You are on page 1of 15

ScaffoldSpecificationTemplate

ScaffoldSpecificationTemplate
ManagementGuide

NASCGuidance
26thApril2011

National Access and Scaffolding Confederation (NASC)

__________________________________________________________________________
th

Page1of15
IssueDate:26 April2011

ScaffoldSpecificationTemplate

Publishedby:

NationalAccess&ScaffoldingConfederation
Email:enquiries@nasc.org.uk
Website:www.nasc.org.uk

NASC2011

Firstpublished2011

ThisguidehasbeenpreparedbytheNationalAccessandScaffoldingConfederation(NASC)
ScaffoldSpecificationWorkingGrouptoimprovethequalityofthescaffoldstructureserectedon
constructionsitesandotherworksofengineeringmaintenanceandwithinaccordancewith
currentlegislation,guidanceandprotocolandinturnminimisetheriskofaccidentorinjuryto
operativesworkingonornearthescaffoldandthegeneralpublic.

Thisdocumentisintendedforusebyanyundertakingthathasresponsibilityforthe
management,use,monitoringandprovisionofscaffolding.

Thisdocumentisformattedinatemplatestylethatwillallowsuchbusinessestoeasilyadopt
thisformat.Werecognisethatsomebusinessesmayhavetheirownpreferredmethodfor
distributionofthecontentandassuchthisdocumentisdeliberatelyinaneditableformatto
allowforlocalvariationsofdistribution,e.g.hardcopy,digital,onlinesoftwareetc.

Theguidehasbeenwrittenontheassumptionthattheexecutionofitsprovisionsisentrustedto
appropriatelyqualifiedandexperiencedpeopleandthatconstructionandsupervisionof
scaffoldswillbecarriedoutbycapableandexperiencedorganisations.

NASCshallbeundernoliabilityofwhatsoeverkindhowevercausedwhetherornotduetothe
negligenceorwilfuldefaultofNASCortheirservantsoragentsarisingoutoforinconnection
withthisdocumentoranypartthereof.

Amendmentsissuedsincepublication
Amd.No.
Date
Comments:

__________________________________________________________________________
th

Page2of15
IssueDate:26 April2011

ScaffoldSpecificationTemplate

Contents

1.

2.

3.

APPLICATION

2.1 Tube&FittingScaffolding
2.2 SystemScaffolding
2.3 LightweightMobileTower

REGULATIONS,CODESOFPRACTICE&BESTPRACTICE

COMPETENCE

4.1 ScaffoldingCompanies

4.2 ScaffoldingOperatives

4.2.1 ScaffoldingLabourer

4.2.2 TraineeScaffolder

4.2.3 Scaffolder

4.2.4 AdvancedScaffolder

SCAFFOLDERSSAFETYANDPPE

5
5
6
6
6
6
7

SCAFFOLDINGDESIGN

MINIMUMSCAFFOLDREQUIREMENTS

6.1 ScaffoldTube

6.2 ScaffoldBoards

6.3 ScaffoldFittings

6.4 Brickguards,SheetingandDebrisNetting
6.5 LoadingBays

6.6 Access/EgresstoScaffolds

6.7 InternalEdgeProtection

6.8 ScaffoldTies
6.9 HopUp/StageBrackets

9
9
9
9
9
9
10
10

11

SCAFFOLDHANDOVERSANDSTATUTORYINSPECTIONS

11

RISKASSESSMENTSANDMETHODSTATEMENTS

12

AppendixA NASCguidancelistingreferredtowithinthisdocument

13

4.

5.

6.

7.

8.

AppendixB

AppendixC

PageNo.

4
4
4
4

ExampleofCISRSScaffolderscards

14

ScaffoldInspectionReportSheet

15

__________________________________________________________________________
th

Page3of15
IssueDate:26 April2011

ScaffoldSpecificationTemplate

1. APPLICATION

Thisspecificationidentifiestheminimumrequirementsandstandardsforallscaffolding
andedgeprotectiondesigned,erected,altered,inspected,usedand/ordismantled.
Thisspecificationmaybeenhancedbyanindividualcompanysspecificscaffolding
policyandbranding.

Hoists,Ladders,StepladdersandPodiumStepsarenotincludedaspartofthis
standard.

1.1. TubeandFittingScaffolding

Thisappliestotraditionalsteeltubeandfittingscaffoldsandincludestheuseof
systemtypecomponentssuchasReadylokorEasifixtransoms,extending
transoms,steelandaluminiumladderbeamsandunitbeams.Allsuch
componentsmustbeusedinstrictaccordancewiththemanufacturers
instructions/designguidance,andtheinformationsuppliedtositeupon
request.

