Capital cost of Rs. 34.15
crores. Revised cost estimate of the project amounting to Rs. 81.60 crores was approved in November, 94 Basement work (two levels under ground floor) is
completed. Part of super structure work has also been completed. Part equipments have been procured. Specifications for remaining equipment have been
prepared and purchase action is in progress. Project was expected to be completed by the end of 2000-2001. The anticipated completion date is June, 2004.
The physical progress as in March,04 is 95.23%.
(b)
I.
Structure including brick work plaster and flooring completed. Stone cladding in external face and internal lobby at advance stage of completion. Finishing
works of building in progress. Aluminium doors/windows fixed. False ceiling and cavity flooring work completed except false ceiling in G.F. entrance
workfoyer and lift lobby.
Electrical works viz. E.F.A. & sprinkler system completed and being tested in technical areas.
A/C plant installed and tested.
Installation works in three studios completed and in progress in remaining three studios.
2 MVA power supply obtained.
Building works completed except stone cladding in one of the panel. Finishing works including road work, street light etc. to be in progress. Site visited by Dy.
C.F.O. and inspection note issued.
II.
III.
IV.
V.
VI.
I.
II.
III.
Reason for delay : The delay has been mainly due to the poor performance of the previous agency, with whom the contract had been rescinded in September,2000. Fresh
contracts for balance civil works had been awarded on 8-5-2001.
SECTOR: I & B
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------ALL INDIA RADIO
--------------1. NEW BROAD.
1996/02 2000/03
N.R.
N.A.
N.A.
N.A.
59.17
59.17
0
44.64
11.35
8.60
53.24
90.00
HOUSE DELHI
2003/03
N.A.
N.A.
0
DELHI
DOOR DARSHAN
-----------2. D.D.BH.DELHI
IC/CB PPFVAN
1987/04
1994/11
1990/03
1999/03
2004/06
171
489
63
44
34.15
81.60
81.60
139
0
78.89
4.47
9.97
0.80
79.69
96.00
DELHI
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
VII. MINES
Project Review
7.1
There were 3 projects on the monitor at the end of the quarter ending December, 2003. One major project titled Installation of 8th Unit of CPP at Angul (Orissa)' of
NALCO was commissioned during the intervening period. There were thus only 2 projects at the end of the quarter ending March, 2004.
7.2
Project status :
7.3
(A)
NALCO PROJECTS :
1.
Expansion of Captive Aluminium Smelter and Captive Power Plant at Angul, Orissa (NALCO)
The project involving expansion of capacity of aluminium smelter from 2,30,000 Tonnes Per Annum (TPA) to 3,45,000 and that of the captive power plant from the
existing level of 720 MW to 840 MW (i.e. addition of one unit of 120 MW) at the existing facility of NALCO at Angul with a total investment of Rs. 2061.98 crores
including a foreign exchange component of Rs. 448.69 crores at 1997 price level was approved by the Government in February, 1998 with commissioning schedule of
May, 2002.
Present Status:
Mechanical completion of all the 240 pots which since been achieved. As per the latest indications, the project is likely to be commissioned by April, 2004.
2.
3.
SECTOR: MINES
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------NATIONAL ALUMINUM COMPANY LIMITED (NALCO)
----------------------------------------1. EXP.OF CAP.
1150 TPA
1998/02 2002/05 2004/04
23
0
23
2061.98
2061.98
0 1593.05
1593.05
SMELTER-CPP
SMELTER
45
45
0
ANGUL
120 MW CPP
ORISSA
2. SPL.GRADE
ALUMINA
ANGUL
ORISSA
TPA
26400
1995/07
1999/12
2004/04
52
98
52
98
56.78
56.78
0
0
49.37
1.80
51.17
3. INST.OF 8TH
UNIT-CPP
ANGUL
ORISSA
MW
120
2001/02
2004/02
2004/02
0
0
0
0
480.00
480.00
0
0
204.15
62.83
266.98
100.00 (COMPLETED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
VIII. STEEL
Project Review:
8.1
There were 7 projects on MOS&PI' monitor at the end of the quarter ending December, 2003.
8.2
The overall status of the projects w.r.t the original schedules is as follows:
Status of Projects as on 31.03.2004
-------------------------------------------------------WITHIN
WITHIN
TIME
COST
WITH
BUT
BUT
TIME
WITH
WITH
&
TOTAL
WITHIN
COST
TIME
COST
CATNO. OF
TIME &
OVEROVEROVEREGORY
PROJECTS
COST
RUNS
RUNS
RUNS
-------------------------------------------------------1
2
3
4
5
6
-------------------------------------------------------MEGA
0
0
0
0
0
MAJOR
3
2
0
1
0
MEDIUM
3
1
1
1
0
-------------------------------------------------------TOTAL
6
3
1
2
0
-------------------------------------------------------SAIL PROJECTS:
1.
2.
3.
4.
5.
(B)
NMDC PROJECTS:
6.
SECTOR: STEEL
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------STEEL AUTHORITY OF INDIA LIMITED (SAIL)
--------------------------------------1. HDGL PROJECT
1997/01 1999/01
N.A.
N.A.
N.A.
N.A.
42.85
50.50
18
15.90
15.90
AT DAGAON
N.A.
N.A.
18
ASSAM
2. UPGRADATION
ERW PPEPLANT
ROURKELA
ORISSA
2002/03
2003/11
2005/05
18
90
14
18
90
89.15
89.15
0
0
1.34
50.00
25.00
2.37
3.71
3. LONG RAIL
FACILITIES
BHILAI
CHHATISGARH
2002/09
2004/08
2004/08
0
0
0
0
320.00
320.00
0
0
25.67
145.00
160.00
171.36
197.03
4. TURBO GENER.
CPP-I
ROURKELA
ORISSA
2002/10
2004/10
2004/10
0
0
0
0
32.03
32.03
0
0
0.10
7.50
-
6.56
6.66
2003/03
2005/03
2005/03
0
0
0
0
112.39
112.39
0
0
1.07
50.00
14.40
7.95
9.02
20
29
20
29
298.68
298.68
0
0
17.58
193.87
-
7.87
25.45
5. REBUILDING
COKE OVEN
ROORKELA
ORISSA
BATTERY-1
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
There are 32 projects in the QPISR file at the end of the 4th quarter of the year 2003 -2004 as against 31 projects in the October-December quarter of 2003-2004.
Appendix IV gives details of projects added/dropped during the quarter.
10.2
The overall status of the projects w.r.t the original schedules is as follows:
Status of Projects as on 31.03.2004
-------------------------------------------------------WITHIN
WITHIN
TIME
COST
WITH
BUT
BUT
TIME
WITH
WITH
&
TOTAL
WITHIN
COST
TIME
COST
CATNO. OF
TIME &
OVEROVEROVEREGORY
PROJECTS
COST
RUNS
RUNS
RUNS
-------------------------------------------------------1
2
3
4
5
6
-------------------------------------------------------MEGA
12
4
1
3
4
MAJOR
16
9
2
4
1
MEDIUM
4
3
0
1
0
-------------------------------------------------------TOTAL
32
16
3
8
5
--------------------------------------------------------
10.3
The latest anticipated cost of 32 projects, is Rs.39,939.10 crores which forms 16.17% of the total cost (568 projects costing Rs.2,47,039.20 crores) of all the central
sector projects on the monitor of MOS&PI. The Cost overrun with respect to the original cost (Rs. 38,099.0 crores) is 4.8%. There are 12 mega projects costing
Rs.32,534.79 crores . Expenditure till 31.03.2003 on all these 32 projects is Rs.4631.01 Crores. Expenditure incurred on these 32 projects till March,2004 is
Rs.11,562.0 crores. Against an outlay of Rs.7376.28 crores for the year 2003-04, expenditure reported is Rs.6931.18 crore. The projects in this sector have few
insurmountable constraints, as once the implementation starts, project authorities will see its execution to completion and commissioning. During the year 2003-2004, 3
MMTPA of additional Crude Oil Refining Capacity will be made operational.
Project Status
The implementation status of each of the projects and the statistical details of cost and time schedules, original, revised and anticipated, are given in the succeeding
section.
1.
project was approved by the Board in December,2000 and with expected date of commissioning by September,2003. The now anticipated capital cost of the project is
Rs.1831.00 crores and the anticipated date of commissioning is October,2004.
Status
Hydrocracker Unit (Process Licensor - M/s. Chevron):
All major civil / structural works completed.
Out of total 208 major equipments, 189 nos. received and 160 nos. erected. Piping fabrication / erection works in progress (1,45,175 ID out of 2,73,415 ID fabrication
and 90,759 IM out of 2,83,822 IM completed). Structural erection activities completed for all heaters, refractory castable and coil works are in progress. Site erection
activities in progress for LP Air Coolers, Recycle Gas Compressor, Make up gas compressors & Off gas compressors.
Receipt of HP Air Coolers from M/s. BHPV, balance imported piping material is critical for project completion schedule.
Hydrogen Unit (Process Licensor - M/s. Haldor Topsoe):
Unit is mechanically ready. Liquidation of check list points of task force. No load motor trial run & Instrument loop checking are under progress.
Sulphur Recovery Block (Designer - M/s EIL):
All equipments received and erected. Piping works are nearing completion. Hydrotest of 236 out of 428 piping loops have been completed. Alignment of
Rotary equipments (without piping) in progress. The balance activities of this unit are expected to be completed by May04.
CDU/VDU & Utilities / Offsites (Designer - M/s. EIL):
All equipments received and erected at site. Piping fabrication / erection and structural works are in progress by M/s. Newton. 262 out of 771 piping loops
hydrotested. Electrical works for cable laying, lighting poles / fixtures erection and Instrumentation works for cable tray, cable laying and instrument
installation are in progress by respective sub-contractors of M/s. Newton. Steam tracing, HP Steam piping, Fire proof / gunniting, Jacketed / Fire water
piping, FG/FO and misc. piping works being executed by the newly lined up contractors against offloading of M/s. Newton. The balance piping works are
being expeditiously followed up for completion by May04.
Pre-conmissioning activities of the unit by the task force in progress. No load trial run of motors, system checks including instrument loop checks, relief valve
testing, vessel inspection and preparation of punch list etc. in progress.
Utilities/Offsites (Designer - M/s. EIL):
DM Plant All Streams of DM Plant and Condensate polishing unit commissioned.
Nitrogen Plant Cold Test achieved and Peralite filling completed. All other construction activities completed and Pre-commisioning activities in progress.
Cooling Tower (Sea/Raw): Unit is mechanically completed. Check listing & liquidation in progress along with Motor trial run. Raw water : Unit is totally ready.
Control Room / Sub-Statin All the electrical panels commissioned in SRU sub station and Crude oil sub station.
Major Civil works completed for Offsites. Balance structural works for pipe racks by the newly lined up contractors are expected to be completed in April04.
Mechanical piping fabrication, erection work is in progress and efforts are being made to complete the balance major activities by May04. Balance works of
Contaminated Rain Water Service piping is expedited for completion by May04. Termination & control gear installation in progress for electrical works. Multi core
and power cable laying works in progress for Instrumentation works. Balance works of electrical / instrumentation are anticipated to be completed by May04.
S.No.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Milestone Description
FAT & Delivery of DCS
System
Piping Erection / Hook up /
Hydrotesting (Completed )
HGU
Complete Mech / Piping Works
for (CDU/VDU)
Receipt of Blowers (SRU)
Receive HC Reactors, Heat
Exchangers / Coolers at site
(HCU)
Mechanical
completion
of
CDU/VDU
Completion of DM Plant / CW
System & Nitrogen Plant Work
Mech. Completion of Hydrogen
Unit
Commissioning of CDU/VDU
Receive MUG/RG Compressor
at site (HCU)
Receipt of Major Elec./Instr.
Items (HCU)
Major Mech. Works complen.
For Offsites
Sch. Date
3.10.2003
4.10.2003
Status
FAT (Factory Acceptance Test) completed & DCS
delivered.
155 loops hydrotested out of total 252 nos.
15.10.2003
15.10.2003
25.10.2003
31.10.2003
10.11.2003
10.11.2003
30.11.2003
20.12.2003
31.12.2003
31.12.2003
Total cumulative physical progress is 92%. Cumulative progress till last quarter was 87.8%%.
2.
3.
LPG pipeline will cater to the requirement of LPG bottling plants in Andhra Pradesh in addition to those at Sholapur and Chandanpur in Maharashtra and Bellary in
Karnataka. Both the tap-off facility at Vijayawada and receipt terminal at Cherlapalli will have custody transfer metering. For effective communication, an Optical
Fibre based telecommunication system will be provided. For a reliable health check and operational control of the pipeline, including leak detection, a modern SCADA
alongwith APPS system is envisaged.
Status
Overall progress is 99%.
This pipeline is mechanically complete and the supply of LPG from Oil Marketing Companies (BPCL and EIPL) is awaited. Signing of transport service
agreement is required.
4.
Cumulative progress is 98.3%. Entire Stretch of Dahej Vijaypur pipeline (611 Kms) alongwith all associated facilities commissioned in a record time of one
month from the date of availability of R-LNG from Petronet LNG terminal at Dahaj. Hot taping completed at Dahej for supplying gas to GSPCL. First Gas
Turbine compressor at Vijaipur has given first started.
5.
6.
Green Fuels and Emission Control Project at Mumbai Refinery (HPCL) Mumbai, Maharashtra
The project of modernization of Mumbai Refinery Green Fuels and Emission Control (GFEC) was approved by the Board of Directors at its meeting held on
October 16, 20-02 at a capital out of Rs.1152 crore. The project cost includes foreign exchange component of Rs.179 Crore at September,2002 prices with a
completion schedule of 30 months from the date of approval of the Board. The objective of this project is to upgrade the Motor Spirit quality and to meet the
future specifications of Euro-III for MS with a capability to make Euro-IV MS and Euro-III quality for Diesel and to Maximize the yield of Middle Distillates,
to reduce sulphur emissions and achieve crude processing capacity of 7.9 MMTPA. As envisaged under GFEC, the major changes of MS quality are with
respect to Benzene, Aromatics, Olefins and Sulphur content. On implementation of this project, HPCL Mumbai Refinery, would be able to produce cleaner
Automobile fuels which conforms to Euro-III. The Project envisages the following new units and revamp of the existing units as stated: Revamp of FRCDU/VDU; Revamp of FRE CDU/VDU; Revamp of LR-VDU; Revamp of FCCU; NHT/CCR; ISOM; FCC Gasoline Treating Unit; FGD; NSU; LPG
Treatment; SWS; Amine Regeneration Unit; Amine Absorption Unit; Utilities / Offsites. The proposed Modernization is basically an Environmental
Protection project as it significantly improves the quality of automobile fuels. The project will help in increased availability of eco-friendly automobile fuels in
our contry. The benefits of the proposed project are the improvement in quality of MS and HSD, which will drastically reeduce the emissions from vehicles.
In this way, the proposed facilities will contribute towards a very significant improvement in the quality of ambient air at the national level.
Process Engineering:
Licensed Units: PFD review completed for the Licensed units. P&ID review expected to be completed for the Licensed units by End April,2004. Critical
equipment data sheets for FCCU Revamp, NHT/CCR and ISOM / Prime G+ issued to EIL. Residual process engineering is in progress. Critical equipment
data sheets for FGSU expected by end April,2004. Process Design packages finalized and issued for Engineering for following: CDU/VDU Revamp;
Compressed Air System; Naphtha Splitter Unit; Inert Gas system; Cooling Tower; GTG-VI; LPG Treating and ARU (Revised); SWSU.
Procurement / Tendering:
P.O. placed for Flanges, tubes, Fittings for Heaters; Cooling Tower (4 cells); Studded tubes for Furnaces; Trays / Structured Packings / Internals for columns;
Tube supports castings. P.Os under approvals for placement are Cooling Water pumps for Cooling Tower; APH for Furnaces of CDU / VDU/LR; Plain
Tubes; Air Compressor; GTG VI and HRSG; Ware house / Work shop construction; Exchangers for SWS; Pumps for SWS.
Construction:
Admin Building First slab casting in progress. Fire Station Building All slabs completed. Relocation of chemical block and dismantling of existing
equipment is in progress for providing area to DM plant.
The project is anticipated to complete by December05 due to delay in Licensor selection.
Actual progress is 0.8% against a schedule of 13.6%.
7.
Integrated Para Xylene / PTA Project at Panipat, Panipat Refinery, Haryana (IOC)
The project has been envisaged based on aromatic cut Naphtha (110-165 Deg C) from Panipat and Mathura Refineries. The project is proposed to be located in the
vicinity of Panipat Refinery where IOCL has also proposed to set up a Power Plant based on residue from Panipat Refinery. Project envisages a grass-root para-xylene
Project for production of maximum of Para-xylene, minimum quantity Orthoxylene and Benzene to its potential as well as wants to have a flexibility for producing
Orthoxylene to Para-xylene in the ratio of 0.25. The complex will process two alternate feed stocks as given below: Bombay High - 425,000 TPA of 110-165 Deg C
cut Naphtha from Mathura Refinery and 275,000 TPA of 110-165 Deg C cut from Panipat Refinery is available. Out of this 500,000 TPA of heart cut Naphtha (122147 Deg C Cut) is derived and used as feed stock to the complex. Bonny Light - 375,000 TPA of 113-160 Deg C cut Naphtha from Mathura Refinery, and 275,000
TPA of 113-160 Deg C cut Naphtha from Panipat Refinery is available. Out of this a total of 500,000 TPA of heart cut Naphtha (113-142 Deg C cut) is derived and
used as feed stock to the complex.
A decision has been taken by IOCL to resite the PxPTA Project inside Panipat Refinery and integrate the Utilities & Offsites with Panipat Refinery Expansion Project to
effect savings in overall Project Cost. This has resulted in:
Execution of Process units Px1, Px2 & PTA units at new site on EPCC basis
Dropping of Utilities & Offsites, Steam & Power Packages i.e. EPCC-4 & 5
Integrating Steam & Power Package & some Utilities with PREP
Stand alone systems like C.W system, Flare System, ETP, Tankages, Offsite Interconnecting Piping; Electrical & Instrumentation work under PXPTA Project.
The total Utilities, Offsites and Power Plant are being executed under Conventional Mode.
Process Units
Capacity
Licensor
Paraxylene
361,940 TPA
UOP
PTA
553,000 TPA
DUPONT
Utilities & Offsites
As Required
EIL
EPCC Packages:
EPCC-1
EPCC-2
EPCC-3
:
:
:
ENABLING WORKS, C.W. SYSTEM, FLARE SYSTEM, ETP, TANKAGES, UTILITIES / OFFSITES
INTERCONNECTIONS & ASSOCIATED ELECTRICAL & INSTRUMENTATION WORKS
Project Status
EPCC-3 (PTA) - Job awarded to M/s L&T. Out of estimated 8498 MT of Structural Steel, fabrication drawings for 4297 MT and erection drawings for 1203 MT
released for construction. LOI for all 44 Duponts Mandatory items issued by L&T. 6785 MT of Structural Steel received at site out of total 8498 MT. 3000 Nos. of
Piles completed against schedule of 3110 Nos. (Total 3110 Nos.). Piling in thermal oxidiser / hot oil, Offgas fired heater and DG shed in progress. Balance piling
targeted for completion by last week of March,2004. 12966 M3 of RCC completed against schedule of 23822 M3. (Total 28258 M3). 998 MT of Structural Steel
erected against schedule of 3652 MT.
EPCC-1 & 2 - Job awarded to M/s. EIL. Contract for ETP awarded. Tender for mechanical works refloated for Uttilities & Offsites. Work in progress.
Overall cumulative progress is 44.8%.
8.
9.
10.
MS Quality Upgradation & Additional Diesel Hydro Treating Facility at Mathura Refinery, Mathura, U.P. (IOC)
Background
In order to cater to the need for supply of MS as per Bharat Stage-III fuel quality in NCR w.e.f. 2005, the processing facilities will upgrade entire quantity of MS of
about 1.1 MMTPA produced from Mathura Refinery to Bharat Stage-III fuel specification. For Bharat Stage III Quality Diesel in NCR w.e.f. 2005, the entire quantity
of about 3.0 MMTPA HSD produced from Mathura Refinery will be upgraded to Bharat Stage III specifications. Following facilities are envisaged:
MS Quality Upgradation
Isomerisation
440 TMTPA
DHDT
1.8 MMTPA
LNHDT
440 TMTPA
HGU
60000 TPA
Reformate Splitter
480 TMTPA
TGT
220 TPD
480 TMTPA
SWS
20 MT/HR
GT & HRSG
20 MW X 100 TPH
(Common for DHDT & MSQ)
DHDT/MSQ
Completion Schedule:
Mech. Comp - Approved
Mech. Comp - Contract
Commissioning - Approved
Commissioning - Contract
Approved Cost
:
:
:
:
:
Status
The overall progress achieved by LSTK contractors is 76.29% against a planned progress of 74.93%. The overall progress achieved by the contractors handling major
packages such as EPCC-1, 2, 3 & 7 continues to be more than the schedule, whereas the progress achieved by the other contractors handling non critical packages such
as EPCC-4, 5 & 6 continues to be behind schedule. The non critical packages continue to consume the float available.
EPCC-1
Civil / Structural works of DHDT / HGU is under delay by 4-6 weeks. 2495 MT Structural Steel received at site out of total quantity of 2600 MT.
Out of 102 nos. equipment available at site, 73 nos. have been erected. 2134 MT against 2493 planned fabrication completed & 1625 against 1743 MT of erection
completed. Additional resources like manpower and machinery to be increased.
Cumulative physical progress is 76.93% as against 61.69% last quarter.
11.
Kandla Bhatinda Pipeline Conversion to Crude Oil Service and Mundra Kandla Crude Oil Pipeline Guj/Raj./Haryana(IOCL)
This project will supply crude oil to 6 MMTPA Panipat Refinery Expansion Project. The existing POL pipeline of KBPL is to be converted to crude oil carrying service
and Koyali - Sidhpur - Sanganer (near Jaipur) and Panipat- Rewari Pipeline will be laid to carry POL to terminals at these two places (Sanganer near Jaipur & Rewari in
Southern Haryana). Milestones are yet to be identified. The cost of the project for carrying crude oil to the Refinery Expansion project has been reduced by
Rs.1000 crores in lieu of the now abandoned project of SMPL. Augmentation (originally costing Rs.1734 crores). As this project consists of 3 (2 major and 1
medium project) separate pipeline projects, it will be monitored on a monthly basis as far as the 2 major projects are concerned (KBPL Conversion to Crude Oil Service
for supply of crude to Panipat and Koyali Sidhpur - Sanganer pipeline near Jaipur for supply of POL from Gujarat Refinery to POL Terminal) monitored through
Monthly Flash Report.
Commissioning of the project is now put at January, 2005 as against Aug.2004. The project consists of utilizing M/s. Gujarat Adani Port
Ltd.'s SPM facilities for handling additional crude oil for Panipat Refinery Expansion and taking to Mundra Crude Oil Terminal. Developing a tank farm consisting of
8x60000 KL crude oil storage tanks and laying 73 km. 28" dia pipeline from Mundra to Churwa Scraper Station. Conversion of Kandla - Panipat Section of KBPL into
crude oil service. Milestones will reflect this aspect.
Status:
Environmental clearance from MoE&F, New Delhi received on 19.11.2003.
MoE&F, Bhopal has cleared the proposal for protected forest in the new ROW. No unprotected forest lies in the pipeline route. Proposal for protected and
reserved forests in GAPL corridor has been cleared by MoE&F, New Delhi.
Permissions available for all crossings barring one railway crossing in GAPL corridor, follow up for which is being done by GAPL.
62% physical progress has been made by GAPL on development of crude oil handling facilities at Mundra.
Construction of tank farm boundary wall and foundations for all 8 crude oil storage tanks as well as 4 firewater storage tanks has been completed. Shell
welding has been completed for 4 and in progress for other crude oil tanks.
Mainline laying is in progress and 24 km. welding has been completed.
Works for Mundra station construction, mainline cathodic protection system, control system, telecommunication system and oil water separator system are in
progtress.
Production of mainline pipes completed. Coating completed for 57 km.
All critical materials are available at site.
Cumulative physical progress is 63%.
12.
Status
Environmental clearance from MoE&F, New Delhi has been issued on 23.12.2002.
Forest clearance is available.
ROW acquisition has been completed.
Permanent land acquisition completed for Kot pump station & Baghsuri scraper station.
Mainline laying works are in progress and 381 km. welding has been completed.
Production of mainline pipes has been completed. Coating of pipes is nearing completion.
Orders for supply of all major materials have been placed and materials are being received progressively at site.
Cumulative physical progress is 63.5% as against 49.45% last quarter.
13.
14.
15.
16.
17.
Status of Implementation:
NOA placed on M/s. EIL, on nomination basis, on 8.2.2002 at a cost of Rs.821.19 Crore. LOI for 164 Nos. equipments / packages issued by EIL. Fabrication of deck
structure commenced on 20.8.02 at L&T Yard, Hazira and is in progress. Fabrication of Deck Structure, LQ module, PGC module and switchgear module & piles
completed. Erection of all major equipment viz. GTGs, Compressor, Transformers, MIPs, Booster Pumps, Emergency Generator, Sea Water Life Pumps, IA/UA
Compressor & Start-Up Compressor etc. are completed. Fabrication of jacket completed and jacket installed. Fabrication of piles completed. String test of Process
Gas Compressor completed at yard. Jacket launched on 12.11.03. Installation has been completed. Deck, PGC / SWGR / LQ Modules, Deoxy & Fine Filter Skids &
Bridge have been installed on 25.12.03. Commissioning of water injection facilities in progress.
Mumbai High North Clamp-On Structure Project (MNCO Project)
Brief description of facilities : Clamp-On Structures at LD, N6, NQ, NE, NO, NT, N3, N8, LA, LC, N5, N2, NP (13 nos.) platforms. Remaining requirement of
clamp-on at 2 platforms will be reviewed & Clamp on requirement at one platform has been
deferred.
Project status:
Package completed successfully on 19.12.2001, ahead of the scheduled completion date of 28.2.2002.
Package III - N-11/N-12 Well Platform Project (N-11/N-12 WPP)
Brief description of facilities: Fabrication and installation of two nine slot well platforms
Laying of 11 new pipeline segments totalling 55 kms. Modification on 18 existing platforms.
Project Status
Installation of well platforms N-11 & N-12 completed. Drilling Rig deployed at N11 & N12 Well Platforms and drilling is in progress.
Drilling Rig deployed on N11 Well Platform on 11.5.2003.
Package IV - N-9/N-10 Well Platforms
Fabrication and installation of two nine slot well head platforms (N-9 & N-10). Laying of 8 new pipeline segments (two well fluid, two gas lift & four water injection)
totaling 26 kms. Modification on 7 existing platforms.
Status of Implementation:
NOA placed to M/s. L&T, Mumbai on 20.5.2003 at a cost of Rs.365.27 Crore with the following schedule :RFD : 30.4.2004 ; Project Completion : 31.12.04. Kick Off
meeting held on 3.6.2003. Pre engineering survey for modification works on platforms completed. Design Centre opened on 20.6.03 at Valdel, Bangalore and review
of documents & drawings are in progress. 461 nos. of drawing & documents submitted. Planning Package has been submitted. Fabrication of Jacket & Deck started on
1.10.2003 at MFY Yard Hazira. Jacket Face Dive Survey, Jacket Location Survey and Pipeline Survey completed on 12.11.203. Coating and wrapping of pipeline
completed. Installation of N-10 Jacket started and piling in progress. N-9 Jacket load out planned on 3.4.04.
Package V-3 Pipeline Project (earlier part of N-9 & N-10 w/platform project)
Brief Description of Facilities
Status
LOI placed on 18.4.2002 on M/s. Bridge & Roof, Mumbai for Rs.15 Crore with scheduled completion of 17.10.2003.
Electrical work has started on 2.4.2003.
Instrumentation work has started on 23.5.2003. Construction work in progress. Mechanical / Structural work started on 26.11.2003. Against the schedule progress of
100%, actual progress is 87.13% by end of March,2004.
Package IV: LP Gas Compressor Phase-I - Installation of 7 compressors (4 at GGS I and 3 at GGS IV), including 2 standby, for compression of 0.91 mmcmd of low
pressure gas.
Status
Compressor Package LOI placed on M/s. BPCL, Naini, on 20.9.2000 at a cost of Rs.58.40 Crore with contractual completion by 19.9.2001. Work behind schedule.
All four compressor units for GGS-I and three compressor units for GGS-IV delivered and received at site. Gas compression facility at GGS-I, Gandhar is operational.
LSTK Work LOI placed on M/s. Engineering Projects India Ltd(EPIL) on 6.10.2000 at a cost of Rs.18.45 Crore with contractual completion by 5.1.2002.
the schedule progress of 100%, actual progress is 95.70% by end of March ,2004.
Against
Package V : LP Gas Compressor Phase-II - installation of 5 compressors, including 1 standby, for compression of 0.90 mmcmd of low pressure gas.
Status
Compressor Package NOA placed on M/s. Kirloskar Pneumatics Ltd. on 15.5.2003 for Rs.41.422 Crore. The delivery schedule as per NOA is 14.5.2004.
Two skids are under packaging. String test of first machine scheduled on 29.3.04.
LSTK Works - NOA placed on M/s. Bridge & Roof Co. (I) Ltd. in 2003 for Rs.12.09 Crore. The completion schedule as per NOA is 14.9.2004. Detailed design
engineering and procurement is in progress. Project progress is slow. Overall progress is 67.71% against scheduled 78.32%.
Package VI: Collector & Feeder Lines - To provide collector and feeder lines between various installations.
Status
The project is being executed by 10 packages. The various feeder / collector pipelines are in different stages of progress. The overall progress is 96.46% against the
schedule of 100%.
Package VII : Effluent Treatment Plant (ETP) : To augment the effluent treatment capacity by 1000 m3.
Status
As per present status, there is no requirement of new ETP.
Overall Status of IOR Gandhar Project
Sl.No.
Project
1.
Surface facilities
2.
Wells
3.
Flow lines
Overall
Sch.%
31.52%
45.00%
7.85%
84.37
Act.%
20.07
45.00
6.05
71.12
19.
20.
Date of Approval:
Approval cost:
Completion:
16.9.2000
Rs.99.67 crores.
Sch : March,2007
Present status:
During 2002-03, 10 wells drilled against plan of 9 wells. 37 Wells completed including two multilateral wells by end of March,2004. These high technology wells
attempted for the first time in onshore fields. 45 zone transfers carried out against plan of 31, hydrofracturing done in 52 wells against plan of 50 and artificial lift mode
changed in 45 wells against plan of 66 wells by end March.2004. One HP compressor of 0.5 LCMD capacity from M/s. Dresser Rand India Pvt. Ltd. installed and
commissioned on 7.7.03. Other surface facilities works like tankage, effluent & oil transfer pumps demulsifier dosing pump and works on heater treater are nearing
completion and likely to be completed by March,05.
21.
16.9.2000
Rs.62.86 crores
2002-03
Present Status:
Drilled 32 wells against plan of 33. TOI placed on M/s. EPIL for turnkey construction of GGS-IV on 23.5.2003. Soil investigation of site completed. Area grading
completed except micro-grading. Construction of approach road, administrative and control room block in progress. Anticipated completion of GGS-IV is 22.11.2004.
All 33 wells planned in the scheme has been completed.
22.
23.
Status:
Package I : Effluent Treatment Package (ETP) : Expansion of ETP from 10000m3 to 2500 m3.
Status
Consultancy job awarded to M/s. PDIL for designing of ETP. NIT issued on 26.2.03. Technical bids opened on 23.5.2003. Price bids opened on 27.8.2003. Award
under hold due to mid term review of requirement.
25.
Package II : Effluent Treatment Plant (ETP) - Revamping and expansion of ETP to 2000 m3.
Status
Package awarded on 30.9.2002 to M/s Santosh Sahewala, Builders & Engineers, Sibsagar at a cost of Rs.3.41 Crore with contractual completion 31.12.2003. Plant
commissioned with existing effluent disposal pumps on 31.12.03. Installation and commissioning of new 3 effluent disposal pumps completed. Liquidation of punch
list items is in progress.
26.
16.10.2001
Rs.5255.97 Crore (including ZA)
(including Rs.2306.08 Crore for drilling)
July,207.
Rs.188.84 Crore
Rs.593.50 Crore
Rs.137.60 Crore
The facilities envisaged under the project are expected to be executed through seven separate packages, including ZA Well Platform approved earlier and now included
in MHS Redevelopment.
Package I - ZA Well Platform - Completed (Expenditure incurred Rs.124.12 Crores till 31st March,2002)
Status
ZA platform made ready for drilling on 31.12.2001.
Package II - Mumbai High South Integrated Process Platform (MSP)
Integrated process platform bridge connected to BHS complex with gas compression capacity of 3.8 mmscmd (2 nos. of 1.9 mmscmd each) booster capacity of 4
mmscmd (2 nos. of 2 mmscmd each), separation capacity of 70,000 blpd, dehydration capacity of 3.8 mmscmd (2 nos of 1.9 mmscmd each), PWC capacity of 85,000
blpd and power generation capacity of 12 MW: augmentation of accommodation for 20 persons; process related modifications at BHS, SHG, IC complex and SCA.
Status
LOI was placed on 10.6.03 to HHI at a cost of US $ 222.3 Million. Kick Off meeting was held on 18.9. 03. Design Enginnering commenced at HHI, Ulsan on
23.6.2003. NOA for consultancy contract for Package 3(a) (Engineering & Procurement Phase) awarded to Worley on 10.7.2003 and contract signed on 22.8.03.
Consultancy contract was signed for Package 3 A on 22.8.2003. NOA for inspection and certification job placed on CEIl on 22.9.2003. Final HAZOP conducted from
1st to 19th December,03 at Bangalore, Out of 51 P.S. documents submitted by HHI, 48 have been approved. Out of 160 P&IDs for modification cases, 157 cases have
been signed.
Package III - Mumbai High South Clamp-on Structures (MSCO) - 8 Clamp-on Structures each having 3 slots at EC, SE, NM, SC, IM, SU, S106 & SG (2 slots).
Status:
NOA issued on 30.8.2002 to M/s. L&T at a cost of Rs.32.62 Crore with contractual completion date 30.3.2003. Package completed on 13.2.03 ahead of schedule.
Package IV Nine Well Platforms (ZB, RS1, Rs2, RS3, RS4, RS5, RS7, RS8 & Rs 11)
As per the decision of EPC meeting held on 4.7.03, 4 Well Platforms Project has been merged with 5 Well Platforms Project and is now being executed as 9
Well Platforms Project under two tenders. Tender I Installation of 9 Well Platforms, Tender II Pipelines Laying and Platforms Modifications. The
Project 9 Well Platforms (ZB, RS1, RS2, RS3, RS4, RS5, RS7, RS8 & RS 11) is being executed with staggered schedule as follows:
Phase I : 5 Well Platforms ZB (12 slots), RS1 (6 slots) (RS3(6 slots) & RS11 (9 slots) with completion as 15.4.05.
Phase II: 4 Well Platforms RS4 (6 slots), RS5 (9 slots), RS7(9 slots) & RS8(6 slots) with completion date as 28.2.06.
Status:
Scope of work approved. NIT issued on 12.9.2003. Sale of bids closed on 27.10.03. Pre-bid conference held with bidders on 3.11.03. TBO was done on 17.12.03.
The L 1 bidders price was 22% higher than the estimate. Negotiations held and work awarded to L&T on 20.2.04 at Rs.1006.65 Crore. Kick off meeting held on
8.3.04. Design engineering is in progress.
Drilling of Development Wells: Drilling to be initiated after installation of platforms.
Package V Pipeline & Platform Modificatins Project (RSPPM)
As per the decision of EPC meeting held on 4.7.03, 4 Well Platforms Project has been merged with 5 Well Platforms Project and is now being executed as 9
Well Platforms Project under two tenders. Tender-I Installation of 9 Well Platforms, Tender II Pipelines Laying and Platforms Modifications. The project
is being executed with staggered schedule as follows:
Phase I : Laying of 24 pipeline segments (110.8 Kms. 0 & 21 nos. platform modifications.
Phase-II: Laying of 9 pipeline segments (44.0 Kms.) & 3 nos. platform modifications.
Status
Scope of work has been approved. NIT issued on 12.9.2003. Sale of bids closed on 27.10.03. Pre-bid conference held with bidders on 3.11.03. TBO held on
18.12.2003. Work awarded to IOEC on 20.2.04. Kick off meeting held on 9.3.04. First progress review meeting held on 29.3.04.
Package VI : 9 Clamp On Project
Installation of clamp-on structures at 9 nos. of well platforms viz. IC, IB, IH, SI-6, IF, S1-5, IU, IS & ST along with production related modifications.
Status:
The contract has been awarded to L&T on 14.11.03. Kick off meeting held on 21.11.03. Design Engg. In progress at Valdel, Bangalore and Triune, New Delhi.
Fabrication commenced at L&T Yard, Hazira on 16.1.04.
27.
:
:
:
Rs.10.00 Crore
Nil
Status
Soil Survey at D-1 location completed by Marine Survey. Soil investigation report received from IEOT. As per approval of competent authority the previous tender was
closed and fresh tender was invited. NIT issued on 17.11.2003 and Bid Documents issued to 6 parties i.e. M/s. EIL and M/s. J Ray Mc. Dermott, Middle East, M/s.
L&T, M/s. HHI, Korea, M/s. Gulf Piping Co, Abu Dhabi & M/s. OMZ, Russia. TBO held on 5.2.04 and unpiced bid of EIL opened on 23.2.04. Quoted price of L-1
bidder (EIL) was 17.59% higher than estimate. After negotiations EIL agreed to reduced their price by US $ 0.5 million. NOA issued to EIL on 10.3.04 at US $ 62.3
million. Kick off meeting held on 24.3.04. Revised cost of D-1 Project as Rs.506.52 Crore approved by PAC/Board on 25th / 26th .03.2004.
28.
:
:
:
:
:
:
Nil
Nil
Nil
Status
FR of the project has been approved by ONGC Board on 22.4.2003. EIL has been appointed as the consultant to the project. Execution Methodology has been
approved. BEC approved on 22.10.03. NIT issued on 4.11.2003. TBO has been revised to 10.3.04 on request of bidders. Techno-commercial bids received from four
bidders i.e. HHI, Korea; Consortium of SOME & Saipem; SHI, Korea; L&T, Mumbai, Bids opened and TC held.
29.
:
:
:
:
:
Nil
Nil
Status
FR of the project has been approved by ONGC Board on 22.4.2003.
Consultancy Tender: Tender re-invited on 4.11.2003. Price Bids opened on 17.11.2003. NOA issued to M/s. Intec Asia Pacific SDN BHD Kaula Lampur Malaysia on
25.11.2003. Kick off meeting held with the consultant on 11.12.03. Based on comments / discussions with ONGC, consultant has revised and forwarded the
documents.
Marine Survey: GTV Sumudra Sarveshak completed. Geotechnical investigations on 11.3.04 along pipeline route, G-1 subsea PLEM location and GS-15 platform
location. Engineering survey upto 100m. water depth completed.
Current & Turbidity Measurement: M/s. NIO, Vizag completed seond phase of field work on 15.3.04.
On-land export pipeline: NIT issued on 15.1.04, Pre-bid conference held on 26.2.04. Techno commercial bids opened on 9.3.04.
Environmental clearances: Water and sediment samples collected during engineering survey from offshore locations sent to M/s. NEERI, Nagpur. Environmental
impact analysis (EIA), Risk analysis (RA) studies in progress by M/s. NEERI, Nagpur.
Land acquisition: Land acquired on lease at Odalarevu.
30.
31.
32.
SECTOR: PETROLEUM
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------BHARAT PETROLEUM CORPORATION LIMITED
-----------------------------------1. REF.MODERNI- MTPA
2000/12 2003/09 2004/10
13
0
13
1592.65
1831.00
15
532.12
570.00
624.88
1157.00
92.00
SATION
11
2002/04
39
39
1831.00
0
MUMBAI
MAHARASHTRA
2. MUMBAI-MNMAD
POL PLINE
MAH/MP
KMS
334
MMTPA
1.4
2001/04
2004/04
N.R.
2003/09
N.A.
N.A.
N.A.
N.A.
N.A.
336.07
336.07
0
0
205.28
100.00
-
30.52
235.80
2003/08
2004/04
8
26
8
26
490.65
463.26
-6
-6
266.56
120.00
-
123.25
389.81
99.00
2001/12
2004/09
2004/04
-5
-15
-5
-15
2936.00
2444.54
-17
-17
21.09
1800.00
1800.00
1986.78
2007.87
98.30
2002/12
2005/07
2005/12
5
16
5
16
1416.00
1416.00
0
0
0.56
50.00
-
1.97
2.53
9.05
2005/12
8
27
8
27
1152.00
1152.00
0
0
0.43
100.00
55.00
14.42
14.85
0.80
2005/08
0
0
0
0
4228.00
5104.00
5104.00
21
0
509.43
221.00
-
457.49
966.92
44.85
100.00 (COMPLETED)
GUJ,RAJ,MP
5. DAHEJ-HAZIRA
-URAN PIPELN
GUJ/RAJ
HINDUSTAN PETROLEUM CORPORATION LIMITED
--------------------------------------6. GREEN FUELS&
2002/10 2005/04
EMISSION CTL
MUMBAI
MAHARASHTRA
INDIAN OIL CORPORATION LIMITED
-----------------------------7. INTEGERATED
1999/06
PARAXYLENE
2001/10
PANIPAT
HARYANA
2005/08
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: PETROLEUM
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------8. PANIPAT REF.
1999/08 2005/01 2005/04
3
0
3
3365.00
4177.00
24
346.00
800.00
718.88
1064.88
50.20
EXPANSION
2002/01
5
5
4165.00
0
PANIPAT
HARYANA
9. LINEAR ALKYL
BENLENE
VADODRA
GUJARAT
LAC TPA
18.5
2001/05
2004/03
2004/08
5
15
5
15
1248.00
1317.00
6
6
259.80
225.00
-
449.91
709.71
92.91
2001/08
2004/08
2004/12
4
11
4
11
1483.00
1755.00
18
18
186.57
450.00
-
472.34
658.91
76.93
2002/02
2004/08
2004/12
4
13
4
13
305.60
265.00
-13
-13
43.54
100.00
100.00
104.96
148.50
63.00
2002/02
2004/11
2004/11
0
0
0
0
352.69
369.90
5
5
14.17
76.00
120.00
197.75
211.92
63.50
13. MS QUALITY
UPGRAD.FACI.
HALDIA,MIDNA
WEST BENGAL
2003/05
2005/07
2005/07
0
0
0
0
359.00
391.00
9
9
0.89
10.00
-
15.51
16.40
20.14
14. MS QUALITY
UPGRAD.FACI.
VADODARA
GUJARAT
2003/07
2005/07
2006/06
11
46
11
46
390.00
390.00
0
0
0.71
3.25
3.96
2.38
10. MS QUALITY
UPGRADATION
MATHURA
UTTAR PRADESH
11. KBPL CONV.&
POL PPAT-REW
MMTPA
8
GUJ/RAJ/HAR
12. SIDPUR-SANGANER PIPELIN
GUJ/RAJ
MMT
4
KM
506
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: PETROLEUM
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------15. CHENAI-TRCHY
2003/07 2005/07 2005/07
0
0
0
363.21
363.21
0
1.30
10.00
12.43
13.73
21.50
MADURAI PR.
0
0
0
50.00
CHENNAI
TAMIL NADU
16. PANIPAT-REW.
PIPELINE PRO
2002/01
2004/07
2004/11
4
13
4
13
75.96
75.96
0
0
1.24
24.00
25.57
43.11
44.35
2005/12
0
0
0
0
2929.40
2929.40
0
0
555.86
899.41
-
738.00
1293.86
HARYANA
OIL & NATURAL GAS CORPORATION LIMITED
------------------------------------17. MUMBAI HIGH
MMT OIL
2000/12 2005/12
NORTH DEV
24.8
BCM GAS
585
18. IOR GANDHAR
BHARUCH
GUJARAT
MMT OIL
4.82
2000/12
2004/03
2004/12
9
23
9
23
609.44
692.45
14
14
118.28
33.29
-
38.13
156.41
71.12
2001/01
2003/07
2004/10
15
50
15
50
347.69
347.69
0
0
50.61
62.44
-
22.16
72.77
MMT
2.65
BCM
0.46
2000/09
2007/03
2007/03
0
0
0
0
99.67
99.67
0
0
47.99
19.92
-
47.99
MMT
1.09
2000/09
2003/03
N.R.
2003/12
N.A.
N.A.
N.A.
N.A.
N.A.
62.86
62.86
0
0
35.72
8.00
-
0.32
36.04
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: PETROLEUM
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------22. IOR SCHEME
MMT
2001/08 2005/03 2005/03
0
0
0
71.92
71.92
0
25.02
9.74
3.61
28.63
SOBHASAN
1.308
0
0
0
GUJARAT
23. IOR LAKWALAKHMANI
MMT
6.17
2001/09
2007/03
2007/03
0
0
36
0
0
345.10
345.10
0
0
0.22
37.00
-
28.33
28.55
44.82
MMT
3.94
2001/09
2007/03
2007/03
0
0
24
0
0
390.09
390.09
0
0
0.08
4.00
-
0.03
0.11
MMT
1.38
2001/09
2006/03
2006/03
0
0
10
0
0
113.90
113.90
0
0
0.38
20.65
-
17.28
17.66
21.50
2001/10
2007/07
2007/07
0
0
0
0
5255.97
5255.97
0
0
159.53
855.56
-
75.76
235.29
2002/09
2005/03
2005/03
0
0
-1
0
0
310.32
310.32
0
0
10.00
-
0.10
0.10
2003/04
2006/03
2006/03
0
0
0
0
985.17
985.17
0
0
2.78
-
ASSAM
24. IOR GELEKI
GELEKI
ASSAM
25. IOR - RUDRA
SAGAR
RUDRASAGAR
ASSAM
26. MUMBAI HIGH
SOUTH DEV.
W.OFFSHORE
27. DEV.D-1
PROSPECT
W.OFFSHORE
28. DEV.OF BASSE
IN EAST
MMT
4.75
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: PETROLEUM
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------29. DEV OF G1 &
2003/04 2005/03 2005/03
0
0
0
429.82
429.82
0
20.47
20.47
G15
0
0
0
-
2003/12
2006/06
2006/06
0
0
0
0
900.92
900.92
0
0
31. HIGH-URAN
TRUNK P.LINE
MUMBAI
MAHARASHTRA
2003/12
2005/05
2005/05
0
0
0
0
2792.50
2792.50
0
0
3.33
-
1.21
1.21
2004/06
11
31
11
31
2360.38
2360.38
0
0
1247.63
713.59
-
728.33
1975.96
99.00
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
XI. POWER
Project Review
11.1
There were 47 projects on the monitoring system at the end of December,2003. 4 projects have been added during the quarter. There are 50 projects as on 31.03.2004
on the monitor for the quarter ending March,2004. Appendix IV gives details of the projects being added/dropped during the quarter.
The overall status of the projects w.r.t. the original schedule is as follows :
Status of Projects as on 31.03.2004
-------------------------------------------------------WITHIN
WITHIN
TIME
COST
WITH
BUT
BUT
TIME
WITH
WITH
&
TOTAL
WITHIN
COST
TIME
COST
CATNO. OF
TIME &
OVEROVEROVEREGORY
PROJECTS
COST
RUNS
RUNS
RUNS
-------------------------------------------------------1
2
3
4
5
6
-------------------------------------------------------MEGA
17
8
5
0
4
MAJOR
27
13
0
9
5
MEDIUM
6
3
1
2
0
-------------------------------------------------------TOTAL
50
24
6
11
9
--------------------------------------------------------
11.2
These 50 projects are being executed by various Central Public Sector Undertakings as given below:
CPSU
NTPC
NHPC
NEEPCO
SJVNL
THDC
POWERGRID
TOTAL
11.3
No. of projects as
at the end of
December, 2003
6
9
2
1
2
27
47
Projects added
during the quarter
Projects deleted
during the quarter
No. of projects as
in March, 04
4
4
1
1
6
9
1
1
2
31
50
The latest anticipated cost of the 50 projects is Rs.74,424.38 crore, (forming about 30.13% of the total cost of projects being monitored in the central sector) showing
an escalation of 30.9% with respect to the original approved cost of Rs.56,845.9crore. Expenditure till date on all these projects is Rs.33,595.55 Crore. Outlay in 200304 on all these projects is Rs.7376.28 crore against which Rs.7363.7 crore has been spent during the year.
