POST- Sr. PROPOSAL ENGINEER NameMASUD HASAN Education Diploma in Mechanical Engineering, 1996, West Bengal (Government State Council ) INDIA. Computer Knowledge MS OFFICE, .PRIMAVERA, P-6 (Only Theoretical), Certificate in COST ENGINEERING-5th Edition, Revised Nature of Project 14+ Years Experience in EXECUTION OF CONSTRUCTION OF PIPING/STRUCTURE/TANKAGE AND ASSOCIATED MECHANICAL i.e. PAINTING, INSULATION WORKS IN REFINERY, PETROCHEMICALS. Company Details: NAME OF COMPANY FROM 1. GALFAR AL MISNAD ENGG. & 01.06.2008 CONTG. W.L.L, DOHA, QATAR, www.galfarqatar.com.qa 2.MUKAND ENGINEERS LIMITED- 10.12.2007 INDIA, MUMBAI, INDIA. 3. BRIDGE AND ROOF CO (I) LTD. 10.07.1997 (A Government of India Enterprise) -INDIA Brief Job Details: Self Workload
Tendering & Estimation/ Proposal Offsite Piping and associated works for Green Fuel Emission Control Project Piping works -25 K.M Piping works & associated works 1. Piping Works 50 K.M. 2. Structural Steel works -940 MT. Structure steel works for pipe rack of approx 2440 MT. Construction of following Tanks and associated Foam , Sprinkler & Process piping works 2 Nos. 36M Dia. X 20 M ht. Composite mechanical work i.e. piping, painting, insulation and associated civil Work for offsite piping job. 1. Piping 30 K.M. Shut Down Work for Revamping of FCU/FPU Piping works Construction of following Tanks and associated piping works 1. 2 Nos. 72M Dia. X 20 M Ht. 2. 4 Nos. 17.5M Dia. X 20 M ht. 3. 4 Nos. 10M Dia. X 10 M ht. Client/Location Doha. Qatar HPCL/Mumbai/India HPCL/Mumbai/India BPCL/Mumbai /India RIL/Hazira/India GAIL/Gandhar/India IOCL/Baroda/India RPL/Jamnagar /India

TO Till Date

30.04.2008 09.12.2007

POSITION COST & ESTIMATION ENGINEER (MECHANICAL) 5 Month JR. MANAGER (Planning) 10.6 Year CONSTRUCTION ENGINEER

YEARS 3.11 Year

A).1. Present Job Profile-Tendering, Estimation & Project Control . (Since 1st June -2008)
Thoroughly review the scope of works for all discipline i.e. mechanical, electrical, instrumentation & Civil. 2. Coordinate with other department for cost work out. 3. Preparation of queries regarding scope works, scope of supply, and any others.
1. Page 1 of 8 Rev.2 -01.03.2012

CV of Masud Hasan 4. 5. 6. 7. 8.

9. 10.
11.

12. 13.
14. 15.

16. 17.
18. 19. 20. 21.

22.
23. 24.

25.
26. 27. 28. 29. 30. 31. 32.

33. 34. 35.