1.2. SystemScaffolding

Alltypes/brandsofSystemsScaffoldingusedonsitemustconformtothe
relevantBritishandEuropeanStandardsBSEN12810/12811.Theleadhandofa
scaffoldgangusingsystemsscaffoldingmusthavesuccessfullycompletedthe
relevantCISRSSystemsproducttraining.CISRSScaffoldersorTraineeoperatives
willbeable,asamemberofthissquadtoerect,alterordismantlethis
equipmentunderthedirectsupervisionoftheCISRSsystemsqualifiedoperative
priortothemcarryingouttherequisiteCISRStraining.

Seewww.cisrs.org.ukforthecurrentlist.

1.3. LightweightMobileTower

Anominatedpersonispermittedtoerect,inspect,use,move,alterand/or
dismantlealightweightMobileToweriftheyarecompetentandholda
recognisedqualificationspecificallyincludesmobiletowers.

Mobiletowersmustbeinspectedasoftenasisnecessarytoensuresafety.
Recommendedbestpracticeisthattheybeinspectedandareportmadebya
competentpersonafterassembly,orsignificantalteration,andbeforeuse.
Thereafter,theyshouldbeinspectedasoftenasnecessarybutatleastevery7
days,orafteranyeventlikelytohaveaffectedstabilityorstructuralintegrity,
suchasadverseweatherconditions.But,thereisnoneedtoinspectand
reporteverytimethemobiletowerismovedatthesamelocation.
Note:RefertorelevantindustryassociationPrefabricatedAccessSuppliers&
ManufacturersAssociation(PASMA)websitewww.pasma.co.ukformoreinformation.

Deleted:
Deleted:

__________________________________________________________________________
th

Page4of15
IssueDate:26 April2011

ScaffoldSpecificationTemplate

PASMAhasagreedwiththeHSEthatthecompletionandaffixingofaPASMATower
InspectionRecordsatisfiestheregulatoryrequirementtorecordtheinspectionand
delivertothepersonforwhomitwascompleted.

2. Regulations,CodesofPracticeandbestpracticerequirements

Allscaffoldingworksshallbecarriedoutinaccordancewiththefollowing
Regulations,CodesofPracticeandindustrybestpracticerequirements:
2.1. TheHealthandSafetyatWorketcAct1974
2.2. TheManagementofHealthandSafetyatWorkRegulations1999asamended
2.3. TheWorkatHeightRegulations2005asamended
2.4. TheConstruction(DesignandManagement)Regulations2007
2.5. BSEN128112003Scaffoldsperformancerequirements
2.6. BSEN128102003Facadescaffoldsmadeofprefabricatedcomponents
2.7. NASCTG20GuidetoGoodPracticeforScaffoldingwithTubesandFittings.
(LatestEdition)
2.8. NASCSG4Preventingfallsinscaffolding(LatestEdition)
2.9. CISRSCAP609GeneralInformation(LatestEdition)
2.10. BSEN13374Temporaryedgeprotectionsystems
THISLISTISNOTEXHAUSTIVE.

3. COMPETENCE
3.1. ScaffoldingCompanies
3.1.1. ShouldbefullandregulatedmembersoftheNASC.
3.1.2. Theymustmaintaincurrentinsurancesofaminimumof10millionfor
EmployersLiabilityand5millionforPublicLiability.
3.1.3. Theymustbeabletodemonstratethattheyhavecompetentsupervision
(e.g.CISRS5dayScaffoldSupervisortrainingcourseandholdaCISRS
ScaffoldSupervisorcard).
3.1.4. AqualifiedCISRSScaffolderorCISRSAdvancedScaffolderworkingwithin
hiscapabilityissuitablyqualifiedtoleadthescaffoldoperationswithina
gang/squadofscaffoldersandtodirectthepracticaloperationsonsite.
3.1.5. Theymustemploycompetentscaffoldersforthetypeofscaffoldingto
beundertakenonsiteasdefinedinitem3.2below.
3.1.6. Management,Supervisionandoperativesmusthavereceivedrelevant
trainingonTG20andSG4(LatestEditions)
3.1.7. Thecompanymusthaveaccesstocompetentscaffolddesigners.
__________________________________________________________________________
th