11.4
50 projects in the Power sector show a cost overrun of 30.9% w.r.t. the original estimates and 10.3% w.r.t. the latest approved estimates. There are 14 projects with cost
overrun and 19 projects with time overrun w.r.t. the latest approved cost and schedules. The time and cost overrun is mainly due to problems encountered in execution
of Hydro projects. Many of these projects are under execution for many years and once these projects are completed, the cost and time overrun would be contained to a
greater extent.
Out of a total of 568 projects on the monitor, 19 delayed projects account for more than 90% of the cumulative cost overrun (total delayed projects are 211) and among
these 19 projects, 5 are in Power Sector (4 hydro and 1 transmission project ).
There are 3 hydro projects in the Power Sector viz Dulhasti, Dhauliganga and Nathpa Jhakri, which are under construction for more than a decade. These account for
major portion of cost and time overrun. Dulhasti & Nathpa Jhakri projects are now scheduled for completion during the current year and Dhauliganga is to be
completed by early 2005.
11.5
11.6
In all 5 projects in the Power sector have reported increase in cost more than their latest approved costs. Some of them require immediate approval of their revised cost
estimates by the PIB/CCEA. The details are given in Table 12 (giving sector wise distribution requiring review/sanction of RCE).
Problems in Implementation:
The main problems in implementation reported by project authorities are summarised below :
Law & order problems - Projects delayed due to law & order problems are Tehri HEP, Loktak D/S HEP, Dulhasti HEP.
Land acquisition Projects delayed due to land acquisition are Tehri HEP and Loktak D/S HEP
Civil Works Dulhasti and Nathpa Jhakri HEP
Project Status
11.7
The implementation status (as at the end December, 2003) of each project and statistical details of cost and time schedules, original, revised and anticipated, are given in
the succeeding sections.
Lot-IV (Hydro Mechanical Equipment): LoI for Lot-IV has ben issued to M/s Alstomm Power Portugal S.A., New Delhi on 17.11.2003.
Lot-V (Electrical Works): The package covers all electrical works. Work order for this package issued to M/s. BHEL on 26.09.02. Work is in progress.
National Hydro-electric Power Corporation (NHPC)
2.
3.
4.
All major works have been completed. Unit-II was synchronised to grid on 5.12.2003.
5.
6.
7.
8.
9.
10.
12.
Necessary access to the Project in the form of the all-weather road, accommodation and communication facilities, and consultation
power for the project is available. The 33 KV line from Chamba and Bhagirathi Puram to Project site has been constructed. The 33
KV sub-station and 11 KV line to Project site is in operation.
Civil/HM Works
Diversion Tunnel has been constructed and Bhagirathi river diverted in Dec.03. Construction of U/S Coffer Dam is in progress and
has been raised to EL 543 m. The open excavation for Dam, Spillways and Surface Power House is in progress. Out of the total
open excavation of 48.86 Lac.cum., a quantity of 26.00 Lac. Cum. has been executed for Dam, Spillways and Power Intakes.
Hydro-Mechanical Package for Diversion Tunnel Gate has been awarded to M/s. TSPL. Fixing of second stage Embedments for
Diversion Tunnel Gate has been completed. Award for other packages of Hydro-Mechanical Equipment is under process.
Diversion Tunnel
In the Diversion Tunnnel, the invert lining has been completed and 93 meters out of 593 meters of overt linning is pending. The
river diversion was targetted by October, 03 which is now scheduled in the middle of December, 2003. The delay is mainly
because of delay in closure of tunnels T-3 and T-4 of Tehri Stage-I.
The excavation has been taken up in Dam, Spillway and Powerhouse area and 18 lakh cum out of 50 lakh cum have already been
excavated.
The Electro-mechanical package has been awarded to BHEL on 21st March, 2003 and the model testing of Turbine is likely in
December, 2003. Regarding hydro-mechanical package, the award is under process and is likely to be placed during the current
year.
Rehabilitation
For rehabilitation of the project affected persons in the area, a comprehensive plan of action needs to be formulated and followed
up.
kilometre long head race tunnel (HRT) terminating in a 21 metre diametre and 301 metre deep surge shaft, iv) three circular steel lined pressure shafts, each f 4.9 m
diametre and 633 metre long, bifurcating near the Power house (PH) to feed six generating units, v) an under ground power house with a cavern size of 22m x 20 m 49
m having six Frnacis units of 250 MW each to utilise a design discharge of 405 cumecs and design head of 425 metre vi) a 10.15 m dia and 982 m long tail race tunnel
to discharge the water back into the river satluj. The UG Desilting complex capable of segregating the contaminations down to 0.2 mm to prevent them entering the
HRT and Turbines, 27.4 km HRT and 300 m deep surge shaft are distinct and unique features of the project.The HRT of the nathpa Jhakri HEP in the longest in the
world. Besides, this would be the largest UG P.H. in the country to house 6x250 MW units in a single underground cavern.
Contracts awarded
ABB, Siemens, Sulzer & BHEL), has been awarded the main contract of supply and erection of electical generating units in March'94. Dam and desilting chamber
works contract (value Rs.439 Crores) have been awarded to M/s CFJV. Contract for Head Race Tunnel (length 16.05 Km) costing Rs.510 crores has also been awarded
to M/s CFJV. Contract for Power House complex (value Rs.475 Crores) has been awarded to M/s JHC. The other minor contracts awarded are for Butterfly Valves,400
KV SF6 GIS and Bus ducts package, Generator transformers, Gates & Hoists.
Status of main project works
Commissioning
Schedule as per RCE-III
September,2003
November,2003
December,2003
February,2004
May,2004
July,2004
Present Status
Commercial operation commenced on October 06,2003. Synchronised on 20.9.2003.
Commercial operation commenced on January 02,2004. Synchronised on 23.11.2003
Commercial operation commenced on March 30,2004. Synchronised on 13.2.2004
Successful spinning achieved on February 24,2004. Synchronised on 09.3.2004
Successful spinning achieved on March 15,2004. Synchronised on 31.3.2004
Commercial operation commenced on October 06,2003. Synchronised on 20.9.2003
Above four units are operating smoothly and generating electricity, from 1000 MW capacity made operational, depending upon the water availability in the river Satluj.
Out of Rs.258.32 crores billing, Rs.228.01 crores revenue generated (for 1116.2 MU).
Status of other major works
Desilting Chamber No.1,2,3 and 4 - Almost complete.
Concreting of Dam - 99.9%
Head Raise Tunnel (27.394 Km.) Completed. Continuous supply of water maintained since August,2003.
Power House Complex Machine hall concreting completed.
Hydro Mechanical Works Erection of the power packs for all the 5 Radial Gates including laying of Hydraulic pipes and welding of pipes has been completed.
All the gates are being operated using the permanent power pack. All the Intake Gates and HRT Gates have been erected.
15.
16.
17.
18.
19.
21.
22.
23.
24.
100% of engineering works completed. Civil works and control room and switchyard in advance stage of completion. The project is now expected to be completed by
September,2004.
25.
26.
27.
Award for tower pakcage was placed in October,' 01 and for substations in March and November,' 02. Foundation and tower erection works are in progress. 518 nos.
foundation, 355 nos. tower erection and 180 ckm (out of 414 ckm) stringing have been completed by March, 2004. Progress has been affected due to adverse law &
order problem in the State of Bihar. An employee of the Sub-Station contractor was killed in July, 03 seriously affecting progress. The project is anticpated to be
completed by December, 04.
28.
29.
30.
31.
Ramagundam - III Transmission System (1100 ckm) Andhra Pradesh, Southern State
The project was accorded approval in August, 2001 at an estimated cost of Rs.390.12 crore with the commissioning schedule of August, 2005. The system consist of
following:i)
ii)
iii)
iv)
v)
All awards have since been placed. Survey completed, Enginering work under progress. 1547 nos. foundations, 1292 nos. tower erections (total 2438 locations), and
685 Ckm stringing completed upto March, 04. 400 Kv S/C khamam Nagarjunsagar Tr. Line commissioned in Feb.04. 400 Kv D/C Ramagundam-Hyderabad line
expected to be completed by June04 and balance 2 lines shall be completed by Aug05 i.e. as per schedule GOI approves.
32.
33.
400 KV S/C LILO Of Kolaghat Rengali Line at Baripada (New) Substation (38 CKM)
Investment approval for the project was accorded in October, 01 at an estimated cost of Rs.66.24 Cr. The project comprises of the following:LILO of 400 KV S/C Kolaghat-Rengali Transmission line at Baripada.
Construction of new 400/220/132 KV Baridapa Substation.
1x315 MVA, 400/220 KV ICT at Baripada
1x160 MVA, 220/132 KV ICT at Baripada
The transmission project is a regional scheme for improvement of power supply at Baripada and nearby areas in Orissa, West Bengal and Bihar & scheduled for
completion by April, 04.
Present Status: Substation packages were awarded in Sept.,' 02. Award for transmission line placed in August,' 03. Presently 45 foundations & 10 nos. tower
erection out of 49 completed upto March04. Tower supply has been affected due to inadequate of availability of steel by SAIL affecting line completion. While for
Baripada sub station, presently equipment supply and civil work under progress. Here also civil work have been affected due to inadequate supply of steel for
construction & disturbances by local labourers disrupting work. The project is now anticipated to be completed by October,2004. However, efforts being made to
complete the project earlier.
34.
35.
The project is scheduled to be commissioned by July, 2006. Awards for all Transmission lines packages of 400 KV D/C Kishenpur Wagoora Tr. Line placed. Survey
& Engineering work under progress. Erection activities under progress. 220 nos. foundations & 130 nos. tower erection out of 560 nos. completed upto March04. As
regards to Sub station package award placed. Engg. activities are under progress. Efforts are being made to complete the line earlier.
36.
(196 CKM)
(230 CKM)
(10 CKM)
(117 CKM)
Present Status
Presently Tala-Siliguri line I&II and 275 foundation, 121 nos. tower erection out of 768 locs. & 102 ckm stringing out of 553 ckm completed upto March,04, while for
sub station extension supply & equipment erection are under progress. The transmission system shall be completed matching with 1st unit Tala HEP, which is now
anticipated in June,2005.
37.
-Phase-I
-Phase-II
-Phase-I
-Phase-I
-Phase-II
-Phase-I
-Phase-II
Present Status: All awards for tower package since placed. Foundation & tower erection works are in progress. 135 nos of foundation, 60 nos. of tower erection out of
509 nos. completed till March, 2004. In Boisor S/S tower foundation and civil works in control room under progress. In Vapi S/S Tower / equipment foundation and
work in control room under progress.
38.
39.
40.
(596 CKM)
(406 CKM)
(404 CKM)
(146 CKM)
(469 CKM)
(111 CKM)
Present Status: Award of all tower packages have been placed in Dec.02/Jan.03. Also all Conductor & Insulator packages have been awarded Engg. & Survey
under progress. 920 nos. foundation, 463 nos. tower erection out of 3128 locations completd upto March,'04. Also 288 ckm stringing out of 2123 ckm completed so far.
Efforts are being made to match the transmission system with Generation projet for evacuation of power.
41.
i)
ii)
iii)
iv)
(65 Ckm)
(18 CKM)
Present Status :Award for sub station packages have been placed in March,04, while transmission line package & balance S/S packaging are under evaluation and the
awards are expected to be placed progressively by June,04.
42.
43.
44.
Series Compensation on Nagarjuna Sagar Cuddapah and Gooty Nelamangala 400 KV Lines
The project was approved in October, 2002 at an estimated cost of Rs. 57.93 crore with commissioning schedule of April, 2006.
The project provides for 40% fixed series compensation (FSC) on both the circuits of existing Nagarjun Sagar Cuddapah 400 KV Lines at Cuddapah end. The
capaciters will be rated at 67.25 MVAR per phase. Similarly 40% Fixed Series Compensation at Gooty end of Gooty -Nelamangala, two 400 KV single circuit line
have been proposed.
45.
46.
(67 Km.)
(18 Km.)
(18 Km.)
(39 Km.)
(90 Km.)
NIT for tower package held in Feb.04 and award expected by Aug04. For balance transmission lines and Sub station packages tendering activities under progress. The
project is scheduled to be completed by Nov.06 subject to award for tower packagings by August,2004.
47.
Vindhyachal-Korba, Chhatisgarh
The 400 KV Single Circuit Line along with sub station was approved in January,2004 at a cost of Rs.164.02 crores. It is expected to be completed by October,2006.
48.
49.
50.
SECTOR: POWER
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------NORTH EAST ELECTRIC POWER CORPORATION
------------------------------------1. TUIRIAL HE
MW
1998/07 2006/07 2006/07
0
0
0
368.72
368.72
0
102.43
48.00
56.66
159.09
PROJECT
2*30
0
0
0
AIZWAL
MIZORAM
NATIONAL HYDRO-ELECTRIC POWER CORPORATION
----------------------------------------2. DULHASTI HEP MW
1982/11 1990/11
3 X 130
1989/07 1994/07
DODA
2001/03
J & K
2004/11
168
175
44
20
183.45
3559.77
3559.77
4227.92
2205
19
3739.89
496.43
406.77
294.51
4034.40
3. DHAULIGANGA
H.E.P.-I
PITHORAGARH
UTTARANCHAL
MW
4 X 70
1991/04
2000/07
1998/10
2005/03
2005/03
77
86
0
0
601.98
1578.31
1578.31
162
0
943.55
328.43
338.92
338.00
1281.55
4. CHAMERA H.E.
PROJECT
CHAMBA
HIMACHAL PR.
MW
3 X 100
1999/05
2004/05
2004/05
0
0
0
0
1684.02
1684.02
0
0
1606.19
375.91
365.00
293.61
1899.80
5. LOKTAK D/S
HEP
MW
3 X 30
1999/12
2006/06
2008/12
30
38
30
38
578.62
578.62
0
0
20.50
22.35
3.98
3.80
24.30
MW
3 X 170
2000/02
2007/02
2007/02
0
0
0
0
2198.04
2198.04
0
0
698.32
275.00
263.72
277.12
975.44
MW
4 X 200
2002/09
2009/09
2009/09
0
0
24
0
0
3919.59
3919.59
0
0
401.50
318.01
275.00
280.81
682.31
100.00 (COMPLETED)
MANIPUR
6. TEESTA HE
PROJ.ST-V
SIKKIM
7. PARBATI HEP
ST.-II
HIMACHAL PR.
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: POWER
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------8. SUBANSIRI
MW
2003/09 2010/09 2010/09
0
0
0
6285.33
6285.33
0
51.20
270.00
209.79
260.99
LOWER HEP
8 X 250
0
0
0
253.00
ARUNACHAL PR.
9. SEWA H.E.P.
MW
3 X 40
2003/09
2007/09
2007/09
0
0
0
0
665.46
665.46
0
0
32.04
91.08
65.00
55.75
87.79
MW
4 X 33
2003/10
2007/03
2007/03
0
0
0
0
768.92
768.92
0
0
24.52
142.17
68.07
45.68
70.20
2004/03
60
100
60
100
2963.66
5209.10
76
76
4744.55
583.82
5328.37
2006/03
2006/03
0
0
0
0
1301.56
1301.56
0
0
81.66
85.93
167.59
1996/04
1998/12
2002/03
2004/07
99
118
28
18
1678.02
7666.31
8656.61
416
13
7169.93
963.05
819.39
788.90
7958.83
2006/02
2006/02
0
0
0
0
6648.83
7682.00
16
16
3378.76
869.93
881.25
557.35
3936.11
J & K
10. TESSTA LOW
DAM STAGE-II
WEST BENGAL
TEHRI HYDRO DEVELOPMENT CORPORATION LIMITED
------------------------------------------11. TEHRI DAM
MW
1994/03 1999/03
H.P.P.
4 X 250
TEHRI
UTTARANCHAL
12. KOTESHWAR
HEP
TEHRI
UTTARANCHAL
MW
4 X 100
2000/04
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: POWER
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------15. RIHAND STPP
MW
2001/05 2006/05 2006/05
0
0
0
3384.77
4044.53
19
702.36
771.81
690.33
1392.69
ST-II
2 X 500
0
0
19
762.66
UTTAR PRADESH
16. RAMAGUNDAM
STPP ST-III
MW
1 X 500
2001/08
2005/08
2005/08
0
0
0
0
1780.99
2072.45
16
16
554.50
613.09
505.85
435.04
989.54
MW
4 X 200
2002/10
2009/04
2009/04
0
0
0
0
4527.15
5340.07
18
18
330.14
303.57
333.88
196.66
526.80
MW
2X500
2003/02
2007/08
2007/08
0
0
0
0
4125.00
4201.50
2
2
0.40
250.00
458.68
394.26
394.66
2003/07
2007/05
2007/05
0
0
0
0
4002.28
4002.28
0
0
2.28
251.00
299.39
216.15
218.43
2004/12
69
115
24
23
421.00
702.97
721.62
71
3
603.37
59.94
72.35
75.71
679.08
2004/12
15
25
15
25
290.01
396.51
37
37
114.10
98.79
97.81
86.62
200.72
ANDHRA PRADESH
17. KOL DAM HEP
BILASPUR
HIMACHAL PR.
18. VINDHYACHAL
STPP-III
MADHYA PRADESH
19. KAHALGAON
STPP ST-II
MW
2 X 500
WEST BENGAL
POWER GRID CORPORATION OF INDIA LIMITED
--------------------------------------20. TEHRI TR.
KV
1994/03 1999/03
SYSTEM
800
2002/07 2002/12
TEHRI
CKM
DELHI/UA
3000
21. ULDCS FOR
EASTERN REG.
1998/09
2003/09
ER STATES
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: POWER
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------22. KAIGA NAREN- KV
1999/11 2002/11 2006/03
40
7
40
75.99
135.14
78
46.85
17.12
46.67
93.52
DRA TR. SYS. 400
111
111
78
13.11
CKM
KARNATAKA
212
23. MEMRAMUNDALI
-JEYPORE D/C
2000/10
2003/04
2004/01
9
30
9
30
166.51
166.51
0
0
113.95
23.99
21.69
21.46
135.41
100.00 (COMPLETED)
2000/10
2003/10
2004/09
11
31
11
31
195.97
207.15
6
6
107.86
63.06
72.67
60.22
168.08
2001/01
2005/01
2005/01
0
0
0
0
150.53
150.53
0
0
35.16
66.56
50.19
56.77
91.93
2001/02
2003/02
2005/08
30
125
30
125
262.18
226.71
-14
-14
38.57
82.20
56.21
31.98
70.55
ORISSA
24. MADURI-THIRU
VANANTHAPUR
TN/KERALA
25. DHAULINGANGA
TRANS.
UTARNCHAL/UP
26. ULDCS-WR
WR STATES
27. TR.SYSTEM
STRNGTHENING
BIHAR
BIHAR
KV
220
CKM
410
2001/08
2004/02
2004/06
4
13
4
13
162.88
162.88
0
0
50.08
51.43
46.61
36.46
86.54
28. SUBSTN.400/
220 KV KHNWA
KHANDWA
MAHARASHTRA
400 KV
120 CKM
2002/01
2005/01
2005/01
0
0
0
0
109.77
109.77
0
0
13.58
48.74
38.14
45.57
59.15
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: POWER
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------29. HVDC BACK TO MW
2002/01 2005/01 2005/03
2
0
2
769.25
769.25
0
54.79
182.10
158.68
213.47
BACK GAZUVAK 500
6
6
0
154.93
ORISSA/A.P.
30. 400 KV DC-II
KAH.-BIHAR
BIHARSHARIFF
BIHAR
2001/12
2004/06
2004/12
6
20
6
20
135.77
135.77
0
0
38.44
42.25
57.68
57.70
96.14
2001/08
2005/08
2005/08
0
0
0
0
390.12
390.12
0
0
99.26
162.15
126.08
133.17
232.43
CKM
44
2001/08
2003/08
2004/03
7
29
7
29
27.25
27.25
0
0
7.38
8.92
8.05
4.14
11.52
CKM
38
2001/10
2004/04
2004/06
2
7
2
7
66.24
66.24
0
0
5.32
20.21
29.04
16.26
21.58
CKM
130
2002/01
2004/07
2004/07
0
0
-3
0
0
45.90
40.79
-11
-11
1.74
21.03
13.43
10.37
12.11
CKM
415
KV
400
2002/07
2006/07
2006/07
0
0
0
0
567.05
567.05
0
0
221.64
77.42
76.84
80.51
302.15
S.R.STATES
32. RANAGADI-0
TR. 132 KV
ARUNACHAL PR.
33. BARIPADA
400 KV S/S
ORISSA
34. GANGTOK NEW
132 KV S/S
SIKKIM
35. DULHASTI COM
TR. SYSTEM
JK/PB/HP
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: POWER
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------36. TALA-SILIGRI CKM
2002/07 2004/10 2005/06
8
6
8
231.53
253.29
9
18.42
76.55
124.42
142.84
TR. LINE
553
30
30
9
124.29
KV
WEST BENGAL
400
37. TARAPUR 3&4
TR.SYSTEM
KV
316.3
CKM
W.R. STATES 330
2002/09
2005/09
2005/09
0
0
0
0
237.00
237.00
0
0
13.41
66.00
42.28
54.28
67.69
CKM
690
2003/03
2005/12
2005/12
0
0
0
0
248.60
248.60
0
0
73.00
70.18
100.09
100.09
CKM
420
K
400
2003/02
2006/05
2006/04
-1
-3
-1
-3
247.91
247.91
0
0
28.70
24.66
9.37
9.37
2002/12
2005/12
2005/12
0
0
0
0
1044.44
1044.44
0
0
63.21
289.60
249.52
297.05
360.26
2003/02
2006/08
2006/11
3
7
3
7
143.29
143.29
0
0
28.70
29.66
3.38
3.38
2003/06
2006/06
2006/06
0
0
0
0
1980.70
1980.70
0
0
12.00
21.29
12.56
12.56
38. RAIPUR-CHAND
RA PUR 400KV
CHHATI./MH
39. SYS.STRENGTH
-ING IN ER
ER
40. RIHAND-II
TRANSMISSION
NR STATES
CKM
2127
K
400
41. SYS.STRENGTH
ING IN N.R.
NR STATES
CKM
83
KV
400
42. TR.SYSTEM
WITH TALAHEP
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: POWER
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------43. 400 KV S/S
KV
2003/02 2005/08 2005/08
0
0
0
60.51
60.51
0
AT NARENDRA 400
0
0
0
KARNATAKA
44. N'SAGAR-CUD
& GOOTY-BNG
SERIES COMP.
AP/KARNATAKA
KV
400
2002/10
2006/04
2006/04
0
0
0
0
57.93
57.93
0
0
45. RAIPUR-ROUR
KELA D/C
SERIES COMP.
WR/ER STATES
KV
400
2003/01
2005/01
2005/01
0
0
0
0
96.90
98.10
1
1
60.59
31.09
36.09
36.09
2004/01
2006/07
2006/11
4
13
4
13
271.80
271.80
0
0
400 KV S/C
LINE
SUBSTATION
2004/01
2006/10
2006/10
0
0
0
0
164.02
164.02
0
0
2004/01
2006/07
2006/07
0
0
0
0
101.94
101.94
0
0
2004/01
2006/10
2006/12
2
6
2
6
247.78
247.78
0
0
400 KV D/C
LINE, SUBSTATION
UP/RAJASTHAN
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: POWER
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------50. TR. SYSTEM - 400 KV D/C 2004/01 2007/03 2007/03
0
0
0
208.75
208.75
0
TEESTA-V,HEP LINE, SUB0
0
0
STATION
SIKKIM
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
There are 3 projects on the monitoring system at the end of 3rd Quarter of 2003-2004.
12.2
12.3
The anticipated cost of 3 projects is Rs. 780.86 crores against the sanctioned cost of Rs.159.9 crores indicating a cost overrun of 388%. 2 projects are delayed for
periods ranging from 48-72 months and for one project anticipated DOC is not available.
12.4
The Implementation status of each of the project and details of cost and time schedules, original, revised and anticipated, are given in the succeeding section.
1.
North-Eastern Indra Gandhi Regional Institute of H& MS, Shillong, Meghalaya:The project was approved in May, 1986 with an objectives, inter alia to provide advance and specialised medical care to the people of the North Eastern Region at super
specialty level in selected fields, to provide post- graduate education and training in identified fields of super specialisation, etc.
Status : The present DOC of the project is March, 2005. Construction activities of Package-I, Phase-I, Consisting Dwelling Units, Guest house & Roads & Services etc.
has been under taken and the works are in various stages of Inplementation. For Phase-I, Package-II, the construction activities are yet to be undertaken. Since the
project has been delayed in terms of construction of buildings, the project management consultant HSCCIL has been requested to make up for the delay. HSCCIL has
been entrusted with total project management. The Director of the institute has also been appointed and certain medical services like OPD/emergency have started in
temparary sheds. Planning committee has been constituted with Secretary Health as Chairman to monitor the work progress as per the schedule. Consultant HSCC has
been requested to provide PERT chart. Project authorities should also give details of envisaged constraints which they intends to monitor closely. The project is lagging
behind the schedule in respect of identification of equipment for the entire complex/finalize equipment specifications for buildings in package II, inviting tenders for
supply of equipment for OPD, Emergency Services (Package II) and award of works and start construction of Phase I package IV and Phase II. The meeting of the
Planning committee for review of the project has since been held on 6-11-2002. A High Level Technical Committee has been constituted for identification of equipment
to the finalize equipment specifications. Technical committee meeting was held on 27-02-2003 for identification and finalising the specifications of the equipment for
the main project. Draft agreement to be signed between NEIGRIHMS & HSCCIL has been sent to Ministry and was placed in the meeting of SFC held on 17.09.2003.
On the overall Phase-I construction work is in advance stage and the cumulative progress for the Phase-I is 99%. The OPD in the new building is expected to start in
July, 2004.
External Problems
i)
ii)
iii)
2.
National Institute of Biologicals (NIB) Noida, Utter Pradesh:Background : The project was approved in March 1992 at an estimated cost of RS 69.74 crores. It is being set up as an apex scientific institution in the country for
promoting high standard and good quality of biological products i.e. vaccines, anti-sera, anti-toxins, blood products, recombinant DNA products, reagents, immunodiagnostic kits, etc. that are indigenously manufactured for consumption within the country or for exports and those imported into the country.
Status: The revised cost estimate of Rs. 269.24 crores has been approved in February,2001. The present DOC of the project is March 2005. The phase I of the project
(14 labs) have been made operational. The phase II consisting of Biological testing lab for animals and auditorium is in progress. Auditorium inside campus & staff
quarter (outside compus) have been deferred by the EFC in meeting held on 25-9-2000 to a subsequent phase. The work order for construction of laboratory & Animal
House and the main science building of the institute, costing Rs.114.11 crore was placed to M/s L & T. The construction work commenced in March,2003. The period
of completion is 25 months from the date of commencement i.e. April, 2005. Maintenance of engineering building, gate house, essential staff quarters costing Rs. 1.89
crore would be completed by April 2004. The hold on imposed by the Quarterly Progress Review Committee on construction of Library Building has been removed and
approval of competent authority to start the work has been sought. Almost all critical milestones have been achieved by the end of March, 2004. The NIB has been
notified as Cntral Drug Laboratory for (a) Immunodiagnostic kits (b) Blood Grauging Reagents & (c) Oral Polio Vaccine, under 3A of the drugs & consmeties rules
1945 vide notification No.158 of GOI extra ordinary part II, Section 3, Subsection (1) dated 4/4/2004. The overall progress of the project is quite satisfactory
3.
Regional Institute of Medical Sciences(RIMS), Imphal, Manipur:The project RIMS was originally approved in 6/1986 at an estimated cost of RS 19.02 crores. Now the anticipated cost is Rs 89.02 crores . The institute has an annual
intake capacity of 85 students at the under graduate level & 40 student at the post graduate level.
Status : The latest status is not available. Ministry of Health and Family welfare has been requested to furnish detailed report in the prescribed format. The present DOC
of the project is not available.
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------HEALTH & FAMILY WELFARE
----------------------1. NEIG INSTIT- BEDS
1986/05 1999/03 2005/03
72
0
0
71.18
422.60
494
27.11
65.00
97.08
124.19
99.00
UTE OF H&FW
580
2001/02 2005/03
47
0
422.60
0
SHILLONG
MEGHALAYA
2. BIOLOGICALS
N.INSTITUTE
NOIDA
UTTAR PRADESH
3. INSTITUTE OF
MED.SCIENCES
IMPHAL
MANIPUR
BEDS
881
1992/03
2001/02
1998/09
2005/03
2005/03
78
100
0
0
69.74
269.24
269.24
286
0
104.91
25.10
-
24.00
128.91
1986/06
1990/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
19.02
89.02
368
368
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
XIII. RAILWAYS
Project Review
13.1
There were 200 projects in Railways on the Monitoring System at the end of January-March,2004 as against 173 projects last quarter. List of Railway projects added
and dropped is given in Appendix IV.
Status of Projects as on 31.03.2004
-------------------------------------------------------WITHIN
WITHIN
TIME
COST
WITH
BUT
BUT
TIME
WITH
WITH
&
TOTAL
WITHIN
COST
TIME
COST
CATNO. OF
TIME &
OVEROVEROVEREGORY
PROJECTS
COST
RUNS
RUNS
RUNS
-------------------------------------------------------1
2
3
4
5
6
-------------------------------------------------------MEGA
6
0
4
0
2
MAJOR
101
15
59
7
20
MEDIUM
93
42
39
4
8
-------------------------------------------------------TOTAL
200
57
102
11
30
--------------------------------------------------------
13.2
The anticipated cost of 200 projects is Rs.47,666.79 crores against the original sanctioned cost of Rs.32,385.61 crore, indicating a cost overrun (which is mainly on
account of material modification of original projects) of 47%. Many of the projects in Railways, during the course of execution show cost increase, mainly on account
of addition of related projects along an earlier sanctioned route, called material modification in the Railways vocabulary. Cost overrun is more an indication of firming
up of cost, after final location survey and detailed project report is prepared, as against the sanction of a project on the basis of rough thumb rules for costing major
works. 42 projects are delayed by a period ranging from 3 to 168 months. (Table 6). 132 projects with the original approved cost of Rs.22,091.6 crores, have shown
a cost overrun of 71%, with an anticipated cost of Rs.37,683.5 crores. Agency-wise analysis of projects in various sections in Railways is given below to give the
magnitude of the latest approved cost of projects and the expenditure incurred therein, since the start of work. Actually this cumulative expenditure given below has
been incurred over a period, for the projects taken on the monitor.
Original
Cost
(Rs.Crore)
Number
of
Projects
Latest
Approved
Cost
(Rs.Crore)
Now
Outlay for Cumulative
Throw
Anticipated 2003-2004 Expenditure forward
Cost
(Rs. Crore)
since
(Rs.Crore)
(Rs.Crore)
inception
(Rs. Crore)
1141.45
1659.41
1954.27
60.00
146.64
1807.63
520.00
1098.00
426.12
0.00
275.39
150.73
GAUGE CONVERSION
44
8329.39
11546.83
13194.35
807.15
4078.88
9115.47
LINE DOUBLING
45
3184.93
3475.07
3916.35
357.92
1860.06
2056.29
10
3602.05
3733.50
3996.79
227.57
1732.15
2264.64
NEW LINE
56
13068.66
15526.92
21015.29
1033.94
RAILWAY ELECTRIFICATION
1218.02
1283.16
1403.13
46.49
908.20
494.93
125.00
125.00
125.00
0.00
17.57
107.43
194.32
218.98
260.56
6.16
103.24
157.32
TRAFFIC FACILITIES
211.05
278.94
287.27
18.38
107.07
180.20
16
790.74
939.85
1087.66
129.28
692.31
395.35
200
32385.61
39885.66
47666.79
2686.89
13.3
4819.95 16195.34
14741.46 32925.33
The most serious problem in the Railway Sector is sanction of large number of projects without completing essential pre-project activities (like survey, detailed cost
estimates, and financial tie up for seeing the projects through, to the completion stage) and without due regard to the availability of resources, and even without any
mention of original DOC. For many projects on the monitor Date of commissioning has not been fixed ( or even indicated).There are many projects which are included in
the Pink Book (Railway Budget) without proper appraisal. After the Budget is passed by the Parliament, they are posed to the Expanded Board of Railways (EBR), even
though many of them are not viable and many have large negative rate of return. This has resulted in a large number of projects remaining non-starters, resulting in
slow progress, as well as thin dispersal of limited resources over a large number of projects. New projects are sanctioned, while old projects, which can start earning
revenue if adequately financed, remain starved of funds. The other factors affecting implementation include delays in land acquisition, award of contracts, slow
mobilization of resources by civil contractors, and delay in sanction of detailed estimates. None of the Railway projects are monitored by the MOS&PI through a
predetermined set of milestones. Clear directive regarding the commissioning date has been given for two new line projects in the State of J&K, namely Jammu-Udhampur
Railway Line & Udhampur - Srinagar - Baramullah Line, as they have been given substantial outlays in the last three years.
Projects costing Rs.500 crores & above
There are 22 projects costing Rs.500 crores and more in this sector. 8 of these projects are behind original commissioning schedule. There are 10 projects without original
date of commissioning (DOC) and 8 with netiher original nor latest anticipated date of commissioning. Cumulative expenditure in 7 of the projects is less than 10% of the
anticipated cost and in one of these projects it is less than Rs.5 crore.
Sub-Sector
No. of Projects
Doubling
GC
MTP
NL
B&S
Total
1
6
3
11
1
22
Category
(B)
(C)
(A)
1
2
2
3
8
3
6
1
10
2
6
1
9
1
1
1
3
2
5
7
13.4
During the quarter (October-December,2003), 2 projects reported additional delay ranging between 6 to 48 months. Consolidated details are given in Table-10. 1
Project has reported additional cost-overrun of Rs.91.66 crores during this quarter as detailed in Table-11.
Problems in Implementation
13.5
At the current rate of outlay being provided for projects by the Railways, it will take many years to complete the existing projects, which is highly unrealistic. There is an
urgent need to suitably prioritise between the various projects and step up the allocation of funds adequately on these priority projects. There is a need to observe
moratorium on sanctioning of new investments, till on-going projects get completed. This will make available more resources, which are spread thinly over a large
number of projects.
For Freight Operation Information System (FOIS) Project (being implemented by the Centre for Railway Information System - CRIS), an immediate decision needs to be
taken regarding provision of adequate funding.
Project Status
13.7
The implementation status of each of the projects and statistical details of cost and time schedules, original, revised and anticipated, are given in the succeeding paras.
2.
Rail -cum -Road Bridge across River Brahmaputra at Bogibeel and Link Lines (Assam) (NEFR) :
@@@@@
Original cost was Rs. 1000 crore based on rough estimate (April, 1996). Rs.1500 crore was approved in September,1997 as Revised cost. Now anticipated cost is Rs.1767
crores. Cost is to be shared between Railways and Ministry of Road Transport. Funding pattern yet to be finalized.
Railway Board has now advised to takeup this project as a Single Line Bridge with 2 lanes for Road Traffic. RITES have been awarded the contract for finalizing detailed
design and drawings. Collection of boulders, construction of service roads to Bridge site, office & staff quarters, major & minor bridges and earth work in Railway
approach embankment are in progress. Physical progress achieved up to the quarter is is 7.0%.
3.
4.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Rs.3890.65 lakhs
Rs. 169.93 lakhs
Rs. 33.82 lakhs
Rs. 91.21 lakhs
Rs.4185.61 lakhs
Year
1997-1998
1998-1999
1999-2000
2000-2001
2001-2002
2002-2003
Total upto March, 2003
2003-2004
RBG
Budget Grant
150 (RBG)
6800
114613
104052
106210
76741 (RBG)
390852
10000 (RBG)
Grand Total
Or Say
Rail Bridge
(Figures in '000)
Expenditure
98
4730
104033
100933
106208
74850
8200 (Upto June'03)
399052
Rs.39.91 Crores
Status
This project was sanctioned in April,1996 at a cost of Rs.23.52 crore. The revised Cost of Rs.41.86 crore was approved in January,1998 by the Railway Board. Original
date of commissioning of the project was March,1999.
Earth work, work relating to minor bridges and ballasting completed between Vijayawada and Krishna Canal. Work on all major bridges completed. Phase-II : Bridge
No.3(12x89.9 m. steel girders): Engineering - Total span = 12. No. of spans erected and launched = 12, painting works is in progress. Fabrication of channel sleepers
completed. Fixing of channel sleepers completed for 9 spans. Track linking work is in progress on both sides of the bridge.
S&T - About 80% outdoor work has been completed.
achieved is 97%.
16.
Overhead Electrification work completed. Section is being opened for passenger traffic. Physical progress
Agency
Contract
Contract
Contract
Contract
Contract
Contract
Ant. Completion
86.7% completed. Balance work in progress.
75% completed. Balance work in progress.
52% completed. 11 in progress.
82% completed. Balance work in progress.
42% completed. Balance work in progress.
56% completed. Work in progress.
The overall physical progress (In this Section, Bellary - Tornagalluu -32 Km. length) is 50%.
17.
18.
19.
20.
21.
22.
23.
24.
Karpurigram-Siho (ER):
This project was sanctioned at an estimated cost is Rs. 30.98 crore in July, 2000. Earth work in 3 block sections covering a route length of 16 Kms. (out of the total line
doubling of 26 Kms.) completed. Physical progress as per the available report is 4%.
25.
26.
New Delhi Tilak Bridge (5th and 6th line), Delhi (NR) :
Original cost of this project when sanctioned in June, 2000 was Rs. 36 crore but subsequently revised to revised to Rs. 34 crore in Sep., 2000. This revised cost was to
take up only 6th Line. The cost for civil, electrical and S&T works is estimated at is Rs.21.74 crores, 3.85 crores, and 8.35 crores respectively.
Board approved exchange of land with Masjid Authority in January,2002 and the Division has been asked to take appropriate action. Civil works for Earth Work,
construction of retention wall, quarters, etc. are in progress. Contract for widening of Tilak Bridge Road Under Bridge (TKJ-RUB) has been awarded on 31.3.2003.
Overall progress is 30%.
27.
civil,
Out of 3 major bridges, work in respect of two major bridges completed Out of 93 minor bridges, work completed in 74 and work in respect of remaining bridges is in
progress
Track linking, supply of ballast and signalling work has been awarded to M/s. RITES. About 3.20 lakh cu.m. of Earth work out of 4.42 lakh cu.m.
completed. Physical progress is achieved is estimated at 49%.
28.
Shoranur-Kuttipuram-Calicut including Material Modification for doubling between Shoranur Mangalore Section (Kerala) :
The above project (line doubling of 86 Kms. route length) was sanctioned in March, 2001 at an estimated cost of Rs. 178.76 crore but subsequently revised to Rs.
177.34 crore. Now the anticipated cost is Rs. 177.34 crore.
In the current year 30 kms of doubling was targeted. Accordingly the new second (up) main line between Tanur Calicut (33 kms) was programmed for completion. Out
of which 4 kms of track has been doubled in the Ferok Villikunnu section and has been commissioned for passenger traffic on 23.12.2003. Track linking work of
Calicut Tanur is now fully completed and CRS inspection is being processed. Works are in progress on the remaining portion between Shoranur and Tanur.
Cumulative progress is 25% (for TAN CLT Section).
29.
30.
31.
Scope of Work
Bank 117500 M3
Cutting 25000 M3
Major bridges 5 Nos.
Minor bridges 127 Nos.
Track works & Ballast
Work in progress
Work in progress
Work in progress
Work in progress
Work will be taken up under Rail Vikas Yojana
33.
34.
35.
36.
Earthwork, work relating to Bridges work and collection of ballast are in progress for 12 km length from Korukkupettai to Ennore. Progress of Earthwork is 57%, Bridge
work is 51%, Collection of Ballast is 23%. Earthwork and work relating to bridges are in progress for 3 kms from Attipattu Pudu Nagar to Attipattu. Construction of
foundation and substructure I\completed for Ennore Creek Bridge and Superstructure is also completed in respect of 6 spans out of 17 spans.
37.
38.
39.
40.
41.
Mavelikarai Kayankulam
This project was sanctioned in April, 2003 at an estimated cost of Rs. 21.84 crore Net work included in the Pink Bood for the year 2003-04. Foundation stone laid for this
doubling project on 04.10.2003 at Kayankulam. Approached State Government for acquisition of land.
42.
Cheppad Kayankulam
This project was sanctioned in April, 2003 at an estimated cost of Rs. 21.48 crore The final location survey for the work almost been completed. Tentative plans has been
prepared and are under verification Requisition for land acquisition has been given to the State Government. Detailed estimate is in progress.
43.
44.
45.
46.
47.
48.
49.
50.
Earth work and minor bridges works are in progress in all 10 reaches. Overall physical progress achieved upto the current quarter progress is 30%.
51.
52.
Rajkot-Veraval - Somnath Section Material Modification to Wansjaliya to Jatalsar, Gujarat (W. Rly.) :
This project was sanctioned in April, 1992. Detailed estimate for Rs. 153.36 crore sent to Railway Board on 14.11.97 for sanction. The estimate was further revised to Rs.
193.61 (Rajkot-Veraval only) in November, 2000. The latest revised cost of this section (Rajkot - Veraval) is Rs.232.75 crores with a further revision to Somnath costing
Rs.247.27 crores. In addition to this, Jetalsar to Wansjaliya Gauge Conversion (90.61 Km.) costing Rs.112.53 crores has also been included. This brings the total cost of
the project to Rs.359.8 crores. In effect, a number of projects have been added to the original project (Rajkot Veraval), whose cost was Rs.193.61 crores. Now
anticipated project cost is Rs. 363.80 crore. There are several contracts which have been awarded keeping in view the availability of funds. The balance contracts are to be
awarded after receipt of budget grants each year and depending on through forward liability. The project is not being executed through package or turn key system. The
details of progress of different sections is given below:
Rajkot-Veraval Gauge Conversion (185 Kms):
Rajkot-Junagarh (103 Km) : Work completed and opened to goods traffic on 30.3.03 and Section authorised for running of passenger traffic.
Junagarh-Veraval gauge conversion (82 km) : This section has been opened for goods traffic on 31.03.04.
Veraval-Somnath (New Line ) 4+1 = 5 Km.
About 90% (13.94 Ha out of 15.30 Ha ) land has been acquired. For the balance, negotiations are going on. Tender for earthwork awarded and work commenced.
Tender for construction of bridges also awarded.
54.
55.
56.
57.
58.
59.
Trichy-Nagore-Karaikal Gauge Conversion (Tanjavur - Nagore - Karaikkal and Nagapattinam - Vailankanni) Tamil Nadu (S.Rly):
This project (guage conversion of 200 Kms.) was sanctioned in November, 1995 at an estimated cost of Rs.140 crores. Revised cost is Rs.170 crores and this was
included for implementation during the year 1995-96. Now the anticipated cost is Rs. 213.36 crore.
Phase-I work of Tiruchchirappalli Tanjavur New Parallel BG (50 Kms) line was completed and opened for passenger traffic on 01.01.98 and handed over to open line.
Gauge conversion work between Tanjavur Tiruvavur is being taken up as Phase-II. Super structure of bridge work is in progress between Nagapattinam and Vailakanni.
Earthwork and minor bridges are in progress. All tenders for earthwork and minor bridges awarded. Station building at Vailankanni completed upto roof level. Tenders
for four major bridge awarded (between Tanjavur Tiruvarur) and piling work has just commenced.
Land acquisition process is completed for Nagapattinam and Vailankanni, new line work and land for 4 villages has been taken over. Tender for major bridges (8 out of 12
Nos). between Thanjavur Nagore has been opened and awarded (in respect of 4). Tender for major bridges between Nagore Karaikal also awarded. Govt. land
between Nagore Karaikkal has been taken over.
Physical progress achieved upto the current quarter is 58%.
60.
61.
62.
63.
64.
65.
66.
Kanpur - Farrukhhabad
Farrukhabad - Kasganj
Kasganj Mathura
Kasganj - Bareilly - Lalkuan
Earth work, work relating bridges, S & T, P.Way and material collection for Phase-I is in progress.
Phase-I and 25% for the entire project.
67.
Track linking work completed for 29 km out of 38 km. Buildings, platforms and FOB works have been completed.. Other works are in progress. Out of 3 major bridges,
Br.No.24 has been completed. Substructure has been completed in the remaining two bridges. Substructure is in progress in Bridge No.113 and Bridge No.57
Superstructure work is in progress for Br.57 (Line block for GC has been taken up from 10.12.2002). CRS/SBS has cleared for Goods Traffic between Villupuram
Chinnababu Samudram. Accordingly, the first Goods Train was run on 25.9.03. Physical progress is 65%.
68.
69.
70.
71.
72.
73.
Secunderabad-Mudkhed-Jankampet-Bodhan, AP (SCR) :
This project (guage conversion of 297 Kms.) was sanctioned in August,1988 at a cost of Rs.98.42 crores and the original date of commissioning is March,2004. Latest
revised cost is Rs.278.99 crores (Date of approval of RCE not indicated).
This project consists of 4 Phases. Phase I Mudkhed-Dharmabad (50 kms) was commissioned for goods traffic on 31.3.2002 and passenger traffic on 1.6.2002. Phase II
Dharmabad-Nizamabad (40 km.) and Janakampet - Bodhan (20 Km.- branch line) was opened for goods traffic on 27.8.2002 and for passenger traffic on 3.10.2002.
Bolurum Manoharabad section (28 kms) completed during 2003-04 and opened for traffic on 14--02-2004. Details are as follows:
Ph.III, IV & V. Nizamabad to Malkajgiri (156.70 KM)
Earthwork 575000 Cum.
Major bridges 10 Nos.
Minor bridges 268 Nos.
Ballast 312000 Cum.
S&T rooms
Platform 22 Nos.
Completed
Completed
Completed
Work in progress
in progress ( 90%)
75.
estimates sanctioned for Rs.88.70 crores. The physical works is proposed to be taken up at a later date to match with completion of gauge conversion work in LumdingSilchar section.
Salient Features:
Length
States Served
Year of Sanction
Cost
Expenditure upto 31.3.2003
Outlay during 2003-2004
Present progress
:
:
:
:
:
:
:
84 Kms.
Assam & Mizoram
1997-98
Rs.200.00 Crores
Nil
Rs.1.00 Crore
Nil
77.
78.
Transportation of 164000 sleepers out of 246000 Nos. (for which RO issued) done.
Cumulative physical progress achieved till quarter is 20%
79.
Project is in initial stages. Tender for works relating to Reach I & III in Vellore Katpadi has been awarded. Cumulative physical progress is 2%.
80.
81.
:
:
:
:
:
:
:
200 Kms.
Bihar & West Bengal
1997-98
Rs.402.98 Crores
Rs.33.84 Crores
Rs.21.00 Crore
16%
Earthwork and work relating to major and minor bridges is in progress in the entire section. Physical progress achieved upto the current quarter is 19 %.
82.
83.
Fatuha Islampur including Daniawan Bihar Sharif Barbigha (Restoration of dismantled line), Bihar (ECR) :
Original cost of this project when sanctioned in July, 1998 was Rs.49.50 crore for taking up guage conversion in a route length of 59.5 Kms. Subsequently the cost was
revised to Rs.78.04 crore. Original Date of Commissioing was fixed as December, 2002 but no revised date of commissioning has been communicated by the project
authorities
84.
Phase II - Hingoli - Akola (128.50 Km.) - Tenders schedules for earthwork, minor bridges and major bridges (80 km) finalized. Work is in progress on 40 minor bridges
and 4 major bridges.
Cumulative physical achieved upto the current quarter is progress is 16%.
85.
86.
87.
88.
