Professional Documents
Culture Documents
Topics Today
Review of recommended design
Project Area
Project Purpose
Reduce the risks of coastal storm and seismic damages Protect public safety, critical infrastructure, and associated economic activities along Seattles central waterfront Improve the degraded ecosystem functions and processes of the Elliott Bay nearshore in the vicinity of the existing seawall
5
Whats at Risk?
Public safety
Transportation corridor
Critical utilities Residential and commercial structures Public recreation
Jet Grouting
Drilled Shafts
11
Riparian vegetation
Substrate enhancement Cobble reefs
12
13
existing seawall N
Recommended Design
14
alternative seawall
Recommended Design
15
Recommended Design
16
Recommended Design
17
Existing Zone 1
18
19
Existing Zone 1
20
15
21
Existing Zone 2
22
15
23
Existing Zone 3
24
10-15
25
Existing Zone 4
26
10
27
Existing Zone 4
28
10
29
Managing change orders and cost reduction incentive proposals Panel (with new designers) to convene in late May
30
31
32 32
33 33
34 34
35 35
Alt A
$35 M
Alt B
$40 M
Current CIP
35% Design
$40 M
Ecosystem Restoration
Roadway and Access Contingency
$8 M
$19 M $63 M
$23 M
$23 M $81 M
$11 M
$23 M $48 M
Subtotal
Public Utilities Infrastructure
SPU Facilities (full cost) SCL Facilities (full cost)
$310 M
$6 M
$390 M
$7 M
$330M
$300M
$6 M
$19 M
$19 M
$19 M
Total
$335 M
$416 M $365M
$325M
37
35% Design
Central seawall project boundary stays at Virginia Street Total distance (S. Washington to Virginia): 3,700 lineal feet
Reduced contingency from 30% to 25% Costs for utilities assumed to be same as 10% estimates
39
40
41
42