Page5of15
IssueDate:26 April2011

ScaffoldSpecificationTemplate

3.1.8. Thecompanymustensurethatalldeliveriesofscaffoldingmaterialsare
undertakeninasafemannerandconsiderationisgiventotheriskof
fallsfromvehiclesandassuchthisworkisundertakeninlinewithNASC
SG30(LatestEdition)WorkingfromVehicles.
3.1.9. Alldeliverieswherepoweredliftingisused(e.g.:HIAB)willrequireproof
ofOperatorcompetenceandthattheliftingequipmenthasacurrent
certificateoftestandthoroughexamination.
3.2. ScaffoldingOperatives
3.2.1. ScaffoldingLabourers
3.2.1.1. Labourersmusthavereceivedscaffoldingmanualhandling
traininginaccordancewithNASCGuidanceNoteSG6Manual
Handling.
3.2.1.2. Labourersmustbeadequatelytrainedtoallowthemtocarryout
theirdutiessafely
3.2.1.3. ACISRSScaffoldersLabourerscardisavailableforoperatives
carryingouttheseduties
3.2.1.4. Labourersareonlyallowedtoworkatgroundlevelorwithsafe
accesstoafullyboardedanddoubleguardrailedsectionofa
scaffoldplatformpassingscaffoldingequipment.
3.2.2. TraineeScaffolder
3.2.2.1. Traineesmusthavereceivedscaffoldingmanualhandling
traininginaccordancewithNASCGuidanceNoteSG6Manual
Handling.
3.2.2.2. TheymustholdacurrentCISRSTraineeScaffolderscard
(SeeappendixA)
3.2.2.3. ThemusthavereceivedSG4(LatestEdition)trainingandworkin
compliancewiththeguidance
3.2.2.4. TheycanonlyworkunderthedirectsupervisionofeitheraCISRS
ScaffolderorCISRSAdvancedScaffolderatalltimes.
3.2.2.5. AnoperativeisconsideredaTraineeScaffolderuntiltheyhave
completedallrequisitetrainingandassessmenti.e.CISRSPart1,
CISRSPart2,S/NVQ2,H&StestingandholdaCISRSScaffolder
Card,irrelevantoftheirtimeintheindustry.
3.2.3. Scaffolder
3.2.3.1.

TheScaffoldermustholdacurrentCISRSScaffolderscard
(seeappendixA)

3.2.3.2.

TheymusthavereceivedSG4(LatestEdition)trainingandworkin
compliancewiththeguidance

__________________________________________________________________________
th

Page6of15
IssueDate:26 April2011

ScaffoldSpecificationTemplate

3.2.3.3.

Theleadhandofascaffoldgangusingsystemscaffoldingmust
havesuccessfullycompletedtherelevantCISRSSystemsproduct
training.

3.2.3.4.

Scaffolderscanworkonthefollowingstructures:

Independenttiedscaffolding

Putlogscaffolding

Birdcagescaffolding

Towerscaffolding(steel)

Trussoutscaffold

Scaffoldswithbeams

Protectivefans

Pavementgantry

Loadingbay

Roofsaddlescaffold

Splayscaffold

Roofedgeprotection

Tietesting

TheyareentitledtoworkonAdvancedorcomplexdesign
structuresbutonlyunderthedirectsupervisionofan
AdvancedScaffolder.

THISISNOTANEXHAUSTIVELIST

3.2.4. AdvancedScaffolder
3.2.4.1.

MustholdacurrentCISRSAdvancedScaffolderscard
(seeappendixA)

3.2.4.2.

TheymusthavereceivedSG4(LatestEdition)trainingandworkin
compliancewiththeguidance

3.2.4.3.

Theleadhandofascaffoldgangusingsystemsscaffoldingmust
havesuccessfullycompletedtherelevantCISRSSystemsproduct
training.

3.2.4.4.

Advancedscaffolderscanworkonanytubeandfittingsteel
scaffoldingstructureincludingthefollowing:

Tubulardropscaffoldfromsteelwork
Cantileverdropscaffold
2CordRakingshore
3CordRakingshore