Tiruchchirappalli Nagore Karaikkal Gauge Conversion (Tanjavur Nagore Karaikkal and Nagapattinum Vailankanni)
The above project was included during the year 1995 1996 at a cost of Rs.100 crores (Now the anticipated cost is fixed at Rs. 213.35 crore). The estimate for this work
was sanctioned during 1996. Material modification estimate for construction of New line from Nagore Karaikkal as a part of GC project was sanctioned by Railway
Board for Rs.33.78 crores (Cost of the TJ-NCR-KIK project is Rs.170.69 crores) vide Boards letter No.92/W2/GC/S/25 dated 20.11.2002 and under this sanction Phase I
work of Tiruchchirappalli Tanjavur New Parallel BG (50 kms) line was completed and opened for passenger traffic on 1.1.98 and handed over to open line. Gauge
conversion work between Tanjavur Tiruvavur is taken up as Phase I. Superstructure of bridge work is in progress between Nagapattinam and Vailankanni. Earthwork
and minor bridges are in progress. One tender for earthwork and minor bridges in Tanjavur Tiruvavur has already been awarded and works are progressing. 3 more
tenders for minor bridges for balance portion are opened. Station building at Vailankanni is coming up.
Land acquisition process has been completed for Nagapattinam and Vailankanni. New Line work and land acquisition in respect of 4 villages has been completed.
Tender for major bridges 8 out of 12 Nos. between Thanjavur Nagore has been opened. Tender for major bridges between Nagore Karaikal also opened. Government
land between Nagaore Karaikkal has been taken over. Physical progress achieved upto the current quarter is 58%.
89.
90.
91.
92.
93.
95.
96.
Kurla-Bhandup, 5th & 6th Line ( Phase-I of Kurla - Thane), Maharashtra, Mumbai (CR) :
The addition of new lines (10 Kms.) to existing subarban lines was approved in April,1995 at a cost of Rs.49.84 crores. Now anticipated cost is Rs.120.20 crores.
Earth work, work of formation , supply of ballast, track linking and construction of bridges is in progress wherever space is available. Hutments encroached in the project
site are partially removed. Cumulative physical progress achieved upto the current quarter is 74%.
97.
Thirumalai-Velacheri, MRTS (Mass Rapid Transit System) Extension (Phase-II), Chennai, Tamil Nadu (SR) :
The first phase of the project from Chennai Beach Thirumailai was commissioned in October,1997 at a cost of Rs.264.93 crores. The 2nd phase is under implementation
and this project is one of the 54 Railway projects taken up for special monitoring by the Committee of Secretaries, of which 14 has already been commissioned (balance 39
projects are in various stages of implementation, some of which are also suffering funds constraint).
Phase-I
Length
Salient features of Phase-II ( Thirumailai Velacheri Mass Rapid Transit System, Chennai under implementation)
This project involves extension of existing Chennai Beach - LUZ MRTS Ph. I double electrified elevated track (10.30 km). Detailed estimate of Rs. 691.04 crore was
sanctioned in April,1996 with the original date of commissioning as March,2002. The cost will be shared in the ratio of 33:67 by Railway and Tamil Nadu Govt.
Length :11.166 kms (Double Line) 7.848 kms.Elevated 3.318 kms. Surface
Overall Financial Progress is 96.9%.
Stations:
Mandaiveli
Greenways Road
Kotturpuram
Kasturibai Nagar
Indira Nagar
Tiruvanmiyur
Taramani
Perungudi
Velacheri
Estimated Cost
(Elevated)
9.699
11.020
11.892
12.824
13,796
14,655
16,570
17,713
19,340
Rs.689.01 Crore (To be shared in the ratio of 33:67 by the Railway and Govt. of Tamil Nadu, that is Rs.227.37 Cr. By Railways and Rs.461.64
Cr. by TN State Govt.)
Foundation, sub-structure and super-structure works and blastless tracks for the entire elevated section has been completed. Due to continued settlement of embarkment
near Taramani station, execution of earth work and work relating to track linking in surface portion is held up. Commissioning of completed section between Thirumalai
and Tiruvanmiyur for single line operation was proposed and CRS Insepction also carried out on 28th & 29th September, 2003.
All stations are incomplete, although the structures including platforms are in the advanced stages of implementation, along with completion of ground improvement
works. However, for the stations to be operational along the route, lighting and escalators have to be provided which will take an addition 8 to 12 months to be completed.
The track linking is yet to start. Physical progress is achieved upto the current quarter 72.2%
98.
Kurla - Thane 5th & 6th Line Phase-II of Bhandup - Thane, Mumbai Maharashtra (CR) :
This project was initially approved at a cost of Rs.46.69 crore in April,1997. Route Km. involved is 7 Kms
approval not given). Now anticipated cost is Rs.83.57 crores.
.
Earth work, work of formation , supply of ballast, track linking and construction of bridges is in progress wherever space is available. Hutments encroached in the project
site are partially removed. Cumulative physical progress achieved upto the current quarter is 65%.
99.
100.
Barasat-Hasnabad Electrification :
This project with an estimated cost of Rs. 27 crore was sanctioned in April, 1998 (subsequently revised to Rs.37.70 crores in the month March, 2002). Physical progress
achieved is 90 %.
101.
102.
104.
105.
Work is in progress from Una Himachal to Churaru Takarla. Detailed estimate for this section is Rs.47.30 Crore. The work completed in Nangaldam-Una section (17
kms) and opened for traffic in the year 1991. In the next phase, Una Himachal-Churaru Takarala (16 km) work has been completed and locomotive trial run carried out.
DE for next block section i.e. Churaru Takarala Amb Andura sanctioned (cost Rs.48.34 crore).
Acquisition of land is in progress in this section. Physical progress upto the current quarter is 41%.
106.
107.
108.
109.
110.
111.
112.
113.
114.
115.
116.
117.
118.
119.
In reference to Railway Boards Letter No.2003/W1/WR/Indore(SEZ) dated 25.6.03, present traffic potential has been taken into consideration from Special Economic
Zone and IRR of Godhra-Dahod-Indore 3rd line has been worked out as 0.74% and sent to Board on 22.8.03. As advised by the Board, part estimates foritems like
preliminary expenses, land acquisition, earthwork and bridges are being worked.
Progress achieved upto the quarter is 15%.
120.
121.
122.
123.
124.
125.
126.
127.
128.
129.
130.
131.
132.
133.
134.
135.
136.
137.
138.
139.
Work in Chandigarh Morinda (45 km.) has been taken up in Phase I. Entire land measuring 457 acres acquired. 27.45 lac cum out of 30.77 lac cum earthwork
completed. 96 out of 100 minor bridges completed. Out of a total 9 major bridges work in respect of 2 bridges completed, in respect of remaining 7 work is in progress.
8 out of 17 ROB/RUB completed and work in respect of remaining 9 is in progress. No date of commissioning has been fixed. Physical progress achieved upto the
current quarter is 32%.
140.
Agra Etawah , New Line via Fatehabad, Uttar Pradesh (North Central Rly.)
Approved in April, 1999 at a cost of Rs. 108 crore for laying new line measuring 110.50 kms. Subsequently, the cost estimate has been revised to Rs. 214.09 crore.
Detailed estimate sanctioned by Railway Board for entire length. Land acquisition is in progress. Tenders for 6 minor bridges and earthwork awarded. Physical progress
is 4%.
141.
142.
143.
144.
145.
146.
147.
148.
New Line from New Maynaguri to Jogighopa via Chandrabandha, West Bengal & Assam (N.E.F. Railway)
New Railway Line Project of 261.62 Kms. was approved in February,2000 for a total cost of Rs.733.0 crores. Date of commissioning of the project is not fixed.
Final location survey for a part (59 Kms) has been completed and part estimate sanctioned. Joint Survey with State Govt. authorities for acquisition of land has been
carried out for 187 Kms. Earthhwork is in progress in Gauge Conversion portion in Maynaguri Road Changrabandha Section.
Physical progress achieved upto the current quarter is 2%.
149.
Gandhinagar Kolol:
This new line project between Gandhinagar and Kalol (Route length 20.49 km) was sanctioned in April, 2000, at an estimated cost of 49.96 crore. Work of soil data
collection for major & minor bridges completed. Tender for Earthwork, extension of major & minor bridges on G.C. portion awarded.
In New line portion tender for Earthwork & bridges awarded on 08.09.03 & on 29.09.03 respectively and work is in progress. Tender for transportation of 40,000
sleepers from Digsar sleeper factory aarded on 05.01.2004. Tender for supply of ballast for new line opened on 31.10.2003 and is under finalisation. The process of land
acquisition between Moti Adraj and Gandhinagar, Section VI is in progress. So far 35.45 hectare out of 55 hectare of land handed over by State for new line.
Out of 3.57 lakh cum, 85000 cum earthwork (50,000 cum in New line portion) have been completed. The work of bridges in the GC portion (Moti Adraj Kalol) has
been started. Sub-structure of 1 major bridge out of 1 & 3 minor bridge out of 21 completed. Earthwork (2500 m3 received) is in progress.
150.
151.
152.
153.
154.
155.
156.
157.
158.
159.
160.
Software Development
78. Preparation and Submission of Final User Manual
Field Deployment
53. Channels for SCR Sites
Channels for CR Sites
Channels for WR Sites
Channels for SER Sites
Channels for ER Sites
107. Deployment on SR Sites
108. Deployment for SCR Sites
22.8.2002
20.9.2002
20.10.2002
4.12.2002
18.1.2003
20.11.2002
4.1.2003
Field Deployment of 52 Channels for Southern Railway Sites has been completed. March,2003 was the earlier date for productionised version over Indian Railways of
RMS and TMS (Rake Management System and Train Management System) for software development and this has been delayed up to November,2004. M/s. CMS has to
get a draft manual ready. CRIS the agency for implementing FOIS has requested for additional sanction from Railway Board to keep the programme going.
Railway Electrification (RE):
161.
Ambala-Moradabad :
The project was approved at an estimated a cost of Rs.152.21 crores in March,1993 with original date of commissioning as March,1998. Latest approved cost is
Rs.157.75 crores. Ambala-Saharanpur-Khanalampura Section (79 Running Kms.) has been energized. Section from Khannalampura (excluding) to Roorkee
(excluding ) has been energized on 30.03.04. Now anticipated date of commissioning is March, 2005 for complete section upto Moradabad. Physical progress achieved
upto the current quarter is 44 %.
162.
30.6.2003
31.5.2003
31.3.2004
Completed
90% complete
63% complete
30% complete
The project is now expected to be completed by March, 2004. Physical progress achieved is 63%.
163.
164.
165.
166.
Gr.118
167.
1.
30.09.2004
2.
31.12.2004
3.
30.10.2004
4.
31.01.2005
169.
Mumbai CST (Chhatrapati Shivaji Terminus-Formerly Victoria Terminus) Station Remodelling (Phase-I), Maharashtra (C.RLys) :
Latest approved cost of execution of this project is Rs. 80.64 crore. Originally, when the project was sanctioned in April, 1995, the estimnated cost was Rs. 19.72 crore
and was to be completed by December, 1998 (Latest date of completion is not fixed)
Work on ROBs and extension of Platforms is in progress. Handing over of 5555 sq.mt. of land by the State Government and removal of 52 hutments by Municipal
Corporation is yet to be commenced. Physical progress achieved upto the quarter is 23 %.
170.
171.
172.
173.
175.
176.
CLW (Chittaranjan Locomotive Works)-Additional Facilities for Manufacture of High Horse Power 3-Phase ABB (Asia Brown Boveri) Locomotives, West
Bengal:
This scheme, which was originally proposed mainly for augmentation of production at CLW, has been modified for absorption of state-of-art 3-phase electric locomotives
technology. The detailed estimate amounting to Rs.29.82 crores (now anticipated cost is Rs.39.91 crore) has been sanctioned in January,1996. The work is likely to be
completed by 31.3.2005.
177.
178.
179.
180.
181.
182.
183.
184.
185.
186.
Perambur (Tamil Nadu) - Additional facilities for reduction in POH Cycle time :
Original cost of implementing the project was is Rs. 18.76 crore (1997-98) but subsequently revised to Rs. 20.57 crore and sanctioned in August, 1999. The objective of
the work is to reduce POH cycle time for BG/ AC and non- AC coaches. Work is in progress.
187.
Perambur (Tamil Nadu) Integral Coach Factory (ICF) Creation of proper painting facilities :
The work was sanctioned at a cost of Rs. 26.55 crore in 2001-02. The objective of the work is to minimize corrosion by improving painting quality and to avoid
environment pollution. The detailed estimate of the work costing 26.05 crore was sanctioned on 29.11.2001. Original date of completion of this project is 31st December,
2003 (revised date of completion not fixed). The work is in progress.
188.
189.
191.
192.
193.
194.
The work on Train Management / Train Describer System including Mobile Communication on Churchgate - Virar Section was included in the Works Programme 199596. Detailed Estimate for this work was sanctioned at a cost of Rs.33.37 crores. The material modification for the new TMS Control Centre building has also been
sanctioned at a cost of Rs.2.05 crores.
Project envisages "On Line" operation of the existing Train Indicators at various stations and also provision of Video Display Units for indicating train running information
to the commuters. Countdown in Minutes shall provide minute to minute train arrival information to the commuters. Announcements at stations shall also be done
automatically from the Control Centre. The project also envisages "Live display" of movements of all trains to the Controllers in the Central Control at Mumbai Central on
Rear Video Projection Screens & Workstations.
Scheme also envisages providing Mobile Communication between Motormen/Guards of Suburban Trains and the Controllers at Mumbai Central.
The Contract for the above work was signed on 14.7.98 with M/s. ABB-Daimler Benz Transportation (India) Ltd., Vadodara at a cost of Rs.28.10 Crores (now M/s.
Bombardier Transportation India Limited).
Depending upon the success of the system, Mumbai Kalyan Train Management System will also be implemented in a similar fashion.
Project status
Mobile communication system on CCG-VR section commissioned on 27.12.02. Mobile units have been installed in 150 EMU cabins. The mobile system is working
satisfactorily.
Train Management system:
1.
2.
3.
4.
5.
195.
Sealdah North Control Communication through wireless in place of P & T Cables in 47 Stations :
The project costing Rs. 22.09 crore was sanction in March, 1996. Composite contract awarded in May, 2000, for laying of optical fibre cable. Out of 220 Km length of
cable line, 165 Km already laid and other works are in progress.
196.
197.
199.
200.
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------BRIDGES & STRUCTURES
-------------------1. BIRUPA MAHA1997/04
N.A. 2007/07
N.A.
0
N.A.
93.10
113.00
21
4.69
7.70
12.39
1.00
NADI:2ND BRD
N.A.
N.A.
21
ECOR
ORISSA
2. B'PUTRA BR,
BOGIBIL&LINK
NEFR
ASSAM
KMS
73.00
1996/04
2008/04
2008/04
0
0
0
0
1000.00
1500.00
1767.00
77
18
77.15
60.00
-
53.09
130.24
7.00
3. CHEYYARREBUILDING
SCR
ANDHRA PRADESH
2000/02
2005/06
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
30.29
37.95
25
25
0.39
0.39
4. REBUILDING
KRISHNA BDG.
SCR, KRISHNA
ANDHRA PRADESH
2000/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
18.06
23.72
36.02
36.32
101
1
3.62
3.62
1990/04
1994/04
1994/06
1995/12
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
29.28
35.40
37.90
29
7
36.14
36.14
99.00
1992/03
2002/05
1996/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
108.11
105.01
137.49
27
31
103.69
27.00
-
21.99
125.68
83.00
1993/04
1995/06
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
29.30
32.11
10
10
30.38
30.38
99.00
LINE DOUBLING
------------5. BOBBILI-GAJA KM
PATINA-GARAM 32
SER
ANDHRA PRADESH
6. KUPPAMWHITEFIELD
SWR
KR/AP
KMS
81.21
7. GAJAPATIAKM
NAGARAM-VIZ- 23
INAGRAM,SER
ANDHRA PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------8. RAJATGARH KMS
1994/04 1997/06
N.A.
N.A.
N.A.
N.A.
41.22
75.00
82
73.82
73.82
95.00
NERGUNDI TA- 25
N.A.
N.A.
42.95
75
LCHER,ECOR
ORISSA
9. AKALTARA-CHAMPA 3RD LIN
SECR
ORISSA
KMS
37
1994/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
40.00
53.61
34
34
47.10
47.10
90.00
10. CALICUTMANGALORE,SR
KMS
221
1996/02
2000/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
240.00
454.96
563.08
135
24
485.73
25.00
-
16.55
502.28
97.00
KMS
9
1995/04
2000/12
2005/06
54
79
54
79
20.00
64.09
220
220
49.01
49.01
56.00
KMS
21
1995/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
24.60
35.95
31.55
28
-12
31.28
31.28
99.00
13. GURAP-SHAKTIGARH,3RD
LINE,ER
WEST BENGAL
KMS
25.42
1996/04
N.A.
2005/03
N.A.
N.A.
N.A.
N.A.
41.43
52.65
52.65
27
0
31.16
20.00
-
13.31
44.47
98.00
14. GORAKHPURSAHJANWA,NER
KMS
17.70
1997/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
61.51
61.51
0
0
1.55
7.94
-
7.38
8.93
KE/KR
11. KANPUR-PANKI
3RD LINE,NR
UTTAR PRADESH
12. TUNDLAYAMUNA BR;NR
UTTAR PRADESH
UTTAR PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------15. V'WADA-KRIS- KMS
1996/04 1999/03
N.R.
N.A.
N.A.
N.A.
23.52
41.86
78
40.53
40.53
97.00
HNA 3RD LINE 5.05
2000/12 2003/07
N.A.
N.A.
78
SCR
ANDHRA PRADESH
16. HOSPETGUNTAKAL,SCR
KMS
115.40
1996/03
1999/12
2004/06
54
120
54
120
105.22
154.14
46
46
56.86
35.00
27.87
27.87
84.73
50.00
17. GUDUR-RENIKMS
GUNTA,SCR
83.17
TIRUPATI
ANDHRA PRADESH
1997/04
2000/04
2000/12
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
139.69
157.34
167.43
20
6
99.92
18.00
30.98
30.98
130.90
85.00
18. IRUGUR-COIMBATORE,SR
1996/04
2000/02
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
25.10
38.66
38.66
54
0
9.64
7.28
7.00
2.59
12.23
30.00
19. NERGUNDI- CU
TTACK R'PUR
ECOR
ORISSA
1997/04
N.A.
2005/12
N.A.
N.A.
N.A.
N.A.
105.32
112.86
7
7
61.84
26.69
88.53
38.00
20. CHAMPA-SARAG
BUNDIA
SECR
ORISSA
1997/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
39.74
56.57
42
42
14.29
14.29
1997/04
2000/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
37.35
40.96
10
10
12.81
12.81
18.00
AP/KR
KMS
17.70
TAMIL NADU
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------22. KENGERRI RAM KMS
1996/03
N.A. 2004/02
N.A.
0
N.A.
45.00
58.85
31
0.30
5.00
1.74
2.04
ANAGARAM
32.43
N.A.
N.A.
58.85
0
SWR
KARNATAKA
23. SARONA BHILAI 3RD LINE
SER
CHHATISGARH
1997/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
33.30
48.61
46
46
35.00
11.00
46.00
99.00
KMS
26
2000/07
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
30.98
30.98
0
0
8.03
8.03
4.00
30.0 KMS
1999/04
2000/09
N.A.
2004/09
N.A.
N.A.
N.A.
N.A.
49.00
51.41
65.92
35
28
46.19
6.00
13.50
12.48
58.67
86.00
2.639 KMS
1998/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
36.00
34.00
-6
-6
5.77
10.00
7.50
6.67
12.44
30.00
1998/04
2004/12
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
47.12
65.84
40
40
14.73
5.00
5.57
4.49
19.22
49.00
28. K-PURAM-CALI
-CUT-SHORAN
SR, KURADA
KERALA
2001/03
2001/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
178.76
177.34
178.23
0
1
82.92
30.00
-
23.95
106.87
25.00
24. KARPURIGRAMSIHO,ER
BIHAR
25. AMROHAMORADABAD,NR
UTTAR PRADESH
26. NEW DELHITILAK BRIDGE
NR:NEW DELHI
DELHI
KMS
86
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------29. DIVA-KALYAN
KMS
2000/09
N.A.
N.A.
N.A.
N.A.
N.A.
47.70
48.06
1
28.37
10.00
10.62
38.99
43.00
5TH/6TH LINE 10.73
N.A.
N.A.
48.06
0
CR
MAHARASHTRA
30. JALL.-P'KOT
JAMMU TAWI
NR
PB./JK
KMS.
203
2002/03
2007/06
2007/06
0
0
0
0
409.00
408.70
0
0
39.13
21.83
54.06
52.90
92.03
20.00
2002/05
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
304.50
305.95
346.99
14
13
23.43
40.00
11.53
11.53
34.96
10.00
KMS.
30
2001/02
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
63.22
63.22
0
0
0.61
10.01
-
11.29
11.90
32.00
33. AMROHA-KANKA
THER, NR
KMS.
31
2000/04
2005/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
57.00
56.98
0
0
20.18
8.00
9.50
10.70
30.88
56.00
KMS.
41.49
1990/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
97.64
97.64
0
0
1.15
18.00
5.38
5.40
6.55
7.00
2003/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
35.11
35.11
0
0
1.00
-
UTTAR PRADESH
34. KALAPIPAL PANDA(WR)
MADHYA PRADESH
35. AKODIA-MOH.- KMS.
KHERA-SHUJ'P 13.5
(WR)
MADHYA PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------36. ATTIPATTUKMS
1999/04
N.A.
N.A.
N.A.
N.A.
N.A.
40.10
70.56
76
9.09
15.00
4.25
13.34
29.00
KORUKUPET,SR 15
N.A.
N.A.
76
3.00
TAMIL NADU
37. ERNAKULAMMULANTURUTTI
SR
KERALA
KMS
17.37
2001/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
35.00
58.23
66
66
7.01
3.88
3.68
6.11
13.12
30.00
38. PATTABIRAMARAKKONAM,SR
KMS
41.89
2002/04
2004/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
71.94
71.94
0
0
3.88
3.68
12.76
12.76
8.00
KMS
14.56
2003/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
22.94
22.94
0
0
3.88
3.68
40. CHENNAIKURUKKUPET
3RD LINE,SR
TAMIL NADU
KMS
4.10
2003/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
59.57
59.57
0
0
3.88
3.68
41. MAVELKKARAI
KAYANKULAM
SR
KERALA
KMS
7.88
2003/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
21.84
21.84
0
0
3.88
3.68
0.13
0.13
KMS
7.76
2003/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
21.48
21.48
0
0
3.88
3.68
0.02
0.02
TAMIL NADU
39. AMBATHURAIKODAIKNAL,SR
TAMIL NADU
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------43. MAVELIKARAKMS
2003/04
N.A.
N.A.
N.A.
N.A.
N.A.
33.65
21.48
-36
5.00
CHENGANNUR
12.3
N.A.
N.A.
-36
SR
KERALA
44. MADURAIDINDIGUL,SR
KMS
63
2003/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
73.19
73.19
0
0
KMS
22.1
2003/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
50.23
50.23
0
0
46. JAFRABADKMS
UTRATIA PH-2 34
NR
UTTAR PRADESH
2000/04
2005/03
2005/03
0
0
0
0
64.20
64.20
0
0
9.41
8.50
-
9.03
18.44
47. ROHTAKJAKHAL
NR
HARYANA
2003/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
47.49
44.49
-6
-6
48. SAHIBABADKMS
ANAND VIHAR
16.4
3&4 LINE,NR
UTTAR PRADESH
2003/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
49.58
49.58
0
0
0.01
0.01
49. PANSKURAHADIA(PH.2)
SER
WEST BENGAL
2001/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
48.00
26.02
-46
-46
0.49
10.50
-
0.06
0.55
TAMIL NADU
45. CHENNAI-BEAC
H-ATTIPATTU
SR
TAMIL NADU
KMS
52
KMS
14
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------GAUGE CONVERSION
---------------50. ADILABADKMS
1996/08 1995/03 2007/03
144
21
144
117.97
199.06
69
29.80
30.00
29.98
59.78
30.00
MUDKHED
162
-847
-847
178.00
12
SCR:ADILABD
AP/MH
51. NIMACHRATLAM,WR
KMS
135.95
1993/04
1996/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
65.00
167.51
167.51
158
0
39.93
30.00
16.50
14.56
54.49
35.00
KMS
281
1992/04
1996/03
2004/03
96
204
96
204
112.53
320.66
363.80
223
13
124.04
35.00
78.21
78.11
202.15
53. ARSIKERE-HASSAN-MANGLOR
SWR
KARNATAKA
KMS
236
1995/04
1997/03
1996/03
2000/03
2004/12
105
955
57
97
186.16
185.16
312.42
68
69
208.38
2.00
-
36.74
245.12
90.00
54. HOTGIGADAG,SWR
KMS
300
1994/04
1999/03
2003/03
2006/03
84
142
36
34
180.00
318.66
77
77
162.78
10.00
-
37.94
200.72
74.00
KMS
35
1995/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
35.00
33.67
-4
-4
0.10
0.10
KMS
152
1995/04
1997/03
1999/12
2005/03
96
417
63
113
88.73
161.03
81
81
17.23
22.15
39.38
11.00
MADHYA PRADESH
52. RAJKOT-VERAVAL,WR
GUJARAT
KR/MA
55. MATHURAACHNERA,NCR
UTTAR PRADESH
56. AGRABANDIKUI
NCR
UP/RJ
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------57. RUPSA-BANGR- KMS
1996/02 1998/03
N.A.
N.A.
N.A.
N.A.
57.94
50.54
-13
12.30
14.75
2.07
14.37
26.00
IPOSI,SER
89.4
N.A.
N.A.
50.54
0
ORISSA
58. VIRAMGAMBHILDI,WR
KMS.
157
1990/04
1995/06
2004/06
108
174
108
174
155.66
119.75
119.75
-23
0
16.33
31.00
-
30.83
47.16
16.00
59. TRICHY-NAGOR
E-KARAIKAL
SR
TAMIL NADU
KMS
200
1995/11
2002/11
N.A.
N.R.
2004/06
N.A.
N.A.
N.A.
N.A.
N.A.
140.00
170.69
213.35
52
25
84.88
12.00
-
6.56
91.44
58.00
60. MIRAJ-LATUR
ROAD,CR
KMS
374
1993/04
2002/04
2001/03
2003/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
225.00
323.00
332.34
48
3
170.26
25.16
-
17.52
187.78
37.00
61. LUMDINGSILCHAR
NEFR
ASSAM
KMS
291.53
1996/04
2002/05
N.A.
N.R.
2004/04
N.A.
N.A.
N.A.
N.A.
N.A.
648.00
1401.01
1491.61
130
6
184.98
75.00
-
56.93
241.91
16.00
62. PH I:MANSISAHARSA
ECR
BIHAR
KMS
43.61
1996/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
55.11
89.50
62
62
27.06
27.06
30.00
63. AJMER-U'PUR
CHITTAURGARH
NWR
RAJASTHAN
KMS
300
1996/09
2002/01
N.A.
2000/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
262.00
433.39
455.18
74
5
36.68
29.14
65.82
GUJ/RAJ
MAHARASHTRA
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------64. GONDIA-JABA- KMS
1997/02 1998/03
N.R.
N.A.
N.A.
N.A.
356.00
511.86
44
52.79
7.15
59.94
8.55
LPUR,SECR
265.45
2003/12
N.A.
N.A.
44
MP,MAH
65. SURENDRANGR
BHAVANAGAR
WR
GUJARAT
KMS
421.60
1997/03
2004/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
437.40
528.49
21
21
376.93
15.00
61.50
77.64
454.57
66. KANPUR-K'GNJ
-MATHURA,NER
KMS
545.50
1997/03
2001/03
2003/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
395.00
598.98
658.11
658.11
67
0
115.64
23.20
38.20
41.83
157.47
25.00
67. VILLUPURAM P
ONDICHERRY
SR
TAMIL NADU
KMS.
38
1997/04
2004/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
30.00
43.83
43.83
46
0
18.82
10.00
11.20
11.87
30.69
75.00
KMS.
90
1997/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
46.53
66.95
46.53
0
-31
69. DELHI-REWARI
2ND LINE,NR
KMS
79
1995/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
42.27
44.55
69.00
63
55
39.26
39.26
58.00
KMS
167
1995/04
2000/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
227.00
995.58
995.58
339
0
37.17
15.00
-
11.86
49.03
5.00
UTTAR PRADESH
DEL,HR
70. HUBLIANKOLA,SWR
KARNATAKA
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------71. RANCHI-LOHA- KMS.
1997/04
N.A. 2006/03
N.A.
15
N.A.
193.78
185.31
-4
39.57
17.34
13.14
52.71
31.00
RDAGA,SER
133
N.A.
N.A.
-4
13.50
JHARKHAND
72. LUNI-BARMERMUNABAO,NWR
KMS
297
1997/04
N.A.
2004/03
N.A.
N.A.
N.A.
N.A.
240.00
283.94
18
18
134.41
42.00
176.41
30.00
73. S'BAD-M'KHED
-J'PET-B'HAN
SCR
AP/MH
KMS
269
1988/08
1998/06
2001/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
98.42
276.28
278.99
183
1
148.53
30.00
60.35
60.35
208.88
68.00
74. MADURAI-RAMESWARAM(SR)
MADURAI
TAMIL NADU
KMS
162
1998/07
2006/07
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
193.18
243.00
26
26
6.34
10.00
-
22.56
28.90
8.00
75. KATHAKAL-BHAIRABHI(NEFR
HAILAKANDI
AS/MI
KMS
84.15
1999/02
2001/11
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
88.87
88.87
0
0
KMS.
417.00
1998/11
1999/02
2003/03
2004/06
15
29
15
29
536.85
523.17
723.00
35
38
414.49
65.00
-
162.61
577.10
80.00
77. J'NGR-DARBHANGA-N'GANJ
DHARBNGA,ECR
BIHAR
KMS
259.13
1997/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
233.00
335.77
324.73
39
-3
14.05
11.52
25.57
9.00
RAJASTHAN
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------78. GANDHIDHAMKMS
1998/04
N.A.
N.A.
N.A.
N.A.
N.A.
318.00
344.63
8
27.35
100.00
53.17
80.52
20.00
PALANPUR,WR
313
N.A.
N.A.
358.74
-4
53.17
GANDHIDHAM
GUJARAT
79. VILLUPURAMKATPADI (SR)
KMS
161
2000/02
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
175.00
240.00
37
37
0.10
1.00
-
1.98
2.08
2.00
80. TRICHY
MANAMADURAI
(SR)
TAMIL NADU
KMS
150
2000/02
2002/05
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
175.00
187.91
187.81
7
0
0.48
5.00
-
0.55
1.03
3.00
81. KATIHAR-JOGBANI(NEFR)
KMS.
200.00
2001/09
2001/09
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
100.00
402.98
402.98
303
0
33.84
21.00
-
44.24
78.08
19.00
82. TAHANJAVURVILLUPURAM
(SR)
TAMIL NADU
KMS
192
2001/10
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
223.00
231.00
4
4
7.31
15.00
24.95
42.58
49.89
55.00
TAMIL NADU
83. FATUA-I.PURBIHARS-BBIGA
ECR
BIHAR
KMS
59.5
1998/07
2002/12
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
78.04
78.04
0
0
15.96
15.96
84. ANKOLA-PURNA
SCR
KMS.
210
2000/02
2002/02
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
228.00
245.20
245.22
8
0
4.78
15.00
-
14.61
19.39
16.00
MAHARASHTRA
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------85. KAPTANGANJKMS,
2001/09
N.A.
N.R.
N.A.
N.A.
N.A.
320.10
320.10
0
6.08
10.00
10.02
16.10
5.00
THAWE-SIWAN
233.50
2005/03
N.A.
N.A.
0
9.00
NER
UP/BIHAR
86. GONDA-GORAKH KMS
PUR-A.NGR.
260.17
NER
UTTAR PRADESH
2002/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
383.15
381.17
-1
-1
1.50
19.94
13.44
16.50
18.00
6.00
87. QUILON-TIRUN
ELVELI-TENKS
SR
KER/TN
KMS
357
1998/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
280.00
577.61
106
106
79.89
12.00
34.95
57.81
137.70
33.00
88. TIRCHPALLI-N
AGOREKARAKAL
SR
TAMIL NADU
KMS
200
1995/09
2002/11
1995/09
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
100.00
170.69
213.35
113
25
84.88
12.00
-
6.56
91.44
58.00
89. SHIMOGATALAGUPPA
S.W.RLY.
KARNATAKA
KMS.
97
1992/12
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
46.00
46.00
0
0
1.15
0.01
-
1.30
2.45
5.00
90. CUDDLORESALEM, SR
KMS.
191
1999/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
198.68
261.10
31
31
32.07
0.10
10.00
8.63
40.70
KMS. 96
1998/03
2005/03
2005/03
0
0
0
0
111.90
111.90
0
0
27.61
24.86
-
9.51
37.12
TAMIL NADU
91. BANKURA DAMODAR(SER)
WEST BENGAL
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------92. GONDA-B'RACH KMS
1997/04
N.A.
N.A.
N.A.
N.A.
N.A.
73.42
73.42
0
0.20
0.50
0.44
0.64
-S'PUR-L'NOW 60
N.A.
N.A.
0
NER
UTTAR PRADESH
93. TIRUPATI-P'K
ALA-KATPADI
KMS.
104
1992/04
2000/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
71.70
130.00
190.36
165
46
137.07
12.90
-
12.90
149.97
2000/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
403.39
403.39
403.39
0
0
261.91
1.00
-
39.17
301.08
71.00
ANDHRA PRADESH
METROPOLITAN TRANSPORT PROJECTS
------------------------------94. THANE-TURBHE 22.60
1992/05
-NERUL-VASHI KMS
MUMBAI
MAHARASHTRA
95. B'PUR-S'WOOD
-URAN ELEC.
MUMBAI
MAHARASHTRA
KMS
27
1996/03
1997/07
2004/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
401.81
495.44
23
23
38.53
1.00
-
12.42
50.95
10.00
KMS
10
1995/04
2000/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
49.84
95.00
102.00
105
7
75.06
10.00
-
4.12
79.18
74.00
KMS
11.08
1996/04
2002/03
2005/03
36
51
12
36
51
605.70
691.04
14
14
473.12
15.00
-
29.52
502.64
72.00
98. BHANDU-THANE
5&6TH LIN II
MUMBAI
MAHARASHTRA
KMS.
7
1997/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
46.69
56.79
83.57
79
47
35.75
10.00
-
5.51
41.26
65.00
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------99. GC-CHENNAI116
1999/04 2004/04
N.A.
N.A.
N.A.
N.A.
464.99
622.52
34
171.28
34.00
50.56
221.84
75.00
CHENGALPATTU KMS
N.A.
N.A.
34
CHENNAI
TAMIL NADU
100. ELEC.BARASAT
-HASNABAD
KOLKATTA
WEST BENGAL
KMS
60.00
1998/04
2002/03
2004/06
27
57
27
57
37.70
37.70
0
0
20.13
1.33
2.55
1.38
21.51
90.00
101. BORIVILIVIRAR,WR
MUMBAI
MAHARASHTRA
KMS
25.84
1995/04
2004/03
2000/06
2000/06
2005/03
12
11
57
92
325.47
401.66
383.94
18
-4
200.85
115.00
69.02
69.02
269.87
63.00
8.7
2000/03
2006/12
2007/06
6
7
6
7
907.69
907.69
0
0
110.26
50.00
-
39.74
150.00
15.00
KMS
39.25
1999/03
2004/12
2004/12
0
0
0
0
358.77
269.50
-25
-25
80.88
35.00
-
12.94
93.82
40.00
KMS
53.00
1981/03
1990/03
1994/03
2000/12
2004/04
121
78
40
17
50.00
112.00
407.74
510.00
920
25
423.22
60.00
-
59.78
483.00
99.50
KMS.
113
1981/03
1985/05
1995/03
2008/03
156
93
156
93
37.68
150.00
210.00
457
40
69.15
12.31
19.73
20.01
89.16
41.00
NEW LINE
-------104. JAMMU TAWIUDHAMPUR,NR
J & K
105. NANGALDAMTALWARA,NR
PB/HP
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------106. TAMLUK DIGHA KMS
1984/03 1997/03 2005/06
99
3
99
43.72
293.97
572
226.19
15.00
8.90
235.09
77.00
SER
88.9
63
63
77.13
281
15.90
WEST BENGAL
107. GUNA-ETAWAH,
ECR
KMS
348.25
1985/04
2001/01
1994/03
2005/03
132
123
132
123
158.77
274.56
400.00
152
46
310.92
5.12
316.04
89.00
KMS
48
1987/03
1990/04
1994/03
1996/03
2004/03
120
143
96
89
40.90
39.16
100.89
100.89
147
0
84.08
7.00
-
9.95
94.03
109. EKLAKHIBALURUGHAT
NFR
WEST BENGAL
KM
113.00
1986/01
1994/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
36.80
105.91
274.41
646
159
177.27
15.00
16.00
27.31
204.58
75.00
110. DUOHNOIDEPA
NFR
AS/ME
KMS
15.50
1992/04
1997/12
N.R.
2007/03
N.A.
N.A.
N.A.
N.A.
N.A.
22.33
22.33
0
0
0.50
0.01
-
0.50
KMS
147
1993/03
2000/11
1997/12
2004/12
84
147
84
147
242.50
537.74
401.56
590.60
144
47
322.07
47.41
369.48
35.50
112. PEDAPALLIKMS
K'NGR-NZMBAD 177
SCR
ANDHRA PRADESH
1994/12
1997/04
2003/03
N.A.
2000/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
124.43
273.00
383.03
383.03
208
0
73.45
15.00
13.22
13.22
86.67
25.00
M.P./U.P.
108. LAKSHMIKANTA
PUR-NAMKH,ER
100.00 (COMPLETED)
WEST BENGAL
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------113. AMRAVATIKMS
1994/06 1999/06 2005/03
69
0
69
120.90
284.27
135
79.00
10.00
16.75
95.75
36.00
NARKHER,CR
138
1996/07
115
115
175.30
62
28.80
MAHARASHTRA
114. HOWRAH-AMTACHAMPADANGA,
SER
WEST BENGAL
KMS
73.5
1974/04
2001/07
N.A.
2007/03
N.A.
N.A.
N.A.
N.A.
31.42
154.30
154.30
391
0
63.42
5.00
9.60
4.89
68.31
40.00
115. UDHAMPUR-S'NGR-B'MULLA,
NR
J & K
KMS
290
1995/03
2001/03
2007/08
77
107
77
107
2500.00
3564.00
43
43
789.78
500.00
-
501.82
1291.60
38.00
116. LANJHIGARHJUNAGARH,
ECOR
ORISSA
KMS
56
1993/04
2002/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
100.00
119.24
19
19
13.22
5.71
18.93
9.50
117. DALIRAJHARAJAGDALPUR
SECR
CHHATISGARH
KMS
235
1995/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
369.00
369.00
0
0
0.45
0.07
0.52
118. PANVELKARJAT,CR
MUMBAI
MAHARASHTRA
KMS
28.05
1996/02
1997/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
89.00
106.89
137.44
54
29
88.75
20.00
27.00
17.68
106.43
90.00
119. GODRA-INDORE
DEWAS-MAKSI
WR
MP/GUJ
KMS
344.90
1989/04
1996/03
1996/12
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
297.15
1007.14
1007.14
239
0
61.99
20.00
2.00
0.22
62.21
15.00
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------120. KOTTURKMS
1995/04 1999/04 2005/04
72
0
72
65.94
124.13
88
2.38
5.00
7.43
9.81
16.00
HARIHAR,SWR
65
150
150
88
KARNATAKA
121. KUMARGHATAGARTALA
NEFR
TRIPURA
KMS
109
1996/04
N.A.
2007/03
N.A.
N.A.
N.A.
N.A.
575.00
895.00
56
56
259.67
85.00
-
38.20
297.87
33.00
122. SAKRIHASSANPUR
ECR
BIHAR
KMS
76
1996/12
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
96.03
89.70
-7
-7
20.65
20.65
18.00
123. MANDERHILLDUMKA-R'HAT
ER
JHARKHAND
KMS
130
1995/04
N.A.
2007/03
N.A.
N.A.
N.A.
N.A.
184.00
254.27
254.07
38
0
40.74
10.00
-
19.67
60.41
16.00
124. HASSAN-BANGLORE-S'B'GOL
SWR
KARNATAKA
KMS
166
1997/02
2003/01
2004/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
295.00
412.91
412.91
40
0
83.51
26.00
-
37.23
120.74
28.00
KMS
250
1997/02
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
353.08
353.00
0
0
6.33
15.37
4.60
4.12
10.45
55.00
KMS
92.67
1997/02
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
151.84
217.93
44
44
0.32
14.98
15.30
RAJASTHAN
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------127. KARUR-SALEM, KMS
1997/02
N.A.
N.A.
N.A.
N.A.
N.A.
155.55
229.88
48
53.49
15.69
11.20
64.69
38.00
SR
85
2000/10
N.A.
N.A.
229.98
0
TAMIL NADU
128. MUZAFFARPURS'MARHI,ECR
KMS
62.72
1997/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
100.00
210.79
111
111
10.62
12.19
22.81
2.60
KMS
44
1997/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
78.23
73.37
162.87
108
122
5.81
3.03
8.84
5.00
130. NANDYALKMS
YERRAGUNTLA
126
SCR
ANDHRA PRADESH
1997/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
155.74
164.36
164.36
6
0
9.38
5.00
4.90
4.90
14.28
131. KADUR-C'MAGALUR-S'PUR
SWR
KARNATAKA
KMS
100
1996/04
1999/04
2005/03
71
197
71
197
157.00
283.34
80
80
17.29
15.00
-
15.57
32.86
12.00
132. MUNIRABADMAHBUBNAGAR
SCR
AP/KR
KMS
230.00
1996/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
377.32
460.00
449.60
19
-2
14.85
10.00
8.66
8.66
23.51
133. KALKA-PARWAN
OO NR
KMS.
4.00
1997/04
1999/02
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
23.00
27.00
37.00
61
37
0.14
0.01
-
0.01
0.15
BIHAR
129. KHAGARIAK'ASTHAN,ECR
BIHAR
HR/HP
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------134. ARA-SASARAM
KMS
1997/07
N.A.
N.A.
N.A.
N.A.
N.A.
120.00
191.00
59
28.42
17.13
45.55
ECR
98
N.A.
N.A.
59
BIHAR
135. MACHERLAKMS
NALGONDA(SCR 76
NALGONDA
ANDHRA PRADESH
1998/07
2008/07
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
125.00
265.67
113
113
0.10
1.00
0.15
0.15
0.25
136. KODERMAR
ANCHI(BARKNA
RANCHI,(ECR)
JHARKHAND
KMS
189
1999/03
2005/07
2006/03
8
11
8
11
491.19
1028.00
109
109
56.31
93.04
149.35
137. DIPU TO
KARONG,NEFR
KMS
123
1999/08
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
800.00
1600.00
100
100
0.02
3.00
-
0.02
138. LALITPURSATNA-REWA
WCR
UP/MP
KMS.
541
1998/09
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
925.00
925.00
0
0
32.00
2.00
34.00
3.00
139. CHANDIGARHLUDHIANA,NR
CHANDIGARH
PUNJAB
KMS
112.09
1997/07
1998/09
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
248.44
100.00
382.27
54
282
89.95
15.00
30.00
31.11
121.06
32.00
140. AGRA-ETAWAH
KMS
VIA FATEBAD
110.50
NCR
UTTAR PRADESH
1999/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
108.00
214.09
98
98
26.99
0.54
27.53
4.00
ASSAM
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------141. ANGAMALI
KMS
1998/10
N.A.
N.A.
N.A.
N.A.
N.A.
550.00
550.00
0
4.91
10.00
0.49
5.40
SABARIMALA
120
N.A.
N.A.
0
4.09
(SR)
KERALA
142. MANIKPURCHEOKI
(CR)
MAHARASHTRA
143. PANVEL-JASAI
-JNPT
(CR)
MAHARASHTRA
32.08 KM.
28.5 KM.
2001/06
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
48.00
46.16
-4
-4
8.11
8.11
20.00
2001/10
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
53.23
53.23
0
0
0.50
20.00
-
0.31
0.81
2.00
144. PUNTAMBASHIRDI
(CR)
MAHARASHTRA
KMS
16.60
2002/02
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
32.00
48.78
52
52
8.37
10.00
7.91
4.19
12.56
20.00
145. BIDAR-GULBERGA,SCR
KMS
140
1999/02
2003/06
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
242.42
369.70
369.70
53
0
5.36
15.00
14.65
14.65
20.01
KMS
58.25
2001/12
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
330.00
450.00
36
36
9.27
5.00
0.19
0.19
9.46
1999/02
2006/12
2007/03
3
3
3
3
180.73
180.73
0
0
20.91
15.00
-
13.34
34.25
11.00
KARNATAKA
146. KOTLPALLINARASPUR,SCR
ANDHRA PRADESH
147. DEOGHARDUMKA, ER
KMS
67
JHARKHAND
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------148. NL-MAYNAGURI KMS.
2000/02
N.A.
N.A.
N.A.
N.A.
N.A.
733.00
733.00
0
9.24
25.00
4.93
14.17
2.00
- JOGIGHOPA 261.62
N.A.
N.A.
0
VIA CHANGRA,
NFR,WB/ASSAM
149. GANDHINAGARKALOL (NL)
WR
GUJARAT
KMS.
20.49
2000/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
49.96
49.96
0
0
10.28
15.00
4.18
3.43
13.71
22.00
150. PAKNISOLAPUR
CR
MAHARASHTRA
KMS.
16.28
2002/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
33.33
38.52
38.52
16
0
0.23
15.00
-
0.48
0.71
151. BANGLORESATYAMANGLAM
SWR
KARNATAKA
KMS.
260
1999/02
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
138.00
225.00
63
63
0.22
0.10
-
0.22
1.00
KMS.
112
2000/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
138.00
373.44
171
171
34.78
9.00
-
8.24
43.02
13.00
KMS.
54
1998/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
75.00
138.48
85
85
3.71
4.00
1.00
0.49
4.20
6.00
KMS
58.8
1998/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
92.63
108.91
18
18
4.24
5.00
4.99
4.90
9.14
6.79
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------155. KOTTAYAM KMS. 44
1998/04
N.A.
N.A.
N.A.
N.A.
N.A.
200.00
200.00
0
0.05
0.05
0.09
0.14
ERUMELI(SR)
N.A.
N.A.
0
KERALA
156. KUTTIPURAMGURUVYAR,SR
KMS
36
1995/04
1996/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
40.00
90.00
137.71
244
53
0.72
1.00
-
6.00
6.72
KMS
21.5
1999/01
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
38.00
38.00
0
0
3.11
3.30
-
7.11
10.22
KMS
42.72
2001/09
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
86.44
86.44
0
0
1.91
0.21
-
0.11
2.02
KMS.
84.75
2000/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
157.96
276.00
75
75
22.16
1.00
-
0.49
22.65
1.00
1995/03
2004/12
117
89
117
89
520.00
1098.00
426.12
-18
-61
273.79
1.60
275.39
1998/03
2005/03
84
140
84
140
152.21
157.75
4
4
135.38
1.00
-
19.17
154.55
44.30
KERALA
157. TARN-TARNGOINDWAL
PUNJAB
158. ABOHARFAZILKA
PUNJAB
159. TARAKESWAR BISHNUPUR
ER
WEST BENGAL
1993/03
PB/HR/UP
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------162. KHARAGPURKMS
1995/03 2000/03 2004/12
57
9
57
258.58
402.17
56
293.67
1.11
294.78
63.00
BHUBANESWAR
540
1997/03
95
95
304.33
32
OR/WB
163. UDHNAJALGAON
KMS
306
1997/03
2002/03
N.R.
2003/03
N.A.
N.A.
N.A.
N.A.
N.A.
124.39
140.98
13
13
108.90
90.60
199.50
KMS
135
1998/11
1999/04
2001/11
2003/02
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
78.80
98.19
98.19
25
0
74.79
1.00
-
24.27
99.06
99.80
165. CONV.EXISTIN
G1500V DC
MUMBAI
MAHARASHTRA
1996/07
2005/03
2005/03
0
0
0
0
273.67
273.67
0
0
31.45
6.87
38.32
166. ERNAKULAMTRIVANDRUM
2001/05
2003/08
2004/12
16
59
16
59
162.03
162.03
0
0
60.09
21.97
35.06
36.08
96.17
40.00
2000/06
2003/04
2004/03
11
32
11
32
168.34
168.34
0
0
17.83
30.00
9.43
7.99
25.82
53.75
1987/03
1991/07
1992/12
1996/06
2004/03
135
196
93
84
20.10
22.58
30.90
54
37
40.21
0.10
-
0.96
41.17
88.95
GU/MH
164. LUDHIANA- A
MRITSAR(NR)
LUDHIANA
PUNJAB
KERALA
167. RENIGUNTAGUNTAKAL
ANDHRA PRADESH
TRAFFIC FACILITIES
-----------------168. REMOD OF YD. KMS
PH-I ST-I,ER 9.30
BARDMAN
WEST BENGAL
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------169. MUMBAI CST
1995/04 1998/12
N.A.
