MECHANICAL STATION : NTPC / RSTPS 1 X 500 MW

COMMISSIONING STANDARD CHECK LIST SHEET 1 OF 2

PLANT ITEM : FILTER-BASKET TYPE PLANT NOMENCLATURE: UNIT : SL. NO. 1 7 SYSTEM: ACTIVITY / CHECKS STATUS YES / NO REMARK LOCATION:

General conditions satisfy the site standing instruction as listed in the plant item commissioning essential prerequisites. The name plate legend agrees with the approved NTPC plant nomenclature, is clearly visible , securely fixed , durable, correlates with remote labels . The installation is complete and correct in accordance with latest drawings and specifications. Check that the facilities and access for removal of basket and maintenance generally are convinient and adequate. Check that basket is in position, undamaged and are of correct mesh . Check direction of flows is correct & is worked Carryout filter stream changeover to ensure freedom of movement where applicable Ensure that filter body & basket are free from debris. check that drain & vent lines are provided.

6 7

10

Check that position indicators are visible and operating correctly. Check that change over facility adequately isolate the non-working filter.

11

MECHANICAL

COMMISSIONING

STATION : NTPC / RSTPS 1 X 500 MW PLANT ITEM : FILTER ---BASKET TYPE PLANT NOMENCLATURE: UNIT : SL. NO. 12 13 14 7 ACTIVITY / CHECKS

STANDARD CHECK LIST

SHEET 2 OF 2

LOCATION: SYSTEM: STATUS YES / NO REMARK

Check that differential pr. gauges are fitted. Drainage and venting facilities adequate ? Confirm that for an arrangement of Two individual filters in paralleled the valves are interlocked to prevent both filters being isolated together. Check that joints on pipe work back to isolating valves are correctly made and that isolating valves are closed. Confirm cleaning and handling arrangements.

15

16

NTPC Comg.

NTPC Erec.

Agency Elect. Mech. C&I

Name

Signature

Date

Elect. Mech. C&I BHEL Erec. BHEL Comg.

MECHANICAL STATION : NTPC / RSTPS 1 X 500 MW

COMMISSIONING STANDARD CHECK LIST SHEET 1 OF 2

PLANT ITEM : FILTER --- PLATE TYPE PLANT NOMENCLATURE: UNIT : 7 SL. NO. 1 ACTIVITY / CHECKS LOCATION: SYSTEM: STATUS YES / NO REMARK

General conditions satisfy the site standing instruction as listed in the plant item commissioning essential prerequisites. The name plate legend agrees with the approved NTPC plant nomenclature, is clearly visible , securely fixed , durable, correlates with remote labels . The installation is complete and correct in accordance with latest drawings and specifications. Check that the facilities and access for removal of plates and maintenance generally are convinient and adequate. Check that plates are in position, undamaged and are of correct mesh . Check direction of flows is correct & is worked Carryout filter stream changeover to ensure freedom of movement where applicable Ensure that filter body & plates are free from debris. If plant is motor driven confirm that D.O.R. is correct. Check that position indicators are visible and operating correctly.

6 7

10

MECHANICAL

COMMISSIONING

STATION : NTPC / RSTPS 1 X 500 MW PLANT ITEM : FILTER --- PLATE TYPE PLANT NOMENCLATURE: UNIT : SL. NO. 11 12 13 7 ACTIVITY / CHECKS

STANDARD CHECK LIST

SHEET 2 OF 2

LOCATION: SYSTEM: STATUS YES / NO REMARK

Check that differential pr. gauges are fitted. Drainage and venting facilities adequate ? Confirm that for an arrangement of Two individual filters in paralleled the valves are interlocked to prevent both filters being isolated together. Check that joints on pipe work back to isolating valves are correctly made and that isolating valves are closed. Confirm cleaning and handling arrangements.

14

15

Agency Elect. Mech. C&I Elect. Mech. C&I BHEL Erec. BHEL Comg. NTPC Comg.

Name

Signature

Date

NTP C Erec.