__________________________________________________________________________
th

Page7of15
IssueDate:26 April2011

ScaffoldSpecificationTemplate

Deadshore
Flyingshore
Temporaryroofscaffold
Stairways
Ramps

THISISNOTANEXHAUSTIVELIST

4. SCAFFOLDERSSAFETYANDPERSONALPROTECTIVEEQUIPMENT
4.1. ScaffoldersshallatalltimeswearthefollowingminimumPPEatalltimeswhilst
workingonsite:
4.1.1. Safetyhelmet
4.1.2. Safetyfootwear
4.1.3. HighVisibilityvest.
4.1.4. Gloves
4.1.5. Fallarrestharnesswithreardorsalring,afallarrestlanyardand55mm
openingscaffoldconnectorsasdetailedinNASCSG4(LatestEdition)
4.1.6. OtherPPEasrequiredbytheworktaskorlocalsiterequirements
4.2. Wheneverharnessesbeingareused,rescueplan(s)inlinewithNASCSG19
(LatestEdition)GuidetoFormulatingaRescuePlanmustbeinplacebefore
commencementofworkonsite.
4.3. AllscaffoldingshallbeerectedinstrictaccordancewithNASCSG4(Latest
Edition)andcontractorsshalladheretorecommendedmethodsofworkwithin
theguidance,givingcollectivemethodspriorityoverothermethodswhere
practicable.
4.4. AllScaffoldingmaterialsmustbepassedfromhandtohandorraisedand
loweredinacontrolledmanner.(lightlineorGinWheel&Ropeetc)The
uncontrolledpassingordroppingofanyscaffoldingmaterialsisnotpermitted.
Note:NASCGuidanceNoteSG6ManualhandlingintheScaffoldingIndustry
containsfurtherguidance.
4.5. AllliftingoperationsmustbeundertakenwithinthescopeoftheLifting
Operations&LiftingEquipmentRegulations(LOLER)

5. SCAFFOLDINGDESIGN

5.1Whereadditionalscaffoldingdesigninputisrequired(i.e.:thosescaffoldsthat
arenotdesignatedasaBasicScaffoldinNASCTG20LatestEdition)thedesign
shallbeprovidedbyacompetentscaffolddesignerandtheappropriatedesign
standardfollowed.Thecostsofproducingandamendingdesignschemes
(whererequired)willbereflectedwithinthescaffoldcontractorsquotationetc.

__________________________________________________________________________
th

Page8of15
IssueDate:26 April2011

ScaffoldSpecificationTemplate

5.2Allsystemscaffoldingistobeerectedinaccordancewiththemanufacturers
designmanual/erectionguideorbesubjecttoaspecificdesign.

5.3 Wheredesigndrawingsareproduced,theyshallincludeanelevationofthe
scaffoldwithalltiepositionsmarkedonthedrawingclearlystatingtherequired
tieclassificationlightduty(3.5KN),standard(6.1KN)orheavyduty(12.2KN).

5.4 Whereappropriate,standardscaffolddesignsolutionsmaybepermittedto
determinedesigninputofcertainscaffoldstructures(Stairtowersetc)

5.5 Asystemforthemanagementofdesignvariationsshallbeinplace.

5.6 Copiesofscaffolddesigndrawingsshallbeissuedto/heldonsite.

6. MINIMUMSCAFFOLDREQUIREMENTS
Thefollowingminimumscaffoldrequirementsshallbeinplaceonallsites:

6.1. ScaffoldTube
AllscaffoldtubemustbegalvanisedandcomplywithBSEN39:2001orBSEN
1021012006andtobemarkedinsuchawayastoidentifythescaffolding
companywhoownit.

6.2. ScaffoldBoards
6.2.1. AllscaffoldboardsmustcomplywithBS2482:2009

6.2.2. Shortboards(lessthan2.14metreslong)aretobesecuredtoprevent
displacementasareinternalboardsthatareconsideredlikelytobe
displacedaccidently.

6.2.3. Otherthanatreturnsofscaffoldslappedboardstobeavoidedsofaras
reasonablypractical.

6.3. ScaffoldFittings
6.3.1. AllscaffoldfittingsmustcomplywithcurrentUKindustrystandards.
(BSEN74etc)

6.4. Brickguards,SheetingandDebrisnetting
6.4.1. Inaccordancewiththecontractspecifications,(whichshouldincludea
suitableriskassessmentbythemaincontractor)scaffoldsmayrequire
brickguards,sheetingordebrisnettingfitted

6.5. ScaffoldLoadingBays
6.5.1. AllScaffoldloadingbays(exceptwherecranesareused)shallbefitted
withscaffoldloadingbaygatesthatprotectoperativesfromtheexposed
edgewheninanopenpositionandpreventfallsofoperativesand/or
materialswheninaclosedposition.