N.A.
N.A.
N.A.
19.72
80.64
309
30.49
6.27
7.30
37.79
23.00
REMOD;PH-I
N.A.
N.A.
80.64
0
CR
MAHARASHTRA
170. KURLA PSR.
TRM.FAC.PH2S
CR
MAHARASHTRA
1996/04
1999/12
N.R.
2003/06
N.A.
N.A.
N.A.
N.A.
N.A.
34.94
39.43
39.44
13
0
16.86
0.01
-
16.86
1997/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
45.00
45.00
0
0
172. ARAKKONAM
KATPADI AUTO
SIG,SR
TAMIL NADU
1997/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
22.98
22.98
0
0
0.38
0.38
173. STN.CONST.AT
GOMTINAGAR
2003/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
68.31
68.31
0
0
12.00
-
10.87
10.87
10.00
1985/08
1989/02
1992/03
2003/03
2006/03
168
213
36
17
180.00
314.57
451.26
151
43
385.37
35.82
29.26
21.00
406.37
1991/03
1995/03
2003/09
N.R.
2003/09
N.A.
N.A.
N.A.
N.A.
N.A.
23.30
39.89
71
71
33.67
1.00
-
33.67
DELHI
UTTAR PRADESH
WORKSHOPS & PRODUCTION UNIT
--------------------------174. RCF KAPURTH- COACH
ALA,PH-II,NR 1000
KAPURTHALA
PUNJAB
175. 60LOCO DIESEL SHED
ANGUL,SER
ORISSA
NO.
60
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------176. CLW-MFR.OF
KMS.
1992/03 1999/06 2005/03
69
0
24
29.82
39.91
34
32.34
0.53
1.12
33.46
HIGH HP ABB
150
2003/03
79
18
34
LOCOS,ER
WEST BENGAL
177. KAZIPET-ELEC
LOCOSHED,SCR
LOCOS
100
1996/03
2000/03
2003/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
23.00
29.27
25.20
10
-14
13.12
1.56
-
2.75
15.87
ANDHRA PRADESH
178. LUDHIANAELEC.LOCOSHE
NR
PUNJAB
LOCOS
100
1996/08
2000/03
2003/03
2005/03
60
140
24
30
20.00
24.35
24.35
22
0
21.90
1.00
-
0.50
22.40
179. CLW-ELEC.
LOCO.AUG.,ER
170
LOCO/YEAR
1997/07
2002/03
2004/03
24
43
24
43
25.84
18.19
-30
-30
7.18
7.18
180. WORKSHOP
UNITS
AUGMENTATION 250
GORAKHPUR,NR
UTTAR PRADESH
1998/05
2002/03
2004/12
33
72
33
72
21.50
19.69
19.69
-8
0
2.13
5.50
-
0.60
2.73
1998/05
2003/03
2004/03
2004/03
12
21
0
0
47.31
47.71
1
1
36.95
9.32
-
2.31
39.26
1999/04
2003/03
2003/05
2006/03
36
77
34
69
155.54
155.44
141.22
-9
-9
22.88
22.64
-
13.45
36.33
WEST BENGAL
182. 4000/3000 HP
DIESEL LOCOS
NR:VARANSI-2
UTTAR PRADESH
WHEEL SETS
20000
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------183. DLW-4000HP:I
1998/10 2001/03 2005/03
48
0
12
37.44
43.27
16
23.88
14.29
8.18
32.06
DIESEL LOCOS
2004/03
166
18
43.27
0
NR:VARANASI
UTTAR PRADESH
184. SETTINGUP OF
EL.LOCO SHED
BOKARO,ER
JHARKHAND
100
ELECTRIC
LOCOS SHED
1996/04
2001/03
2004/03
2005/12
57
97
21
22
22.36
22.36
0
0
0.96
1.00
-
0.32
1.28
185. CONST.OF 50
LOCO SHEDS
HUBLI,SR
KARNATAKA
NOS.
50
1997/04
2003/03
2004/03
12
17
12
17
15.26
22.26
46
46
19.44
1.00
-
1.22
20.66
186. REDUCTION IN
POH TIME
PERMABUR
TAMIL NADU
1999/04
2003/10
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
18.76
20.57
10
10
18.22
1.05
1.38
19.60
187. ICF-PAINTING
FACILITIES
PERAMBUR
TAMIL NADU
2001/03
2003/12
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
26.55
26.05
-2
-2
6.67
10.68
-
0.10
6.77
188. ICFAUG.OF FA
CILITIES FOR
PERAMBUR
TAMIL NADU
2002/03
2005/12
2005/03
2005/03
-9
-20
0
0
45.32
46.99
4
4
0.17
14.32
-
0.50
0.67
2003/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
98.74
98.74
0
0
16.13
-
14.00
14.00
COACHES
50
BIHAR
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------SIGNALLING & TELECOMMUNICATIONS
------------------------------190. REPL.MW EQP, CH
1991/04 1997/12
N.A.
N.A.
N.A.
N.A.
22.49
38.05
69
31.79
31.79
GRK'PUR- KTH 960
N.A.
N.A.
69
NER
BI/UP
191. MUMBAI-KALYAN TRAIN DES
SYS,CR
MAHARASHTRA
192. LONAVALAPUNE AUTO BL
SIGNAL,CR
MAHARASHTRA
KMS
64
193. VGM-G'DHAM,
REPL. LEVER
KANDLA PORT
GUJARAT
1996/04
1999/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
25.89
35.79
38
38
0.60
0.60
1996/04
1999/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
25.00
34.33
37
37
1998/04
2002/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
25.32
26.02
26.02
3
0
23.47
2.83
2.16
2.50
25.97
98.00
60 KMS.
1995/04
2000/09
2003/03
2004/03
42
65
12
13
9.79
33.75
33.37
241
-1
24.73
10.00
4.00
3.67
28.40
90.00
195. WIRELESS IN
PL.OF P&T CA
SEALDAH
WEST BENGAL
47
STATIONS
1996/03
1999/12
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
22.09
22.09
0
0
14.99
14.99
196. REPL.LEVER-B
'ROUTE -OPS
MUMBAI
MAHARASHTRA
STNS.
19
2001/05
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
35.76
39.96
12
12
0.54
0.54
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: RAILWAYS
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------197. REPL.LEVER-A STNS.
2001/05
N.A.
N.A.
N.A.
N.A.
N.A.
27.98
30.95
11
0.95
0.95
'ROUTE-OPS
16
N.A.
N.A.
11
MUMBAI
MAHARASHTRA
SETTING UP OF NEW RAILWAY ZONES
------------------------------198. WEST CENT.
1997/05
RLY.ZONE(CR)
JABALPUR
MADHYA PRADESH
2001/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
41.67
41.67
0
0
5.46
5.46
50.00
1997/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
41.67
41.67
0
0
6.89
6.89
6.00
1997/02
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
41.66
41.66
0
0
5.22
5.22
10.00
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
There were 119 projects on the monitoring system at the end of the quarter ending March, 2004 under Road Transport & Highways Sector:
Status of Projects as on 31.03.2004
-------------------------------------------------------WITHIN
WITHIN
TIME
COST
WITH
BUT
BUT
TIME
WITH
WITH
&
TOTAL
WITHIN
COST
TIME
COST
CATNO. OF
TIME &
OVEROVEROVEREGORY
PROJECTS
COST
RUNS
RUNS
RUNS
-------------------------------------------------------1
2
3
4
5
6
-------------------------------------------------------MEGA
0
0
0
0
0
MAJOR
92
41
0
47
4
MEDIUM
27
5
0
21
1
-------------------------------------------------------TOTAL
119
46
0
68
5
-------------------------------------------------------Project Status:
As of now, work on 2, 244 km stretch of the NHDP has been completed so far of which 2,082 km stretch belongs to the Golden Quadrilateral (GQ). As regards the NorthSouth & East-West Corridors, 4-laning has been completed on 588 km stretch, while another 475 km stretch is currently under execution.
The main factors contributing to occurrence of time overrun in the NHDP projects include grave law and order situation in States like Bihar and Jharkhand, and Orissa;
difficulties experienced in land acquisition as in Maharashtra , Karnataka, and Tamil Nadu forest clearance, removal of large number of structures including places of
worship, water mains, electrical lines, sewer lines telephone lines, pending court cases, slow progress on the part of some contractors, non-availability of quarry stone of
the desired grade, award of contracts without land acquisition, delay in obtaining approval for rail over bridges (ROB's), and inadequate deployment of qualified staff by
contractors at project sites.
14.2.1
The implementation status of each of the projects and the statistical details of cost and time schedules, original, revised and anticipated, are given in the succeeding paras:-
Golden Quadrilateral
North South Corridor
East corridor
Port Connectivity
Others
Date of approval in respect of the NHDP project at S.No. 1 to 134 except those at S. Nos 91 to 94 on MOS7PI's monitor is April,2000.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
51.
52.
53.
54.
55.
56.
57.
58.
59.
60.
61.
62.
63.
64.
65.
66.
67.
68.
69.
70.
71.
72.
73.
74.
75.
76.
77.
78.
79.
80.
81.
82.
83.
84.
Naini Bridge over Yamuna River at Allahabad with Approach Road on NH-27 in U.P. (GQ)
Naini Bridge project was approved in March, 1995 for implementation with OECF (now Japan Bank of International Cooperation) (JBIC) assistance. The original
estimated cost of the project is Rs.100.36 crore (3/1995), now revised to Rs. 219.78 crore, and is expected to be completed by May,2004. The project was transferred to the
NHAI in December, 1998. There has been a change of technology in this project from the earlier conceived Box Girder to Cable Stayed.
Physical progress achieved so far is 91.50%.
85.
Allababad: km 198-km242.71
Project cost is Rs. 534.39 crore. It is a recently awarded package.
86.
88.
89.
Kanyakumari-Panagudi:
Project costs is 120 crores. It is a recently awarded package.
90.
Srinagar-Bypass:
Project costs is 120 crores. It is a recently awarded package.
91.
92.
93.
94.
95.
96.
97.
98.
99.
100.
101.
102.
Nagpur Hyderabad and Hyderabad Bangalore Section (Km.464-474)& (Km.9.4 22.3) (NS-II) :
Project cost is Rs. 88 cr. Physical progress achieved is 45%.
103.
104.
105.
106.
107.
109.
110.
111.
112.
113.
114.
115.
116.
118.
119.
Nandigama Vijayawada(OP):
Project cost is Rs.138.65 crore. Project is nearing completion (95.70% physical progress achieved so far).
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------NATIONAL HIGHWAYS AUTHORITY OF INDIA
-----------------------------------GOLDEN QUADRILATERAL
-------------------1. J'PURBYPASS
KM.
2000/04 2004/06 2004/10
4
7
4
210.00
210.00
0
90.26
76.63
56.74
147.00
59.70
PH2 GQ
221-246
8
8
0
RAJASTHAN
2. M'PURE-K'GAR
H GQ
KM.
273.5-363
2000/04
2005/10
2004/12
-10
-15
-10
-15
644.00
644.00
0
0
37.00
107.50
-
265.90
302.90
38.26
KM.
363.9-15
2000/04
2004/05
2004/01
-4
-8
-4
-8
113.50
113.50
0
0
69.91
82.90
-
27.54
97.45
100.00 (COMPLETED)
KM.
15-70
2000/04
2004/05
2004/01
-4
-8
-4
-8
182.09
182.09
0
0
77.99
151.90
-
55.01
133.00
100.00 (COMPLETED)
KM.
70-120
2000/04
2004/05
2004/04
-1
-2
-1
-2
164.25
164.25
0
0
71.82
100.00
-
50.28
122.10
79.00
KM.
120-183
2000/04
2004/05
2004/04
-1
-2
-1
-2
202.88
202.88
0
0
89.31
115.70
-
70.19
159.50
89.00
KM.
220-172
2000/04
2004/05
2004/01
-4
-8
-4
-8
161.20
161.20
0
0
54.85
86.82
-
60.15
115.00
RAJASTHAN
3. K'GARH-NAS'B
AD GQ
RAJASTHAN
4. NAS'BAD-G'PU
RA GQ
RAJASTHAN
5. G'PURA-BH'WA
RA GQ
RAJASTHAN
6. B'WARA-CHI'G
ARH GQ
RAJASTHAN
7. CHI'GARH-M'W
AR GQ
100.00 (COMPLETED)
RAJASTHAN
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------8. M'WAR-UDAIPU KM.
2000/04 2004/05 2004/04
-1
1
-1
170.00
170.00
0
60.58
132.70
91.12
151.70
63.00
R GQ
172-114
-2
-2
0
RAJASTHAN
9. UDAIPUR-K'RI
AJI GQ
KM.
278-340
2000/04
2004/04
2004/02
-2
-4
-2
-4
245.91
245.91
0
0
100.60
98.51
-
101.50
202.10
100.00 (COMPLETED)
KM.
340-388
2000/04
2004/04
2004/07
3
6
3
6
226.05
226.05
0
0
49.95
100.80
-
53.25
103.20
69.53
KM.
443-495
2000/04
2003/12
2004/12
12
27
12
27
180.31
175.00
-3
-3
3.10
71.90
-
24.97
28.07
9.80
KM.
263-343
2000/04
2003/10
2004/06
8
19
8
19
275.58
275.58
0
0
188.90
90.00
-
150.00
338.90
65.58
KM.
343-382
2000/04
2003/04
2004/01
9
25
9
25
174.59
174.59
0
0
146.20
60.00
-
64.10
210.30
KM.
825-30
2000/04
2005/02
2004/11
-3
-5
-3
-5
146.25
146.25
0
0
21.10
88.86
-
41.02
62.12
RAJASTHAN
10. K'RIAJI-RTNP
UR GQ
RAJASTHAN
11. HI'NGR-CHILO
DA GQ
GUJARAT
12. SURAT-ATUL G
Q
GUJARAT
13. ATUL-KAIJALI
GQ
100.00 (COMPLETED)
GUJARAT
14. KATRAJ REALI
GN GQ
44.09
MAHARASHTRA
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------15. SATARA-KAGAL KM.
2000/04 2004/05 2004/08
3
3
3
600.00
600.00
0
165.00
108.20
199.30
364.30
50.12
GQ
725-592
6
6
0
MAHARASHTRA
16. M'TRA BRDR B
LGM GQ
KM.
592-575
2000/04
2004/12
2004/06
-6
-11
-6
-11
332.00
332.00
0
0
191.40
19.00
-
282.20
473.60
80.73
KM.
575-495
2000/04
2003/12
2004/07
7
16
7
16
115.90
115.90
0
0
55.26
78.83
-
40.87
96.13
70.30
KM.
495-433
2000/04
2004/02
2004/10
8
17
8
17
279.00
279.00
0
0
42.38
110.40
-
75.72
118.10
27.70
KM.
404-340
2000/04
2003/12
2004/12
12
27
12
27
260.93
260.93
0
0
49.40
100.30
-
37.93
87.33
19.69
2000/04
2004/08
2004/12
4
8
4
8
241.00
241.00
0
0
40.10
120.00
-
40.92
81.02
18.50
2000/04
2004/08
2004/12
4
8
4
8
318.00
318.00
0
0
67.05
155.00
-
52.85
119.90
24.50
KARNATAKA
17. BELGAUM BYPA
SS GQ
KARNATAKA
18. B'GAUM-D'WAD
GQ
KARNATAKA
19. HUBLI-HAVERI
GQ
KARNATAKA
20. HAVERIHARIHAR (GQ)
KARNATAKA
21. H'HAR-CHI'DU
RGA GQ
KM.
284-207
KARNATAKA
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------22. CHI'DURGA BY KM.
2000/04 2004/08 2004/08
0
0
0
104.00
104.00
0
23.91
75.00
20.58
44.49
21.20
PASS GQ
207-189
0
0
0
KARNATAKA
23. CHI'DURGA-SI
RA GQ
KM.
189-122
2000/04
2004/08
2004/08
0
0
0
0
304.00
304.00
0
0
62.44
155.00
-
66.96
129.40
33.50
KM.
116-75
2000/04
2004/08
2004/08
0
0
0
0
184.00
184.00
0
0
55.49
85.00
-
52.61
108.10
53.00
KM.
49-94
2000/04
2004/06
2004/01
-5
-10
-5
-10
213.00
213.00
0
0
95.86
143.60
-
51.54
147.40
KM.
0-49
2000/04
2004/06
2004/05
-1
-2
-1
-2
195.00
195.00
0
0
87.12
100.10
-
85.08
172.20
70.02
KM.
49-100
2000/04
2004/06
2004/09
3
6
3
6
223.00
223.00
0
0
71.13
91.88
-
63.87
135.00
44.58
KM.
100-145
2000/04
2004/04
2004/09
5
10
5
10
211.00
211.00
0
0
62.48
101.60
-
50.72
113.20
40.04
KARNATAKA
24. SIRA-TUMKUR
GQ
KARNATAKA
25. HOSUR-K'GIRI
GQ
100.00 (COMPLETED)
TAMIL NADU
26. K'GIRI-V'BAD
I GQ
TAMIL NADU
27. V'BADI-P'KON
D GQ
TAMIL NADU
28. P'KONDA-W'PE
T GQ
TAMIL NADU
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------29. W'PET-K'PURA KM.
2000/04 2004/03 2004/01
-2
0
-2
130.00
130.00
0
56.72
75.96
44.98
101.70
100.00 (COMPLETED)
M GQ
106-70
-4
-4
0
TAMIL NADU
30. KANCHI-PMALL
I GQ
KM.
70-14
2000/04
2003/12
2004/12
12
27
12
27
211.00
211.00
0
0
37.50
110.40
-
33.15
70.65
24.27
KM.
18-76
2000/04
2004/03
2004/12
9
19
9
19
393.00
393.00
0
0
187.50
397.50
-
81.40
268.90
49.63
KM.
72-142
2000/04
2003/12
2004/06
6
14
6
14
375.00
375.00
0
0
222.80
293.80
-
94.00
316.80
84.86
KM.
53-119
2000/04
2004/03
2004/05
2
4
2
4
332.00
332.00
0
0
147.50
325.80
-
80.20
227.70
43.98
KM.
0-53
2000/04
2003/12
2004/12
12
27
12
27
272.00
272.00
0
0
107.70
184.70
-
34.10
141.80
41.62
KM.
137-199
2000/04
2004/02
2004/06
4
9
4
9
227.25
227.25
0
0
70.45
97.64
-
23.76
94.21
46.80
TAMIL NADU
31. D'KUNI-L'GHA
T GQ
WEST BENGAL
32. K'GHAT-KH'PU
R GQ
WEST BENGAL
33. KH'PUR-L'NAT
H GQ
WEST BENGAL
34. L'NATH-B'SHW
AR GQ
ORISSA
35. B'SORE-BHDRK
GQ
ORISSA
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------36. BHDRK-CH'KHO KM.
2000/04 2003/12 2004/06
6
0
6
305.30
305.30
0
176.80
185.10
48.10
224.90
78.35
L GQ
61-136
14
14
0
ORISSA
37. BRIDGS GQ
(OR-V)
B'SORE-CHADI
ORISSA
KM.
80-162 NH5
2000/04
2004/05
2004/05
0
0
0
0
155.00
155.00
0
0
52.84
91.76
-
20.44
73.28
43.61
38. BH'WAR-KHURD
A GQ
KM.
388-418
2000/04
2004/01
2004/05
4
9
4
9
140.85
140.85
0
0
67.64
108.00
-
19.40
87.04
62.96
KM.
388-388
2000/04
2003/12
2004/06
6
14
6
14
189.68
189.68
0
0
59.47
176.80
-
27.76
87.23
41.46
KM.
338-284
2000/04
2004/04
2004/12
8
17
8
17
225.00
225.00
0
0
53.66
142.30
-
15.76
69.42
8.60
KM.
284-223
2000/04
2004/02
2004/12
10
22
10
22
256.55
256.55
0
0
80.90
159.50
-
10.60
91.50
11.65
KM.
233-200
2000/04
2004/01
2004/09
8
18
8
18
143.05
143.05
0
0
27.76
60.66
-
14.39
42.15
36.59
ORISSA
39. KHURDA-S'KHA
LA GQ
ORISSA
40. S'KHALA-G'JA
M GQ
ORISSA
41. GANJAM-I'PUR
AM GQ
ORISSA
42. I'PURAM-KORL
AM GQ
ANDHRA PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------43. K'LAM-PALASA KM.
2000/04 2004/01 2004/09
8
0
8
135.11
135.11
0
31.38
74.48
17.33
48.71
41.23
GQ
200-171
18
18
0
ANDHRA PRADESH
44. PALASA-S'KAK
ULAM GQ
KM.
171-97
2000/04
2003/12
2004/12
12
27
12
27
324.00
324.00
0
0
118.10
89.00
-
40.20
158.30
64.10
2000/04
2004/02
2004/06
4
9
4
9
171.97
171.97
0
0
64.83
104.40
-
24.64
89.47
42.43
2000/04
2004/02
2004/05
3
7
3
7
200.00
200.00
0
0
112.60
89.63
-
40.80
153.40
76.65
2000/04
2004/11
2004/11
0
0
0
0
283.20
283.20
0
0
13.01
1.25
-
110.09
123.10
59.52
2000/04
2004/11
2004/11
0
0
0
0
231.90
231.90
0
0
83.83
1.50
-
33.27
117.10
63.57
2000/04
2004/11
2004/11
0
0
0
0
206.00
206.00
0
0
86.30
1.50
-
63.90
150.20
77.31
ANDHRA PRADESH
45. S'KAKULAM-CH
'WATI GQ
KM.
97-49
ANDHRA PRADESH
46. CH'WATI-VIZA
G GQ
KM.
49-28
ANDHRA PRADESH
47. A'PALLI-TUNI
GQ
KM.48-49
ANDHRA PRADESH
48. TUNI-D'VARAM
GQ
KM.
300-253
ANDHRA PRADESH
49. D'VARAM-R'MU
NDRY
KM.
253-200
ANDHRA PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------50. D'CHERU-GTAM KM.
2000/04 2003/12 2004/06
6
0
6
130.80
130.80
0
51.33
42.87
13.90
65.23
61.37
I GQ
200-165
14
14
0
ANDHRA PRADESH
51. BRIDGES-AP19
V-V SECTION
KM.
162-200
NH-5
ANDHRA PRADESH
52. G'TAMI-G'GOL
ANU GQ
KM.
165-80
2000/04
2004/02
2004/09
7
15
7
15
136.45
136.45
0
0
58.65
47.51
-
28.86
87.51
78.81
2000/04
2004/02
2004/01
-1
-2
-1
-2
323.35
323.35
0
0
231.30
88.27
-
73.00
304.30
2000/04
2004/02
2004/06
4
9
4
9
131.33
131.33
0
0
47.63
47.74
-
17.97
65.60
64.13
2000/04
2003/12
2004/09
9
20
9
20
319.21
319.21
0
0
120.40
176.90
-
30.60
151.00
46.57
2000/04
2004/04
2004/12
8
17
8
17
321.41
321.41
0
0
109.70
222.30
-
59.80
169.50
54.98
2000/04
2004/01
2004/12
11
24
10
11
24
181.00
181.00
0
0
105.20
100.90
-
42.40
147.60
73.14
100.00 (COMPLETED)
ANDHRA PRADESH
53. BRIDGES-AP20
GQ,W-SECT.
KM.
80-162 NH5
ANDHRA PRADESH
54. CH'PET-ONGOL
E GQ
KM.
358-291
ANDHRA PRADESH
55. ONGOLE-KAVAL
I GQ
KM.
291-222
ANDHRA PRADESH
56. KAVALI-NLR G
Q
KM.
222-178
ANDHRA PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------57. NLR BY PASS
KM.
2000/04 2003/12 2004/05
5
2
5
143.20
143.20
0
60.00
1.20
71.30
131.30
92.48
GQ
178-161
11
11
0
ANDHRA PRADESH
58. TADA-CHENNAI
GQ
KM.
53-11
2000/04
2003/12
2004/12
12
27
12
27
233.00
233.00
0
0
132.30
136.90
-
52.30
184.60
70.80
KM.
200-251
2000/04
2005/03
2004/12
-3
-5
-3
-5
367.49
367.49
0
0
84.74
157.60
-
68.86
153.60
29.44
KM.
251-308
2000/04
2005/03
2004/12
-3
-5
-3
-5
261.22
261.22
0
0
32.69
92.81
-
20.97
53.66
8.50
KM.
321-393
2000/04
2005/03
2004/12
-3
-5
-3
-5
348.44
348.44
0
0
54.90
154.50
-
69.36
124.26
15.60
KM.
393-470
2000/04
2004/08
2004/08
0
0
0
0
323.62
323.62
0
0
114.30
156.50
-
49.12
163.42
44.03
KM.
470-483
2000/04
2005/03
2004/12
-3
-5
-3
-5
495.35
495.35
0
0
117.90
260.40
-
98.90
216.80
29.87
TAMIL NADU
59. AGRA-S'HABAD
GQ
UTTAR PRADESH
60. S'HABAD-ETAW
A GQ
UTTAR PRADESH
61. ETAWA-R'PUR
GQ
UTTAR PRADESH
62. SKDRA-BAUNTI
GQ
UTTAR PRADESH
63. K'PUR-FATEPU
R GQ
UTTAR PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------64. F'PUR-KHAGA
KM.
2000/04 2004/07 2004/12
5
0
5
372.40
372.40
0
57.63
80.03
46.45
104.08
14.35
GQ
38-115
10
10
0
UTTAR PRADESH
65. KHAGA-K'RAJ
GQ
KM.
115-158
2000/04
2004/02
2004/06
4
9
4
9
151.70
151.70
0
0
61.39
88.88
-
69.97
131.36
57.61
KM.
245-317
2000/04
2004/07
2004/12
5
10
5
10
286.00
286.00
0
0
72.39
88.46
-
81.95
154.34
25.29
KM.
317-329
2000/04
2005/03
2004/11
-4
-7
-4
-7
467.93
467.93
0
0
104.40
186.20
-
96.49
200.89
26.74
KM.
65-110
2000/04
2004/02
2004/12
10
22
10
22
230.55
230.55
0
0
67.38
107.40
-
34.66
102.04
30.36
KM.
110-40
2000/04
2005/03
2004/11
-4
-7
-4
-7
221.87
221.87
0
0
33.05
105.80
-
27.87
60.92
10.64
KM.
140-180
2000/04
2004/02
2004/06
4
9
4
9
242.61
242.61
0
0
107.20
74.55
-
35.85
143.05
52.12
UTTAR PRADESH
66. HANDIAVARANASI GQ
UTTAR PRADESH
67. V'NASI-MOHAN
IA GQ
UP/BIHAR
68. MOHANIA-SASA
RAM GQ
BIHAR
69. S'RAM-D'ON-S
ON GQ
BIHAR
70. D'ON-SON-AU'
BAD GQ
BIHAR
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------71. AU'BAD-B'CHA KM.
2000/04 2005/03 2004/12
-3
0
-3
320.42
320.42
0
66.67
105.80
41.83
108.50
20.41
TTI GQ
180-240
-5
-5
0
BIHAR
72. RAJGANJ-B'KA
TA GQ
KM.
240-320
2000/04
2005/03
2004/11
-4
-7
-4
-7
452.71
452.71
0
0
76.76
241.80
-
61.94
138.70
15.61
KM.
320-399
2000/04
2005/03
2004/12
-3
-5
-3
-5
399.75
399.75
0
0
90.90
74.77
-
70.13
161.03
29.54
KM.
517-581
2000/04
2004/12
2004/09
-3
-5
-3
-5
350.00
350.00
0
0
130.60
1.66
-
152.10
282.70
46.54
KM.
581-646
2000/04
2005/02
2004/12
-2
-3
-2
-3
432.40
432.40
0
0
78.51
1.60
-
140.29
218.80
39.49
2000/04
2005/06
2005/12
6
10
6
10
600.00
641.00
7
7
21.98
0.12
22.10
2000/04
2004/05
2004/05
0
0
0
0
97.90
97.90
0
0
36.34
30.07
-
6.57
42.91
37.25
BIHAR/J'KHND
73. G'HAR-B'ADDA
GQ
JHARKHAND
74. P'GARH-P'STT
GQ
WEST BENGAL
75. P'SIT-D'KUNI
GQ
WEST BENGAL
76. V'NANDA BRID
G & APPCH GQ
WEST BENGAL
77. KATRAJ-SAROLE826-797,GQ
KMS
29
MAHARASHTRA
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------78. TUMKUR BYPA- KMS
2000/04 2003/12 2004/03
3
0
3
83.00
83.00
0
19.53
43.00
22.85
42.38
30.75
SSK75-62,GQ
14
7
7
0
KARNATAKA
79. D'KUNJ-KH'PU
RK18-136,GQ
KMS
119.4
2000/04
2004/02
2004/06
4
9
4
9
81.00
81.00
0
0
44.14
43.45
-
11.24
55.38
75.15
KM.
119
2000/04
N.A.
2004/09
N.A.
N.A.
N.A.
N.A.
80.00
80.00
0
0
30.52
71.30
-
11.52
42.04
49.06
KM.
136
2000/04
2004/03
2004/03
0
0
0
0
79.14
79.14
0
0
33.00
39.06
-
14.35
47.35
67.20
KM.
14.6
2000/04
2003/10
2004/06
8
19
8
19
89.50
89.50
0
0
27.85
62.06
-
7.32
35.17
22.48
KMS
92.85
1986/01
1998/12
1991/12
1991/12
1998/12
2004/03
147
207
63
41
128.40
766.50
766.50
497
0
554.17
179.20
-
109.30
663.47
79.33
1995/03
2001/06
2001/06
1998/12
2004/05
35
47
65
144
100.36
300.00
219.78
119
-27
191.70
70.00
85.00
72.10
263.80
91.50
WEST BENGAL
80. KH'PUR-B'SWA
R K 0-119 GQ
ORISSA
81. S'LAM-I'PURA
M K233-98 GQ
ANDHRA PRADESH
82. ETA.BYPASS K
308-321 GQ
UTTAR PRADESH
83. AHMBD-VADOD.
EXP.WAY,NHAI
GUJARAT
84. NAINI BRIDGE
:NH2 & NH27
ALLHABAD
UTTAR PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------85. ALLAHABAD:KM KM.1982000/04
N.A.
N.A.
N.A.
N.A.
N.A.
534.39
534.39
0
4.03
4.03
198-KM242.71 KM.242.71
N.A.
N.A.
0
ALLAHABAD
UTTAR PRADESH
86. ALLAHABAD(KM KM. 158 158-KM.198)
KM. 198
ALLAHABAD
UTTAR PRADESH
2000/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
440.93
440.93
0
0
6.65
6.65
2002/02
2004/04
26
118
26
118
54.09
63.46
17
17
81.93
20.80
-
4.33
86.26
76.65
2000/04
2003/11
2004/11
12
28
12
28
57.53
57.53
0
0
11.53
44.07
-
0.92
12.45
13.30
2004/01
N.A.
2006/09
N.A.
N.A.
N.A.
N.A.
120.00
120.00
0
0
0.25
0.25
2003/12
2006/05
2006/05
0
0
0
0
125.00
125.00
0
0
8.25
8.25
3.47
2002/03
2004/12
33
143
33
143
62.98
62.98
0
0
37.99
14.76
-
1.39
39.38
63.00
KM.
8
DELHI
89. KANYAKUMARIPANAGUDI NS2
TAMIL NADU
90. SRINAGAR
BYPASS-NS II
J & K
EAST WEST CORRIDOR - PHASE I
---------------------------91. P'NEA-G'KOTA KM.
2000/04
K410-419EWI
15
BIHAR
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------92. DKHOLA-I'PUR KM.
2000/04 2002/03 2004/03
24
0
24
72.56
72.56
0
48.09
30.80
8.64
56.73
85.00
K447-470EWI 23
104
104
0
WEST BENGAL
93. DKHOLA-I'PUR
K476-500EWI
KM.
24
2000/04
2002/12
2004/12
24
75
24
75
90.06
90.06
0
0
44.77
0.57
-
9.44
54.21
62.50
KM.
8
2000/04
2002/06
N.R.
2003/12
N.A.
N.A.
N.A.
N.A.
N.A.
54.87
54.87
0
0
52.05
7.45
-
7.79
59.84
KM.
16
2000/04
2001/12
2005/05
41
205
41
205
51.28
51.28
0
0
16.45
30.67
-
6.69
23.14
32.00
2003/09
2004/03
6
15
6
15
71.18
71.18
0
0
30.23
53.53
-
12.50
42.73
72.50
WEST BENGAL
94. GHATIBYPASS
K156-164EWI
100.00 (COMPLETED)
ASSAM
95. LKO-KANPUR K
60-76GQEWI
UTTAR PRADESH
NORTH-SOUTH CORRIDOR - PHASE II
------------------------------96. J'DHAR-P'KOT KM.
2000/04
K4-26 NSII
22.23
HARYANA
97. DELHI-HARYAN
AK-44-66NSII
KM.
22
2000/04
2003/09
2004/09
12
29
12
29
82.00
82.00
0
0
18.39
65.79
-
9.11
27.50
21.85
KM.
12.79
2000/04
2003/04
2004/09
17
47
17
47
71.00
71.00
0
0
14.13
68.08
-
5.01
19.14
16.85
HARYANA
98. 8LANEDLH'YAN
AK17-9NSII
DELHI
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------99. DHOLPUR-SEC. KM.
2000/04 2003/08 2004/03
7
0
7
76.00
76.00
0
73.61
30.67
14.01
87.62
97.00
K-24-41 NSII 17
18
18
0
U.P./RAJ.
100. AGRA-G'LIOR
K70-85 NSII
KM.
15
2000/04
2003/08
2004/03
7
18
7
18
49.00
49.00
0
0
37.26
10.19
-
12.34
49.60
94.50
2000/04
N.A.
2004/06
N.A.
N.A.
N.A.
N.A.
69.50
69.50
0
0
40.61
18.92
-
9.48
50.09
71.50
2000/04
2003/11
2004/07
8
19
8
19
88.00
88.00
0
0
35.09
36.02
-
16.06
51.15
45.00
KM.
19.2
2000/04
2003/08
2004/10
14
35
14
35
82.49
82.49
0
0
38.26
44.99
-
30.07
68.33
60.60
104. BL'ORE-SALEM
MADURAI
K248-260 NS
TAMIL NADU
KM.
11.5
2000/04
2002/11
2004/03
16
52
16
52
21.40
21.40
0
0
12.59
16.04
-
8.70
21.29
98.00
105. ALUVA-A'MALI
K333-16 NSII
KM.
16.6
2000/04
2003/08
2004/04
8
20
8
20
77.38
77.38
0
0
51.60
24.19
-
11.18
62.78
76.00
MADHYA PRADESH
101. AGRA-G'LIORK
-85-103NSII
KM.
18
MADHYA PRADESH
102. N'PUR-HYD.K4
64-74 NSII
KM.
10
12.9
ANDHRA PRADESH
103. BLR-MADURAIK
180-199NSII
TAMIL NADU
KERALA
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------106. HYD-B'LORE N KM.
2000/04 2004/03 2004/12
9
0
9
172.06
172.06
0
74.52
124.10
18.26
92.78
20.70
S-II
556-539
19
19
0
124.10
KARNATAKA
107. JAMMU-P'KOT
NS-II
KM.
80-97
2000/04
2004/12
2004/12
0
0
0
0
110.00
110.00
0
0
15.17
35.77
-
6.77
21.94
12.90
2003/12
2004/06
6
14
6
14
94.91
94.91
0
0
32.72
58.19
-
29.43
62.15
61.57
J & K
EAST WEST CORRIDOR - PHASE II
----------------------------108. LKO-K'PUR KM KM.
2000/04
21.8-44 EWII 22.2
UTTAR PRADESH
109. GUHA.BYPASS
K146-157EWII
KM.
10.5
2000/04
2003/05
2004/06
13
35
13
35
63.69
63.69
0
0
35.90
36.69
-
12.78
48.68
80.00
KM.
15.5
2000/04
2003/05
2004/06
13
35
13
35
50.02
50.02
0
0
12.61
36.69
-
14.45
27.06
45.18
KM.
419-447
& 470-476
2000/04
2004/07
2004/12
5
10
5
10
205.73
205.73
0
0
31.55
41.00
87.14
11.77
43.32
15.40
2000/04
2004/06
2004/12
6
12
6
12
182.52
185.52
2
2
97.74
73.09
-
40.46
138.20
57.42
ASSAM
110. LKO-K'PUR KM
44-59.5 EW 9
UTTAR PRADESH
111. PURNEA-G'KOT
EW-II
BIHAR
112. LUCK BYPASS
EW NH 25&28
UTTAR PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------PRADHAN MANTRI BHARAT JORHO PRIYOJANA (PMBJP)
--------------------------------------------113. PUNE-NASIK
2003/08 2005/08 2005/08
0
0
0
127.60
127.60
0
(KM 12.9-42)
0
0
0
MAHARASHTRA
PORT CONNECTIVITY
----------------114. JNPT-PORTCON
NECT NH-4B
2000/04
2004/04
2004/08
4
8
4
8
177.12
177.12
0
0
61.59
119.00
125.40
20.56
82.15
50.76
NH41
2000/04
2004/07
2005/03
8
16
8
16
273.00
273.00
0
0
24.39
87.32
-
43.07
67.46
12.83
KM.
12
2000/04
2004/10
2004/12
2
4
2
4
93.79
93.79
0
0
21.75
40.96
-
30.38
52.13
49.90
KM.
143-42
2000/04
2005/04
2005/04
0
0
0
0
555.00
555.00
0
0
114.00
6.20
-
114.00
NH28-121
2000/04
2004/11
2004/06
-5
-9
-5
-9
375.00
375.00
0
0
3.13
4.00
10.30
10.30
13.43
2000/04
2003/12
2004/04
4
9
4
9
138.65
138.65
0
0
86.64
2.50
-
86.64
95.70
MAHARASHTRA
115. HALDIAPORT-P
.CONNECT
WEST BENGAL
116. VIZAG PORT
(PC)
ANDHRA PRADESH
OTHER PROJECTS
-------------117. DELI-G'GAONOTHER
DELHI/HAR.
118. T'BRM-T'VNM
OTHER
TAMIL NADU
119. N'GAMA-V'WAD
A OTHER NH9
ANDHRA PRADESH
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
There were 39 projects on the monitoring system in the previous quarter . Two projects have been commissioned and two new projects have been taken on monitor in the
intervening period. There are thus 39 projects on the monitoring system at the end of quarter ending March,2004 under Shipping and Ports Sector.
Status of Projects as on 31.03.2004
-------------------------------------------------------WITHIN
WITHIN
TIME
COST
WITH
BUT
BUT
TIME
WITH
WITH
&
TOTAL
WITHIN
COST
TIME
COST
CATNO. OF
TIME &
OVEROVEROVEREGORY
PROJECTS
COST
RUNS
RUNS
RUNS
-------------------------------------------------------1
2
3
4
5
6
-------------------------------------------------------MEGA
0
0
0
0
0
MAJOR
7
4
0
2
1
MEDIUM
32
11
4
10
7
-------------------------------------------------------TOTAL
39
15
4
12
8
-------------------------------------------------------Inland Water Transport :
1.
Procurement of Cutter Suction Dredgers & Allied Vessels for National Waterways Nos.-1 & 2 :
The project was approved in January, 2002 at estimated cost of Rs.41.30 crore with completion schedule of January, 2003 but subsequently revised to March, 2005.
All the three dredgers have been delivered. Accommodation boats are expected to be delivered in 2004-05. Cumulative expenditure incurred so far is Rs. 20.24 crore.
Physical progress achieved is 80%
2.
3.
4.
5.
6.
7.
Cumulative expenditure incurred over the project so far is Rs. 32.11 crore.
Cochin Port Trust :
8.
9.
10.
11.
12.
13.
14.
15.
16 .
17.
18.
19.
20.
21.
River Water Regulatory Measures for improvement of draught in Hooghly Estuary of Kolkata Port Trust:
This project related to taking corrective measures to increase the navigational depth in the Hooghly estuary to facilitate easy passage of ships, was sanctioned by the Govt.
in November, 2001 at an estimated cost of Rs.350.84 crore with expected commissioning schedule of December, 2003. (Anticipated date of commissioning is December,
2004)
M/s NIOT, Chennai has been shortlisted by the Kolkata Port Trust for execution of the works related to capital dredging. Physical progress achieved so far has been
minimal.
22.
23.
24.
25.
26.
27.
29.
30.
31.
32.
33.
35.
36.
Acquisition of 2 Nos. 1, 46,860 DWT Crude Oil Tanker from M/s DAEWOO:
The project was sanctioned in December, 2001 at estimated cost of Rs.457.78 crore with commissioning schedule of September, 2004.
37.
38.
39.
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------INDIAN WATER TRANSPORT
---------------------1. CUTTER SUC.
NOS.
2002/01 2003/01 2005/03
26
12
26
41.30
41.30
0
7.07
19.80
13.17
20.24
80.00
-DGERS& VESS 3
217
217
0
-
2. TERMINAL AT
GAIGHAT
PATNA
BIHAR
2002/03
2004/03
2005/03
12
50
12
12
50
25.50
25.50
0
0
13.99
2.00
16.75
13.76
27.75
62.00
3. CONSTN. OF
PERM. TER..
PANDU
ASSAM
2002/03
2004/09
2005/04
7
23
7
23
30.00
30.00
0
0
10.00
10.00
-
6.00
16.00
4. CAPITAL
DREDG.
KOLLAM-KOCHI
KERALA
1997/12
2001/03
2004/03
36
92
36
92
26.00
30.93
19
19
18.09
1.00
3.60
2.47
20.56
71.00
1999/05
2004/08
63
263
63
263
49.63
76.37
54
54
42.89
42.89
68.00
1996/08
2000/01
2004/03
50
122
50
122
70.00
70.00
0
0
40.83
5.00
45.83
90.00
1998/03
2001/09
2004/04
31
74
31
74
64.00
60.00
-6
-6
30.49
15.02
-
1.62
32.11
PORTS
----ANDAMAN & NICOBAR ADMINISTRATION
-------------------------------5. CONST.400 PA PASSENGER
1997/05
X VESSEL
400
PORT BLAIR
CARGO
A & N ISLANDS 100 MT
CHENNAI PORT TRUST
-----------------6. REPL. DREGER
COLEROON
CHENAI
TAMIL NADU
7. REPL.7 NOS.
WHARF CRANE
CHENNAI
TAMIL NADU
MT
15
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------COCHIN PORT TRUST
----------------8. CONS.OF
2001/04 2003/08
N.R.
N.A.
N.A.
N.A.
30.00
30.00
0
1.30
1.30
RECLM.WALL
2003/08
N.A.
N.A.
0
MULTISTATE
KANDLA PORT TRUST
----------------9. ADDL.FACILI- MMTPA
TIES-CRUDE
10
VADINAR
GUJARAT
1999/03
2001/03
N.R.
2003/11
N.A.
N.A.
N.A.
N.A.
N.A.
25.50
31.81
31.81
25
0
17.41
0.10
-
17.41
10. RES.QRS.'Q'
TYPE
KANDLA
GUJARAT
1999/03
2001/03
2004/12
45
188
45
188
9.93
31.25
31.25
215
0
1.31
0.05
-
0.38
1.69
2001/05
2004/03
2004/03
0
0
0
0
20.00
35.00
75
75
27.49
5.50
-
4.08
31.57
90.17
12. PROCUREMENT
OF VTMS
KANDLA
GUJARAT
2000/08
2004/03
2004/03
0
0
0
0
50.00
42.15
-16
-16
2.50
-
13. REPL. OF
KUTCH KESARI
KANDLA
GUJARAT
2000/10
2004/03
2004/03
0
0
0
0
16.00
20.00
25
25
8.00
-
14. DEV./UPGRADE
OPEN PLOTS
KANDLA
GUJARAT
2000/06
2002/10
2004/07
21
75
21
75
8.00
34.45
34.45
331
0
9.36
7.00
-
2.07
11.43
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------15. DEEP.&WIDEN.
2001/05 2004/03 2004/03
0
0
0
40.00
49.00
23
40.78
6.50
4.79
45.57
93.01
OF SOGAL CH.
0
0
23
KANDLA
GUJARAT
16. MODN.OF BUNDER BASIN
KANDLA
GUJARAT
TPD
600
2001/10
2003/06
2005/03
21
105
21
105
20.53
20.53
0
0
0.47
1.00
-
0.03
0.50
17. PROCURE 4
WHARF CRANE
KANDLA
GUJARAT
MT
20 TO 25
EACH
2000/08
2002/07
2004/10
27
117
27
117
24.00
36.75
36.75
53
0
0.03
11.00
-
17.05
17.08
54.00
18. CONSTN.OF9TH
CARGO BERTH
KANDKA
GUJARAT
0.80
MTPA
1999/01
2003/12
2004/06
6
10
6
10
45.00
47.89
6
6
34.62
10.00
-
6.96
41.58
90.00
MTPA
0.80
2002/10
2005/03
2005/03
0
0
0
0
47.89
46.98
-2
-2
0.02
0.50
-
0.34
0.36
NOS.
3
2003/08
2005/08
2005/08
0
0
0
0
24.00
24.00
0
0
2.40
-
2001/11
2003/12
2004/12
12
48
12
48
350.84
350.84
0
0
2.51
175.00
-
0.10
2.61
2.00
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------22. ROAD INSIDE
2002/10
N.A.
N.A.
N.A.
N.A.
N.A.
30.00
30.00
0
OUTSIDE DOCK
N.A.
N.A.
0
WEST BENGAL
23. SHIP-SHORE
GANTRY CRANE
HALDIA
WEST BENGAL
NOS.
2
2002/10
2004/11
2004/11
0
0
0
0
28.50
28.50
0
0
2002/12
2004/11
2004/11
0
0
0
0
28.50
28.50
0
0
2.00
-
2003/09
2004/04
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
25.00
25.00
0
0
40.00
25.00
25.32
25.32
1997/08
2003/02
2004/12
22
33
22
33
167.99
215.34
28
28
128.87
20.00
-
33.00
161.87
92.50
2000/02
2003/06
2004/03
9
23
9
23
69.50
69.49
36.00
-48
-48
14.40
19.50
-
16.00
30.40
96.00
2001/07
2004/01
2005/12
23
77
23
77
37.54
44.54
44.54
19
0
0.07
20.93
-
4.39
4.46
GOA
MUMBAI PORT TRUST
----------------26. MODERN OF
MTPA
MOT JETTIES
4
MUMBAI
MAHARASHTRA
27. REPL.COMMON
SHORE P.LINE
MUMBAI
MAHARASHTRA
NEW MANGALORE PORT TRUST
-----------------------28. CONST.ADDL.
MTPA
GEN. BERTH
5
MANGALORE
KARNATAKA
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------PARADEEP PORT TRUST
------------------29. CONSTN OF
MMTPA
1997/01 2000/01 2004/05
52
2
52
46.18
46.18
0
44.96
4.41
3.02
47.98
98.00
OIL JETTY
6
144
144
0
PARADIP
ORISSA
VIZAG PORT TRUST
---------------30. PROCURE:GRAB
HOPPER DRGER
VIZAG
ANDHRA PRADESH
1999/08
2001/04
2004/06
38
190
38
190
30.90
30.90
0
0
20.18
2.00
-
0.82
21.00
70.00
31. PROCURE 2
TON
UNLOADERS
33
VIZAG
ANDHRA PRADESH
1998/09
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
44.82
44.82
0
0
0.02
0.02
32. PROCURE 4
TON
NOS.CRANES
20
VIZAG
ANDHRA PRADESH
1998/10
N.A.
2004/03
N.A.
N.A.
N.A.
N.A.
32.64
27.53
-16
-16
1.87
12.00
-
18.89
20.76
98.00
33. CONSTN. OF
WEST QUAY
VIZAG
ANDHRA PRADESH
2000/08
2002/07
2004/01
2004/04
3
7
3
7
44.57
34.04
44.57
0
31
13.70
13.80
-
10.04
23.74
74.00
2002/03
N.R.