Preparation of bill quantities for pipes and fittings, valves , other tag items, structural steel, painting, insulation, scaffolding requirement etc, Sending RFQ to various vendor/ sub contractors/ suppliers for engineering works, materials etc. Review of vendors/suppliers technical documents in line with the requirement of client as per tender requirement. Review and compare of various commercial offers from different vendors for the same items and discuss with management. Review of subcontractor works.i.e. tender qualification, bid review and comparison, negotiation meeting to finalize price. Preparation of pre-estimates and post estimates for various contract, Attending site visit/ tender meeting with client. Complying all cost in works out sheet along with other discipline cost. Preparation of rate analysis for different items. Discuss with management for final price and distribution the price in client BOQ ( Schedule of price) Preparation of response for technical clarification received from client after submission and coordination with various vendor/supplier for compiling with the technical clarifications. Coordination with finance department for arranging Tender bond and amendment of tender bond, if required. Review of already submitted commercial price if client called for negotiation. Discussion with various vendors/ suppliers/ subcontractors for revised price. Coordination with QA/QC & Safety department for preparing the QA/QC documents, HSE requirement inline with the requirement of tender documents. Coordination with planning department for preparing the planning package, histogram, S-curve inline with the requirement of tender documents. Preparation of list of proposed key personnel for particular project in line with the requirement of tender documents and submitting CV,s as per requirement of tender . Preparation of Sub contractors list proposed for particular project in line with the requirement of tender documents and submitting the company profile for client approval. Preparation of suppliers list proposed for particular project in line with the requirement of tender documents and submitting the technical submittal for the proposed material. Preparation of list of plant, equipment proposed for project. Preparation of Method statement in line with requirements of tender documents. Co ordination with concern person for timely submission of tender documents. Maintains strict confidential of all commercial matter. Prepares and assists in developing project monthly reports including project planning updates and monthly project updates , Preparation and monitoring of project expenditures, progress and completion status, budget and cash flows. Preparation and monitoring of project commitment to inform management obligations. Preparation of forecast and cost of active capital projects and control project cost to avoid budget overrun. Assists in developing annual operating plan and 5-year business plan. Assists in the preparation of annual operating and business plans, including capital and operating budget accountability reports. Provides explanation and justifications for any deviation from forecast and graphs as required. Frequent contacts with immediate associates within same and other departments for project coordination in person Periodic contacts at department level regarding task review and progress of the project through personal, telephone and email communications Occasional personal contacts with next higher levels in other departments regarding project presentations

1. Project Details in Qatar


1.

Client Qatar Petroleum (QP)- GC070119A- QP Refinery , Mesaieed Position- Site In charge Period - June11 to Till Date Project Title- Provision of Technical Support Services (Value-38 Million) Contract period -5 Years Scope of Works Supply of Technical and skilled personnel on regular basis and on Call off Basis, Responsibility Providing the regular manpower to client. Arranging manpower on call off basis from local sub contractors.
Page 2 of 8 Rev.2 -01.03.2012

CV of Masud Hasan


2.

Maintaining welfare facilities/personal grievances of approx. 85 people. Coordination with client for call off requirement. Preparation of monthly invoices. Certification of subcontractor invoices. Updating the project cost Preparation of budget income for next few months Preparation of variation bill

SEEF Limited , Mesaieed, Qatar,(GTC-05/09) Position- Estimation Engineer Period - Nov-Dec 09 (Shut down) Project Title- SEEF TURNAROUND PLANT MAINTENANCE JOBS-2009(Value 14 Million) Scope of Works Maintenance of plant equipments and all associated piping, painting, insulation, scaffolding, refractory works during shutdown Responsibility Preparation of scope of works for various activities. Preparation of work package. Preparation method statement prior to shutdown and approval from client mainly followings activities, Bolting Spading & de spading Isolating, Purging Steam Cleaning Hot Oil Draining and Recharging Cleaning of Oily Water System Flare Tip Repair Vessels Inspection and Repair Furnace Inspection and Repair Inspection of Slug Catcher Unloading, Loading and Storage of Molecular Sieve Pressure Testing Activated Carbon Handling Column works. Civil Works Material Handling and Storage Refractory & fire proofing works. Insulation & painting works. Various types of valve maintenance works. Scaffolding works. Identify and finalization of subcontractor for shutdown for different activities. Mobilization of vendor/subcontractor/hire people as per schedule. Mobilization of required plant, equipment, tools, tackles as per schedule. Updating the status to client. Daily Co ordination with site engineers/supervisor, subcontractor for daily progress of each activity. Coordination with planning engineer to update the daily status. Preparation of daily works measurement of various activity carried out during shutdown Preparation of client bill and certification Certification of subcontractor bill. Preparation of variation bill and certification from client Familiar with SAP for making purchase order, service entry, amendment of PO etc,

Acquired Knowledge
Well familiar with the tender requirements, mainly for the following clients 1. M/s- Qatar Petroleum, M/s- Qatar Steel, M/s- SEEF Limited, M/s- Qatar Fertilizer, M/s- Qatar Petrochemical, M/s- ORYX Ltd., M/s- ASHGAL (Public Works Authority)
Page 3 of 8 Rev.2 -01.03.2012