__________________________________________________________________________
th

Page9of15
IssueDate:26 April2011

ScaffoldSpecificationTemplate

6.5.2. Scaffoldloadingbaystobeprovidedwithbrickguardsorsimilar
protectiontotheperimeter.

6.5.3. Scaffoldloadingbaysmusthaveclearsignagetoprovideuserswithclear
informationregardingsafeworkingloads.

6.6. Access/egresstoScaffolds
6.6.1. Access/egresstoscaffoldsmustbeprovidedinordertocomplywiththe
WorkatHeightRegulations2005,HSEguidanceandNASCSG25(Latest
Edition)Accessandegressfromscaffolds,withregardtothehierarchy
asfollows:

6.6.2. Externalladderaccessshouldbeprovidedtonomorethantwolifts
(Nominally4m)

6.6.3. Considerationsthatneedtobemaderegardingtheassessmentof
suitableaccessandegressfromscaffoldsmayinclude:
Heightandwidthofscaffold.
Numberofpeopleusingthescaffoldatanyonetime.
Durationofscaffoldhire.
Localemergencyrequirements.(Fire,evacuationetc.)
Typeofworktobeundertakenonscaffold(e.g.accesstoconfinedspaceentry
workandasbestosremovalenclosureswhilstusingfullfacerespiratorsetc.
requiresahigherdegreeofassessmentforaccessandegress).

6.7. InternalEdgeProtection
6.7.1.InternaledgeprotectiononscaffoldplatformstoconformtoNASCSG29
(LatestEdition)InternalEdgeProtectiononScaffoldPlatforms

6.8. ScaffoldTies
6.8.1. Allconcrete/masonryanchorsthatareusedfortheinstallationof
scaffoldtiesmustbetestedinaccordancewithNASCTG4(Latest
Edition)Anchoragesystems(i.e.:minimumof3perscaffoldor5%of
totalnumberoftieswhicheveristhegreater)withaproofloadof1.5
timestherequiredtensileloadusingapurposemadescaffoldtietester.
Recordsoftietestresultmustbemaintained.

__________________________________________________________________________
th

Page10of15
IssueDate:26 April2011

ScaffoldSpecificationTemplate

6.8.2. Whenworkingondomesticpremisestheoccupiermustbeinformed
priortoanydrillingtakingplaceformasonryanchors,orwhereitmaybe
necessarytorakeoutbrickworkjointstosupportaputlogscaffold.

6.9. HopUp/StageBrackets
6.9.1 Hopup/stagebracketsshallbeusedinaccordancewithNASCGuidanceNote
SG32GuidanceontheProvisionofInsideBoardBrackets(Hopup/Stepdown)
(LatestEdition).

7. SCAFFOLDHANDOVERSANDSTATUTORYINSPECTIONS

7.1. AllScaffoldingshoulduseaDONOTUSEnoticeforrestrictingaccesstothe
scaffolduntilthescaffoldinghasbeeninspectedandhandedoverforuse.

ScaffoldHandover

7.2. Wheneachscaffoldiscompleted,acompetentemployeeoftheScaffolding
Contractorwillinspectthescaffoldforcompliancewithregulations,codesof
practiceandthispolicyandthencompleteaScaffoldHandovercertificate.This
shouldconformtothecurrentNASCtemplateSG35HandoverofScaffold
Structures(LatestEdition)asaminimumandensurethattheclients
representativereceivesacopy.Whereapplicable,thegreeninsertofatagtype
inspectionsystem(ifused)shallbecompletedandlocatedattheaccesspoint
ofthescaffold,andthefirstentrymadeinthestatutoryscaffoldinspection
registerbythecompetentperson.

ScaffoldInspection

7.3. Regularstatutoryinspectionsofthescaffoldingshalltakeplaceatleastevery7
daysorafteranyeventlikelytohaveaffectedthescaffoldsstabilityand
recordedinthescaffoldregister(SeeappendixC).Thetagtypesysteminsert(if
used)willalsobeupdatedtorecordtheinspection.(Whereapplicable).
Note:Anytagsystemisasupplementarycheckonlyanddoesnotreplacethe
statutoryinspectionandreportasrequiredwithintheWorkatHeight
Regulations2005.

7.4. Allinitialandweeklyscaffoldinspectionsmustbeundertakenbyacompetent
personwhohasattendedanationallyrecognisedscaffoldinspectiontraining
course.(e.g.CISRSScaffoldInspectionTrainingScheme(SITS)Basicor
Advanced),alternativelyaCISRSScaffolderorAdvancedcardholdercanbe
deemedcompetenttoinspectstructuresuptothegradeoftheircardi.e.CISRS
ScaffolderBasicStructures,andAdvancedScaffolderallstructures.