2002/12
N.A.
N.A.
N.A.
N.A.
N.A.
49.68
49.68
0
0
17.08
17.08
2002/07
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
151.29
151.29
0
0
93.79
93.79
SHIPPING
-------SHIPPING CORPORATION OF INDIA
----------------------------34. ACQ.3BP TUGS 50 TE
2000/05
ABG SHIPYARD EACH
MUMBAI
MAHARASHTRA
35. ACQ.IND.LRII TANKER
MUMBAI
MAHARASHTRA
2000/03
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------36. ACQ.OF2-146, 2-146,860
2001/12 2004/09 2004/05
-4
-1
-4
457.78
457.78
0
189.96
180.03
176.74
366.70
860 DWT OIL
DWT CRUDE
-12
-12
0
MUMBAI
OIL TANK
MAHARASHTRA
37. ACQ.OF 700
PASS.+160 T
MUMBAI
MAHARASHTRA
PASSENGERS
700 CUM
160T CARGO
VESSELS
2000/06
2004/02
2004/02
0
0
0
0
129.62
129.62
0
0
56.51
28.49
85.00
38. ACQ.2-300000
DWT LATGE CR
MUMBAI
MAHARASHTRA
2003/05
N.A.
2005/10
N.A.
N.A.
N.A.
N.A.
610.80
610.80
0
0
244.32
-
239.30
239.30
39. ESTABLISH
TVS IN GULF
KUTCH
GUJARAT
2002/01
2005/12
2006/06
6
13
6
13
165.00
165.00
0
0
0.23
6.50
-
0.14
0.37
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
XV. TELECOMMUNICATIONS
Project Review
15.1
There were 14 projects in the Telecom Sector on MOS& PIs monitor at the end of quarter ending March, 2004.
The overall status of the projects w.r.t. the original schedules is as follows:
Status of Projects as on 31.03.2004
-------------------------------------------------------WITHIN
WITHIN
TIME
COST
WITH
BUT
BUT
TIME
WITH
WITH
&
TOTAL
WITHIN
COST
TIME
COST
CATNO. OF
TIME &
OVEROVEROVEREGORY
PROJECTS
COST
RUNS
RUNS
RUNS
-------------------------------------------------------1
2
3
4
5
6
-------------------------------------------------------MEGA
0
0
0
0
0
MAJOR
2
1
0
1
0
MEDIUM
12
4
2
5
1
-------------------------------------------------------TOTAL
14
5
2
6
1
--------------------------------------------------------
Present Status :
The implementation status of each of the projects in given below:
ITI PROJECTS :
1.
CSN, Bangalore
The project envisaging production of 500 K lines equipment by the Bangalore Unit of ITI was approved by the Govt. in May, 2000 at estimated project cost of Rs.37.98
crore with commissioning schedule of June 2006.
Present Status:
Production activities commenced during the 4th quarter of 2000-01. During 2003-04, ITI is planning to achieve production target of 250 K lines
Physical progress achieved so far is 80%. The likely DOC of the project is now November, 2006.
2.
(B)
3.
MTNL PROJECTS :
Expanasion of Marol Digital Exchange, Mumbai
The project pertaining to laying underground cable for expansion of Marol Digital Exchange in Mumbai was approved by the MTNL Board in June, 2000 at estimated
project cost of Rs.27.92 crore with commissioning schedule of March, 2002.
Present Status :
The physical progress achieved so far is 92%. As per the present indications, the project is likely be commissioned by March, 2004.
4.
5.
6.
7.
Internet Expansion with new POP at Gamdevi, Khar & TURBHP, Mumbai:
The project was approved in July, 2003 at estimated cost of Rs.20.81 crore with completion schedule of March, 2004.
50% physical progress has been achieved so far.
( C)
DOT PROJECT :
8.
C-DOT PROJECTS :
9.
10.
11.
12.
13.
IDR VSAT :
The project was sanctioned in April, 2001 at revised cost of Rs. 25.40 crore with completion schedule of July, 2003.
Physical progress achieved so far is 95%. Latest position in regard to commissioning of the project has not been reported by the project authorities. Due to subsequent
change in scope, the project cost was revised to Rs. 96.7 crore during the year 2002-03.
14.
SBM Exchange :
The project was sanctioned in July, 2001 at revised cost of Rs. 25.00 crore with completion schedule of June 2003.
98% physical progress has been achieved so far. Latest position in regard to commissioning of the project has not been intimated by the project authorities.
SECTOR: TELECOMMUNICATION
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------INDIAN TELEPHONE INDUSTRY
------------------------1. BANGALORE:
K
2000/05 2006/06 2006/11
5
0
5
37.98
37.98
0
23.57
1.19
23.57
80.00
CSN
500 LINES
7
7
0
BANGALORE
KARNATAKA
2. MANAKPUR:
K
CSN-MM
500 LINES
MANAKPUR
UTTAR PRADESH
2000/05
2006/06
2006/11
5
7
5
7
36.41
36.41
0
0
23.06
23.06
80.00
2002/03
2004/03
24
114
24
114
27.92
27.92
0
0
14.63
3.82
-
0.34
14.97
92.00
2000/02
2002/09
2004/05
20
65
20
65
35.00
35.00
0
0
5.00
-
3.00
3.00
75.00
LINES
125 K
2002/09
2003/04
N.R.
2003/11
N.A.
N.A.
N.A.
N.A.
N.A.
67.53
67.53
0
0
14.26
9.20
23.46
85.00
6. ADDL.GSM.EQ.
PH-II
LINES
125K
2003/06
2003/11
2004/02
3
60
3
60
66.03
66.03
0
0
40.29
35.03
-
2.02
42.31
88.00
2003/07
2004/03
2004/03
0
0
0
0
20.81
20.81
0
0
20.81
-
6.79
6.79
50.00
DELHI
7. EXPANSION
INTERNET
MUMBAI
MAHARASHTRA
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
SECTOR: TELECOMMUNICATION
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DEPARTMENT OF TELECOMMUNICATION
------------------------------8. NRSM SYSTEM
2000/08 2005/12 2005/12
0
12
0
279.97
279.97
0
17.74
131.17
58.88
76.62
IN WPC
0
0
0
DELHI
CENTRE FOR DEVELOPMENT OF TELEMATICS, TELECOM, TECHNOLOGY
--------------------------------------------------------9. CAMP.CONS.
1994/04 1998/08 2004/03
67
C-DOT PROJ.
2002/05 2003/09
129
6
5
80.00
96.74
96.74
21
0
31.72
42.98
-
13.42
45.14
92.00
DELHI
10. CELL & PKT.
VOICE & DATA
2003/03
2005/12
2005/12
0
0
0
0
25.23
25.23
0
0
3.64
-
3.77
3.77
2003/03
2004/12
2004/12
0
0
0
0
33.00
33.00
0
0
9.89
26.14
-
3.27
13.16
2003/03
2006/03
2006/06
3
8
15
3
8
147.00
147.00
0
0
19.62
20.26
-
9.68
29.30
2001/04
2002/12
N.R.
2003/12
N.A.
N.A.
N.A.
N.A.
N.A.
25.40
25.97
2
2
25.01
2.57
-
2.46
27.47
100.00 (COMPLETED)
2001/07
2002/06
N.R.
2003/12
N.A.
N.A.
N.A.
N.A.
N.A.
25.00
27.08
8
8
24.59
3.02
-
3.24
27.83
100.00 (COMPLETED)
DELHI
11. SERVICES FOR
BUSINESS
DELHI
12. 2ND&3RD GEN.
MOBILE COMM.
DELHI
13. IDR-VSAT
DELHI
14. SBM EXCH.
DELHI
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
Project Review
16.1.1
Eleven civil work projects are being implemented by the Central Public Works Department (CPWD) for the different Ministries/Department four projects are being
implemenation by NBCC and one projects is being implemented by Urban Development Ministry. The overall status of projects was as under.
Status of Projects as on 31.03.2004
-------------------------------------------------------WITHIN
WITHIN
TIME
COST
WITH
BUT
BUT
TIME
WITH
WITH
&
TOTAL
WITHIN
COST
TIME
COST
CATNO. OF
TIME &
OVEROVEROVEREGORY
PROJECTS
COST
RUNS
RUNS
RUNS
-------------------------------------------------------1
2
3
4
5
6
-------------------------------------------------------MEGA
1
0
0
0
1
MAJOR
0
0
0
0
0
MEDIUM
16
11
2
2
1
-------------------------------------------------------TOTAL
17
11
2
2
2
-------------------------------------------------------Project Status
The implementation status of each of the projects and the statistical details of cost and time schedules, original, revised and anticipated, are given in the succeeding paras:-
1.
Background
It is a project of the Ministry of Human Resources Development, Department of Cullture. The project was to be taken up in phased manner in 8th and 9th five year plans.
Present Status: Drawings were submitted to Calcutta Corporations (CMC) in 10/93. Go ahead approval for pile foundation and basement was given in 12/94. Foundation
work awarded on 21.1.95. Piles casting work started from 29.5.95. Raft for Block 1,2 and 3 have been cast and structure drawings for block 4 & 7 are under preparation in
CDO. Almost 3000 Sq. m. roof slab for block already cast for block 1,2,3 and 5. Laying of raft foundation is in progress. Pile foundation and basement work completed
under Phase-I. The work for superstructure Part-I completed. A few rebidual work can be completed on completion of elect. Part I main building completed. Deep
tubewell sinking completed. Furniture work done. All works have been physically completed. The project is likely to be completed.
2.
There has been lot of delays in obtaining various approvals from the local bodies.
Delay in awards.
Non-recipt of Architectural & structural drawings from the consultant appointed by IGNOU.
65% of pipe work (3.00 crores out of 38.03 crores spent) Pile foundation is completed. Super structure casting of columns GIF of 2nd floor in progress. G.F. slab casting in
progress 34% of the total project completed.
Reasons for delay
Final and full approval of plans by the local bodies and finalisation of works and drawing of the architect awaited who has again been reminded for the same. Also the
departmental officers are pursuing the matter with C.M.C.
4.
Construction of Residential and non-residential Complex for Income Tax Department at E.M. Bye Pass, Kolkata
Background
(G+10) Storeyed admn. Building, ( G+10) Computer Centre, RTI as Hostel Building.
The Project is of the M/O Finance being executed by the C.P.W.D. Kolkata.
The Project was approved by the Govt. of India in November, 1998 vide M/O Finance letter No. 194/4/94-AD-VIII dated 18.11.98. Its scheduled completion date is
December,2001 and anticipated completion date is 2/2005. Revised cost with date of approval is Rs. 35.12 crores sanctioned vide M/O Finance letter No. F.No. 194/4/94AD.VIII (DT) dated 18.11.98. Anticipated completion cost is yet to be worked out. Cumulative expenditure is 4.23 crores till September,2003. Piling work completed in
Admn. Bldg. Pre qualification for Admn. Bldg. In progress. NIT for pile work at computer centre & RTI under issue in CE office.
Final and full approval of plans by the client Department and finalisation of working drawing by the Department awaited. Architect has been reminded again.
Departmental Officers are pursuing the matter with C.M.C. Foundation work is complete. Tender for pile foundation of car parking in progress. The present progress of
work is 20%.
5.
Construction of Sardar Swarn Singh (SSS) National Institute of Renewable Energy (NIRE), Jallundhar
The project is of M/o Non-convertional Energy Sources and Centre for Architectural System. Altterations, New Delhi. Two main consultant contractors are U.P., Rajkiya
Nir man Nigam. The project was approved in July,2001. Scheduled completion date is June,2004. Approved original cost is Rs.21.53 crore. Anticipated completion cost is
also Rs.21.53 crore. However, the revised cost estimate is Rs.19.89 crore. Work for technical service block, Adm. Block, R & D Block, Common Facilities Block, Trainees
Hostel, Work Shop & Residential Quarters services are in progress. The delay is due to delay in supply of drawings by consultant who are being persuaded. Overall
progress is more than 25%.
6.
Construction of New Office Building for UPSC at Shahjahan Road, New Delhi
The project was approved by the Govt. in October ,2000. The likely date of completion is March,04. The approved cost is Rs.21.02 crore.
Demolition on of concerned old structures completed. Except canteen building excavation 80% vertical water proofing completed. Portion A & B completed. Raft
foundation for block A,B & D completed. Earthwork & water proofing in block A & B completed. Horizontal water profing completed. Basement of roof slab of block A
casted. 60% of basement of Block B casted. Shultering of basement of roof of C block is in progress. 40% of 1st floor of A block casted. Overall progress is 57%.
Superstructure work L-5 level completed & L-6 level in in progress. Superstructure work upto terrace level completed. B.W. flooring also in progress.
CPWD
7.
8.
9.
10.
11.
12.
Construction of Residential Quarters, T-I, T-II, T-III, T-IV at A.G., 9.A. 2 A.D. Bihar
The project was approved by the Government in September,2002 with an original cost of Rs.20.32 crore. The likely date of commissioning is November,2004.
13.
To assist DMRC in the implementation of the project, General consultants comprising a consortium of five international consultancy companies have been appointed and
started functioning w.e.f. 14.9.98. The consortium consists of Pacific Consultants International of Japan (Leader) Parson Brinkerhoff International of USA Japan Railway
Technical Services Tonichi Engineering Consultants of Japan and Rail India technical and Economic Services.
Phase 1 of the MRTS consists of a Rail Corridor of two lines, namely Shahadra Barwala via Tri nagar & Rithala (28 KM) Barahkambha Road to Dwarka (23.16 KM)
approximately half of these lines are elevated and half on the surface and a fully underground Metro Corridor from Vishwa Vidyalaya to Central Secretariat for 11 KM.
Present status
The project was to be implemented in a period of 10 years from 1.4.95 to September, 2005 which is the revised date of commissioning. However, three years delay had
already taken place by the time DMRC started functioning. The implementation schedule was, therefore, recast to complete the whole project in 7 years time, adhering to
the original target of March, 2005 for commissioning of this project.
DMRC has awarded contracts for civil works and power supply & electric traction works of Metro Corridor and system-wide contracts (covering both Metro and Rail
Corridors) for rolling stock, signaling and telecommunication and automatic fare collection system.
Tenders for power supply and electric traction and track work of rail corridor have been finalized and the contractors are mobilizing.
Utilities affected by the aligment of Metro Corridor are being diverted by DMRC and sheet piling & Diaphragm works on Metro Corridor have commenced.
Refurbishment as well as manufacturer of Tunnel Boring Machine is in progress. Metro Corridor will be commissioned in two stages: the first stage from Vishwa Vidalaya
to ISBT (4 Km ) by June, 2004, and the second stage from ISBT to Central Secretariat (7 Km ) by March, 2005.
As for the Rail Corridor, Civil works were started on its first section from Shahdara to Tis hazari (8.3 Km) on 1.10.98. This section has been commissioned in December,
2002. Civil work on 2nd section of Rail Corridor in between Tis Hazari and Tri Nagar completed and commissioned in September,2003.
Tender for viaduct construction between Tri Nagar and Rithala has been awarded. Work of piling, pier, casting & launching of segment is in progress. Contracts for 8
stations on Tri Nagar Rithala Section have also been awarded and piling work has started. Tri Nagar Rithala section is commissioned in March,2004. The remaining
sections of the Rail Corridor will subsequently be commissioned in stages, the last stage being commissioned in September,2005. The cumulative physical progress is
61.5% as in March,2004.
NBCC, M/O Urban Development
14.
15.
16.
17.
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------CENTRAL PUBLIC WORKS DEPARTMENT
------------------------------1. CONST.OF LIB
1989/03 1997/01
N.R.
N.A.
N.A.
N.A.
35.34
77.04
118
46.37
6.68
1.97
48.34
99.00
BHASA BHAWAN
1993/01
2003/06
N.A.
N.A.
41.57
0
KOLKATA
1999/05
77.04
WEST BENGAL
2. IGNOU CAMPUS
AT MAIDAN
GARHI
DELHI
1991/11
1992/10
1996/11
1999/06
N.R.
2003/02
N.A.
N.A.
N.A.
N.A.
N.A.
21.74
23.17
32.30
49
39
31.10
2.02
33.12
100.00
3. CENTRAL
EXCISE BLDG.
KOLKATA
WEST BENGAL
1998/11
2001/12
2005/02
38
103
38
103
25.75
38.03
48
48
11.40
3.07
27.00
1.26
12.66
34.00
4. RESIDENTIAL
COMP.IT DEP.
KOLKATA
WEST BENGAL
1998/11
2001/12
2005/02
2006/12
60
162
22
29
35.12
35.12
0
0
4.23
2.87
4.50
0.11
4.34
13.00
5. CONST.-SSS
NIRE
JULLUNDER
PUNJAB
2001/07
2003/03
2004/06
2004/06
15
75
0
0
21.53
21.53
0
0
2.76
0.36
3.12
22.00
6. CONST.BLDG.
FOR UPSC
2000/10
2004/03
2004/03
0
0
0
0
21.02
21.02
0
0
6.01
6.15
-
3.23
9.24
63.00
1999/01
2003/12
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
23.00
23.00
0
0
3.31
1.55
4.86
67.00
DELHI
7. CONST.OF FSI
AT JNU
NDZ-III
DELHI
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------8. QTR.CONST.
49 FAMILY
2001/05
N.A.
N.A.
N.A.
N.A.
N.A.
26.80
26.80
0
0.74
0.90
1.64
12.00
FOR GC,CRPF
QUARTERS
N.A.
N.A.
0
MUZAFFARPUR
BIHAR
9. CONST.OF NI
OF SIDHHA
CHENNAI
TAMIL NADU
2002/03
N.A.
2004/04
N.A.
N.A.
N.A.
N.A.
20.00
20.00
0
0
0.54
4.11
4.65
37.00
10. CONST. OF
TRADE CENTRE
CHENNAI
TAMIL NADU
2002/06
2003/09
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
25.26
25.26
0
0
2.41
0.88
3.29
57.00
2002/06
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
49.45
N.A.
N.A.
0.54
9.40
-
6.92
7.46
20.00
2002/09
2004/04
2004/04
0
0
0
0
20.32
20.32
0
0
2005/03
2005/09
6
6
6
6
4860.00
10571.00
10571.00
118
0
3743.70
2298.90
-
1556.25
5299.95
56.00
2004/07
0
0
0
0
24.26
24.26
0
0
4.95
12.00
-
3.35
8.30
45.00
DELHI
12. C/O RES.QTR.
TYPE 1 TO IV
PATNA
BIHAR
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------15. CONST.DEVL.
2002/11 2004/11 2004/11
0
0
0
24.68
24.68
0
1.10
12.00
1.96
3.06
20.00
STORM WATER
0
0
0
GUWAHATI
ASSAM
16. FLYOVER CONS
2002/11
2004/11
2004/11
0
0
0
0
24.93
24.93
0
0
0.02
12.00
-
2.39
2.41
9.00
2002/11
2004/11
2004/11
0
0
0
0
20.94
20.94
0
0
10.00
-
4.11
4.11
25.00
IMPHAL
MANIPUR
17. STORM WATER
DRAINAGE SCH
DIMAPUR
NAGALAND
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
There are two projects in water resources on the monitoring system at the end of October-December,2002 this is newly added sector.
Status of Projects as on 31.03.2004
-------------------------------------------------------WITHIN
WITHIN
TIME
COST
WITH
BUT
BUT
TIME
WITH
WITH
&
TOTAL
WITHIN
COST
TIME
COST
CATNO. OF
TIME &
OVEROVEROVEREGORY
PROJECTS
COST
RUNS
RUNS
RUNS
-------------------------------------------------------1
2
3
4
5
6
-------------------------------------------------------MEGA
1
0
1
0
0
MAJOR
1
0
1
0
0
MEDIUM
0
0
0
0
0
-------------------------------------------------------TOTAL
2
0
2
0
0
--------------------------------------------------------
Project Status
The implementation status of each of the project and satistical details of cost and time schedules, original, revised and anticipated are given in the succeeding paras :1.
2.
YEAR
: 2003-2004
QUARTER
: JAN-MAR
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI- 2003-2004 ANNUAL
CUMULATIVE
PHYSICAL
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
--------- EXPENDIEXPENDITURE
PROGRESS
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/2003
B.E.
TURE
(%)
NO. (DISTRICT)
VAL
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
-------------------------------------------------------------------------------------------------------------------------------------------------------------------1. CAE WORKS IN
GANGA BASIN
2001/08
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
159.33
192.00
192.00
21
0
2002/09
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
250.00
1030.00
1030.00
312
0
BI/UP/WB/UCH
2. PAGLADIYES
DAM PROJECT
ASSAM
-------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
APPENDIX-I
LIST OF PROJECTS COMPLETED IN 2003-3004
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
----------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULATIVE
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
-------- EXPENDIEXPENDITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
----------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
----------------------------------------------------------------------------------------------------------------------------------------------------------SECTOR: CIVIL AVIATION
=======
AAI
--1. NEW TERMINAL
1998/05 2002/03
N.R.
N.A.
N.A.
N.A.
79.66
79.66
0
49.40
9.14
4.74
54.14
CHENNAI AIR
2003/03
N.A.
N.A.
0
CHENNAI
TAMIL NADU
SECTOR: COAL
=======
SECL
---2. CHIRIMIRI
0.43
ZERO SEAMRPR MTY
SURGUJA
MADHYA PRADESH
NLC
--3. TPS-I EXP.
NEYELLI
TAMIL NADU
SECTOR: I & B
=======
AIR
--4. REP/INST 3SW
TRSKHAMPUR
DELHI
1998/03
2003/03
2004/03
12
20
12
20
49.21
49.21
0
0
48.96
48.96
420
MW
1996/02
2001/12
2001/03
2002/05
2003/12
33
54
19
25
1590.58
1420.27
1423.47
-11
0
1161.60
124.83
-
24.38
1185.98
NOS.
3X250
1995/02
1998/03
N.R.
2002/12
N.A.
N.A.
N.A.
N.A.
N.A.
42.84
42.84
0
0
28.83
28.83
SECTOR: MINES
=======
NALCO
----5. INST.OF 8TH
MW
2001/02 2004/02 2004/02
0
0
0
480.00
480.00
0
204.15
62.83
266.98
UNIT-CPP
120
0
0
0
ANGUL
ORISSA
----------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
----------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULATIVE
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
-------- EXPENDIEXPENDITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
----------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
----------------------------------------------------------------------------------------------------------------------------------------------------------SECTOR: STEEL
=======
SAIL
---6. BOKARO STEEL
1999/10 2000/12 2003/06
30
2
30
63.23
64.58
2
53.31
2.44
53.31
PLANT RHF-2
214
214
64.58
0
BOKARO
JHARKHAND
7. 100 ATA STEA
MPIPELINES
BOKARO
JHARKHAND
SECTOR: PETROLEUM
=======
BPCL
---8. MUMBAI-MNMAD
POL PLINE
MAH/MP
GAIL
---9. KANDLA-SAMAKHYALI LPG
1997/03
1999/05
2003/11
54
208
54
208
43.97
54.06
23
23
45.14
5.00
-
0.29
45.43
KMS
334
MMTPA
1.4
2001/04
2004/04
N.R.
2003/09
N.A.
N.A.
N.A.
N.A.
N.A.
336.07
336.07
0
0
205.28
100.00
-
30.52
235.80
MMTPA
0.8
2001/02
2002/09
2003/04
7
37
7
37
99.51
99.51
0
0
46.26
46.26
66500 KL
2001/09
2003/05
2003/08
3
15
3
15
76.24
76.24
0
0
57.90
10.00
-
4.10
62.00
TPA
49000
1999/02
2002/11
2003/06
7
16
7
16
419.00
432.00
3
3
386.48
23.00
-
1.27
387.75
GUJARAT
HPCL
---10. MKTG&HOOK UP
B'LORE MBPL
HASSANA
KARNATAKA
IOCL
---11. NEW SOLVENT
DEWAXING
DIGBOI
ASSAM
12. HYDROTREATER
1999/02 2002/05 2004/02
21
4
21
343.00
364.00
6
331.94
6.00
22.21
354.15
DIGBOI REF.
54
54
6
DIGBOI
ASSAM
----------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
----------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULATIVE
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
-------- EXPENDIEXPENDITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
----------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
----------------------------------------------------------------------------------------------------------------------------------------------------------13. AUG.KOYALI2001/08 2003/07 2003/10
3
0
3
119.01
61.50
-48
43.55
36.26
15.18
58.73
VIRAMGAM PL
13
13
-48
15.78
SIDPUR
GUJARAT
14. AUG.VIRANGAM
KOYALI SM
GUJARAT
SECTOR: POWER
=======
NEEPCO
-----15. KOPILI HEP
ST-II
N.C.HILLS
ASSAM
NHPC
---16. CHAMERA H.E.
PROJECT
CHAMBA
HIMACHAL PR.
2001/05
2003/03
2003/07
4
18
4
18
329.05
134.00
-59
-59
108.49
70.00
-
13.66
122.15
MW
25
1999/07
2003/07
2003/12
5
10
5
10
76.09
99.35
31
31
67.67
21.49
-
12.02
79.69
MW
3 X 100
1999/05
2004/05
2004/05
0
0
0
0
1684.02
1684.02
0
0
1606.19
375.91
365.00
293.61
1899.80
1997/08
2000/03
2003/12
45
145
45
145
158.94
249.27
57
57
132.83
89.54
-
0.97
133.80
2000/01
2003/01
2003/06
5
14
5
14
3086.73
2998.32
-3
-3
2642.81
2642.81
MVA
315
2000/04
2002/10
2003/10
12
40
12
40
80.20
86.81
8
8
77.38
8.61
-
4.61
81.99
2000/10
2003/04
2004/01
9
30
9
30
166.51
166.51
0
0
113.95
23.99
21.69
21.46
135.41
CKM
70
2002/05
2004/05
2003/06
-11
-46
-11
-11
-46
49.49
49.49
0
0
28.72
14.76
-
3.42
32.14
P.GRID
-----17. LD&C SCHEME
IN NER
NER
18. TALCHER-II
TRNS.SYSTEM
EASTERN REG.
19. 400/220 KV
PURNEA
BIHAR
20. MEMRAMUNDALI
-JEYPORE D/C
ORISSA
21. CHAMERA-II
TRANS.400 KV
HIMACHAL PR.
----------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
----------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULATIVE
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
-------- EXPENDIEXPENDITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
----------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
----------------------------------------------------------------------------------------------------------------------------------------------------------SECTOR: RAILWAYS
=======
B&S
--22. J'PETTAI B'L
1992/04 2001/03 2003/05
26
0
26
41.96
41.96
0
9.10
32.86
41.96
ORE NEW ROB
24
24
0
SR
KARNATAKA
LD
-23. KORBA-SARAGBUNDIA,
SECR
MP,OR
KMS
15
1996/04
1998/12
2003/06
54
169
54
169
27.45
40.30
47
47
27.20
27.20
KMS
20.65
1994/08
1998/03
2003/09
66
153
66
153
21.78
23.73
29.81
37
26
30.85
30.85
25. GHAZIABADKMS
MORADABAD -I 36.97
NR
UTTAR PRADESH
1995/04
1998/06
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
30.00
43.64
65.81
119
51
65.29
0.10
-
0.02
65.31
1987/03
1990/04
1994/03
1996/03
2004/03
120
143
96
89
40.90
39.16
100.89
100.89
147
0
84.08
7.00
-
9.95
94.03
27. KATRAKMS
FAIZABAD,NER 8.70
UTTAR PRADESH
1994/04
2003/03
2003/05
2
2
2
2
51.26
80.72
95.57
86
18
85.95
3.00
-
4.55
90.50
1995/04
2003/03
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
10.19
20.19
23.80
134
18
23.59
8.73
32.32
NL
-26. LAKSHMIKANTA
PUR-NAMKH,ER
KMS
48
WEST BENGAL
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
----------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULATIVE
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
-------- EXPENDIEXPENDITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
----------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
----------------------------------------------------------------------------------------------------------------------------------------------------------30. NAS'BAD-G'PU KM.
2000/04 2004/05 2004/01
-4
0
-4
182.09
182.09
0
77.99
151.90
55.01
133.00
RA GQ
15-70
-8
-8
0
RAJASTHAN
31. CHI'GARH-M'W
AR GQ
KM.
220-172
2000/04
2004/05
2004/01
-4
-8
-4
-8
161.20
161.20
0
0
54.85
86.82
-
60.15
115.00
KM.
8
2000/04
2002/06
N.R.
2003/12
N.A.
N.A.
N.A.
N.A.
N.A.
54.87
54.87
0
0
52.05
7.45
-
7.79
59.84
KM.
278-340
2000/04
2004/04
2004/02
-2
-4
-2
-4
245.91
245.91
0
0
100.60
98.51
-
101.50
202.10
KM.
388-443
2000/04
2004/05
2003/12
-5
-10
-5
-10
182.29
182.29
0
0
84.14
94.84
-
46.46
130.60
KM.
343-382
2000/04
2003/04
2004/01
9
25
9
25
174.59
174.59
0
0
146.20
60.00
-
64.10
210.30
KM.
382-439
2000/04
2003/10
2003/10
0
0
0
0
192.71
192.71
0
0
198.60
65.00
-
40.20
238.80
KM.
0-34
2000/04
2002/08
2003/10
14
50
14
50
109.38
109.38
0
0
140.00
39.68
-
11.60
151.60
KM.
797-760
2000/04
2004/04
2003/12
-4
-8
-4
-8
118.93
118.93
0
0
51.27
35.23
-
27.27
78.54
KM.
760-725
2000/04
2003/12
2003/12
0
0
0
0
139.00
139.00
0
0
71.01
32.51
-
41.09
112.10
RAJASTHAN
32. GHATIBYPASS
K156-164EWI
ASSAM
33. UDAIPUR-K'RI
AJI GQ
RAJASTHAN
34. R'PUR-HIMTNG
R GQ
GUJARAT
35. ATUL-KAIJALI
GQ
GUJARAT
36. KAIJALI-MANO
R GQ
MAHARASHTRA
37. WEST DIVERSN
GQ
MAHARASHTRA
38. SAROLE-WATHE
R GQ
MAHARASHTRA
39. WATHER-SATAR
A GQ
MAHARASHTRA
----------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
----------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULATIVE
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
-------- EXPENDIEXPENDITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
----------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
----------------------------------------------------------------------------------------------------------------------------------------------------------40. TUMKUR-N'MAN KM.
2000/04 2003/12 2003/12
0
0
0
155.00
155.00
0
114.40
14.00
79.00
193.40
GAL GQ
62-30
0
0
0
KARNATAKA
41. HOSUR-K'GIRI
GQ
KM.
49-94
2000/04
2004/06
2004/01
-5
-10
-5
-10
213.00
213.00
0
0
95.86
143.60
-
51.54
147.40
KM.
106-70
2000/04
2004/03
2004/01
-2
-4
-2
-4
130.00
130.00
0
0
56.72
75.96
-
44.98
101.70
KM.
165-80
2000/04
2004/02
2004/01
-1
-2
-1
-2
323.35
323.35
0
0
231.30
88.27
-
73.00
304.30
2000/04
2003/12
2003/12
0
0
0
0
621.35
621.35
0
0
456.10
33.35
-
157.60
613.70
2000/04
2004/02
2003/08
-6
-13
-6
-13
11.00
71.00
545
545
42.87
34.45
-
28.13
71.00
1996/02
2000/02
N.R.
2003/03
N.A.
N.A.
N.A.
N.A.
N.A.
25.12
25.12
0
0
16.62
16.62
1999/07
2002/01
2003/05
16
53
16
53
236.50
135.00
-43
-43
126.94
126.94
TAMIL NADU
42. W'PET-K'PURA
M GQ
TAMIL NADU
43. G'TAMI-G'GOL
ANU GQ
ANDHRA PRADESH
44. NELLORE-TADA
(GQ)
KM.
164-53
ANDHRA PRADESH
45. BR.CH'WATI-S
'KULAMK49-97
KM.
49
ANDHRA PRADESH
SECTOR: SHIPPING & PORTS
=======
PORTS
----46. CONS.OF 4TH
LAKH
OIL JETTY
20
KANDLA
GUJARAT
47. MRPL REF.
EXPN
MANGALORE
KARNATAKA
MTPA
7.90
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
----------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULATIVE
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
-------- EXPENDIEXPENDITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
----------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
----------------------------------------------------------------------------------------------------------------------------------------------------------49. REPL.-BARGE
M
1998/08 2000/10 2004/10
48
9
48
40.00
40.00
0
17.72
10.50
12.02
29.74
UNLOADERS
750T
185
185
0
11.40
MURMUGAO
GOA
50. CONST.MULTI
LIQ BULKJETY
NEWM'LORE
KARNATAKA
MTPA
3.79
1998/05
2000/11
2003/04
29
97
29
97
31.00
26.00
-16
-16
24.80
0.90
-
24.80
51. MODERN. OF
WQ& NQ BERTH
CHENNAI
TAMIL NADU
0.80+1.75
MT
1997/08
2002/10
N.R.
2002/12
N.A.
N.A.
N.A.
N.A.
N.A.
47.50
47.50
0
0
31.61
31.61
110000*4
2000/05
DWT
CRUDE OIL
CARRIERS
2003/08
2003/08
0
0
0
0
672.28
629.38
628.09
-7
0
400.48
207.01
-
236.18
636.66
2000/03
2001/02
N.R.
2002/03
N.A.
N.A.
N.A.
N.A.
N.A.
63.24
63.24
0
0
55.36
0.91
56.27
2000/03
2001/02
N.R.
2002/10
N.A.
N.A.
N.A.
N.A.
N.A.
63.24
64.00
1
1
55.87
55.87
1998/07
2001/07
1999/07
2001/07
N.R.
2003/06
N.A.
N.A.
N.A.
N.A.
N.A.
10.50
25.00
27.08
158
8
27.83
27.83
2000/04
2001/04
2000/10
2002/12
N.R.
2003/07
N.A.
N.A.
N.A.
N.A.
N.A.
19.44
25.40
25.97
34
2
27.47
27.47
2001/04
2002/12
N.R.
2003/12
N.A.
N.A.
N.A.
N.A.
N.A.
25.40
25.97
2
2
25.01
2.57
-
2.46
27.47
SHIPP.
-----52. ACQ.OF4-DWT
110000 COC
MUMBAI
MAHARASHTRA
SECTOR: TELECOMMUNICATION
=======
MTNL
---53. GSM CELLULAR K
MOBILE
100 LINES
MUMBAI
MAHARASHTRA
54. GSM CELLULAR
MOBILE
DELHI
DELHI
C-DOT
----55. SBM EXCH.
K
100 LINES
C-DOT PROJ.
56. IDR-VSAT
C-DOT PROJ.
57. IDR-VSAT
DELHI
----------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
----------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULATIVE
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
-------- EXPENDIEXPENDITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
----------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
----------------------------------------------------------------------------------------------------------------------------------------------------------58. SBM EXCH.
2001/07 2002/06
N.R.
N.A.
N.A.
N.A.
25.00
27.08
8
24.59
3.02
3.24
27.83
2003/12
N.A.
N.A.
8
DELHI
SECTOR: URBAN DEVELOPMENT
=======
CPWD
---59. SPG PROJECT
1995/07
1998/07
N.R.
2003/05
N.A.
N.A.
N.A.
N.A.
N.A.
98.88
105.00
6
6
103.71
103.71
P.KALLAN
DELHI
----------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
APPENDIX-II
PROJECTS COSTING RS. 20 CRORES AND ABOVE DUE FOR COMMISSIONING DURING 2003-04
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------STATUS AS ON
--------------------------------------------------------------------30.06.2003
30.9.2003
31.12.2003
31.03.2004
SR. NAME OF THE PROJECT
AGENCY ORIGINAL LATEST
NOW ANTI- ORI- LATEST
NOW ANTI- --------------- ----------------- ----------------- ----------------NO.
APPROVED CIPATED
GINAL APPROVED CIPATED
DOC
COST
DOC
COST
DOC
COST
DOC
COST REMARKS
------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
UCIL
61.07
61.07
61.07
N.A.
AAI
24.03
24.03
28.87 2004/01
BCCL
199.87
199.87
CCL
46.78
46.78
CCL
110.89
SECL
N.A.
61.07
28.87 2004/03
28.87 2004/03
28.87
182.60 2004/03
182.60 2004/03
182.60 2004/03
182.60
46.78 2005/03
46.78 2005/03
46.78 2005/03
46.78
110.89
110.89 2004/03
110.89 2004/03
110.89 2004/03
110.89
49.93
49.93
49.93 2004/03
49.93 2004/03
49.93 2004/03
49.93
SECL
49.21
49.21
49.21
SECL
49.90
49.90
49.90 2004/03
49.90 2004/03
49.90 2004/03
49.90
SECL
26.30
26.30
26.30 2004/03
26.30 2004/03
29.91 2004/03
29.91
SECL
26.30
26.30
26.30 2004/03
26.30 2004/03
26.30 2004/03
26.30
SECL
23.92
23.92
23.92 2004/03
23.92 2004/03
23.92 2004/03
23.92
ECL
95.28
95.28
53.42 2004/03
54.15 2004/03
54.15 2004/03
54.15
NCL
868.93
1281.39
1281.39 2004/03
1281.39 2004/03
1281.39 2004/03
1281.39
NCL
1846.49
1846.49
1846.49 2004/03
1846.49 2004/03
1846.49 2004/03
1846.49
MCL
92.11
92.11
92.11 2004/01
92.11 2004/01
92.11 2004/01
92.11
WCL
46.17
46.17
46.17 2004/03
46.17 2004/03
46.17 2004/03
46.17
NLC
1590.58
1420.27
1423.47 2003/12
SCCL
27.05
27.05
27.05 2004/03
27.05 2004/03
27.05 2004/03
27.05
SCCL
39.14
25.84
25.84 2004/03
25.84 2004/03
25.84 2004/03
25.84
SCCL
21.95
21.95
21.95 2005/03
21.95 2005/03
21.95 2005/03
21.95
SCCL
49.51
49.51
49.51 2004/03
49.51 2004/03
49.51 2004/03
49.51
SCCL
40.19
40.19
40.19 2004/03
40.19 2004/03
40.19 2004/03
40.19
N.A.
61.07
N.A.
1423.47
N.A.
N.A.
N.A.
61.07
N.A.
N.A.
N.A.
N.A.
N.A. COMPLETED
N.A. COMPLETED
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------STATUS AS ON
--------------------------------------------------------------------30.06.2003
30.9.2003
31.12.2003
31.03.2004
SR. NAME OF THE PROJECT
AGENCY ORIGINAL LATEST
NOW ANTI- ORI- LATEST
NOW ANTI- --------------- ----------------- ----------------- ----------------NO.
APPROVED CIPATED
GINAL APPROVED CIPATED
DOC
COST
DOC
COST
DOC
COST
DOC
COST REMARKS
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------SECTOR: FERTILISERS
-----23. NAMRUP PLANT REVAMP
BVFC
350.00
509.40
509.40 2001/05 2001/05 2003/12 2004/02
509.40 2004/02
509.40 2004/05
509.40 2004/05
509.40
NAMRUP, ASSAM
SECTOR: I & B
-----24. D.D.BH.DELHIIC/CB PPFVAN
DELHI
SECTOR: MINES
-----25. SPL.GRADE
ALUMINA
ANGUL, ORISSA
26. INST.OF 8TH UNIT-CPP
ANGUL, ORISSA
SECTOR: STEEL
-----27. BOKARO STEEL PLANT RHF-2
BOKARO, JHARKHAND
28. 100 ATA STEAMPIPELINES
BOKARO, JHARKHAND
29. UPGRADATION ERW PPEPLANT
ROURKELA, ORISSA
D.D.
34.15
81.60
81.60 2003/12
81.60 2004/06
81.60 2004/06
81.60
NALCO
56.78
56.78
56.78 2004/03
56.78 2004/03
56.78 2004/04
56.78
NALCO
480.00
480.00
480.00 2003/12
480.00 2004/02
480.00 2004/02
SAIL
63.23
64.58
64.58
SAIL
43.97
43.97
SAIL
89.15
89.15
490.65
SECTOR: PETROLEUM
-----30. VISAKH-SECN-DERABAD LPG
GAIL
SECNDERABAD, ANDHRA PRADESH
31. MKTG&HOOK UP B'LORE MBPL HPCL
HASSANA, KARNATAKA
32. NEW SOLVENT DEWAXING
IOCL
DIGBOI, ASSAM
33. HYDROTREATER DIGBOI REF. IOCL
DIGBOI, ASSAM
34. AUG.KOYALI- VIRAMGAM PL
IOCL
SIDPUR, GUJARAT
35. AUG.VIRANGAM KOYALI SM
IOCL
GUJARAT
36. IOR GANDHAR
ONGCL
BHARUCH, GUJARAT
37. IOR SCHEME
NEELEM
ONGCL
38. IOR SCHEME NORTH KADI
KARKADI, GUJARAT
39. IOR LAKWA- LAKHMANI
ASSAM
40. REFIN.EXPN. CUM.MOD.
MANALI, TAMIL NADU
SECTOR: POWER
-----41. KOPILI HEP ST-II
N.C.HILLS, ASSAM
42. DULHASTI HEP
DODA, J & K
43. TEHRI DAM
H.P.P.
TEHRI, UTTARANCHAL
44. NATHPA JHKRI H.E.P.
KINNAUR, HIMACHAL PR.
N.A.
N.A.
480.00 COMPLETED
N.A.
N.A.
N.A.
N.A. COMPLETED
54.06 2003/11
54.06 2003/11
54.06
N.A.
N.A. COMPLETED
89.15 2004/03
89.15 2004/03
89.15 2005/05
89.15
490.65
490.66 2003/10
457.77 2004/02
463.26 2004/04
463.26
76.24
76.24
76.24 2003/08
419.00
419.00
432.00
343.00
343.00
119.01
119.01
329.05
76.24
N.A.
N.A.
N.A.
N.A. COMPLETED
N.A.
N.A.
N.A.
N.A.
N.A. COMPLETED
363.00 2003/10
364.00 2004/02
364.00
N.A.
N.A. COMPLETED
81.02 2003/10
61.00 2003/10
61.50
N.A.
N.A. COMPLETED
329.05
134.00 2003/07
134.00
N.A.
N.A.
N.A. COMPLETED
609.44
609.44
692.45 2004/03
692.45 2004/03
692.45 2004/12
692.45
347.69
347.69
347.69 2003/11
347.69 2004/10
347.69 2004/10
347.69
ONGCL
62.86
62.86
62.86 2003/12
62.86 2003/12
ONGCL
345.10
345.10
345.10 2007/03
CPCL
2360.38
2360.38
76.09
76.09
NHPC
183.45
THDCL
SJVNL
NEEPCO
N.A.
N.A.
62.86
N.A.
62.86
345.10 2004/03
345.10 2007/03
345.10
2360.38 2004/01
2360.38 2004/01
2360.38 2004/06
2360.38
99.35 2003/11
99.35 2003/12
3559.77
4227.92 2003/12
4227.92 2004/07
4227.63 2004/11
4227.92
2963.66
2963.66
5209.10 2003/12
5209.10 2004/03
5209.10 2004/03
5209.10
1678.02
7666.31
8656.61 2004/07
8656.61 2004/07
8656.61 2004/07
8656.61
99.35
N.A.
N.A. COMPLETED
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------STATUS AS ON
--------------------------------------------------------------------30.06.2003
30.9.2003
31.12.2003
31.03.2004
SR. NAME OF THE PROJECT
AGENCY ORIGINAL LATEST
NOW ANTI- ORI- LATEST
NOW ANTI- --------------- ----------------- ----------------- ----------------NO.
APPROVED CIPATED
GINAL APPROVED CIPATED
DOC
COST
DOC
COST
DOC
COST
DOC
COST REMARKS
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------45. LD&C SCHEME IN NER
P.GRID
158.94
158.94
249.27 2000/03 2002/03 2003/12 2003/12
249.27
N.A.
N.A.
N.A.
N.A.
N.A.
N.A. COMPLETED
NER
46. TEHRI TR.
SYSTEM
P.GRID
421.00
702.97
702.97 1999/03 1999/03 2003/09 2004/03
702.29 2004/03
702.29 2004/12
702.29 2004/12
721.62
TEHRI, DELHI/UA
47. TALCHER-II TRNS.SYSTEM
P.GRID
3086.73
3086.73
2998.32 2003/01 2002/12 2003/06 2003/06
2998.32
N.A.
N.A.
N.A.
N.A.
N.A.
N.A. COMPLETED
EASTERN REG.
48. 400/220 KV
P.GRID
80.20
80.20
86.81 2002/10 2002/10 2003/06 2003/07
86.81 2003/09
86.81 2003/10
86.81
N.A.
N.A. COMPLETED
PURNEA, BIHAR
49. MEMRAMUNDALI-JEYPORE D/C P.GRID
166.51
166.51
143.02 2003/04 2003/04 2003/05 2003/07
143.02 2003/10
143.02 2004/01
166.51 2004/01
166.51 COMPLETED
ORISSA
50. MADURI-THIRU VANANTHAPUR P.GRID
195.97
195.97
195.97 2003/10 2003/10 2004/02 2004/03
195.97 2004/02
195.97 2004/02
207.15 2004/09
207.15
TN/KERALA
51. TR.SYSTEM
STRNGTHENING P.GRID
162.88
162.88
162.88 2004/02 2004/02 2004/01 2004/01
162.88 2004/01
162.88 2004/03
162.88 2004/06
162.88
BIHAR, BIHAR
52. RANAGADI-0 TR. 132 KV
P.GRID
27.25
27.25
27.25 2003/08 2003/08 2003/08 2003/11
27.25 2004/01
27.25 2004/03
27.25 2004/03
27.25
ARUNACHAL PR.
SECTOR: RAILWAYS
-----53. KUPPAMWHITEFIELD
SWR, KR/AP
54. CALICUTMANGALORE,SR
KE/KR
55. V'WADA-KRIS-HNA 3RD LINE
SCR, ANDHRA PRADESH
56. GUDUR-RENI- GUNTA,SCR
TIRUPATI, ANDHRA PRADESH
57. KENGERRI RAMANAGARAM
SWR, KARNATAKA
58. VIRAMGAMBHILDI,WR
GUJ/RAJ
59. GONDIA-JABA-LPUR,SECR
MP,MAH
60. SURENDRANGR BHAVANAGAR
WR, GUJARAT
61. KANPUR-K'GNJ-MATHURA,NER
UTTAR PRADESH
62. LUNI-BARMER-MUNABAO,NWR
RAJASTHAN
63. B'PUR-S'WOOD-URAN ELEC.
MUMBAI, MAHARASHTRA
64. TRU-VELLACH-ERI,MRTS EXT
CHENNAI, TAMIL NADU
65. ELEC.BARASAT-HASNABAD
KOLKATTA, WEST BENGAL
66. BORIVILIVIRAR,WR
MUMBAI, MAHARASHTRA
67. JAMMU TAWI- UDHAMPUR,NR
J & K
68. NANGALDAM- TALWARA,NR
PB/HP
69. LAKSHMIKANTAPUR-NAMKH,ER
WEST BENGAL
70. KATRAFAIZABAD,NER
UTTAR PRADESH
71. PANVELKARJAT,CR
MUMBAI, MAHARASHTRA
72. HASSAN-BANG-LORE-S'B'GOL
SWR, KARNATAKA
73. KHARAGPUR- BHUBANESWAR
OR/WB
LD
108.11
105.01
137.49 2004/03
137.49 2004/03
137.49
N.A.
137.49
LD
240.00
459.55
563.08
563.08 2004/03
563.08
N.A.
563.08
LD
23.52
23.52
41.86 2003/07
N.A.
41.86
N.A.
41.86
LD
139.69
139.69
133.33 2004/03
157.34 2004/03
157.34
N.A.
167.43
LD
45.00
58.85
58.85 2004/02
58.85 2004/02
58.85 2004/02
58.85
GC
155.66
119.75
119.75 2004/06
119.75
GC
356.00
356.00
511.86 2003/12
511.86 2003/12
511.86
N.A.
511.86
GC
437.40
437.40
522.64 2004/03
528.49 2004/03
528.49
N.A.
528.49
GC
395.00
658.11
598.98
N.A.
658.11 2004/03
658.11 2004/03
658.11
N.A.