CV of Masud Hasan

Acquired general knowledge about various clients standards /specification while doing the tendering and estimation works mainly followings QP-SPC-L-002 Rev 2-QP Technical Specification for Painting & Wrapping of metal surface QPR-MCP( M)-012 QP Procedure for Hydrostatic and Pneumatic testing QP-STD-Q-004 Rev 1 QP Corporate Standard for Quality requirement. QP-PHL-S-001 Rev1 - QP Corporate Philosophy for Fire & Safety. QP-SPC-L-011 Rev 1 - QP Corporate Technical specification for Hydrostatic Testing of New Pipeline. QP-SPC-L-012 Rev1 QP Corporate Technical specification for Pre-Commission / commissioning of New Pipeline. ES.5.06.0011 Rev A - QP Engineering Standard for Thermal Insulation Hot services. ES.5.06.0012 Rev A - QP Engineering Standard for Thermal Insulation Cold services QP_REG-Q-001 Rev4 QP Corporate Lifting Equipment Regulation ES.2.14.0046 QP Standard for Cathodic Protection. QPED- 9721 Rev2 - Piping Material specifications.

B) Previous overall Experience Summary


1. 2.

Till -30.04.2008

3. 4.
5. 6. 7. 8. 9.

10.
11. 12. 13. 14. 15. 16. 17.

18.
19. 20. 21.

22.
23. 24. 25. 26. 27. 28. 29. 30.

Executing the construction of piping/ structural / tankage and all associated mechanical work i.e. painting, insulation, associated pipe support foundation at site under different client. Preparation of measurement all quantities -piping/ tankage/ structural, insulation, painting etc. Executing the work with coordination of different sub contractor. Preparation daily , weekly report, Discussion with client on daily, weekly basis regarding progress, front availability, material availability and others hindrance. Preparation of bill of material as per drawing for isometric, GAD, plot plan , P &IDs Preparation of quantity of structural steel, scaffolding requirement, insulation , painting of various schedule, Issue of material as per schedule. Preparation of procurement schedule of material as per requirement as per execution schedule. Preparation of WPS/PQR documents. Preparation of test pack for piping loops, Preparation of mechanical clearance check list, punch point. Preparation of check list for pre-hydro test, post-hydro test, pre-com-commissioning of piping system ,tanks, Clear understating of all drawings Isometric, P &ID, GAD Plot plan. Etc. Preparation of detailed drawings from design drawings. Co-ordination of all related department i.e. instrument, electrical for installation of online instrument like control valve, Gauges, PSV/TSVs, Electrical termination of pumps motor etc. Preparation of client bill and sub contractor bill for various items. Preparation of variation bill. Preparation of tender specification for specific job. Reconciliation of material for final bill and job closing. Preparation of final Documents. Ensures compliance with requirements of standards, specifications co-procedures. Solves complex project problems through the application of acquired knowledge, experience. Checks, verifies and approves calculation, fabrication drawings, procedure. Co-ordinate the activities of respective engineering disciplines engineering elements and technical expertise. Ensure correct implementation of plant modifications, verifies and approve new project and modifications. Familiarity with the construction industries PC and applicable software. Exposure to overall project contract planning, pre qualification. Negotiation, awarding, as well as closure of construction and engineering contract. Develop detail drawing and bill of materials, checking feasibility based on site conditions. Finalize drawings from prepared sketches.

C) Company & Project Details


1.0 1.1 1.2 1.3 1.4 Name of Company Period Position Project Title : GALFAR AL MISNAD ENGG. & CONTG. W.L.L, DOHA, QATAR. : 01.06.2008 to till date : Cost Engineer : Tendering , Estimation & Project Control

Client

: Qatar Petroleum (QP), Qatar Fertilizer(QAFCO), SEEF Limited , Qatar Petrochemical (QAPCO), Qatar Fuel Additives, ORYX Limited, Qatar
Page 4 of 8 Rev.2 -01.03.2012

CV of Masud Hasan

Steel, Public Works Authority (ASHAGAL).