__________________________________________________________________________
th

Page11of15
IssueDate:26 April2011

ScaffoldSpecificationTemplate

CISRSBasicand

AdvancedScaffold

inspectionCards

8. RISKASSESSMENTANDMETHODSTATEMENT

8.1. Eachindividualscaffoldstructuremusthaveajobandsitespecificrisk
assessmentrecordedinwritingwhichisacceptedbytheContractorthatthe
ScaffoldingContractorisworkingforbeforeworkcommencestoerect,alteror
dismantleascaffold.
8.1.1. AllriskassessmentwillbecarriedoutinlinewiththeScaffold
ContractorsHealthandSafetyPolicywhichasaminimumstandard
followNASCSG7:(LatestEdition)GuidetoRiskAssessments.

8.1.2. Allmethodstatementswillincludeafulldescriptionofthescaffold
includingsize,location,numberofboardedlifts,numberofworkinglifts,
sheetingstatusandloadingclassificationinlinewithTG20(Latest
Edition)table1andbeinlinewithNASCSG24(LatestEdition)AGuide
toScaffoldPlans(MethodStatements)

8.1.3. RiskAssessmentandMethodStatementsshallbecommunicatedto
operatives.CopiesofallRiskAssessmentsandMethodStatements
shouldbeheldasaminimumforthedurationofthecontract.

__________________________________________________________________________
th

Page12of15
IssueDate:26 April2011

ScaffoldSpecificationTemplate

APPENDIXALISTOFNASCREFERENCEGUIDANCEREFERREDTOWITHINTHIS
DOCUMENT

Note:RefertoNASCwebsiteatwww.nasc.org.ukforlatesteditionsoftheguidance
listedbelow.

Health&SafetyGuidanceNotes
SG4

PreventingFallsinScaffolding

SG6

ManualHandlingintheScaffoldingIndustry

SG7

GuidetoRiskAssessment

SG19

AGuidetoFormulatingaRescuePlan

SG24

AGuideforScaffoldPlans(MethodStatements)

SG25

AccessandEgressfromScaffolds

SG29

InternalEdgeProtectiononScaffoldPlatforms

SG30

WorkingfromVehicles

SG32

GuidanceontheProvisionofInsideBoardBrackets(Hopup/Stepdown)

SG35

HandoverofScaffoldStructures

TechnicalGuidanceNotes

TG4

AnchorageSystems

TG20

GuidetoGoodPracticeforScaffoldingwithTubesandFittings

CompetenceGuidanceDocuments

CISRSCap609GeneralInformationBooklet

__________________________________________________________________________
th

Page13of15
IssueDate:26 April2011

ScaffoldSpecificationTemplate

APPENDIXBEXAMPLEOFCISRSSCAFFOLDERSCARDS

Onlytoworkatgroundleveloronafully
boardedanddoubleguardrailedscaffold
platformpassingscaffoldingequipment.

Workunderthedirectandimmediate
supervisionofeitheraCISRSScaffolder
orAdvancedScaffolderatalltimes.

HaveaCISRSScaffolderscardendorsed
fortubeandfittingscaffoldingor
systemscaffoldtobeused.Canwork
onscaffoldslistedinSection3.2.3.4
andanyotherscaffoldnotincludedon
thislistbutonlyunderthedirectand
immediatesupervisionofanAdvanced
Scaffolder.

HaveaCISRSScaffolderscardendorsed
fortubeandfittingscaffoldingor
systemscaffoldtobeused
Canworkonanysteelscaffolding
structure.

CardisusedtoprovideproofthattheScaffold
Supervisoristrainedandcompetent.

__________________________________________________________________________
th

Page14of15
IssueDate:26 April2011

ScaffoldSpecificationTemplate

APPENDIXCSCAFFOLDINSPECTIONREPORTSHEET(EXAMPLE)
ScaffoldInspectionReport(inlinewithregulation12ofTheWorkatHeightRegulations2005)
CompanyName
&Address:

Sheet:

SiteAddress:
No

Locationanddescriptionof
workplaceinspected

Date&
Mattersobservedthatgiveriseto
Detailsofaction
Timeof
anyhealthandsafetyrisks
takenattimeof
inspection
inspection

Detailsofanyfurther
actionconsidered
necessary

Name,signature&
positionof
inspector

_______________________________________________________________________________________________________________________
IssueDate:26thApril2011

Page15of15