658.11
GC
240.00
240.00
283.94
N.A.
283.94
N.A.
283.94 2004/03
283.94 2004/03
283.94
MTP
401.81
401.81
495.44
N.A.
495.44
495.44
N.A.
495.44
MTP
605.70
605.70
691.04 2003/09
691.04 2004/03
691.04 2005/03
691.04
MTP
37.70
37.70
37.70 2003/12
37.70 2003/12
37.70 2004/06
37.70
MTP
325.47
401.66
N.A.
401.70 2005/05
383.94
N.A.
383.94 2005/03
383.94
NL
50.00
407.74
479.00 2004/03
479.00 2004/03
515.00 2004/04
510.00
NL
37.68
150.00
210.00 2004/03
210.00 2008/03
210.00 2008/03
210.00
NL
40.90
100.89
100.89 2004/03
100.89 2004/03
100.89 2004/03
100.89 COMPLETED
NL
51.26
80.72
NL
89.00
106.89
NL
295.00
295.00
RE
258.58
304.33
58.85
N.A.
119.75
95.57
N.A.
N.A.
N.A.
41.86
119.75
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A. COMPLETED
137.44 2004/03
137.44 2004/03
137.44
N.A.
137.44
412.91 2004/03
412.91 2004/03
412.91
N.A.
412.91
402.17 2004/03
402.17 2004/03
402.17 2004/12
402.17
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------STATUS AS ON
--------------------------------------------------------------------30.06.2003
30.9.2003
31.12.2003
31.03.2004
SR. NAME OF THE PROJECT
AGENCY ORIGINAL LATEST
NOW ANTI- ORI- LATEST
NOW ANTI- --------------- ----------------- ----------------- ----------------NO.
APPROVED CIPATED
GINAL APPROVED CIPATED
DOC
COST
DOC
COST
DOC
COST
DOC
COST REMARKS
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------74. LUDHIANA- AMRITSAR(NR)
RE
78.80
98.19
98.19 2001/11 2001/11 2004/03 2004/03
98.19 2004/03
98.19 2004/03
98.19
N.A.
98.19
LUDHIANA, PUNJAB
75. KURLA PSR. TRM.FAC.PH2S TF
34.94
34.94
39.44 1999/12 2003/02 2003/06 2003/06
39.44
N.A.
39.44
N.A.
39.44
N.A.
39.44
CR, MAHARASHTRA
76. 60LOCO DIES-EL SHED
WS&PU
23.30
23.30
39.89 1995/03 1995/03 2003/09 2003/09
39.89 2003/09
39.89
N.A.
39.89
N.A.
39.89
ANGUL,SER, ORISSA
77. CLW-MFR.OF HIGH HP ABB
WS&PU
29.82
29.82
39.91 1999/06 2003/09 2004/03 2004/03
39.91 2005/03
39.91 2005/03
39.91 2005/03
39.91
LOCOS,ER, WEST BENGAL
78. KAZIPET-ELECLOCOSHED,SCR WS&PU
23.00
29.27
25.20 2000/03 2003/03 2004/03 2004/03
25.20 2004/03
25.20 2004/03
25.20
N.A.
25.20
ANDHRA PRADESH
79. LUDHIANAELEC.LOCOSHE WS&PU
20.00
24.35
24.35 2000/03 2003/03 2004/03 2005/03
24.35 2005/03
24.35 2005/03
24.35 2005/03
24.35
NR, PUNJAB
80. CLW-ELEC.
LOCO.AUG.,ER WS&PU
25.84
25.84
18.19 2002/03 2003/03 2004/03 2004/03
18.19 2004/03
18.19 2004/03
18.19 2004/03
18.19
WEST BENGAL
81. DLW-4000HP:IDIESEL LOCOS WS&PU
37.44
43.27
43.27 2001/03 2001/03 2004/03 2004/03
43.27 2005/03
43.27 2005/03
43.27 2005/03
43.27
NR:VARANASI, UTTAR PRADESH
82. SETTINGUP OFEL.LOCO SHED WS&PU
22.36
22.36
22.36 2001/03 2004/03 2004/03 2004/03
22.36 2005/12
22.36 2005/12
22.36 2005/12
22.36
BOKARO,ER, JHARKHAND
83. CONST.OF 50 LOCO SHEDS
WS&PU
15.26
15.26
22.26 2003/03 2004/03 2004/03 2004/03
22.26 2004/03
22.26 2004/03
22.26 2004/03
22.26
HUBLI,SR, KARNATAKA
84. ICF-PAINTING FACILITIES
WS&PU
26.55
26.55
26.05 2003/12 2003/12 2003/12 2003/12
26.05 2003/12
26.05 2003/12
26.05
N.A.
26.05
PERAMBUR, TAMIL NADU
85. CCG-VR TRAIN DESCRIBER
S&T
9.79
33.75
35.52 2000/09 2000/09 2003/06 2004/03
35.52 2004/03
33.37 2004/03
33.37 2004/03
33.37
MUMBAI, MAHARASHTRA
SECTOR: ROAD TRANSPORT & HIGHWAYS
-----86. J'PURBYPASS PH2 GQ
NHAI
RAJASTHAN
87. LKO-K'PUR KM21.8-44 EWII NHAI
UTTAR PRADESH
88. J'DHAR-P'KOT K4-26 NSII
NHAI
HARYANA
89. K'GARH-NAS'BAD GQ
NHAI
RAJASTHAN
90. N'GAMA-V'WADA OTHER NH9
NHAI
ANDHRA PRADESH
91. JDHARBYPASS K372-387NSI
NHAI
PUNJAB
92. 8LANEDLH'YANAK17-9NSII
NHAI
DELHI
93. NAS'BAD-G'PURA GQ
NHAI
RAJASTHAN
94. 8-LANENHIDELHI K8-16NSI
NHAI
DELHI
95. G'PURA-BH'WARA GQ
NHAI
RAJASTHAN
96. P'NEA-G'KOTAK410-419EWI
NHAI
BIHAR
97. GUHA.BYPASS K146-157EWII NHAI
ASSAM
98. DHOLPUR-SEC.K-24-41 NSII NHAI
U.P./RAJ.
99. B'WARA-CHI'GARH GQ
NHAI
RAJASTHAN
100. DKHOLA-I'PUR K447-470EWI NHAI
WEST BENGAL
101. AGRA-G'LIOR K70-85 NSII
NHAI
MADHYA PRADESH
102. CHI'GARH-M'WAR GQ
NHAI
RAJASTHAN
210.00
210.00
210.00 2003/12
210.00 2004/03
210.00 2004/10
210.00
94.91
94.91
94.91 2004/03
94.91 2004/06
94.91 2004/06
94.91
71.18
71.18
71.18 2003/12
71.18 2004/03
71.18 2004/03
71.18
113.50
113.50
113.50 2003/12
113.50 2004/01
113.50 2004/01
113.50 COMPLETED
138.65
138.65
138.65 2003/12
138.65 2004/02
138.65 2004/04
138.65
54.09
54.09
63.46 2003/10
63.46 2004/04
63.46 2004/04
63.46
71.00
71.00
71.00 2004/02
71.00 2004/09
71.00 2004/09
71.00
182.09
182.09
182.09 2003/12
182.09 2004/01
182.09 2004/01
57.53
57.53
57.53 2004/11
57.53 2004/11
57.53 2004/11
57.53
164.25
164.25
164.25 2003/12
164.25 2004/02
164.25 2004/04
164.25
62.98
62.98
62.98 2004/03
62.98 2004/12
62.98 2004/12
62.98
63.69
63.69
63.69 2004/03
63.69 2004/06
63.69 2004/06
63.69
76.00
76.00
76.00 2003/11
76.00 2004/03
76.00 2004/03
76.00
202.88
202.88
202.88 2003/12
202.88 2004/02
202.88 2004/04
202.88
72.56
72.56
72.56 2003/12
72.56 2004/03
72.56 2004/03
72.56
49.00
49.00
49.00 2003/12
49.00 2004/02
49.00 2004/03
49.00
161.20
161.20
161.20 2003/12
161.20 2004/01
161.20 2004/01
182.09 COMPLETED
161.20 COMPLETED
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------STATUS AS ON
--------------------------------------------------------------------30.06.2003
30.9.2003
31.12.2003
31.03.2004
SR. NAME OF THE PROJECT
AGENCY ORIGINAL LATEST
NOW ANTI- ORI- LATEST
NOW ANTI- --------------- ----------------- ----------------- ----------------NO.
APPROVED CIPATED
GINAL APPROVED CIPATED
DOC
COST
DOC
COST
DOC
COST
DOC
COST REMARKS
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------103. DKHOLA-I'PUR K476-500EWI NHAI
90.06
90.06
90.06 2002/12 2002/12 2003/06 2004/03
90.06 2004/03
90.06 2004/12
90.06 2004/12
90.06
WEST BENGAL
104. AGRA-G'LIORK-85-103NSII
NHAI
69.50
69.50
69.50
N.A.
N.A. 2003/06 2003/12
69.50 2003/12
69.50 2004/05
69.50 2004/06
69.50
MADHYA PRADESH
105. M'WAR-UDAIPUR GQ
NHAI
170.00
170.00
170.00 2004/05 2004/05 2003/12 2003/12
170.00 2003/12
170.00 2004/03
170.00 2004/04
170.00
RAJASTHAN
106. GHATIBYPASS K156-164EWI
NHAI
54.87
54.87
54.87 2002/06 2002/06 2003/05 2003/12
54.87 2003/12
54.87 2003/12
54.87
N.A.
54.87 COMPLETED
ASSAM
107. N'PUR-HYD.K464-74 NSII
NHAI
88.00
88.00
88.00 2003/11 2003/11 2003/11 2003/11
88.00 2003/11
88.00 2004/07
88.00 2004/07
88.00
ANDHRA PRADESH
108. UDAIPUR-K'RIAJI GQ
NHAI
245.91
245.91
245.91 2004/04 2004/04 2003/12 2003/12
245.91 2003/12
245.91 2004/02
245.91 2004/02
245.91 COMPLETED
RAJASTHAN
109. BLR-MADURAIK180-199NSII
NHAI
82.49
82.49
82.49 2003/08 2003/08 2003/08 2003/08
82.49 2004/03
82.49 2004/10
82.49 2004/10
82.49
TAMIL NADU
110. K'RIAJI-RTNPUR GQ
NHAI
226.05
226.05
226.05 2004/04 2004/04 2003/12 2003/12
226.05 2003/12
226.05 2004/03
226.05 2004/07
226.05
RAJASTHAN
111. BL'ORE-SALEM MADURAI
NHAI
21.40
21.40
21.40 2002/11 2002/11 2003/12 2003/12
21.40 2003/12
21.40 2004/01
21.40 2004/03
21.40
K248-260 NS, TAMIL NADU
112. R'PUR-HIMTNGR GQ
NHAI
182.29
182.29
182.29 2004/05 2004/05 2003/12 2003/12
182.29 2003/12
182.29 2003/12
182.29
N.A.
N.A. COMPLETED
GUJARAT
113. ALUVA-A'MALIK333-16 NSII NHAI
77.38
77.38
77.38 2003/08 2003/08 2003/08 2003/08
77.38 2004/05
77.38 2004/04
77.38 2004/04
77.38
KERALA
114. HYD-B'LORE NS-II
NHAI
172.06
172.06
172.06 2004/03 2004/03 2004/03 2004/03
172.06 2004/03
172.06 2004/12
172.06 2004/12
172.06
KARNATAKA
115. LKO-K'PUR KM44-59.5 EW 9 NHAI
50.02
50.02
50.02 2003/05 2003/05 2003/09 2004/03
50.02 2004/03
50.02 2004/06
50.02 2004/06
50.02
UTTAR PRADESH
116. ATUL-KAIJALI GQ
NHAI
174.59
174.59
174.59 2003/04 2003/04 2003/12 2003/12
174.59 2003/12
174.59 2004/01
174.59 2004/01
174.59 COMPLETED
GUJARAT
117. KAIJALI-MANOR GQ
NHAI
192.71
192.71
192.71 2003/10 2003/10 2003/10 2003/07
192.71 2003/10
192.71 2003/10
192.71
N.A.
N.A. COMPLETED
MAHARASHTRA
118. WEST DIVERSN GQ
NHAI
109.38
109.38
109.38 2002/08 2002/08 2003/08 2003/08
109.38 2003/10
109.38 2003/10
109.38
N.A.
N.A. COMPLETED
MAHARASHTRA
119. SAROLE-WATHER GQ
NHAI
118.93
118.93
118.93 2004/04 2004/04 2003/12 2003/12
118.93 2003/12
118.93 2003/12
118.93
N.A.
N.A. COMPLETED
MAHARASHTRA
120. WATHER-SATARA GQ
NHAI
139.00
139.00
139.00 2003/12 2003/12 2003/12 2003/12
139.00 2003/12
139.00 2003/12
139.00
N.A.
N.A. COMPLETED
MAHARASHTRA
121. TUMKUR-N'MANGAL GQ
NHAI
155.00
155.00
155.00 2003/12 2003/12 2003/12 2003/12
155.00 2003/12
155.00 2003/12
155.00
N.A.
N.A. COMPLETED
KARNATAKA
122. HOSUR-K'GIRI GQ
NHAI
213.00
213.00
213.00 2004/06 2004/06 2003/12 2003/12
213.00 2003/12
213.00 2004/01
213.00 2004/01
213.00 COMPLETED
TAMIL NADU
123. W'PET-K'PURAM GQ
NHAI
130.00
130.00
130.00 2004/03 2004/03 2003/12 2003/12
130.00 2003/12
130.00 2004/01
130.00 2004/01
130.00 COMPLETED
TAMIL NADU
124. BH'WAR-KHURDA GQ
NHAI
140.85
140.85
140.85 2004/01 2004/01 2003/12 2003/12
140.85 2003/12
140.85 2004/05
140.85 2004/05
140.85
ORISSA
125. CH'WATI-VIZAG GQ
NHAI
200.00
200.00
200.00 2004/02 2004/02 2004/02 2004/02
200.00 2004/02
200.00 2004/02
200.00 2004/05
200.00
ANDHRA PRADESH
126. BRIDGES-AP19 V-V SECTION NHAI
136.45
136.45
136.45 2004/02 2004/02 2004/02 2004/02
136.45 2004/02
136.45 2004/02
136.45 2004/09
136.45
ANDHRA PRADESH
127. G'TAMI-G'GOLANU GQ
NHAI
323.35
323.35
323.35 2004/02 2004/02 2003/10 2003/10
323.35 2003/10
323.35 2004/01
323.35 2004/01
323.35 COMPLETED
ANDHRA PRADESH
128. CH'PET-ONGOLE GQ
NHAI
319.21
319.21
319.21 2003/12 2003/12 2003/12 2003/12
319.21 2003/12
319.21 2004/09
319.21 2004/09
319.21
ANDHRA PRADESH
129. KAVALI-NLR GQ
NHAI
181.00
181.00
181.00 2004/01 2004/01 2004/02 2004/02
181.00 2004/02
181.00 2004/02
181.00 2004/12
181.00
ANDHRA PRADESH
130. NLR BY PASS GQ
NHAI
143.20
143.20
143.20 2003/12 2003/12 2004/03 2004/03
143.20 2004/03
143.20 2004/03
143.20 2004/05
143.20
ANDHRA PRADESH
131. NELLORE-TADA (GQ)
NHAI
621.35
621.35
621.35 2003/12 2003/12 2003/12 2003/12
621.35 2003/12
621.35 2003/12
621.35
N.A.
N.A. COMPLETED
ANDHRA PRADESH
132. TADA-CHENNAI GQ
NHAI
233.00
233.00
233.00 2003/12 2003/12 2004/03 2004/03
233.00 2004/03
233.00 2004/03
233.00 2004/12
233.00
TAMIL NADU
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------STATUS AS ON
--------------------------------------------------------------------30.06.2003
30.9.2003
31.12.2003
31.03.2004
SR. NAME OF THE PROJECT
AGENCY ORIGINAL LATEST
NOW ANTI- ORI- LATEST
NOW ANTI- --------------- ----------------- ----------------- ----------------NO.
APPROVED CIPATED
GINAL APPROVED CIPATED
DOC
COST
DOC
COST
DOC
COST
DOC
COST REMARKS
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------133. TUMKUR BYPA-SSK75-62,GQ
NHAI
83.00
83.00
83.00 2003/12 2003/12 2003/12 2003/12
83.00 2003/12
83.00 2004/03
83.00 2004/03
83.00
KARNATAKA
134. KH'PUR-B'SWAR K 0-119 GQ NHAI
80.00
80.00
80.00
N.A.
N.A. 2003/12 2003/12
80.00 2004/09
80.00 2004/09
80.00 2004/09
80.00
ORISSA
135. S'LAM-I'PURAM K233-98 GQ NHAI
79.14
79.14
79.14 2004/03 2004/03 2004/03 2004/03
79.14 2004/03
79.14 2004/03
79.14 2004/03
79.14
ANDHRA PRADESH
136. BR.CH'WATI-S'KULAMK49-97 NHAI
11.00
11.00
71.00 2004/02 2004/02 2003/08 2003/08
71.00 2003/08
71.00
N.A.
N.A.
N.A.
N.A. COMPLETED
ANDHRA PRADESH
137. ETA.BYPASS K308-321 GQ
NHAI
89.50
89.50
89.50 2003/10 2003/10 2003/04 2003/04
89.50 2004/06
89.50 2004/06
89.50 2004/06
89.50
UTTAR PRADESH
138. AHMBD-VADOD.EXP.WAY,NHAI NHAI
128.40
766.50
766.50 1991/12 1991/12 2003/12 2003/12
766.50 2003/12
766.50 2004/03
766.50 2004/03
766.50
GUJARAT
139. NAINI BRIDGE:NH2 & NH27
NHAI
100.36
300.00
219.78 2001/06 1998/12 2004/02 2004/02
219.78 2004/02
219.78 2004/02
219.78 2004/05
219.78
ALLHABAD, UTTAR PRADESH
SECTOR: SHIPPING & PORTS
-----140. CUTTER SUC. -DGERS& VESS
141. TERMINAL AT GAIGHAT
PATNA, BIHAR
142. CAPITAL
DREDG.
KOLLAM-KOCHI, KERALA
143. MODERN OF
MOT JETTIES
MUMBAI, MAHARASHTRA
144. MRPL REF.
EXPN
MANGALORE, KARNATAKA
145. CONS.OF
RECLM.WALL
MULTISTATE
146. ACQ.OF 2 NO.TUGS
MORMUGAO, GOA
147. CONSTN OF
OIL JETTY
PARADIP, ORISSA
148. PROCURE 4
NOS.CRANES
VIZAG, ANDHRA PRADESH
149. CONSTN. OF WEST QUAY
VIZAG, ANDHRA PRADESH
150. REPL.COMMON SHORE P.LINE
MUMBAI, MAHARASHTRA
151. REPL.7 NOS. WHARF CRANE
CHENNAI, TAMIL NADU
152. CONST.ADDL. GEN. BERTH
MANGALORE, KARNATAKA
153. DEEP. APPRCHSOGAL CHANEL
KANDLA, GUJARAT
154. PROCUREMENT OF VTMS
KANDLA, GUJARAT
155. REPL. OF
KUTCH KESARI
KANDLA, GUJARAT
156. DEEP.&WIDEN.OF SOGAL CH.
KANDLA, GUJARAT
157. MODN.OF BUN-DER BASIN
KANDLA, GUJARAT
158. CONSTN.OF9THCARGO BERTH
KANDKA, GUJARAT
159. ACQ.OF4-DWT 110000 COC
MUMBAI, MAHARASHTRA
160. ACQ.OF 700 PASS.+160 T
MUMBAI, MAHARASHTRA
161. ACQ. 3 NOS. BOLLARD TUGS
MUMBAI, MAHARASHTRA
IWT
41.30
41.30
41.30 2004/03
41.30 2004/03
41.30 2005/03
41.30
IWT
25.50
25.50
25.50 2004/03
25.50 2004/03
25.50 2005/03
25.50
SAIL
26.00
26.00
28.60 2004/03
28.60 2004/03
30.93 2004/03
30.93
PORTS
167.99
167.99
215.34 2004/06
215.34 2004/12
215.34 2004/12
215.34
PORTS
236.50
236.50
135.00
PORTS
30.00
30.00
PORTS
46.00
PORTS
N.A.
N.A.
N.A.
N.A.
N.A.
30.00 2003/08
30.00
N.A.
30.00
N.A.
46.00
40.50 2003/11
40.00 2003/12
40.00
N.A.
46.18
46.18
46.18 2003/12
46.18 2004/03
46.18 2004/05
46.18
PORTS
32.64
32.64
32.64
27.53 2004/01
27.53 2004/03
27.53 2004/03
27.53
PORTS
44.57
34.04
44.57 2004/02
44.57 2004/04
44.57 2004/04
44.57
PORTS
69.50
69.49
36.00 2003/12
36.00 2004/03
36.00 2004/03
36.00
PORTS
64.00
64.00
60.00 2004/03
60.00 2004/04
60.00 2004/04
60.00
PORTS
37.54
37.54
37.54 2004/01
37.54 2005/12
44.54 2005/12
44.54
PORTS
20.00
20.00
20.00 2004/03
20.00 2004/03
35.00 2004/03
35.00
PORTS
50.00
50.00
42.15 2004/03
42.15 2004/03
42.15 2004/03
42.15
PORTS
16.00
16.00
20.00 2004/03
20.00 2004/03
20.00 2004/03
20.00
PORTS
40.00
40.00
40.00 2004/03
40.00 2004/03
49.00 2004/03
49.00
PORTS
20.53
20.53
20.53 2005/03
20.53 2005/03
20.53 2005/03
20.53
PORTS
45.00
45.00
47.89 2003/12
47.89 2004/06
47.89 2004/06
47.89
SHIPP.
672.28
629.38
628.09 2003/08
628.09
SHIPP.
129.62
129.62
129.62 2004/02
129.62 2004/02
SHIPP.
49.59
49.59
N.A.
49.59
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
129.62 2004/02
N.A.
N.A.
N.A. COMPLETED
30.00
N.A. COMPLETED
N.A. COMPLETED
129.62
N.A.
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------STATUS AS ON
--------------------------------------------------------------------30.06.2003
30.9.2003
31.12.2003
31.03.2004
SR. NAME OF THE PROJECT
AGENCY ORIGINAL LATEST
NOW ANTI- ORI- LATEST
NOW ANTI- --------------- ----------------- ----------------- ----------------NO.
APPROVED CIPATED
GINAL APPROVED CIPATED
DOC
COST
DOC
COST
DOC
COST
DOC
COST REMARKS
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------SECTOR: TELECOMMUNICATION
-----162. EXPN. FOR
MAROL EXCH.
MTNL
27.92
27.92
27.92 2002/03 2002/03 2004/03 2004/03
27.92 2004/03
27.92 2004/03
27.92 2004/03
27.92
MUMBAI, MAHARASHTRA
163. SBM EXCH.
C-DOT
10.50
25.00
27.08 1999/07 1999/07 2003/06 2003/06
27.08
N.A.
27.08
N.A.
N.A.
N.A.
N.A. COMPLETED
C-DOT PROJ.,
164. IDR-VSAT
C-DOT
19.44
25.40
25.97 2000/10 2001/07 2003/07 2003/07
25.97
N.A.
25.97
N.A.
N.A.
N.A.
N.A. COMPLETED
C-DOT PROJ.,
165. CAMP.CONS. C-DOT PROJ.
C-DOT
80.00
96.74
96.74 1998/08 2002/12 2003/09 2003/09
96.74 2004/03
96.74 2004/03
96.74 2004/03
96.74
DELHI
SECTOR: URBAN DEVELOPMENT
-----166. CONST.OF LIBBHASA BHAWAN
KOLKATA, WEST BENGAL
167. SPG PROJECT
P.KALLAN, DELHI
168. CONST.BLDG. FOR UPSC
DELHI
CPWD
35.34
77.04
77.04
N.A.
77.04
N.A.
77.04
N.A.
CPWD
98.88
98.88
105.00
N.A.
105.00
N.A.
N.A.
N.A.
UD
21.02
21.02
21.02 2004/03
21.02 2004/03
21.02 2004/03
77.04
N.A. COMPLETED
21.02
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------STATUS AS ON
--------------------------------------------------------------------30.06.2003
30.9.2003
31.12.2003
31.03.2004
SR. NAME OF THE PROJECT
AGENCY ORIGINAL LATEST
NOW ANTI- ORI- LATEST
NOW ANTI- --------------- ----------------- ----------------- ----------------NO.
APPROVED CIPATED
GINAL APPROVED CIPATED
DOC
COST
DOC
COST
DOC
COST
DOC
COST REMARKS
------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
AAI
79.66
79.66
SECL
41.95
41.95
41.95 2004/03
41.95 2004/03
41.95 2004/03
41.95
ECL
184.55
403.96
386.44 2004/03
386.44 2004/03
386.44 2004/03
386.44
AIR
42.84
42.84
BPCL
336.07
336.07
GAIL
2936.00
GAIL
NHPC
P.GRID
SECTOR: RAILWAYS
-----178. J'PETTAI B'LORE NEW ROB
B&S
SR, KARNATAKA
179. KORBA-SARAG-BUNDIA,
LD
SECR, MP,OR
180. KHANA-BOL- PUR ,ER
LD
PH-1&2, WEST BENGAL
181. GHAZIABAD- MORADABAD -I LD
NR, UTTAR PRADESH
182. AMROHAMORADABAD,NR LD
UTTAR PRADESH
183. RAJKOT-VERA-VAL,WR
GC
GUJARAT
184. MIRAJ-LATUR ROAD,CR
GC
MAHARASHTRA
185. VILLUPURAM PONDICHERRY
GC
SR, TAMIL NADU
186. S'BAD-M'KHED-J'PET-B'HAN GC
SCR, AP/MH
187. ADDL LOOPS-8STN VIR-SURT NL
WR, MAHARASHTRA
N.A.
188. RENIGUNTA- GUNTAKAL
RE
ANDHRA PRADESH
N.A.
N.A.
N.A.
(As on 31.03.2004)
N.A.
79.66
42.84
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A. COMPLETED
N.A.
N.A.
N.A.
N.A. COMPLETED
336.07
N.A.
336.07 COMPLETED
N.A. 2004/04
336.07 2004/04
336.07 2004/04
2936.00
2936.00 2004/09
2936.00 2004/03
99.51
99.51
1684.02
1684.02
49.49
49.49
49.49
N.A.
N.A.
N.A.
N.A.
N.A.
N.A. COMPLETED
41.96
41.96
41.96
N.A.
N.A.
N.A.
N.A.
N.A.
N.A. COMPLETED
27.45
27.45
40.30
N.A.
N.A.
N.A.
N.A.
N.A.
N.A. COMPLETED
21.78
21.78
N.A.
23.73 2003/09
29.81
N.A.
N.A.
N.A.
N.A. COMPLETED
30.00
43.64
N.A.
65.81
N.A.
N.A.
N.A.
N.A.
49.00
49.00
66.00
112.53
320.66
225.00
321.83
30.00
N.A.
N.A.
N.A.
1684.02 2004/05
N.A.
51.00 2004/03
N.A.
1684.02 2004/05
66.00 2004/03
N.A.
N.A.
N.A. COMPLETED
1684.02 2004/05
1684.02 COMPLETED
N.A. COMPLETED
66.00 2004/09
65.92
363.80
N.A.
363.80 2004/03
363.80
323.00 2003/07
332.34
N.A.
332.34
N.A.
332.34
43.83
43.83 2004/03
43.83 2004/03
43.83
N.A.
43.83
98.42
278.01
278.01 2004/03
278.99 2004/03
278.99
N.A.
278.99
10.19
N.A.
168.34
20.19
N.A.
N.A.
N.A.
168.34 2004/03
168.34
168.34
N.A.
N.A.
359.80
N.A.
2444.54
N.A.
N.A.
99.51
2936.37 2004/04
20.19
N.A.
168.34 2004/03
23.80
N.A. COMPLETED
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------STATUS AS ON
--------------------------------------------------------------------30.06.2003
30.9.2003
31.12.2003
31.03.2004
SR. NAME OF THE PROJECT
AGENCY ORIGINAL LATEST
NOW ANTI- ORI- LATEST
NOW ANTI- --------------- ----------------- ----------------- ----------------NO.
APPROVED CIPATED
GINAL APPROVED CIPATED
DOC
COST
DOC
COST
DOC
COST
DOC
COST REMARKS
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------189. REMOD OF YD.PH-I ST-I,ER TF
20.10
22.58
30.90 1992/12 1992/12 2004/03
N.A.
30.90 2004/03
30.90 2004/03
30.90 2004/03
30.90
BARDMAN, WEST BENGAL
190. WAP AUG.OF CAPACITY-II
WS&PU
47.31
47.31
47.71 2003/03 1996/06 2004/03 2004/03
47.71 2004/03
47.71 2004/03
47.71 2004/03
47.71
SR:BANGALORE, KARNATAKA
191. REDUCTION IN POH TIME
WS&PU
18.76
18.76
20.57 2003/10 2004/03 2003/10 2004/03
20.57 2003/10
20.57
N.A.
20.57
N.A.
20.57
PERMABUR, TAMIL NADU
SECTOR: SHIPPING & PORTS
-----192. CONS.OF 4TH OIL JETTY
KANDLA, GUJARAT
193. REPL. DREGER COLEROON
CHENAI, TAMIL NADU
194. REPL.-BARGE UNLOADERS
MURMUGAO, GOA
195. ADDL.FACILI-TIES-CRUDE
VADINAR, GUJARAT
196. CONST.MULTI LIQ BULKJETY
NEWM'LORE, KARNATAKA
197. MODERN. OF WQ& NQ BERTH
CHENNAI, TAMIL NADU
198. RES.QRS.'Q' TYPE
KANDLA, GUJARAT
199. PROCURE 4
WHARF CRANE
KANDLA, GUJARAT
PORTS
25.12
25.12
N.A.
N.A.
25.12
PORTS
70.00
70.00
N.A.
70.00 2003/10
70.00 2004/03
70.00 2004/03
PORTS
40.00
40.00
40.00 2004/01
40.00 2004/10
40.00
N.A.
PORTS
25.50
25.50
31.81 2003/11
31.81
N.A.
31.81
N.A.
PORTS
31.00
31.00
26.00
N.A.
N.A.
N.A.
N.A.
N.A.
N.A. COMPLETED
PORTS
47.50
47.50
47.50
N.A.
N.A.
N.A.
N.A.
N.A.
N.A. COMPLETED
PORTS
9.93
9.93
31.25 2003/11
31.25 2004/12
31.25 2004/12
31.25
PORTS
24.00
24.00
36.75 2004/03
36.75 2004/03
36.75 2004/10
36.75
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A. COMPLETED
70.00
N.A. COMPLETED
31.81
SECTOR: TELECOMMUNICATION
-----200. GSM CELLULAR MOBILE
MTNL
63.24
63.24
63.24 2001/02 2001/02
N.A.
N.A.
63.24
N.A.
N.A.
N.A.
N.A.
N.A.
N.A. COMPLETED
MUMBAI, MAHARASHTRA
201. GSM CELLULAR MOBILE
MTNL
63.24
63.24
64.00 2001/02 2001/02
N.A.
N.A.
64.00
N.A.
N.A.
N.A.
N.A.
N.A.
N.A. COMPLETED
DELHI, DELHI
202. EXISTING GSM-EXPANSION
MTNL
67.53
67.53
67.53 2003/04 2003/04 2003/11 2003/08
67.53 2003/11
67.53
N.A.
67.53
N.A.
67.53
MUMBAI, MAHARASHTRA
N.A.
N.A.
203. ADDL.GSM.EQ. PH-II
MTNL
66.03
66.03
66.03 2003/11 2003/11 2004/02 2003/11
66.03 2004/02
66.03 2004/02
66.03
DELHI
N.A.
N.A.
N.A.
N.A.
204. EXPANSION
INTERNET
MTNL
20.81
20.81
20.81 2004/03 2004/03 2004/03 2004/03
20.81 2004/03
20.81
MUMBAI, MAHARASHTRA
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
205. IDR-VSAT
C-DOT
25.40
25.40
25.97 2002/12 2002/12
N.A.
N.A.
25.97 COMPLETED
DELHI
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
206. SBM EXCH.
C-DOT
25.00
25.00
27.08 2002/06 2002/06
N.A.
N.A.
27.08 COMPLETED
DELHI
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
APPENDIX-III
0.45
MTY
1991/08
4. VISWAKARMA
OC
DHANBAD
BIHAR
0.7
MTY
1997/08
2001/03
2002/03
44.74
44.74
0
0
0.84
Land and
Project to start after
funds problem. land acquisition
problems are solved.
0.80
MTY
1990/12
1996/03
N.A.
47.40
47.40
0
0
1.64
Geomining/
To start after land
Technological acquisition problems
problems.
are solved and funds
are available.
CCL
--5. KARMA OC
1998/03
N.A.
45.97
45.97
15.55
0
Due to fire
problem.
MAHARASHTRA
-------------------------------------------------------------------------------------------------------------------------------------BCCL : BHARAT COKING COAL LIMITED
OC : OPEN CAST
MTY : MILLION TONNES PER YEAR
(NIC-MoS&PI)
0.30
MTY
1992/09
1999/03
N.A.
29.34
29.34
0
0
1.10
8. TARMI OC
0.50
MTY
1991/05
1995/03
N.A.
29.55
29.55
0
0
0.23
0.60
MT
1991/03
1993/04
N.A.
48.83
48.83
0
0
0.65
MTY
1994/12
1998/03
N.A.
48.61
48.61
0
0
Technology
to be finalised
and approved by
DGMS.
1989/03
1996/03
N.A.
49.34
49.34
0
0
0.80
BOKARO
BIHAR
9. JIRDIH OC
SECL
---10. CHURCHA WEST
PSLW) UG
MADHYA PRADESH
ECL
--11. LAUDOHA UG
0.68
MTY
Land
problem.
Geomining/
Technological
problems.
do
do
do
DGMS approval
required.
Geomining/
Dropped and assets
technological transferred to
problems.
Jhanjra project
BANKURA
WEST BENGAL
--------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
CCL : CENTRAL COALFIELDS LIMITED
UG : UNDER GROUND
5.10
MTY
WCL
--14. AMB.RIVER
DIVERSION
NLC
--15. BARSINGAR
LIGNITE MINE
BIKANER
RAJASTHAN
MT
1.7
1991/03
1995/03
N.A.
49.19
1993/04
1997/03
N.A.
27.99
1991/04
1995/05
N.A.
242.31
49.19
242.31
0
0
N.A.
N.A.
0.01
0
0
24.48
Funds
constraints.
Dropped
Geomining/
Dropped
technological
Problems.
Geomining/
Being taken up by NLC.
technological FRs under approval
problems.
16. BARSINGAR
MW
1991/04 1996/06
N.A.
585.73
664.11
13
5.06
- do do
LIGNIE TPS
2 X120
13
BIKANER
RAJASTHAN
--------------------------------------------------------------------------------------------------------------------------------------WCL : WESTERN COALFIELDS LTD.
THMT : THOUSAND METRIC TONNES
MW : MEGA WATT
(NIC-MoS&PI)
TPS : THERMAL POWER STATION
NLC : NEYVELI LIGNITE CORPORATION LTD, HFC : HINDUSTAN FERTILIZER CORPORATION LTD.
TH.MT
MADHYA PRADESH
1997/11
1996/09
2000/11
N.A.
463.40
463.40
0
0
13.69
IOC
--20. CONST.POL
1999/09 2003/05
N.A.
569.00
569.00
0
14.77
Frozen deep
TRMNL.ERIP
0
to demand
PARADIP
contracts.
ORISSA
------------------------------------------------------------------------------------------------------------------------------------NALCO : NATIONAL ALUMINIUM CO. LTD.
HEP : HYDRO ELECTRIC PROJECT
CIR : Central India Repra
(NIC-MoS&PI)
SAIL : STEEL AUTHORITY OF INDIA LTD. DVC : DAMODAR VALLEY CORPORATION
PIL : Public Interest Litigates
TPA
2 LAC
1999/10
2003/06
N.A.
220.81
220.81
0
0
38.73
MMT
0.326
2000/09
2004/03
2004/03
38.85
38.85
0
0
17.80
No viable.
MMT
0.62
2000/09
2004/03
2004/03
30.30
30.30
0
0
9.32
No viable.
MW
40
1978/01
1983/01
N.A.
16.03
82.09
412
412
49.22
SECTOR: POWER
======
DVC
25. PANCHET HILL
II HEP
DHANBAD
BIHAR
MW
500
1989/09
1995/12
N.A.
603.65
603.65
0
0
PGCIL
----28. KOEL KARO TR CKM
1991/11 1998/03
N.A.
52.59
52.59
0
To start only
Linked to
LINE
215
0
after generation
generation
JAMSHEDPUR
project takes off.
project
BIHAR
---------------------------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
NHPC : NATIONAL HYDRO ELECTRIC POWER CORPORATION LTD
NTPC : NATIONAL THERMAL POWER CORPORATION LTD
PGCIL : POWER GRID CORPORATION OF INDIA LTD
CKM : CIRCUIT KILOMETERS
IOC: INDIAN OIL CORPORATION
STPP : SUPER THERMAL POWER PROJECTS
RCE : REVISED COST
1990/04
1995/12
N.A.
53.00
53.00
0
0
2.11
Fund
constraints/
Low priority.
31. KARPURIGRAM- KM
SIHO,NER
26
UTTAR PRADESH
1993/04
N.A.
1997/03
1997/03
21.00
21.00
0
0
0.48
Frozen.
1993/02
1995/09
N.A.
66.09
71.34
8
8
3.91
KM : KILOMETRE
GC : GAUGE CONVERSION
(NIC-MoS&PI)
APPENDIX-IIIA
LIST OF PROJECTS TAKEN OFF THE MONITORING SYSTEM WHICH HAVE BEEN SHELVED,
PRIVATISED OR FOR WHICH OTHER ALTERNATIVE ARRAGEMENTS MADE
UNIT : (COST/EXPENDITURE :RS.IN CRORES)
-------------------------------------------------------------------------------------------------------------------DATE OF DATE OF
COST
%
CUMULATIVE
GOVT.
COMMISSIONING
-------------------- COST
EXPENDITURE
SL. PROJECT
CAPACITY
APPRO- ----------------APPROVED ANTICIPATED OVER
NO. (DISTRICT)
ORIGINAL
ANTIRUN
(STATE)
ORGNL (REVISED)
CIPAORIGINAL
ON
REASONS/ACTION TAKEN
(RVSD)
TED
(REVISED)
ORIGINAL
(REVISED)
-------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
-------------------------------------------------------------------------------------------------------------------SECTOR: COAL
=======
CCL
--1. SANGAM EXP
0.50
1995/02 1998/03 2004/03
32.66
13.13
-60
12.27
Dropped.
OC
MT
2001/04
-60
HAZARIBAGH 0.235
JHARKHAND
SECL
---2. SHEETAL
0.51
DHARA UG
MTY
SHALHOL
MADHYA PRADESH
1995/05
2001/03
2001/03
48.22
48.22
0
0
26.52
Dropped and
merged with
kurja project.
3. KAPILDHARA
0.51
1998/03 2003/03 2004/03
47.31
47.31
0
2.81
Project shelved.
UG AUG.
MTY
0
SHAHDOL
MADHYA PRADESH
-------------------------------------------------------------------------------------------------------------------UG : UNDER GROUND
(NIC-MoS&PI)
1.70
0.80
MTY
1989/09
1997/04
1996/03
2004/03
104.97
136.80
136.88
30
0
37.07
NLC
7. NEYVELI STPS
ST-I 0 UNIT
TAMIL NADU
MW
210
1989/03
1993/03
N.A.
397.26
614.49
55
55
0.54
Project foreclosed
at lower capacity.
Privatised.
SECTOR: MINES
BALCO
8. NEW COLD
TPA
1995/12 2000/03 2001/06
157.50
183.61
17
173.11
Privatised.
ROLLING MILL 40000
17
KORBA
MADHYA PRADESH
-------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
OC : OPEN CAST
MW : MEGAWATT
TPA : TONNES PER ANNUM
MMTPA
1.1
1993/03
1995/04
N.A.
35.00
35.00
0
0
1991/07
1994/03
N.A.
31.06
44.00
42
42
1.93
MMTPA
26
1998/11
2001/11
N.A.
96.93
96.93
0
0
0.77
Dropped.
2000/08
2002/09
N.A.
1734.00
329.05
-81
-81
27.61
Alternative is
available at low
cost.
2001/08
2004/09
2004/09
926.00
926.00
0
0
12.33
Merged with
other project.
ONGCL
----16. ZERO FLARING
1998/11 2001/07 2001/07
80.30
80.30
0
4.92
Merged with other
PROJECT
0
ONGC project.
GANDHAR
GUJARAT
-------------------------------------------------------------------------------------------------------------------(NIC-MoS&PI)
IOC : INDIAN OIL CORPORATION LTD.
MMTPA : MILLION METRIC TON PER ANNUM
ONGCL : OIL & NATURAL GAS CORPORATION LTD.
CKM
630
1987/10
1992/07
N.A.
166.57
772.83
364
364
41.08
Replaced by other
transmission
System.
1981/04
1987/10
1989/03
1986/09
1989/10
1991/04
N.A.
75.72
191.25
191.25
307.00
305
61
58.91
Privatised.
PC
-20. BAGASSE BASE
1989/10 1993/10
N.A.
414.46
622.30
50
6.91
Privatised.
NEWS PRINT
50
MORADABAD
UTTAR PRADESH
-------------------------------------------------------------------------------------------------------------------LK.TON : LAC TONNES
(NIC-MoS&PI)
NOS
3
TE
45
1996/12
1999/08
N.A.
28.66
28.66
0
0
Dropped.
1998/06
N.A.
N.A.
16.00
31.18
95
95
Dropped.
2000/06
2002/06
2002/06
34.60
34.60
0
0
Dropped.
25. CONST.CARGO
1999/08 2001/12 2001/12
250.00
250.00
0
Privatised.
5A/6A M.POSE
0
MURMUGOA
GOA
-------------------------------------------------------------------------------------------------------------------LK.TON : LAC TONNES
(NIC-MoS&PI)
KL
9
1989/04
1991/12
N.A.
22.07
22.07
0
0
1992/06
1995/03
N.A.
28.86
28.86
0
0
0.03
Dropped.
Replaced by new
project of 20K
with new technology.
1994/01
1994/09
N.A.
20.72
10K
1994/01
1994/09
N.A.
21.23
1994/03
1994/09
N.A.
20.91
20.72
20.91
0
0
Equipment procured
on lease basis.
N.A.
N.A.
Equipment procured
on lease basis and
completed.
0
0
Equipment procured
on lease basis and
completed.
1994/01
1994/09
N.A.
20.57
20.57
0
0
37. EXPN.OF
FUJITSU EX.
CHANDIGARH
PUNJAB
K
15
1994/12
1996/03
N.A.
29.80
29.80
0
0
38. INST.E-10BEX
AHMEDABAD
K
8
1992/08
1995/03
N.A.
31.06
31.06
0
0
1995/11
2000/09
2000/12
2003/01
546.00
546.00
0
0
550.44
Equipment procured
on lease basis and
completed.
GUJARAT
VSNL
---39. INMARSAT-P
Dropped following
VSNLs disinvesment.
MUMBAI
MAHARASHTRA
-------------------------------------------------------------------------------------------------------------------------------VSNL : VIDESH SANCHAR NIGAM LTD.
MW SYS : MICRO WAVE SYSTEM
(NIC-MoS&PI)
1996/11
1999/01
2000/05
2000/05
40.00
40.00
0
0
Privatised.
1999/12
2001/12
2002/03
231.00
231.00
0
0
144.74
Privatised.
1985/09
1995/05
1989/09
N.A.
29.50
62.75
62.75
113
0
APPENDIX-IV
DETAILS OF PROJECTS ADDED/DROPPED, SECTOR-WISE AND QUARTER-WISE
SR.
NO.
--1.
NAME OF THE
SECTOR
-------------ATOMIC ENERGY
-------------
2. CIVIL AVIATION
--------------
QTR.
SR.
NO.
NO. PROJECTS ADDED
----- ----- -------------------------------III
I
II
3. COAL
----
II
III
IV
PROJECTS DROPPED
--------------------------------
1.
INTEGRATED
CARGO TRML(AAI)
1.
1.
2.
3.
4.
5.
6.
7.
8.
SAUNDA 'D'OC(CCL)
JHILIMILI
UG,RCE(SECL)
SATGRAM UG(ECL)
SARPI REOR- GANISATIONUG(ECL)
EXP.OF MINE-I(NLC)
MINE-1A(NLC)
RAVINDRA
KHANI UG(SCCL)
GDK-6B BG-I(SCCL)
1.
2.
3.
4.
BHARATUR OCP(MCL)
SRP OCP-I(SCCL)
MANUGURU OC III(SCCL)
LHDs OF GDK 8,9,10(SCCL)
CHIRIMIRI
1. BASUNDHRA
1.
2.
3.
4.
5.
(WEST)O.C.P(MCL)
BAROUD OC
EXPANSION(SECL)
SARAIPALI OC(SECL)
KHAIRAHA UG(SECL)
BPA CC-II
EXTN.(SCCL)
DORLI OCP-I(SCCL)
ZERO SEAMRPR(SECL)
TPS-I EXP.(NLC)
SR.
NO.
--4.
NAME OF THE
SECTOR
-------------FERTILISERS
-----------
QTR.
SR.
NO.
NO. PROJECTS ADDED
----- ----- -------------------------------II
IV
5. I & B
----6. STEEL
-----
II
II
IV
7. PETROLEUM
---------
II
III
IV
8. POWER
-----
1. NTRIC
PROJECTS DROPPED
--------------------------------
1. METHYLAMINES EXPAN.PROJ.(RCF)
1.
REP/INST 3SWTRS-(AIR)
1.
1.
1.
2.
3.
4.
5.
SIDPUR-SANG-ANER PIPELIN(IOCL)
DEV.D-1
PROSPECT(ONGCL)
DEV.OF BASSEIN EAST(ONGCL)
DEV OF G1 &
G15(ONGCL)
REPLACMNT OFBRAUNI-PATNA(IOCL)
CONST.POL
TRMNL.ERIP(IOCL)
CATALYTIC
DEWAXINGUNIT(IOCL)
LPG TERMINAL FOR EIRP(IOCL)
FOOD GRADE HEXANE(ONGCL)
1. DAHEJ-HAZIRA-URAN PIPELN(GAIL)
2. MS QUALITY UPGRAD.FACI.(IOCL)
3. MS QUALITY UPGRAD.FACI.(IOCL)
KANDLA-SAMA-KHYALI LPG(GAIL)
NEW SOLVENT DEWAXING(IOCL)
1. PANIPAT-REW.PIPELINE PRO(IOCL)
2. C2-C3 & LPG REC.FROM LNG(ONGC)
3. HIGH-URAN
TRUNK P.LINE(ONGC)
1. 400 KV S/S
AT NARENDRA(P.GRID)
2. N'SAGAR-CUD & GOOTY-BNG(P.GRID)
3. RAIPUR-ROUR KELA D/C(P.GRID)
9. RAILWAYS
--------
QTR.
SR.
NO.
NO.
----- ----II
1.
2.
3.
4.
III
1.
IV
1.
2.
3.
4.
5.
I
II
III
PROJECTS ADDED
--------------------------------
PROJECTS DROPPED
--------------------------------
SUBANSIRI
LOWER HEP(NHPC)
SEWA H.E.P.(NHPC)
KAHALGAON
STPP ST-II(NTPC)
TR.SYSTEM
WITH TALAHEP(P.GRID)
TESSTA LOW
DAM STAGE-II(NHPC)
SYSTEM STRE-NGTHENING-I(P.GRID)
VINDHYACHAL-KORBA(P.GRID)
SYS. STRENG-THENING -IV(P.GRID)
SYS. STRENG-THENING - II(P.GRID)
TR. SYSTEM -TEESTA-V,HEP(P.GRID)
1.
2.
3.
4.
5.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
1.
2.
3.
4.
5.
6.
7.
KALAPIPAL - PANDA(WR)(LD)
AKODIA-MOH.-KHERA-SHUJ'P(LD)
SHIMOGATALAGUPPA(GC)
KOLKATTA CI-RCULAR RLY.(MTP)
GANDHINAGAR-KALOL (NL)(NL)
PAKNISOLAPUR(NL)
POH OF UPTO 50 COACHES(WS&PU)
QTR.
SR.
NO.
NO.
----- ----IV
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
10. ROAD TRANSPORT & HIGHWAYS
------------------------I
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
PROJECTS ADDED
--------------------------------
PROJECTS DROPPED
--------------------------------
ATTIPATTU- KORUKUPET,SR(LD)
ERNAKULAM- MULANTURUTTI(LD)
PATTABIRAM- ARAKKONAM,SR(LD)
AMBATHURAI- KODAIKNAL,SR(LD)
CHENNAIKURUKKUPET(LD)
MAVELKKARAI KAYANKULAM(LD)
CHEPPAD KAYANKULAM(LD)
MAVELIKARA- CHENGANNUR(LD)
MADURAIDINDIGUL,SR(LD)
CHENNAI-BEACH-ATTIPATTU(LD)
JAFRABADUTRATIA PH-2(LD)
ROHTAKJAKHAL(LD)
SAHIBABAD- ANAND VIHAR(LD)
PANSKURAHADIA(PH.2)(LD)
CUDDLORESALEM, SR(GC)
BANKURA DAMODAR(SER)(GC)
GONDA-B'RACH-S'PUR-L'NOW(GC)
TIRUPATI-P'KALA-KATPADI(GC)
BANGLORESATYAMANGLAM(NL)
DEOGHAR SULTANGANJ(NL)
BARAMATI - LONAND(NL)
GADWAL RAICHUR(NL)
KOTTAYAM - ERUMELI(SR)(NL)
TARN-TARN- GOINDWAL(NL)
ABOHARFAZILKA(NL)
TARAKESWAR - BISHNUPUR(NL)
STN.CONST.AT GOMTINAGAR(TF)
CHI'PET-VIJ.NH5: 4LANING(NHAI)
J'PUR-C'KHOLNH5: 4LANING(NHAI)
AGRA-G'LIOR K60-70 NSI(NHAI)
HYD.B'LORE K22-35 NSI(NHAI)
H'PALLI-HOSUR K33-49NSI(NHAI)
SALEM BYPASS K199-207NSI(NHAI)
LKO-KANPUR K11-22GQEWI(NHAI)
G'DAL-RIBDAK 143-160EWII(NHAI)
PPUR-DESSA K350-373EWII(NHAI)
GADHAM-SKHALIK324-346PC(NHAI)
AMRAVATI BY PASS OTHERS(NHAI)
GBAD-HAPURBYPASS OTHERS(NHAI)
QTR.
SR.
NO.
NO.
----- ----III
1.
IV
1.
2.
3.
4.
5.
6.
7.
11. SHIPPING & PORTS
---------------I
1.
2.
3.
4.
5.
6.
7.
II
1.
2.
3.
4.
5.
III
1.
IV
1.
2.
12. TELECOMMUNICATION
----------------I
1.
2.
3.
II
1.
2.
III
1.
2.
PROJECTS ADDED
--------------------------------
PROJECTS DROPPED
-------------------------------BR.CH'WATI-S'KULAMK49-97(NHAI)
ALLAHABAD:KM198-KM242.71(NHAI)
ALLAHABAD(KM158-KM.198)(NHAI)
KANYAKUMARI-PANAGUDI NS2(NHAI)
SRINAGAR
BYPASS-NS II(NHAI)
PUNE-NASIK (KM 12.9-42)(NHAI)
R'PUR-HIMTNGR GQ(NHAI)
KAIJALI-MANOR GQ(NHAI)
WEST DIVERSN GQ(NHAI)
SAROLE-WATHER GQ(NHAI)
WATHER-SATARA GQ(NHAI)
TUMKUR-N'MANGAL GQ(NHAI)
NELLORE-TADA (GQ)(NHAI)
ACQ. OF VESSELS,(CIWTC)(IWT)
EXTN.CONTAI-NER BHARTID.(PORTS)
REPL. VAGAI CRANE(PORTS)
REPL.TUGS
MANI& PALANI(PORTS)
PROCURE 2NO PULL TUGS(PORTS)
ADDL.PORT
CRAFTS(PH-I)(PORTS)
REPL. OF ELL.PORTAL WHAR(PORTS)
ACQ. 3 NOS.
MODERN. OF
CONS.OF 4TH
MRPL REF.
CONST.MULTI
BOLLARD TUGS(SHIPP.)
WQ& NQ BERTH(PORTS)
OIL JETTY(PORTS)
EXPN(PORTS)
LIQ BULKJETY(PORTS)
ACQ.OF 2 NO.TUGS(PORTS)
REPL.-BARGE UNLOADERS(PORTS)
EXISTING GSM-EXPANSION(MTNL)
CELL & PKT. VOICE & DATA(C-DOT)
SERVICES FOR BUSINESS(C-DOT)
ADDL.GSM.EQ. PH-II(MTNL)
2ND&3RD GEN.MOBILE COMM.(C-DOT)
EXPANSION
SBM EXCH.(C-DOT)
IDR-VSAT(C-DOT)
INTERNET(MTNL)
QTR.
SR.
NO.
NO.
----- ----IV
1.
2.
13. URBAN DEVELOPMENT
----------------I
1.
II
1.
2.
3.
4.
5.
6.
III
1.
PROJECTS ADDED
--------------------------------
PROJECTS DROPPED
--------------------------------
IDR-VSAT(C-DOT)
SBM EXCH.(C-DOT)
APPENDIX-IV(A)
SECTORWISE STATEMENT SHOWING PROJECTS WITHOUT D.O.C.
------------------------------------------------------------------------------------------------------------------------S.NO. NAME OF THE PROJECT
AGENCY
DOA
COST (RS. CRORES)
EXP.
D.O.C
------------------------------------------------------ORIGINAL
LATEST
NOW ANTIUPTO
ORIGINAL
LATEST
NOW ANTIAPPROVED CIPATED
APPROVED CIPATED
-------------------------------------------------------------------------------------------------------------------------SECTOR COAL
-----1. BAROUD OC
EXPANSION
SECL
2003/05
28.02
28.02
28.02
0.00
0/00
0/00
0/00
2. SARAIPALI OC
SECL
2003/02
22.82
22.82
22.82
0.00
0/00
0/00
0/00
3. KHAIRAHA UG
SECL
2003/09
88.33
88.33
88.33
0.00
0/00
0/00
0/00
SECTOR STEEL
-----4. HDGL PROJECT AT DAGAON
SAIL
1997/01
42.85
42.85
50.50
15.90
1999/01
1999/01
0/00
H&FW
1986/06
19.02
19.02
89.02
0.00
1990/03
1990/03
0/00
SECTOR RAILWAYS
-----6. CHEYYARREBUILDING
7. REBUILDING KRISHNA BDG.
8. BOBBILI-GAJAPATINA-GARAM
9. KUPPAMWHITEFIELD
10. GAJAPATIA- NAGARAM-VIZ11. RAJATGARH - NERGUNDI TA12. AKALTARA-CH-AMPA 3RD LIN
13. CALICUTMANGALORE,SR
14. KUTTIPURAM- GURUVYAR,SR
15. TUNDLAYAMUNA BR;NR
16. GORAKHPUR- SAHJANWA,NER
17. GUDUR-RENI- GUNTA,SCR
18. IRUGUR-COIM-BATORE,SR
19. CHAMPA-SARAGBUNDIA
20. RAHAMA PARADEEP SER
21. SARONA BHI-LAI 3RD LINE
22. KARPURIGRAM- SIHO,ER
23. NEW DELHI- TILAK BRIDGE
24. UTRATIA-CHANDRAULI-S'PUR
25. K-PURAM-CALI-CUT-SHORAN
B&S
B&S
LD
LD
LD
LD
LD
LD
NL
LD
LD
LD
LD
LD
LD
LD
LD
LD
LD
LD
2000/02
2000/03
1990/04
1992/03
1993/04
1994/04
1994/04
1996/02
1995/04
1995/04
1997/04
1997/04
1996/04
1997/04
1997/04
1997/04
2000/07
1998/04
1998/04
2001/03
30.29
18.06
29.28
108.11
29.30
41.22
40.00
240.00
40.00
24.60
61.51
139.69
25.10
39.74
37.35
33.30
30.98
36.00
47.12
178.76
30.29
36.02
35.40
105.01
29.30
42.95
40.00
454.96
90.00
35.95
61.51
157.34
38.66
39.74
37.35
33.30
30.98
36.00
47.12
177.34
37.95
36.32
37.90
137.49
32.11
75.00
53.61
563.08
137.71
31.55
61.51
167.43
38.66
56.57
40.96
48.61
30.98
34.00
65.84
178.23
0.39
3.62
36.14
125.68
30.38
73.82
47.10
502.28
6.72
31.28
8.93
130.90
12.23
14.29
12.81
46.00
8.03
12.44
19.22
106.87
2005/06
0/00
1995/12
1996/03
1995/06
1997/06
0/00
2000/03
0/00
0/00
0/00
2000/12
0/00
0/00
2000/03
0/00
0/00
0/00
2004/12
0/00
2005/06
0/00
1994/06
1996/03
1995/06
1997/06
0/00
2000/03
0/00
0/00
0/00
2000/12
0/00
0/00
2000/03
0/00
0/00
0/00
2004/12
0/00
0/00
0/00
0/00
0/00
0/00
0/00
0/00
0/00
0/00
0/00
0/00
0/00
0/00
0/00
0/00
0/00
0/00
0/00
0/00
0/00
2000/04
2000/04
534.39
440.93
534.39
440.93
534.39
440.93
4.03
6.65
0/00
0/00
0/00
0/00
0/00
0/00
2002/10
1998/09
2000/03
2003/09
30.00
44.82
151.29
25.00
30.00
44.82
151.29
25.00
30.00
44.82
151.29
25.00
0.00
0.02
93.79
25.32
0/00
0/00
2002/07
2004/04
0/00
0/00
2002/07
2004/04
0/00
0/00
0/00
0/00
PORTS
PORTS
SHIPP.
PORTS
APPENDIX-V
PROJECTS WITH GESTATION PERIOD 60% OR MORE COMPLETED AND EXPENDITURE LESS THAN 20% w.r.t. NOW ANTICIPATED SCHEDULE
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULAT- GESTAT- EXPENDGOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
------EXPENDIIVE
ION
ITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
EXPENDI- PERIOD
%
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.)
TILL
TURE
%
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------SECTOR : COAL
======
SECL
---1. PINDURA UG
0.48
1998/03 2003/03 2004/03
12
0
12
49.93
49.93
0
6.52
2.44
0.15
6.67
97.22
13.36
AUG.
MTY
20
20
0
SHAHOL
MADHYA PRADESH
2. VINDHYA UG
AUG.
0.585
MTY
1998/03
2003/03
2004/03
12
20
12
20
49.90
49.90
0
0
3.29
2.52
-
0.41
3.70
97.22
7.41
3. RANI ATARI
0.48
UG, RPR
MTY
KORBA
MADHYA PRADESH
1999/07
2004/07
2004/07
0
0
0
0
48.54
48.54
0
0
3.22
5.22
-
1.11
4.33
90.00
8.92
4. DAMNI UG
0.48
MTY
2000/04
2005/04
2005/04
0
0
0
0
39.32
39.32
0
0
0.04
-
0.22
0.22
75.00
0.56
0.33
MTY
2000/10
2006/03
2006/03
0
0
0
0
32.07
32.07
0
0
0.33
3.84
-
0.33
60.00
1.03
0.32
MTY
2001/03
2004/03
2004/03
0
0
0
0
23.92
23.92
0
0
94.44
0.00
0.64
MTY
2001/01
2004/01
2004/01
0
0
0
0
92.11
92.11
0
0
1.82
3.49
-
0.04
1.86
100.00
2.02
0.59
MTY
2001/07
2004/03
2005/03
12
38
12
38
69.06
69.06
0
0
10.65
8.20
-
0.12
10.77
68.18
15.60
MADHYA PRADESH
SHAHDOL
MADHYA PRADESH
5. JHIRIA UG
SHAHDOL
MADHYA PRADESH
6. KANCHAN OC
UMARIA
MADHYA PRADESH
MCL
--7. NATRAJ UG
ORISSA
WCL
--8. TANDSI UG
EXPN.
MADHYA PRADESH
------------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-DPI)
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULAT- GESTAT- EXPENDGOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
------EXPENDIIVE
ION
ITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
EXPENDI- PERIOD
%
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.)
TILL
TURE
%
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------SCCL
---9. KTK-8 INCL
0.27
1995/12 2002/01 2008/03
74
0
0
34.51
41.54
20
0.16
3.55
0.16
65.99
0.39
UG
MTY
2002/06 2008/03
101
0
41.54
0
WARANGAL
0.416
ANDHRA PRADESH
MTY
10. KTK-9 & 9A
0.48
UG
MT
WARANGAL
ANDHRA PRADESH
1996/08
2005/03
2005/03
0
0
0
0
43.41
43.41
0
0
0.18
0.05
-
0.18
86.41
0.41
2001/02
2005/03
2005/03
0
0
0
0
21.95
21.95
0
0
2.06
1.25
-
0.26
2.32
71.43
10.57
2001/08
2004/03
2004/03
0
0
0
0
49.51
49.51
0
0
25.00
-
3.30
3.30
93.55
6.67
13. KHAIRAGURA
0.72
OC
MTY
ADILABAD
ANDHRA PRADESH
2001/09
2005/03
2005/03
0
0
0
0
47.46
47.46
0
0
0.75
0.22
0.97
66.67
2.04
14. KASIPET OC
2001/11
2005/03
2005/03
0
0
0
0
47.29
47.29
0
0
10.00
-
65.00
0.00
1998/12
2004/10
2006/06
20
29
20
29
298.68
298.68
0
0
17.58
193.87
-
7.87
25.45
67.78
8.52
0.60
MTY
ANDHRA PRADESH
SECTOR : STEEL
======
NMDC
---15. PIG IRON
PLANT
NAGA. BASTAR
CHHATISGARH
MTPA
0.3
SECTOR : PETROLEUM
======
IOCL
---16. INTEGERATED
1999/06 2005/08 2005/08
0
0
0
4228.00
5104.00
21
509.43
221.00
457.49
966.92
74.32
18.94
PARAXYLENE
2001/10
0
0
5104.00
0
PANIPAT
HARYANA
------------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-DPI)
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULAT- GESTAT- EXPENDGOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
------EXPENDIIVE
ION
ITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
EXPENDI- PERIOD
%
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.)
TILL
TURE
%
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------SECTOR : POWER
======
THDCL
----17. KOTESHWAR
MW
2000/04 2006/03 2006/03
0
0
0
1301.56
1301.56
0
81.66
85.93
167.59
63.38
12.88
HEP
4 X 100
0
0
0
TEHRI
UTTARANCHAL
SECTOR : RAILWAYS
======
B&S
--18. BIRUPA MAHANADI:2ND BRD
ECOR
ORISSA
1997/04
N.A.
2007/07
N.A.
N.A.
N.A.
N.A.
93.10
113.00
21
21
4.69
7.70
12.39
65.85
10.96
KMS
73.00
1996/04
2008/04
2008/04
0
0
0
0
1000.00
1500.00
1767.00
77
18
77.15
60.00
-
53.09
130.24
64.58
7.37
KMS
32.43
1996/03
N.A.
2004/02
N.A.
N.A.
N.A.
N.A.
45.00
58.85
58.85
31
0
0.30
5.00
-
1.74
2.04
98.95
3.47
KMS
65
1995/04
1999/04
2005/04
72
150
72
150
65.94
124.13
88
88
2.38
5.00
-
7.43
9.81
87.50
7.90
22. KADUR-C'MAGALUR-S'PUR
SWR
KARNATAKA
KMS
100
1996/04
1999/04
2005/03
71
197
71
197
157.00
283.34
80
80
17.29
15.00
-
15.57
32.86
86.92
11.60
23. KODERMAR
ANCHI(BARKNA
RANCHI,(ECR)
JHARKHAND
KMS
189
1999/03
2005/07
2006/03
8
11
8
11
491.19
1028.00
109
109
56.31
93.04
149.35
69.05
14.53
24. DEOGHARDUMKA, ER
KMS
67
1999/02
2006/12
2007/03
3
3
3
3
180.73
180.73
0
0
20.91
15.00
-
13.34
34.25
60.82
18.95
JHARKHAND
------------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-DPI)
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULAT- GESTAT- EXPENDGOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
------EXPENDIIVE
ION
ITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
EXPENDI- PERIOD
%
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.)
TILL
TURE
%
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------RE
-25. CONV.EXISTIN
1996/07 2005/03 2005/03
0
0
0
273.67
273.67
0
31.45
6.87
38.32
86.54
14.00
G1500V DC
0
0
0
MUMBAI
MAHARASHTRA
26. RENIGUNTAGUNTAKAL
2000/06
2003/04
2004/03
11
32
11
32
168.34
168.34
0
0
17.83
30.00
9.43
7.99
25.82
95.56
15.34
1998/05
2002/03
2004/12
33
72
33
72
21.50
19.69
19.69
-8
0
2.13
5.50
-
0.60
2.73
86.08
13.86
1996/04
2001/03
2004/03
2005/12
57
97
21
22
22.36
22.36
0
0
0.96
1.00
-
0.32
1.28
80.17
5.72
2002/03
2005/12
2005/03
2005/03
-9
-20
0
0
45.32
46.99
4
4
0.17
14.32
-
0.50
0.67
61.11
1.43
2004/11
2004/06
-5
-9
-5
-9
375.00
375.00
0
0
3.13
4.00
10.30
10.30
13.43
90.00
3.58
ANDHRA PRADESH
WS&PU
----27. WORKSHOP
UNITS
AUGMENTATION 250
GORAKHPUR,NR
UTTAR PRADESH
28. SETTINGUP OF
EL.LOCO SHED
BOKARO,ER
JHARKHAND
100
ELECTRIC
LOCOS SHED
29. ICFAUG.OF FA
CILITIES FOR
PERAMBUR
TAMIL NADU
KM.
443-495
2000/04
2003/12
2004/12
12
27
12
27
180.31
175.00
-3
-3
3.10
71.90
-
24.97
28.07
80.36
16.04
KM.
80-97
2000/04
2004/12
2004/12
0
0
0
0
110.00
110.00
0
0
15.17
35.77
-
6.77
21.94
80.36
19.95
2000/04
2005/06
2005/12
6
10
6
10
600.00
641.00
7
7
21.98
0.12
22.10
66.18
3.45
GUJARAT
32. JAMMU-P'KOT
NS-II
J & K
33. V'NANDA BRID
G & APPCH GQ
WEST BENGAL
------------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-DPI)
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULAT- GESTAT- EXPENDGOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
------EXPENDIIVE
ION
ITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
EXPENDI- PERIOD
%
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.)
TILL
TURE
%
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------SECTOR : SHIPPING & PORTS
======
PORTS
----34. RRM FOR IMP.
2001/11 2003/12 2004/12
12
0
12
350.84
350.84
0
2.51
175.00
0.10
2.61
70.27
0.74
OF DRAUGHT
48
48
0
HALDIA
WEST BENGAL
35. SHIP-SHORE
GANTRY CRANE
HALDIA
WEST BENGAL
2002/10
2004/11
2004/11
0
0
0
0
28.50
28.50
0
0
60.00
0.00
36. RES.QRS.'Q'
TYPE
KANDLA
GUJARAT
1999/03
2001/03
2004/12
45
188
45
188
9.93
31.25
31.25
215
0
1.31
0.05
-
0.38
1.69
84.06
5.41
37. PROCUREMENT
OF VTMS
KANDLA
GUJARAT
2000/08
2004/03
2004/03
0
0
0
0
50.00
42.15
-16
-16
2.50
-
95.35
0.00
38. REPL. OF
KUTCH KESARI
KANDLA
GUJARAT
2000/10
2004/03
2004/03
0
0
0
0
16.00
20.00
25
25
8.00
-
95.12
0.00
2001/10
2003/06
2005/03
21
105
21
105
20.53
20.53
0
0
0.47
1.00
-
0.03
0.50
65.85
2.44
2000/02
2002/09
2004/05
20
65
20
65
35.00
35.00
0
0
5.00
-
3.00
3.00
92.16
8.57
1998/11
2001/12
2005/02
2006/12
60
162
22
29
35.12
35.12
0
0
4.23
2.87
4.50
0.11
4.34
63.92
12.36
NOS.
2
TPD
600
SECTOR : TELECOMMUNICATION
MTNL
---40. FRAUD MANAG.
CENTRE(FMCC)
DELHI
SECTOR : URBAN DEVELOPMENT
======
CPWD
---41. RESIDENTIAL
COMP.IT DEP.
KOLKATA
WEST BENGAL
42. CONST.-SSS
2001/07 2003/03 2004/06
15
0
0
21.53
21.53
0
2.76
0.36
3.12
85.71
14.49
NIRE
2004/06
75
0
0
JULLUNDER
PUNJAB
------------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-DPI)
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF
DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULAT- GESTAT- EXPENDGOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
------EXPENDIIVE
ION
ITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
EXPENDI- PERIOD
%
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.)
TILL
TURE
%
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
------------------------------------------------------------------------------------------------------------------------------------------------------------------------43. C/O RES.QTR.
2002/09 2004/04 2004/04
0
0
0
20.32
20.32
0
84.21
0.00
TYPE 1 TO IV
0
0
0
PATNA
BIHAR
------------------------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-DPI)
APPENDIX-VI
MAJOR FACTORS OF DELAY (CURRENT) FOR PROJECTS COSTING RS 20.00 CRS. AND ABOVE
AS ON MARCH'2004
----------------------------------------------------------------------------------------------------------------------------------------------------------------------LAND ACQUISITION
DELAY IN SUPPLY
INAD---------------TECHNOLOGY
AWARD
OF EQUIPMENTS DELAY
EQUATE
FUND
FOREST OTHER ENVIR- --------------OF
--------------- IN
GOVT.
LAW
SLOW
INFRABAD
SR.
CONSTRACLEAR- ONMENT SELECT- AGREE- CONTR- INDIGE- IMPOR- CIVIL CLEAR- GEOM&
PROCOURT STRUCWEATHER
NO. SECTOR
INTS
ANCES
ION
MENT
ACTS
NOUS
TED
WORKS
ANCE
INING
ORDER
GRESS
CASES TURE
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------1 ATOMIC ENERGY
0
0
0
0
0
0
0
1
0
0
0
0
0
0
0
0
0
2 CIVIL AVIATION
3 COAL
4 FINANCE
5 FERTILISERS
6 I & B
7 MINES
8 STEEL
9 PETROCHEMICALS
10 PETROLEUM
11 POWER
12 HEAVY INDUSTRY
13 HEALTH & FW
34
21
10
10
17 TELECOMMUNICATION
18 URBAN DEVELOPMENT
14 RAILWAYS
19 WATER RESOURCES
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
--------------------------------------------------------------------------------------------------------------------------------------------------------------------T O T A L --->
36
4
27
2
1
1
14
6
0
15
0
1
4
11
2
0
0
---------------------------------------------------------------------------------------------------------------------------------------------------------------------
APPENDIX-VII
LIST OF PROJECTS REPORTING 6 MONTHS OR ABOVE INCREMENTAL DELAY IN ANTICIPATED D.O.C., SECTOR-WISE AND QUARTER-WISE
------------------------------------------------------------------------------------------------------------------------------------------------------------NAME OF THE SECTOR
NAME OF THE PROJECT
QTR.I
QTR.II
QTR.III
QTR.IV
------------------------- ------------------------- ------------------------- ------------------------03/03
06/03
DELAY
06/03
09/03
DELAY
09/03
12/03
DELAY
12/03
03/04
DELAY
------------------------------------------------------------------------------------------------------------------------------------------------------------CIVIL AVIATION
-------------DEVELOPMENT AMRITSAR AIR
- 2004/06 2004/12
6
COAL
---POOTKEE
BALIHARI UG
- 2003/09 2004/03
6
BOKARO OC
- 2004/03 2005/03
12
JHANJRA UG
2003/03 2004/03
12
MANUGURU OCP IV
- 2004/03 2005/03
12
I & B
----D.D.BH.DELHIIC/CB PPFVAN
- 2003/12 2004/06
6
MINES
----SPL.GRADE
ALUMINA
- 2003/09 2004/03
6
STEEL
----100 ATA STEAMPIPELINES
2003/05 2003/11
6
UPGRADATION ERW PPEPLANT
- 2004/03 2005/05
14
PETROLEUM
--------GREEN FUELS&EMISSION CTL
- 2005/04 2005/12
8
MS QUALITY UPGRAD.FACI.
- 2005/09 2006/06
9
IOR GANDHAR
- 2004/03 2004/12
9
IOR SCHEME
NEELEM
- 2003/11 2004/10
11
IOR LAKWA- LAKHMANI
- 2004/03 2007/03
36
- 2004/03 2007/03
36
IOR GELEKI
- 2005/03 2007/03
24
- 2005/03 2007/03
24
IOR - RUDRA SAGAR
- 2005/05 2006/05
12
- 2005/05 2006/03
10
REFIN.EXPN. CUM.MOD.
- 2003/07 2004/01
6
POWER
----DULHASTI HEP
- 2003/12 2004/07
7
PARBATI HEP ST.-II
- 2007/09 2009/09
24
NATHPA JHKRI H.E.P.
2003/12 2004/07
7
TEHRI TR.
SYSTEM
2003/09 2004/03
6
- 2004/03 2004/12
9
KAIGA NAREN-DRA TR. SYS.
- 2005/08 2006/03
7
MADURI-THIRU VANANTHAPUR
- 2004/02 2004/09
7
400 KV DC-IIKAH.-BIHAR
- 2004/04 2004/12
8
TALA-SILIGRI TR. LINE
- 2004/12 2005/06
6
RAILWAYS
-------GURAP-SHAKT-IGARH,3RD
- 2004/06 2004/12
6
NERGUNDI- CUTTACK R'PUR 2004/06 2005/12
18
AMROHAMORADABAD,NR
- 2004/03 2004/09
6
ADILABADMUDKHED
2004/06 2005/03
9
- 2005/06 2007/03
21
RANCHI-LOHA-RDAGA,SER
- 2004/12 2006/03
15
TRU-VELLACH-ERI,MRTS EXT
- 2003/09 2004/03
6 2004/03 2005/03
12
ELEC.BARASAT-HASNABAD
- 2003/12 2004/06
6
NANGALDAM- TALWARA,NR
- 2004/03 2008/03
48
EKLAKHIBALURUGHAT
- 2005/03 2007/03
24
HOWRAH-AMTA-CHAMPADANGA,
- 2005/03 2007/03
24
KHARAGPUR- BHUBANESWAR
- 2004/03 2004/12
9
RCF KAPURTH-ALA,PH-II,NR
- 2005/03 2006/03
12
CLW-MFR.OF HIGH HP ABB
- 2004/03 2005/03
12
LUDHIANAELEC.LOCOSHE 2004/03 2005/03
12
WORKSHOP
AUGMENTATION 2003/03 2004/12
21
-
APPENDIX-VIII
LIST OF PROJECTS REPORTING INCREMENTAL COST OVERRUN OF 20% OR ABOVE, SECTOR-WISE AND QUARTER-WISE
---------------------------------------------------------------------------------------------------------------------------------------------------------------NAME OF THE PROJECT
QTR.I
QTR.II
QTR.III
QTR.IV
---------------------------- ------------------------------- ------------------------------- ------------------------------03/03
06/03
% OVERRUN
06/03
09/03 % OVERRUN
09/03
12/03 % OVERRUN
12/03
03/04 % OVERRUN
---------------------------------------------------------------------------------------------------------------------------------------------------------------POWER
----KAIGA NAREN-DRA TR. SYS.
75.99
135.14
77.84
RAILWAYS
-------KHANA-BOL- PUR ,ER
AMROHAMORADABAD,NR
HOTGIGADAG,SWR
AJMER-U'PUR CHITTAURGARH
KALKA-PARWANOO NR
MACHERLANALGONDA(SCR
CHANDIGARH- LUDHIANA,NR
BIDAR-GULBE-RGA,SCR
KHARAGPUR- BHUBANESWAR
294.69
125.00
248.40
242.42
304.33
455.18
265.67
372.00
369.70
402.17
54.46
112.54
49.76
52.50
32.15
23.73
51.00
-
29.81
66.00
-
25.62
29.41
-
227.00
-
318.66
-
40.38
-
27.00
-
37.00
-
37.04
-
20.00
40.00
35.00
49.00
75.00
22.50
WATER RESOURCES
--------------PAGLADIYES
250.00
1030.00
312.00
DAM PROJECT
APPENDIX-IX
SECTORE-WISE STATEMENT OF PROJECTS SANCTIONED
------------------------------------------------------------------------------------------------------------------------------------------------------------------------SECTOR
BEFORE|1982-|1983-|1984-|1985-|1986-|1987-|1988-|1989-|1990-|1991-|1992-|1993-|1994-|1995-|1996-|1997-|1998-|1999-|2000-|2001-|2002-|2003-|TOTAL
1982 |1983 |1984 |1985 |1986 |1987 |1988 |1989 |1990 |1991 |1992 |1993 |1994 |1995 |1996 |1997 |1998 |1999 |2000 |2001 |2002 |2003 |2004 |
------------------------------------------------------------------------------------------------------------------------------------------------------------------------ATOMIC ENERGY
|
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
3 |
0 |
0 |
2 |
1 |
2 |
10
CIVIL AVIATION
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
1 |
0 |
0 |
0 |
COAL
1 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
0 |
2 |
4 |
3 |
4 |
4 |
10 |
8 |
16 |
9 |
65
FERTILISERS
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
2 |
I & B
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
MINES
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
STEEL
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
0 |
1 |
3 |
0 |
PETROLEUM
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
8 |
12 |
3 |
7 |
32
POWER
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
2 |
0 |
0 |
0 |
0 |
3 |
4 |
5 |
10 |
13 |
10 |
50
HEALTH & FW
0 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
RAILWAYS
3 |
0 |
2 |
0 |
3 |
2 |
0 |
1 |
1 |
4 |
3 |
7 |
4 |
7 |
25 |
31 |
26 |
24 |
15 |
11 |
17 |
2 |
12 |
200
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 | 114 |
0 |
0 |
3 |
119
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
4 |
5 |
3 |
7 |
11 |
4 |
3 |
39
TELECOMMUNICATION
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
1 |
4 |
2 |
4 |
2 |
14
URBAN DEVELOPMENT
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
1 |
0 |
3 |
0 |
1 |
3 |
7 |
0 |
17
WATER RESOURCES
|
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
2
------------------------------------------------------------------------------------------------------------------------------------------------------------------------T O T A L ---->
|
4 |
2 |
3 |
0 |
4 |
4 |
1 |
2 |
2 |
6 |
6 |
8 |
6 |
9 | 29 | 40 | 35 | 44 | 30 | 162 | 67 | 54 | 50 | 568
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------
APPENDIX-X
LIST OF PROJECTS UNDER IMPLEMENTATION FOR MORE THAN 10 YEAR
------------------------------------------------------------------------------------------------------------------------------------------------------------------------------D.O.C.
TIME OVERRUN
COST (RS.CRORES)
COST OVERRUN
LATEST
EXPENDITURE
DATE
---------------------W.R.T. LATEST ---------------------------W.R.T. LATEST
GESTATION ---------------OF
LATEST
NOW
APPROVED DOC ORIGINAL LATEST
NOW
APPROVED COST
PERIOD
UPTO
%
SR.
APPRORIG- APPANTI--------------APPROVED
ANTI---------------- OVER AS ON
03/2004
OF
NO. SECTOR
PROJECT
AGENCY OVAL
INAL
ROVED
CIPATED MONTH
%
CIPATED (RS.CRORES)
%
04/2004(%) (RS.CRORES) NAC
------------------------------------------------------------------------------------------------------------------------------------------------------------------------------1 ATOMIC ENERGY
TARAPUR ATO- NPCIL 1991/01 2007/01 2007/01 2007/01
0
0.00
3447.06
6421.00
6525.00
104.00
1.62
82.81
4203.00
64.41
MIC POWER
2 COAL
POOTKEE
BCCL
1983/12 1994/03 2000/03 2004/03
48
24.62
199.87
199.87
182.60
-17.27
-8.64
100.41
171.92
94.15
BALIHARI UG
3 COAL
J.P.RLY LINE CCL
1982/02 1985/03 1997/06 2005/03
93
50.54
15.93
48.78
48.78
0.00
0.00
96.03
61.33
125.73
4 COAL
JHANJRA UG
ECL
72
39.34
184.55
403.96
386.44
-17.52
-4.34
100.39
364.09
94.22
5 COAL
J.K.NAGAR UG ECL
108
220.41
95.28
95.28
54.15
-41.13
-43.17
100.64
48.71
89.95
6 COAL
DUDHICHUA OC NCL
PHASE-I
D.D.BH.DELHI D.D.
IC/CB PPFVAN
DULHASTI HEP NHPC
0.00
868.93
1281.39
1281.39
0.00
0.00
100.72
1233.43
96.26
63
44.06
34.15
81.60
81.60
0.00
0.00
99.03
79.69
97.66
44
20.00
183.45
3559.77
4227.92
668.15
18.77
97.35
4034.40
95.42
DHAULIGANGA
H.E.P.-I
TEHRI DAM
H.P.P.
NATHPA JHKRI
H.E.P.
TEHRI TR.
SYSTEM
NEIG INSTITUTE OF H&FW
BIOLOGICALS
N.INSTITUTE
INSTITUTE OF
MED.SCIENCES
BOBBILI-GAJA
PATINA-GARAM
KUPPAMWHITEFIELD
GAJAPATIANAGARAM-VIZKALAPIPAL PANDA(WR)
NIMACHRATLAM,WR
RAJKOT-VERAVAL,WR
VIRAMGAMBHILDI,WR
MIRAJ-LATUR
ROAD,CR
S'BAD-M'KHED
-J'PET-B'HAN
SHIMOGATALAGUPPA
TIRUPATI-P'K
ALA-KATPADI
THANE-TURBHE
-NERUL-VASHI
NHPC
0.00
601.98
1578.31
1578.31
0.00
0.00
93.41
1281.55
81.20
THDCL
60
100.00
2963.66
2963.66
5209.10
2245.44
75.77
100.83
5328.37
102.29
SJVNL
28
18.06
1678.02
7666.31
8656.61
990.30
12.92
98.36
7958.83
91.94
24
22.86
421.00
702.97
721.62
18.65
2.65
93.80
679.08
94.10
7 I & B
8 POWER
9 POWER
10 POWER
11 POWER
12 POWER
13 HEALTH & FW
14 HEALTH & FW
15 HEALTH & FW
16 RAILWAYS
17 RAILWAYS
18 RAILWAYS
19 RAILWAYS
20 RAILWAYS
21 RAILWAYS
22 RAILWAYS
23 RAILWAYS
24 RAILWAYS
25 RAILWAYS
26 RAILWAYS
27 RAILWAYS
H&FW
0.00
71.18
422.60
422.60
0.00
0.00
95.13
124.19
29.39
H&FW
0.00
69.74
269.24
269.24
0.00
0.00
92.95
128.91
47.88
H&FW
N.A.
N.A.
N.A.
19.02
19.02
89.02
70.00
368.03
-0.90
N.A.
N.A.
LD
N.A.
N.A.
N.A.
29.28
35.40
37.90
2.50
7.06
-0.70
36.14
95.36
LD
N.A.
N.A.
N.A.
108.11
105.01
137.49
32.48
30.93
-0.61
125.68
91.41
LD
N.A.
N.A.
N.A.
29.30
29.30
32.11
2.81
9.59
-0.55
30.38
94.61
LD
1990/04
N.A.
N.A.
N.A.
N.A.
97.64
97.64
97.64
0.00
0.00
-0.70
6.55
6.71
GC
N.A.
N.A.
N.A.
65.00
167.51
167.51
0.00
0.00
-0.55
54.49
32.53
GC
96
204.26
112.53
320.66
363.80
43.14
13.45
100.70
202.15
55.57
GC
108
174.19
155.66
119.75
119.75
0.00
0.00
98.82
47.16
39.38
GC
N.A.
N.A.
N.A.
225.00
323.00
332.34
9.34
2.89
-0.55
187.78
56.50
GC
N.A.
N.A.
N.A.
98.42
276.28
278.99
2.71
0.98
-0.79
208.88
74.87
GC
1992/12
N.A.
N.A.
N.A.
N.A.
N.A.
46.00
46.00
46.00
0.00
0.00
-0.57
2.45
5.33
GC
1992/04
N.A.
N.A.
N.A.
N.A.
N.A.
71.70
130.00
190.36
60.36
46.43
-0.60
149.97
78.78
MTP
N.A.
N.A.
N.A.
403.39
403.39
403.39
0.00
0.00
-0.60
301.08
74.64
N.A.
------------------------------------------------------------------------------------------------------------------------------------------------------------------------------D.O.C.
TIME OVERRUN
COST (RS.CRORES)
COST OVERRUN
LATEST
EXPENDITURE
DATE
---------------------W.R.T. LATEST ---------------------------W.R.T. LATEST
GESTATION ---------------OF
LATEST
NOW
APPROVED DOC ORIGINAL LATEST
NOW
APPROVED COST
PERIOD
UPTO
%
SR.
APPRORIG- APPANTI--------------APPROVED
ANTI---------------- OVER AS ON
03/2004
OF
NO. SECTOR
PROJECT
AGENCY OVAL
INAL
ROVED
CIPATED MONTH
%
CIPATED (RS.CRORES)
%
04/2004(%) (RS.CRORES) NAC
------------------------------------------------------------------------------------------------------------------------------------------------------------------------------28 RAILWAYS
JAMMU TAWI- NL
1981/03 1994/03 2000/12 2004/04
40
16.88
50.00
407.74
510.00
102.26
25.08
100.00
483.00
94.71
UDHAMPUR,NR
29 RAILWAYS
NANGALDAMNL
1981/03 1995/03 1995/03 2008/03
156
92.86
37.68
150.00
210.00
60.00
40.00
85.49
89.16
42.46
TALWARA,NR
30 RAILWAYS
TAMLUK DIGHA NL
1984/03 1997/03 1997/03 2005/06
99
63.46
43.72
77.13
293.97
216.84
281.14
94.51
235.09
79.97
SER
31 RAILWAYS
GUNA-ETAWAH, NL
1985/04 1994/03 1994/03 2005/03
132
123.36
158.77
274.56
400.00
125.44
45.69
95.40
316.04
79.01
ECR
32 RAILWAYS
LAKSHMIKANTA NL
1987/03 1994/03 1996/03 2004/03
96
88.89
40.90
100.89
100.89
0.00
0.00
100.49
94.03
93.20
PUR-NAMKH,ER
33 RAILWAYS
EKLAKHINL
1986/01
N.A.
N.A.
N.A.
N.A.
N.A.
36.80
105.91
274.41
168.50
159.10
-0.92
204.58
74.55
BALURUGHAT
34 RAILWAYS
DUOHNOINL
1992/04 1997/12 1997/12
N.A.
N.A.
N.A.
22.33
22.33
22.33
0.00
0.00
-0.60
0.50
2.24
DEPA
35 RAILWAYS
DAITARI-KEO- NL
1993/03 1997/12 1997/12 2004/12
84
147.37
242.50
401.56
590.60
189.04
47.08
94.33
369.48
62.56
NJHAR BANSP.
36 RAILWAYS
HOWRAH-AMTA- NL
1974/04
N.A.
N.A. 2007/03
N.A.
N.A.
31.42
154.30
154.30
0.00
0.00
91.14
68.31
44.27
CHAMPADANGA,
37 RAILWAYS
LANJHIGARH- NL
1993/04 2002/03 2002/03
N.A.
N.A.
N.A.
100.00
100.00
119.24
19.24
19.24
-0.55
18.93
15.88
JUNAGARH,
38 RAILWAYS
GODRA-INDORE NL
1989/04 1996/03 1996/12
N.A.
N.A.
N.A.
297.15
1007.14
1007.14
0.00
0.00
-0.75
62.21
6.18
DEWAS-MAKSI
39 RAILWAYS
FREIGHTOPERA FOIS
1984/03 1995/03 1995/03 2004/12
117
88.64
520.00
1098.00
426.12
-671.88
-61.19
96.79
275.39
64.63
TION.INF.SYS
40 RAILWAYS
AMBALARE
1993/03 1998/03 1998/03 2005/03
84
140.00
152.21
152.21
157.75
5.54
3.64
92.36
154.55
97.97
MORADABAD
41 RAILWAYS
REMOD OF YD. TF
1987/03 1992/12 1996/06 2004/03
93
83.78
20.10
22.58
30.90
8.32
36.85
100.49
41.17
133.24
PH-I ST-I,ER
42 RAILWAYS
RCF KAPURTH- WS&PU 1985/08 1992/03 2003/03 2006/03
36
17.06
180.00
314.57
451.26
136.69
43.45
90.69
406.37
90.05
ALA,PH-II,NR
43 RAILWAYS
60LOCO DIES- WS&PU 1991/03 1995/03 2003/09
N.A.
N.A.
N.A.
23.30
23.30
39.89
16.59
71.20
-0.66
33.67
84.41
EL SHED
44 RAILWAYS
CLW-MFR.OF
WS&PU 1992/03 1999/06 2003/03 2005/03
24
18.18
29.82
29.82
39.91
10.09
33.84
92.95
33.46
83.84
HIGH HP ABB
45 RAILWAYS
REPL.MW EQP, S&T
1991/04 1997/12 1997/12
N.A.
N.A.
N.A.
22.49
22.49
38.05
15.56
69.19
-0.65
31.79
83.55
GRK'PUR- KTH
46 ROAD TRANSPORT & HIGHWAYS AHMBD-VADOD. NHAI
1986/01 1991/12 1998/12 2004/03
63
40.65
128.40
766.50
766.50
0.00
0.00
100.46
663.47
86.56
EXP.WAY,NHAI
47 URBAN DEVELOPMENT
CONST.OF LIB CPWD
1989/03 1997/01 1997/01
N.A.
N.A.
N.A.
35.34
77.04
77.04
0.00
0.00
-0.76
48.34
62.75
BHASA BHAWAN
48 URBAN DEVELOPMENT
IGNOU CAMPUS CPWD
1991/11 1996/11 1999/06
N.A.
N.A.
N.A.
21.74
23.17
32.30
9.13
39.40
-0.62
33.12
102.54
AT MAIDAN
------------------------------------------------------------------------------------------------------------------------------------------------------------------------------T O T A L ---->
14490.52 33098.94 37684.26
4585.32
13.85
30712.87
81.50
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
APPENDIX-XI
LIST OF PROJECTS WITH WORLD BANK ASSISTANCE
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
----------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULATIVE
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
-------- EXPENDIEXPENDITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
----------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
----------------------------------------------------------------------------------------------------------------------------------------------------------SECTOR: COAL
======
NCL
--1. DUDHICHUA OC 10.0
1992/08 1998/03 2004/03
72
0
0
868.93
1281.39
47 1135.21
120.82
98.22
1233.43
PHASE-I
MTY
2001/03 1998/03
107
0
1281.39
0
SIDHI
2004/03
M.P./U.P.
SECTOR: POWER
======
SJVNL
----2. NATHPA JHKRI
H.E.P.
KINNAUR
HIMACHAL PR.
MW
6 X 250
1989/04
1998/06
1996/04
1998/12
2002/03
2004/07
99
118
28
18
1678.02
7666.31
8656.61
416
13
7169.93
963.05
819.39
788.90
7958.83
----------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-DPI)
APPENDIX-XII
LIST OF PROJECTS ASSISTED BY BILATERAL AND OTHER AGENCIES
UNIT
: (COST/EXPENDITURE :RS.IN CRORES)
----------------------------------------------------------------------------------------------------------------------------------------------------------DATE OF DATE OF
TIME OVER RUN
COST
%
EXPENDI2003-04
ANNUAL
CUMULATIVE
GOVT.
COMMISSIONING
(MONTHS)
-------------------- COST
TURE
-------- EXPENDIEXPENDITURE
SL. PROJECT
CAPACITY
APPRO- ----------------- -------------------APPROVED ANTICIPATED OVER
TILL 3/03
B.E.
TURE
NO. (DISTRICT)
ORIGINAL
ANTITOTAL
ADDL
TOT
RUN
(R.E.) TILL
(STATE)
ORGNL (REVISED)
CIPA(%
OVER
(%
ORIGINAL
ON
QUARTER
(RVSD)
TED
ON
LAST
ON
(REVISED)
ORIGINAL
(L.REP.) ORIGINAL) QTR. REVISED)
(REVISED)
----------------------------------------------------------------------------------------------------------------------------------------------------------(0) (1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
----------------------------------------------------------------------------------------------------------------------------------------------------------SECTOR: COAL
======
ECL
--1. JHANJRA UG
3.50
1982/12 1994/03 2004/03
120
0
72
184.55
386.44
109
363.69
9.33
0.40
364.09
2.00
1995/08 1998/03
89
39
403.96
-4
BURDWAN
MTY
WEST BENGAL
SECTOR: POWER
======
NEEPCO
-----2. TUIRIAL HE
PROJECT
AIZWAL
MIZORAM
NHPC
---3. DULHASTI HEP
MW
2*30
1998/07
2006/07
2006/07
0
0
0
0
368.72
368.72
0
0
102.43
48.00
-
56.66
159.09
MW
3 X 130
1982/11
1989/07
1990/11
1994/07
2001/03
2004/11
168
175
44
20
183.45
3559.77
3559.77
4227.92
2205
19
3739.89
496.43
406.77
294.51
4034.40
MW
4 X 70
1991/04
2000/07
1998/10
2005/03
2005/03
77
86
0
0
601.98
1578.31
1578.31
162
0
943.55
328.43
338.92
338.00
1281.55
DODA
J & K
4. DHAULIGANGA
H.E.P.-I
PITHORAGARH
UTTARANCHAL
5. CHAMERA H.E. MW
1999/05 2004/05 2004/05
0
0
0
1684.02
1684.02
0 1606.19
375.91
293.61
1899.80
PROJECT
3 X 100
0
0
0
365.00
CHAMBA
HIMACHAL PR.
----------------------------------------------------------------------------------------------------------------------------------------------------------(NIC-DPI)
APPENDIX-XIII
LIST OF DELAYED PROJECTS (w.r.t. ORIGINAL SCHEDULE), in DECENDING ORDER OF THE % COST OVERRUN OF TOTAL ANTICIPATED COST
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------D.O.C.
TIME OVERRUN
COST (RS.CRORES)
COST OVERRUN
EXPENDI- % OF THE
CUMLDATE
---------------------W.R.T.ORIGINAL ---------------------------W.R.T. ORIGINAL
TURE
TOTAL
ATIVE
LATEST
NOW
DATE OF COMM. ORIGINAL LATEST
NOW
APPROVED
COST
UPTO
COST OVERRUN % COST
SR.
APPRORIG- APPANTI--------------APPROVED
ANTI---------------03/2004 FOR DELAYED
OVERUN
NO. SECTOR
PROJECT
AGENCY OVAL
INAL
ROVED
CIPATED MONTH
%
CIPATED (RS.CRORES)
% (Rs.CRORES) PROJECTS
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------1 POWER
NATHPA JHKRI SJVNL 1989/04 1996/04 2002/03 2004/07
99
117.86
1678.02
7666.31
8656.61
6978.59
415.88
7958.83
24.04
24.04
H.E.P.
2 URBAN DEVELOPMENT
DELHI METRO DMRC
1996/09 2005/03 2005/03 2005/09
6
5.88
4860.00 10571.00 10571.00
5711.00
117.51
5299.95
19.67
43.71
RAPID SYS-I
3 POWER
DULHASTI HEP NHPC
1982/11 1990/11 2001/03 2004/11
168
175.00
183.45
3559.77
4227.92
4044.47 2204.67
4034.40
13.93
57.64
4 POWER
TEHRI DAM
H.P.P.
5 RAILWAYS
UDHAMPUR-S'NGR-B'MULLA,
6 POWER
DHAULIGANGA
H.E.P.-I
7 PETROLEUM
PANIPAT REF.
EXPANSION
8 ROAD TRANSPORT & HIGHWAYS AHMBD-VADOD.
EXP.WAY,NHAI
9 RAILWAYS
KODERMAR
ANCHI(BARKNA
10 RAILWAYS
JAMMU TAWIUDHAMPUR,NR
11 COAL
DUDHICHUA OC
PHASE-I
12 HEALTH & FW
NEIG INSTITUTE OF H&FW
13 RAILWAYS
DAITARI-KEONJHAR BANSP.
14 POWER
TEHRI TR.
SYSTEM
15 PETROLEUM
MS QUALITY
UPGRADATION
16 RAILWAYS
RCF KAPURTHALA,PH-II,NR
17 RAILWAYS
RAJKOT-VERAVAL,WR
18 RAILWAYS
TAMLUK DIGHA
SER
19 RAILWAYS
GUNA-ETAWAH,
ECR
20 PETROLEUM
REF.MODERNISATION
21 COAL
JHANJRA UG
THDCL
60
100.00
2963.66
2963.66
5209.10
2245.44
75.77
5328.37
7.73
65.37
NL
77
106.94
2500.00
2500.00
3564.00
1064.00
42.56
1291.60
3.67
69.04
NHPC
77
85.56
601.98
1578.31
1578.31
976.33
162.19
1281.55
3.36
72.40
IOCL
4.62
3365.00
4165.00
4177.00
812.00
24.13
1064.88
2.80
75.20
NHAI
147
207.04
128.40
766.50
766.50
638.10
496.96
663.47
2.20
77.40
NL
10.53
491.19
491.19
1028.00
536.81
109.29
149.35
1.85
79.25
NL
121
77.56
50.00
407.74
510.00
460.00
920.00
483.00
1.58
80.83
NCL
72
107.46
868.93
1281.39
1281.39
412.46
47.47
1233.43
1.42
82.25
H&FW
72
46.75
71.18
422.60
422.60
351.42
493.71
124.19
1.21
83.46
NL
84
147.37
242.50
401.56
590.60
348.10
143.55
369.48
1.20
84.66
69
115.00
421.00
702.97
721.62
300.62
71.41
679.08
1.04
85.70
22 HEALTH & FW
23 RAILWAYS
24 RAILWAYS
25 RAILWAYS
26 FERTILISERS
27 RAILWAYS
BIOLOGICALS
N.INSTITUTE
NEW J'PAIGURI BONGAIGON
NANGALDAMTALWARA,NR
AMRAVATINARKHER,CR
NAMRUP PLANT
REVAMP
KHARAGPURBHUBANESWAR
IOCL
11.11
1483.00
1483.00
1755.00
272.00
18.34
658.91
0.94
86.64
WS&PU
168
212.66
180.00
314.57
451.26
271.26
150.70
406.37
0.93
87.57
GC
96
204.26
112.53
320.66
363.80
251.27
223.29
202.15
0.87
88.44
NL
99
63.46
43.72
77.13
293.97
250.25
572.39
235.09
0.86
89.30
NL
132
123.36
158.77
274.56
400.00
241.23
151.94
316.04
0.83
90.13
BPCL
13
39.39
1592.65
1831.00
1831.00
238.35
14.97
1157.00
0.82
90.95
ECL
120
88.89
184.55
403.96
386.44
201.89
109.40
364.09
0.70
91.65
H&FW
78
100.00
69.74
269.24
269.24
199.50
286.06
128.91
0.69
92.34
GC
15
28.85
536.85
523.17
723.00
186.15
34.67
577.10
0.64
92.98
NL
156
92.86
37.68
150.00
210.00
172.32
457.32
89.16
0.59
93.57
NL
69
115.00
120.90
175.30
284.27
163.37
135.13
95.75
0.56
94.13
BVFC
36
83.72
350.00
509.40
509.40
159.40
45.54
429.31
0.55
94.68
RE
57
95.00
258.58
304.33
402.17
143.59
55.53
294.78
0.49
95.17
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------D.O.C.
TIME OVERRUN
COST (RS.CRORES)
COST OVERRUN
EXPENDI- % OF THE
CUMLDATE
---------------------W.R.T.ORIGINAL ---------------------------W.R.T. ORIGINAL
TURE
TOTAL
ATIVE
LATEST
NOW
DATE OF COMM. ORIGINAL LATEST
NOW
APPROVED
COST
UPTO
COST OVERRUN % COST
SR.
APPRORIG- APPANTI--------------APPROVED
ANTI---------------03/2004 FOR DELAYED
OVERUN
NO. SECTOR
PROJECT
AGENCY OVAL
INAL
ROVED
CIPATED MONTH
%
CIPATED (RS.CRORES)
% (Rs.CRORES) PROJECTS
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------28 RAILWAYS
HOTGIGC
1994/04 1999/03 2003/03 2006/03
84
142.37
180.00
180.00
318.66
138.66
77.03
200.72
0.48
95.65
GADAG,SWR
29 RAILWAYS
KADUR-C'MAG- NL
1996/04 1999/04 1999/04 2005/03
71
197.22
157.00
157.00
283.34
126.34
80.47
32.86
0.44
96.09
ALUR-S'PUR
30 RAILWAYS
ARSIKERE-HA- GC
1995/04 1996/03 2000/03 2004/12
105
954.55
186.16
185.16
312.42
126.26
67.82
245.12
0.43
96.52
SSAN-MANGLOR
31 ROAD TRANSPORT & HIGHWAYS NAINI BRIDGE NHAI
1995/03 2001/06 1998/12 2004/05
35
46.67
100.36
300.00
219.78
119.42
118.99
263.80
0.41
96.93
:NH2 & NH27
32 POWER
ULDCS FOR
P.GRID 1998/09 2003/09 2003/09 2004/12
15
25.00
290.01
290.01
396.51
106.50
36.72
200.72
0.37
97.30
EASTERN REG.
33 PETROLEUM
IOR GANDHAR ONGCL 2000/12 2004/03 2004/03 2004/12
9
23.08
609.44
609.44
692.45
83.01
13.62
156.41
0.29
97.59
34 RAILWAYS
MTP
36
50.70
605.70
605.70
691.04
85.34
14.09
502.64
0.29
97.88
35
GC
144
-847.06
117.97
178.00
199.06
81.09
68.74
59.78
0.28
98.16
GC
96
417.39
88.73
88.73
161.03
72.30
81.48
39.38
0.25
98.41
IOCL
14.71
1248.00
1248.00
1317.00
69.00
5.53
709.71
0.24
98.65
NL
120
142.86
40.90
100.89
100.89
59.99
146.67
94.03
0.21
98.86
40
111.11
75.99
75.99
135.14
59.15
77.84
93.52
0.20
99.06
MTP
12
11.21
325.47
401.66
383.94
58.47
17.96
269.87
0.20
99.26
NL
72
150.00
65.94
65.94
124.13
58.19
88.25
9.81
0.20
99.46
LD
54
120.00
105.22
105.22
154.14
48.92
46.49
84.73
0.17
99.63
D.D.
171
488.57
34.15
81.60
81.60
47.45
138.95
79.69
0.16
99.79
PORTS
22
33.33
167.99
167.99
215.34
47.35
28.19
161.87
0.16
99.95
LD
54
79.41
20.00
20.00
64.09
44.09
220.45
49.01
0.15
100.10
NHAI
9.68
600.00
600.00
641.00
41.00
6.83
22.10
0.14
100.24
CCL
240
648.65
15.93
48.78
48.78
32.85
206.21
61.33
0.11
100.35
PORTS
63
262.50
49.63
49.63
76.37
26.74
53.88
42.89
0.09
100.44
PORTS
21
75.00
8.00
34.45
34.45
26.45
330.63
11.43
0.09
100.53
S&T
42
64.62
9.79
33.75
33.37
23.58
240.86
28.40
0.08
100.61
29.63
231.53
231.53
253.29
21.76
9.40
142.84
0.07
100.68
36
37
38
39
40
41
42
43
44
45
46
47
TRU-VELLACHERI,MRTS EXT
RAILWAYS
ADILABADMUDKHED
RAILWAYS
AGRABANDIKUI
PETROLEUM
LINEAR ALKYL
BENLENE
RAILWAYS
LAKSHMIKANTA
PUR-NAMKH,ER
POWER
KAIGA NARENDRA TR. SYS.
RAILWAYS
BORIVILIVIRAR,WR
RAILWAYS
KOTTURHARIHAR,SWR
RAILWAYS
HOSPETGUNTAKAL,SCR
I & B
D.D.BH.DELHI
IC/CB PPFVAN
SHIPPING & PORTS
MODERN OF
MOT JETTIES
RAILWAYS
KANPUR-PANKI
3RD LINE,NR
ROAD TRANSPORT & HIGHWAYS V'NANDA BRID
G & APPCH GQ
COAL
J.P.RLY LINE
CONST.400 PA
X VESSEL
DEV./UPGRADE
OPEN PLOTS
CCG-VR TRAIN
DESCRIBER
TALA-SILIGRI
TR. LINE
RES.QRS.'Q'
TYPE
CAMP.CONS.
C-DOT PROJ.
MADURI-THIRU
VANANTHAPUR
REMOD OF YD.
PH-I ST-I,ER
PROCURE 4
WHARF CRANE
CENTRAL
EXCISE BLDG.
PORTS
45
187.50
9.93
31.25
31.25
21.32
214.70
1.69
0.07
100.75
C-DOT
67
128.85
80.00
96.74
96.74
16.74
20.93
45.14
0.06
100.81
11
30.56
195.97
195.97
207.15
11.18
5.70
168.08
0.04
100.85
TF
135
195.65
20.10
22.58
30.90
10.80
53.73
41.17
0.04
100.89
PORTS
27
117.39
24.00
36.75
36.75
12.75
53.13
17.08
0.04
100.93
CPWD
38
102.70
25.75
25.75
38.03
12.28
47.69
12.66
0.04
100.97
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------D.O.C.
TIME OVERRUN
COST (RS.CRORES)
COST OVERRUN
EXPENDI- % OF THE
CUMLDATE
---------------------W.R.T.ORIGINAL ---------------------------W.R.T. ORIGINAL
TURE
TOTAL
ATIVE
LATEST
NOW
DATE OF COMM. ORIGINAL LATEST
NOW
APPROVED
COST
UPTO
COST OVERRUN % COST
SR.
APPRORIG- APPANTI--------------APPROVED
ANTI---------------03/2004 FOR DELAYED
OVERUN
NO. SECTOR
PROJECT
AGENCY OVAL
INAL
ROVED
CIPATED MONTH
%
CIPATED (RS.CRORES)
% (Rs.CRORES) PROJECTS
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------58 COAL
KTK-3 INCL
SCCL
1996/08 2003/03 2007/03 2007/03
48
60.76
37.50
47.33
47.33
9.83
26.21
20.35
0.03
101.00
UG
59 RAILWAYS
CLW-MFR.OF
WS&PU 1992/03 1999/06 2003/03 2005/03
69
79.31
29.82
29.82
39.91
10.09
33.84
33.46
0.03
101.03
HIGH HP ABB
60 ROAD TRANSPORT & HIGHWAYS JDHARBYPASS NHAI
2000/04 2002/02 2002/02 2004/04
26
118.18
54.09
54.09
63.46
9.37
17.32
86.26
0.03
101.06
K372-387NSI
61 CIVIL AVIATION
EXT.OF RUNWA AAI
2000/08 2003/02 2003/02 2004/03
13
43.33
24.03
24.03
28.87
4.84
20.14
21.90
0.02
101.08
Y JAIPUR AIR
62 COAL
KTK-8 INCL
SCCL
1995/12 2002/01 2008/03 2008/03
74
101.37
34.51
41.54
41.54
7.03
20.37
0.16
0.02
101.10
UG
63 RAILWAYS
AMBALARE
1993/03 1998/03 1998/03 2005/03
84
140.00
152.21
152.21
157.75
5.54
3.64
154.55
0.02
101.12
MORADABAD
64 RAILWAYS
DLW-4000HP:I WS&PU 1998/10 2001/03 2004/03 2005/03
48
165.52
37.44
43.27
43.27
5.83
15.57
32.06
0.02
101.14
DIESEL LOCOS
65 RAILWAYS
CONST.OF 50 WS&PU 1997/04 2003/03 2003/03 2004/03
12
16.90
15.26
15.26
22.26
7.00
45.87
20.66
0.02
101.16
LOCO SHEDS
66 SHIPPING & PORTS
CAPITAL
SAIL
1997/12 2001/03 2001/03 2004/03
36
92.31
26.00
26.00
30.93
4.93
18.96
20.56
0.02
101.18
DREDG.
67 SHIPPING & PORTS
CONST.ADDL. PORTS 2001/07 2004/01 2004/01 2005/12
23
76.67
37.54
44.54
44.54
7.00
18.65
4.46
0.02
101.20
GEN. BERTH
68 CIVIL AVIATION
DEVELOPMENT AAI
2000/01 2003/11 2003/11 2004/12
13
28.26
79.27
79.27
82.81
3.54
4.47
40.23
0.01
101.21
AMRITSAR AIR
69 COAL
REHAR UG RPR SECL
1998/12 2003/12 2003/12 2004/03
3
5.00
26.30
26.30
29.91
3.61
13.73
10.80
0.01
101.22
70 COAL
SCCL
24
120.00
21.85
21.85
25.10
3.25
14.87
0.04
0.01
101.23
71
WS&PU
60
139.53
20.00
24.35
24.35
4.35
21.75
22.40
0.01
101.24
NHAI
12.00
182.52
182.52
185.52
3.00
1.64
138.20
0.01
101.25
PORTS
10.17
45.00
45.00
47.89
2.89
6.42
41.58
0.01
101.26
IGCAR
81
540.00
28.00
28.00
28.00
0.00
0.00
5.61
0.00
101.26
CCL
60
107.14
46.78
46.78
46.78
0.00
0.00
41.99
0.00
101.26
72
73
74
75
MANUGURU OC
III
RAILWAYS
LUDHIANAELEC.LOCOSHE
ROAD TRANSPORT & HIGHWAYS LUCK BYPASS
EW NH 25&28
SHIPPING & PORTS
CONSTN.OF9TH
CARGO BERTH
ATOMIC ENERGY
PFBR-STAGE
A PHASE-II
COAL
BOKARO OC
76 COAL
MAHAN OC
SECL
48
106.67
41.95
41.95
41.95
0.00
0.00
19.37
0.00
101.26
77 COAL
UG
SECL
12
20.00
49.93
49.93
49.93
0.00
0.00
6.67
0.00
101.26
UG
SECL
12
20.00
49.90
49.90
49.90
0.00
0.00
3.70
0.00
101.26
UG
SECL
5.00
26.30
26.30
26.30
0.00
0.00
6.28
0.00
101.26
&BAR ECL
13.33
45.26
45.26
45.26
0.00
0.00
35.35
0.00
101.26
UG
ECL
12
20.00
38.46
38.46
38.46
0.00
0.00
18.74
0.00
101.26
82 COAL
PINDURA
AUG.
VINDHYA
AUG.
GAYATRI
RPR
AMADAND
TARAI
BAGDEVA
RPR
NAHARIA
UG
WCL
12
14.81
46.17
46.17
46.17
0.00
0.00
23.60
0.00
101.26
83 COAL
ADASA UG
WCL
12
23.53
39.87
39.87
39.87
0.00
0.00
1.58
0.00
101.26
84 COAL
DHURWASA OC
WCL
12
21.82
62.74
62.74
62.74
0.00
0.00
6.42
0.00
101.26
85 COAL
TANDSI UG
EXPN.
EXP.OF CAP.
SMELTER-CPP
SPL.GRADE
ALUMINA
WCL
12
37.50
69.06
69.06
69.06
0.00
0.00
10.77
0.00
101.26
NALCO
23
45.10
2061.98
2061.98
2061.98
0.00
0.00
1593.05
0.00
101.26
NALCO
52
98.11
56.78
56.78
56.78
0.00
0.00
51.17
0.00
101.26
78 COAL
79 COAL
80 COAL
81 COAL
86 MINES
87 MINES
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------D.O.C.
TIME OVERRUN
COST (RS.CRORES)
COST OVERRUN
EXPENDI- % OF THE
CUMLDATE
---------------------W.R.T.ORIGINAL ---------------------------W.R.T. ORIGINAL
TURE
TOTAL
ATIVE
LATEST
NOW
DATE OF COMM. ORIGINAL LATEST
NOW
APPROVED
COST
UPTO
COST OVERRUN % COST
SR.
APPRORIG- APPANTI--------------APPROVED
ANTI---------------03/2004 FOR DELAYED
OVERUN
NO. SECTOR
PROJECT
AGENCY OVAL
INAL
ROVED
CIPATED MONTH
%
CIPATED (RS.CRORES)
% (Rs.CRORES) PROJECTS
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------88 STEEL
UPGRADATION SAIL
2002/03 2003/11 2003/11 2005/05
18
90.00
89.15
89.15
89.15
0.00
0.00
3.71
0.00
101.26
ERW PPEPLANT
89 STEEL
PIG IRON
NMDC
1998/12 2004/10 2004/10 2006/06
20
28.57
298.68
298.68
298.68
0.00
0.00
25.45
0.00
101.26
PLANT
90 PETROLEUM
DAHEJ-HAZIRA GAIL
2002/12 2005/07 2005/07 2005/12
5
16.13
1416.00
1416.00
1416.00
0.00
0.00
2.53
0.00
101.26
-URAN PIPELN
91 PETROLEUM
GREEN FUELS& HPCL
2002/10 2005/04 2005/04 2005/12
8
26.67
1152.00
1152.00
1152.00
0.00
0.00
14.85
0.00
101.26
EMISSION CTL
92 PETROLEUM
MS QUALITY
IOCL
2003/07 2005/07 2005/07 2006/06
11
45.83
390.00
390.00
390.00
0.00
0.00
3.96
0.00
101.26
UPGRAD.FACI.
93 PETROLEUM
IOR SCHEME
ONGCL 2001/01 2003/07 2003/07 2004/10
15
50.00
347.69
347.69
347.69
0.00
0.00
72.77
0.00
101.26
NEELEM
94 PETROLEUM
REFIN.EXPN. CPCL
2000/07 2003/07 2003/07 2004/06
11
30.56
2360.38
2360.38
2360.38
0.00
0.00
1975.96
0.00
101.26
CUM.MOD.
95 POWER
LOKTAK D/S
NHPC
1999/12 2006/06 2006/06 2008/12
30
38.46
578.62
578.62
578.62
0.00
0.00
24.30
0.00
101.26
HEP
96 POWER
MEMRAMUNDALI P.GRID 2000/10 2003/04 2003/04 2004/01
9
30.00
166.51
166.51
166.51
0.00
0.00
135.41
0.00
101.26
-JEYPORE D/C
97 POWER
TR.SYSTEM
P.GRID 2001/08 2004/02 2004/02 2004/06
4
13.33
162.88
162.88
162.88
0.00
0.00
86.54
0.00
101.26
STRNGTHENING
98 POWER
HVDC BACK TO P.GRID 2002/01 2005/01 2005/01 2005/03
2
5.56
769.25
769.25
769.25
0.00
0.00
213.47
0.00
101.26
BACK GAZUVAK
99 POWER
400 KV DC-II P.GRID 2001/12 2004/06 2004/06 2004/12
6
20.00
135.77
135.77
135.77
0.00
0.00
96.14
0.00
101.26
KAH.-BIHAR
100 POWER
RANAGADI-0
P.GRID 2001/08 2003/08 2003/08 2004/03
7
29.17
27.25
27.25
27.25
0.00
0.00
11.52
0.00
101.26
TR. 132 KV
101 POWER
BARIPADA
P.GRID 2001/10 2004/04 2004/04 2004/06
2
6.67
66.24
66.24
66.24
0.00
0.00
21.58
0.00
101.26
400 KV S/S
102 POWER
SYS.STRENGTH P.GRID 2003/02 2006/08 2006/08 2006/11
3
7.14
143.29
143.29
143.29
0.00
0.00
3.38
0.00
101.26
ING IN N.R.
103 POWER
SYSTEM STRE- P.GRID 2004/01 2006/07 2006/07 2006/11
4
13.33
271.80
271.80
271.80
0.00
0.00
N.A.
0.00
101.26
NGTHENING-I
104 POWER
SYS. STRENG- P.GRID 2004/01 2006/10 2006/10 2006/12
2
6.06
247.78
247.78
247.78
0.00
0.00
N.A.
0.00
101.26
THENING - II
105 RAILWAYS
ELEC.BARASAT MTP
1998/04 2002/03 2002/03 2004/06
27
57.45
37.70
37.70
37.70
0.00
0.00
21.51
0.00
101.26
-HASNABAD
106 RAILWAYS
TOLLYGANJ - MTP
2000/03 2006/12 2006/12 2007/06
6
7.41
907.69
907.69
907.69
0.00
0.00
150.00
0.00
101.26
GARIA (MTP)
107 RAILWAYS
DEOGHARNL
1999/02 2006/12 2006/12 2007/03
3
3.19
180.73
180.73
180.73
0.00
0.00
34.25
0.00
101.26
DUMKA, ER
108 RAILWAYS
ERNAKULAMRE
2001/05 2003/08 2003/08 2004/12
16
59.26
162.03
162.03
162.03
0.00
0.00
96.17
0.00
101.26
TRIVANDRUM
109 RAILWAYS
RENIGUNTARE
2000/06 2003/04 2003/04 2004/03
11
32.35
168.34
168.34
168.34
0.00
0.00
25.82
0.00
101.26
GUNTAKAL
110 RAILWAYS
WAP AUG.OF
WS&PU 1998/05 2003/03 2004/03 2004/03
12
20.69
47.31
47.31
47.71
0.40
0.85
39.26
0.00
101.26
CAPACITY-II
111 RAILWAYS
SETTINGUP OF WS&PU 1996/04 2001/03 2004/03 2005/12
57
96.61
22.36
22.36
22.36
0.00
0.00
1.28
0.00
101.26
EL.LOCO SHED
112 ROAD TRANSPORT & HIGHWAYS J'PURBYPASS NHAI
2000/04 2004/06 2004/06 2004/10
4
8.00
210.00
210.00
210.00
0.00
0.00
147.00
0.00
101.26
PH2 GQ
113 ROAD TRANSPORT & HIGHWAYS JNPT-PORTCON NHAI
2000/04 2004/04 2004/04 2004/08
4
8.33
177.12
177.12
177.12
0.00
0.00
82.15
0.00
101.26
NECT NH-4B
114 ROAD TRANSPORT & HIGHWAYS LKO-K'PUR KM NHAI
2000/04 2003/12 2003/12 2004/06
6
13.64
94.91
94.91
94.91
0.00
0.00
62.15
0.00
101.26
21.8-44 EWII
115 ROAD TRANSPORT & HIGHWAYS J'DHAR-P'KOT NHAI
2000/04 2003/09 2003/09 2004/03
6
14.63
71.18
71.18
71.18
0.00
0.00
42.73
0.00
101.26
K4-26 NSII
116 ROAD TRANSPORT & HIGHWAYS HALDIAPORT-P NHAI
2000/04 2004/07 2004/07 2005/03
8
15.69
273.00
273.00
273.00
0.00
0.00
67.46
0.00
101.26
.CONNECT
117 ROAD TRANSPORT & HIGHWAYS DELHI-HARYAN NHAI
2000/04 2003/09 2003/09 2004/09
12
29.27
82.00
82.00
82.00
0.00
0.00
27.50
0.00
101.26
AK-44-66NSII
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------D.O.C.
TIME OVERRUN
COST (RS.CRORES)
COST OVERRUN
EXPENDI- % OF THE
CUMLDATE
---------------------W.R.T.ORIGINAL ---------------------------W.R.T. ORIGINAL
TURE
TOTAL
ATIVE
LATEST
NOW
DATE OF COMM. ORIGINAL LATEST
NOW
APPROVED
COST
UPTO
COST OVERRUN % COST
SR.
APPRORIG- APPANTI--------------APPROVED
ANTI---------------03/2004 FOR DELAYED
OVERUN
NO. SECTOR
PROJECT
AGENCY OVAL
INAL
ROVED
CIPATED MONTH
%
CIPATED (RS.CRORES)
% (Rs.CRORES) PROJECTS
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------118 ROAD TRANSPORT & HIGHWAYS N'GAMA-V'WAD NHAI
2000/04 2003/12 2003/12 2004/04
4
9.09
138.65
138.65
138.65
0.00
0.00
86.64
0.00
101.26
A OTHER NH9
119 ROAD TRANSPORT & HIGHWAYS 8LANEDLH'YAN NHAI
2000/04 2003/04 2003/04 2004/09
17
47.22
71.00
71.00
71.00
0.00
0.00
19.14
0.00
101.26
AK17-9NSII
120 ROAD TRANSPORT & HIGHWAYS 8-LANENHIDEL NHAI
2000/04 2003/11 2003/11 2004/11
12
27.91
57.53
57.53
57.53
0.00
0.00
12.45
0.00
101.26
HI K8-16NSI
121 ROAD TRANSPORT & HIGHWAYS VIZAG PORT
NHAI
2000/04 2004/10 2004/10 2004/12
2
3.70
93.79
93.79
93.79
0.00
0.00
52.13
0.00
101.26
(PC)
122 ROAD TRANSPORT & HIGHWAYS P'NEA-G'KOTA NHAI
2000/04 2002/03 2002/03 2004/12
33
143.48
62.98
62.98
62.98
0.00
0.00
39.38
0.00
101.26
K410-419EWI
123 ROAD TRANSPORT & HIGHWAYS GUHA.BYPASS NHAI
2000/04 2003/05 2003/05 2004/06
13
35.14
63.69
63.69
63.69
0.00
0.00
48.68
0.00
101.26
K146-157EWII
124 ROAD TRANSPORT & HIGHWAYS DHOLPUR-SEC. NHAI
2000/04 2003/08 2003/08 2004/03
7
17.50
76.00
76.00
76.00
0.00
0.00
87.62
0.00
101.26
K-24-41 NSII
125 ROAD TRANSPORT & HIGHWAYS DKHOLA-I'PUR NHAI
2000/04 2002/03 2002/03 2004/03
24
104.35
72.56
72.56
72.56
0.00
0.00
56.73
0.00
101.26
K447-470EWI
126 ROAD TRANSPORT & HIGHWAYS AGRA-G'LIOR NHAI
2000/04 2003/08 2003/08 2004/03
7
17.50
49.00
49.00
49.00
0.00
0.00
49.60
0.00
101.26
K70-85 NSII
127 ROAD TRANSPORT & HIGHWAYS DKHOLA-I'PUR NHAI
2000/04 2002/12 2002/12 2004/12
24
75.00
90.06
90.06
90.06
0.00
0.00
54.21
0.00
101.26
K476-500EWI
128 ROAD TRANSPORT & HIGHWAYS N'PUR-HYD.K4 NHAI
2000/04 2003/11 2003/11 2004/07
8
18.60
88.00
88.00
88.00
0.00
0.00
51.15
0.00
101.26
64-74 NSII
129 ROAD TRANSPORT & HIGHWAYS BLR-MADURAIK NHAI
2000/04 2003/08 2003/08 2004/10
14
35.00
82.49
82.49
82.49
0.00
0.00
68.33
0.00
101.26
180-199NSII
130 ROAD TRANSPORT & HIGHWAYS K'RIAJI-RTNP NHAI
2000/04 2004/04 2004/04 2004/07
3
6.25
226.05
226.05
226.05
0.00
0.00
103.20
0.00
101.26
UR GQ
131 ROAD TRANSPORT & HIGHWAYS BL'ORE-SALEM NHAI
2000/04 2002/11 2002/11 2004/03
16
51.61
21.40
21.40
21.40
0.00
0.00
21.29
0.00
101.26
MADURAI
132 ROAD TRANSPORT & HIGHWAYS ALUVA-A'MALI NHAI
2000/04 2003/08 2003/08 2004/04
8
20.00
77.38
77.38
77.38
0.00
0.00
62.78
0.00
101.26
K333-16 NSII
133 ROAD TRANSPORT & HIGHWAYS HYD-B'LORE N NHAI
2000/04 2004/03 2004/03 2004/12
9
19.15
172.06
172.06
172.06
0.00
0.00
92.78
0.00
101.26
S-II
134 ROAD TRANSPORT & HIGHWAYS LKO-K'PUR KM NHAI
2000/04 2003/05 2003/05 2004/06
13
35.14
50.02
50.02
50.02
0.00
0.00
27.06
0.00
101.26
44-59.5 EW 9
135 ROAD TRANSPORT & HIGHWAYS PURNEA-G'KOT NHAI
2000/04 2004/07 2004/07 2004/12
5
9.80
205.73
205.73
205.73
0.00
0.00
43.32
0.00
101.26
EW-II
136 ROAD TRANSPORT & HIGHWAYS SURAT-ATUL G NHAI
2000/04 2003/10 2003/10 2004/06
8
19.05
275.58
275.58
275.58
0.00
0.00
338.90
0.00
101.26
Q
137 ROAD TRANSPORT & HIGHWAYS ATUL-KAIJALI NHAI
2000/04 2003/04 2003/04 2004/01
9
25.00
174.59
174.59
174.59
0.00
0.00
210.30
0.00
101.26
GQ
138 ROAD TRANSPORT & HIGHWAYS SATARA-KAGAL NHAI
2000/04 2004/05 2004/05 2004/08
3
6.12
600.00
600.00
600.00
0.00
0.00
364.30
0.00
101.26
GQ
139 ROAD TRANSPORT & HIGHWAYS BELGAUM BYPA NHAI
2000/04 2003/12 2003/12 2004/07
7
15.91
115.90
115.90
115.90
0.00
0.00
96.13
0.00
101.26
SS GQ
140 ROAD TRANSPORT & HIGHWAYS B'GAUM-D'WAD NHAI
2000/04 2004/02 2004/02 2004/10
8
17.39
279.00
279.00
279.00
0.00
0.00
118.10
0.00
101.26
GQ
141 ROAD TRANSPORT & HIGHWAYS HUBLI-HAVERI NHAI
2000/04 2003/12 2003/12 2004/12
12
27.27
260.93
260.93
260.93
0.00
0.00
87.33
0.00
101.26
GQ
142 ROAD TRANSPORT & HIGHWAYS HAVERINHAI
2000/04 2004/08 2004/08 2004/12
4
7.69
241.00
241.00
241.00
0.00
0.00
81.02
0.00
101.26
HARIHAR (GQ)
143 ROAD TRANSPORT & HIGHWAYS H'HAR-CHI'DU NHAI
2000/04 2004/08 2004/08 2004/12
4
7.69
318.00
318.00
318.00
0.00
0.00
119.90
0.00
101.26
RGA GQ
144 ROAD TRANSPORT & HIGHWAYS V'BADI-P'KON NHAI
2000/04 2004/06 2004/06 2004/09
3
6.00
223.00
223.00
223.00
0.00
0.00
135.00
0.00
101.26
D GQ
145 ROAD TRANSPORT & HIGHWAYS P'KONDA-W'PE NHAI
2000/04 2004/04 2004/04 2004/09
5
10.42
211.00
211.00
211.00
0.00
0.00
113.20
0.00
101.26
T GQ
146 ROAD TRANSPORT & HIGHWAYS KANCHI-PMALL NHAI
2000/04 2003/12 2003/12 2004/12
12
27.27
211.00
211.00
211.00
0.00
0.00
70.65
0.00
101.26
I GQ
147 ROAD TRANSPORT & HIGHWAYS D'KUNI-L'GHA NHAI
2000/04 2004/03 2004/03 2004/12
9
19.15
393.00
393.00
393.00
0.00
0.00
268.90
0.00
101.26
T GQ
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------D.O.C.
TIME OVERRUN
COST (RS.CRORES)
COST OVERRUN
EXPENDI- % OF THE
CUMLDATE
---------------------W.R.T.ORIGINAL ---------------------------W.R.T. ORIGINAL
TURE
TOTAL
ATIVE
LATEST
NOW
DATE OF COMM. ORIGINAL LATEST
NOW
APPROVED
COST
UPTO
COST OVERRUN % COST
SR.
APPRORIG- APPANTI--------------APPROVED
ANTI---------------03/2004 FOR DELAYED
OVERUN
NO. SECTOR
PROJECT
AGENCY OVAL
INAL
ROVED
CIPATED MONTH
%
CIPATED (RS.CRORES)
% (Rs.CRORES) PROJECTS
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------148 ROAD TRANSPORT & HIGHWAYS K'GHAT-KH'PU NHAI
2000/04 2003/12 2003/12 2004/06
6
13.64
375.00
375.00
375.00
0.00
0.00
316.80
0.00
101.26
R GQ
149 ROAD TRANSPORT & HIGHWAYS KH'PUR-L'NAT NHAI
2000/04 2004/03 2004/03 2004/05
2
4.26
332.00
332.00
332.00
0.00
0.00
227.70
0.00
101.26
H GQ
150 ROAD TRANSPORT & HIGHWAYS L'NATH-B'SHW NHAI
2000/04 2003/12 2003/12 2004/12
12
27.27
272.00
272.00
272.00
0.00
0.00
141.80
0.00
101.26
AR GQ
151 ROAD TRANSPORT & HIGHWAYS B'SORE-BHDRK NHAI
2000/04 2004/02 2004/02 2004/06
4
8.70
227.25
227.25
227.25
0.00
0.00
94.21
0.00
101.26
GQ
152 ROAD TRANSPORT & HIGHWAYS BHDRK-CH'KHO NHAI
2000/04 2003/12 2003/12 2004/06
6
13.64
305.30
305.30
305.30
0.00
0.00
224.90
0.00
101.26
L GQ
153 ROAD TRANSPORT & HIGHWAYS BH'WAR-KHURD NHAI
2000/04 2004/01 2004/01 2004/05
4
8.89
140.85
140.85
140.85
0.00
0.00
87.04
0.00
101.26
A GQ
154 ROAD TRANSPORT & HIGHWAYS KHURDA-S'KHA NHAI
2000/04 2003/12 2003/12 2004/06
6
13.64
189.68
189.68
189.68
0.00
0.00
87.23
0.00
101.26
LA GQ
155 ROAD TRANSPORT & HIGHWAYS S'KHALA-G'JA NHAI
2000/04 2004/04 2004/04 2004/12
8
16.67
225.00
225.00
225.00
0.00
0.00
69.42
0.00
101.26
M GQ
156 ROAD TRANSPORT & HIGHWAYS GANJAM-I'PUR NHAI
2000/04 2004/02 2004/02 2004/12
10
21.74
256.55
256.55
256.55
0.00
0.00
91.50
0.00
101.26
AM GQ
157 ROAD TRANSPORT & HIGHWAYS I'PURAM-KORL NHAI
2000/04 2004/01 2004/01 2004/09
8
17.78
143.05
143.05
143.05
0.00
0.00
42.15
0.00
101.26
AM GQ
158 ROAD TRANSPORT & HIGHWAYS K'LAM-PALASA NHAI
2000/04 2004/01 2004/01 2004/09
8
17.78
135.11
135.11
135.11
0.00
0.00
48.71
0.00
101.26
GQ
159 ROAD TRANSPORT & HIGHWAYS PALASA-S'KAK NHAI
2000/04 2003/12 2003/12 2004/12
12
27.27
324.00
324.00
324.00
0.00
0.00
158.30
0.00
101.26
ULAM GQ
160 ROAD TRANSPORT & HIGHWAYS S'KAKULAM-CH NHAI
2000/04 2004/02 2004/02 2004/06
4
8.70
171.97
171.97
171.97
0.00
0.00
89.47
0.00
101.26
'WATI GQ
161 ROAD TRANSPORT & HIGHWAYS CH'WATI-VIZA NHAI
2000/04 2004/02 2004/02 2004/05
3
6.52
200.00
200.00
200.00
0.00
0.00
153.40
0.00
101.26
G GQ
162 ROAD TRANSPORT & HIGHWAYS D'CHERU-GTAM NHAI
2000/04 2003/12 2003/12 2004/06
6
13.64
130.80
130.80
130.80
0.00
0.00
65.23
0.00
101.26
I GQ
163 ROAD TRANSPORT & HIGHWAYS BRIDGES-AP19 NHAI
2000/04 2004/02 2004/02 2004/09
7
15.22
136.45
136.45
136.45
0.00
0.00
87.51
0.00
101.26
V-V SECTION
164 ROAD TRANSPORT & HIGHWAYS BRIDGES-AP20 NHAI
2000/04 2004/02 2004/02 2004/06
4
8.70
131.33
131.33
131.33
0.00
0.00
65.60
0.00
101.26
GQ,W-SECT.
165 ROAD TRANSPORT & HIGHWAYS CH'PET-ONGOL NHAI
2000/04 2003/12 2003/12 2004/09
9
20.45
319.21
319.21
319.21
0.00
0.00
151.00
0.00
101.26
E GQ
166 ROAD TRANSPORT & HIGHWAYS ONGOLE-KAVAL NHAI
2000/04 2004/04 2004/04 2004/12
8
16.67
321.41
321.41
321.41
0.00
0.00
169.50
0.00
101.26
I GQ
167 ROAD TRANSPORT & HIGHWAYS KAVALI-NLR G NHAI
2000/04 2004/01 2004/01 2004/12
11
24.44
181.00
181.00
181.00
0.00
0.00
147.60
0.00
101.26
Q
168 ROAD TRANSPORT & HIGHWAYS NLR BY PASS NHAI
2000/04 2003/12 2003/12 2004/05
5
11.36
143.20
143.20
143.20
0.00
0.00
131.30
0.00
101.26
GQ
169 ROAD TRANSPORT & HIGHWAYS TADA-CHENNAI NHAI
2000/04 2003/12 2003/12 2004/12
12
27.27
233.00
233.00
233.00
0.00
0.00
184.60
0.00
101.26
GQ
170 ROAD TRANSPORT & HIGHWAYS F'PUR-KHAGA NHAI
2000/04 2004/07 2004/07 2004/12
5
9.80
372.40
372.40
372.40
0.00
0.00
104.08
0.00
101.26
GQ
171 ROAD TRANSPORT & HIGHWAYS KHAGA-K'RAJ NHAI
2000/04 2004/02 2004/02 2004/06
4
8.70
151.70
151.70
151.70
0.00
0.00
131.36
0.00
101.26
GQ
172 ROAD TRANSPORT & HIGHWAYS HANDIANHAI
2000/04 2004/07 2004/07 2004/12
5
9.80
286.00
286.00
286.00
0.00
0.00
154.34
0.00
101.26
VARANASI GQ
173 ROAD TRANSPORT & HIGHWAYS MOHANIA-SASA NHAI
2000/04 2004/02 2004/02 2004/12
10
21.74
230.55
230.55
230.55
0.00
0.00
102.04
0.00
101.26
RAM GQ
174 ROAD TRANSPORT & HIGHWAYS D'ON-SON-AU' NHAI
2000/04 2004/02 2004/02 2004/06
4
8.70
242.61
242.61
242.61
0.00
0.00
143.05
0.00
101.26
BAD GQ
175 ROAD TRANSPORT & HIGHWAYS TUMKUR BYPA- NHAI
2000/04 2003/12 2003/12 2004/03
3
6.82
83.00
83.00
83.00
0.00
0.00
42.38
0.00
101.26
SSK75-62,GQ
176 ROAD TRANSPORT & HIGHWAYS D'KUNJ-KH'PU NHAI
2000/04 2004/02 2004/02 2004/06
4
8.70
81.00
81.00
81.00
0.00
0.00
55.38
0.00
101.26
RK18-136,GQ
177 ROAD TRANSPORT & HIGHWAYS ETA.BYPASS K NHAI
2000/04 2003/10 2003/10 2004/06
8
19.05
89.50
89.50
89.50
0.00
0.00
35.17
0.00
101.26
308-321 GQ
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------D.O.C.
TIME OVERRUN
COST (RS.CRORES)
COST OVERRUN
EXPENDI- % OF THE
CUMLDATE
---------------------W.R.T.ORIGINAL ---------------------------W.R.T. ORIGINAL
TURE
TOTAL
ATIVE
LATEST
NOW
DATE OF COMM. ORIGINAL LATEST
NOW
APPROVED
COST
UPTO
COST OVERRUN % COST
SR.
APPRORIG- APPANTI--------------APPROVED
ANTI---------------03/2004 FOR DELAYED
OVERUN
NO. SECTOR
PROJECT
AGENCY OVAL
INAL
ROVED
CIPATED MONTH
%
CIPATED (RS.CRORES)
% (Rs.CRORES) PROJECTS
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------178 ROAD TRANSPORT & HIGHWAYS LKO-KANPUR K NHAI
2000/04 2001/12 2001/12 2005/05
41
205.00
51.28
51.28
51.28
0.00
0.00
23.14
0.00
101.26
60-76GQEWI
179 SHIPPING & PORTS
CUTTER SUC. IWT
2002/01 2003/01 2003/01 2005/03
26
216.67
41.30
41.30
41.30
0.00
0.00
20.24
0.00
101.26
-DGERS& VESS
180 SHIPPING & PORTS
TERMINAL AT IWT
2002/03 2004/03 2004/03 2005/03
12
50.00
25.50
25.50
25.50
0.00
0.00
27.75
0.00
101.26
GAIGHAT
181 SHIPPING & PORTS
CONSTN. OF
IWT
2002/03 2004/09 2004/09 2005/04
7
23.33
30.00
30.00
30.00
0.00
0.00
16.00
0.00
101.26
PERM. TER..
182 SHIPPING & PORTS
REPL. DREGER PORTS 1996/08 2000/01 2000/01 2004/03
50
121.95
70.00
70.00
70.00
0.00
0.00
45.83
0.00
101.26
COLEROON
183 SHIPPING & PORTS
RRM FOR IMP. PORTS 2001/11 2003/12 2003/12 2004/12
12
48.00
350.84
350.84
350.84
0.00
0.00
2.61
0.00
101.26
OF DRAUGHT
184 SHIPPING & PORTS
CONSTN OF
PORTS 1997/01 2000/01 2000/01 2004/05
52
144.44
46.18
46.18
46.18
0.00
0.00
47.98
0.00
101.26
OIL JETTY
185 SHIPPING & PORTS
PROCURE:GRAB PORTS 1999/08 2001/04 2001/04 2004/06
38
190.00
30.90
30.90
30.90
0.00
0.00
21.00
0.00
101.26
HOPPER DRGER
186 SHIPPING & PORTS
CONSTN. OF
PORTS 2000/08 2004/01 2004/01 2004/04
3
7.32
44.57
34.04
44.57
0.00
0.00
23.74
0.00
101.26
WEST QUAY
187 SHIPPING & PORTS
MODN.OF BUN- PORTS 2001/10 2003/06 2003/06 2005/03
21
105.00
20.53
20.53
20.53
0.00
0.00
0.50
0.00
101.26
DER BASIN
188 SHIPPING & PORTS
ESTABLISH
SHIPP. 2002/01 2005/12 2005/12 2006/06
6
12.77
165.00
165.00
165.00
0.00
0.00
0.37
0.00
101.26
TVS IN GULF
189 TELECOMMUNICATION
BANGALORE:
ITI
2000/05 2006/06 2006/06 2006/11
5
6.85
37.98
37.98
37.98
0.00
0.00
23.57
0.00
101.26
CSN
190 TELECOMMUNICATION
MANAKPUR:
ITIT
2000/05 2006/06 2006/06 2006/11
5
6.85
36.41
36.41
36.41
0.00
0.00
23.06
0.00
101.26
CSN-MM
191 TELECOMMUNICATION
EXPN. FOR
MTNL
2000/06 2002/03 2002/03 2004/03
24
114.29
27.92
27.92
27.92
0.00
0.00
14.97
0.00
101.26
MAROL EXCH.
192 TELECOMMUNICATION
FRAUD MANAG. MTNL
2000/02 2002/09 2002/09 2004/05
20
64.52
35.00
35.00
35.00
0.00
0.00
3.00
0.00
101.26
CENTRE(FMCC)
193 TELECOMMUNICATION
ADDL.GSM.EQ. MTNL
2003/06 2003/11 2003/11 2004/02
3
60.00
66.03
66.03
66.03
0.00
0.00
42.31
0.00
101.26
PH-II
194 TELECOMMUNICATION
2ND&3RD GEN. C-DOT 2003/03 2006/03 2006/03 2006/06
3
8.33
147.00
147.00
147.00
0.00
0.00
29.30
0.00
101.26
MOBILE COMM.
195 URBAN DEVELOPMENT
RESIDENTIAL CPWD
1998/11 2001/12 2005/02 2006/12
60
162.16
35.12
35.12
35.12
0.00
0.00
4.34
0.00
101.26
COMP.IT DEP.
196 URBAN DEVELOPMENT
CONST.-SSS
CPWD
2001/07 2003/03 2004/06 2004/06
15
75.00
21.53
21.53
21.53
0.00
0.00
3.12
0.00
101.26
NIRE
197 PETROLEUM
PANIPAT-REW. IOCL
2002/01 2004/07 2004/07 2004/11
4
13.33
75.96
75.96
75.96
0.00
0.00
44.35
0.00
101.26
PIPELINE PRO
198 RAILWAYS
WORKSHOP
WS&PU 1998/05 2002/03 2002/03 2004/12
33
71.74
21.50
19.69
19.69
-1.81
-8.42
2.73
-0.01
101.25
AUGMENTATION
199 SHIPPING & PORTS
REPL.7 NOS. PORTS 1998/03 2001/09 2001/09 2004/04
31
73.81
64.00
64.00
60.00
-4.00
-6.25
32.11
-0.01
101.24
WHARF CRANE
200 ROAD TRANSPORT & HIGHWAYS HI'NGR-CHILO NHAI
2000/04 2003/12 2003/12 2004/12
12
27.27
180.31
180.31
175.00
-5.31
-2.94
28.07
-0.02
101.22
DA GQ
201 RAILWAYS
CLW-ELEC.
WS&PU 1997/07 2002/03 2002/03 2004/03
24
42.86
25.84
25.84
18.19
-7.65
-29.61
7.18
-0.03
101.19
LOCO.AUG.,ER
202 RAILWAYS
4000/3000 HP WS&PU 1999/04 2003/03 2003/05 2006/03
36
76.60
155.54
155.44
141.22
-14.32
-9.21
36.33
-0.05
101.14
DIESEL LOCOS
203 COAL
POOTKEE
BCCL
1983/12 1994/03 2000/03 2004/03
120
97.56
199.87
199.87
182.60
-17.27
-8.64
171.92
-0.06
101.08
BALIHARI UG
204 COAL
KUMBHARHKANI WCL
1998/12 2004/03 2005/03 2005/03
12
19.05
56.90
34.91
34.91
-21.99
-38.65
19.82
-0.08
101.00
UG
205 PETROLEUM
VISAKH-SECN- GAIL
2001/01 2003/08 2003/08 2004/04
8
25.81
490.65
490.65
463.26
-27.39
-5.58
389.81
-0.09
100.91
DERABAD LPG
206 POWER
ULDCS-WR
P.GRID 2001/02 2003/02 2003/02 2005/08
30
125.00
262.18
262.18
226.71
-35.47
-13.53
70.55
-0.12
100.79
207 RAILWAYS
VIRAMGAMBHILDI,WR
GC
108
174.19
155.66
119.75
119.75
-35.91
-23.07
47.16
-0.12
100.67
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------D.O.C.
TIME OVERRUN
COST (RS.CRORES)
COST OVERRUN
EXPENDI- % OF THE
CUMLDATE
---------------------W.R.T.ORIGINAL ---------------------------W.R.T. ORIGINAL
TURE
TOTAL
ATIVE
LATEST
NOW
DATE OF COMM. ORIGINAL LATEST
NOW
APPROVED
COST
UPTO
COST OVERRUN % COST
SR.
APPRORIG- APPANTI--------------APPROVED
ANTI---------------03/2004 FOR DELAYED
OVERUN
NO. SECTOR
PROJECT
AGENCY OVAL
INAL
ROVED
CIPATED MONTH
%
CIPATED (RS.CRORES)
% (Rs.CRORES) PROJECTS
---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------208 SHIPPING & PORTS
REPL.COMMON PORTS 2000/02 2003/06 2003/06 2004/03
9
22.50
69.50
69.49
36.00
-33.50
-48.20
30.40
-0.12
100.55
SHORE P.LINE
209 COAL
J.K.NAGAR UG ECL
1991/02 1995/03 1995/03 2004/03
108
220.41
95.28
95.28
54.15
-41.13
-43.17
48.71
-0.14
100.41
210 PETROLEUM