1.5 Responsibilities : As mentioned in clause A.

2.0 2.1 2.2 2.3 2.4 2.5

Name of Company : MUKAND ENGINEERS LIMITED , MUMBAI, INDIA Period : 10.12.2007 to 30.04.2008 Position : Piping Engineer Project Title : Offsite Piping and associated works for Green Fuel Emission Control Project Client : Hindustan Petroleum Corporation Limited (HPCL ), Mumbai, India Responsibilities : Executing the Offsite piping and associated mechanical works i.e. piping (approx 25 K.M) of various

size and materials , associated civil foundation for pipe supports, tee supports, Executing the painting of pipe for different services as per EIL standards with coordination of subcontractor. Executing the insulation of pipe approx. 4 K.M with coordination of subcontractor. Collection of free issue material from client and Fabrication of piping as per sequence of front availability and completion of all required NDT as required prior to erection. Installation of piping and completion of all support as per approved drawings, P&IDs, , pipe support standards.. Making check list file for each loops and taking mechanical clearance from client by attending all punch list. Completion of all NDT requirements. Making the pre-hydro and post hydro list check list and completion of hydro test as the line schedule. Re installation of online instruments. Final Box up the loops and hand over to clients. Attending all final check list given by client operation department. Preparation of daily, weekly, monthly progress report. Preparation of quantities for all piping, painting, insulation , structural items Attending review meeting with client. Preparation of client bill and certifying the sub contractor bill Review of subcontractors quotation and finalization. Allocation of resources and review of progress. Preparation of variation bill. Preparation of as built drawings. Preparation of final documents/ dossiers, Preparation of material reconciliation and final billing for job closing.
: BRIDGE AND ROOF COMPANY (INDIA) LIMITED ( A Government of India Enterprise,), MUMBAI, INDIA : 26.10.2005 to 09.12.2007 : Construction Engineer : Composite mechanical work i.e. piping, equipment, painting, insulation and associated civil work for SRU/ PRIME G+/LTU of Green Fuel Emission Control Project. : Hindustan Petroleum Corporation Limited (HPCL ), Mumbai, India

3.0 Name of Company 3.1 Period 3.1 Position 3.1 Project Title

3.1 Client 3.1 Responsibilities Executing the piping works i.e. fabrication, erection, testing, pre commission, and commissioning

assistance to client of various size and different services of approx. 50 K.M. Fabrication, erection, testing of steam tracing (0.5) and associated works for steam line, fuel gas line, flare line of approx. 5 K.M. Fabrication, installation, testing of 36 Flare line. Executing the cement lining of fire water network line as per relevant specification in coordination of sub contractor. Executing the painting works for piping & equipment and wrapping coating off U/G piping as per relevant specification in coordination of sub contractor.
Page 5 of 8 Rev.2 -01.03.2012

CV of Masud Hasan

Executing the insulation works for piping &equipment of different thickness and material as per relevant specification in coordination of sub contractor. Executing the structural steel work (Approx. 952 M.T.) and associated grating works (Approx. 90 M.T.) for operation platform, walkway platform, horizontal platform, and circular platform of vertical vessel, horizontal vessel, and column & pipe supports. Preparation of test pack, mechanical clearance of piping loop. Preparation of as built drawings of piping and approval from client/ consultancy. Follow up with QA/QC department for preparation of WPS/PQR with coordination of client QA/QC department.. Preparation of daily, weekly, monthly schedule for piping, painting, insulation works and execution the works as per schedule in coordination with sub contractor, Daily co ordination with client/ consultant regarding progress, material availability and work front availability and discuss according in case of non availability of material / work front. Co ordination with QA/QC department to conduct the NDT works / completion of the loops. Preparation of reconciliation statement piping materials, final dossiers and final billing,
4.0 Name of Company : BRIDGE AND ROOF COMPANY (INDIA) LIMITED ( A Government of India Enterprise,), MUMBAI, INDIA.

4.1 Period : 26.11.2002 to 25.10.2005 4.2 Position : Construction Engineer 4.3 Project Title : Refinery Modernization Project (RMP) 4.4 Client : Bharat Petroleum Corporation Limited (BPCL) Mumbai, India 4.5 Responsibilities Executing the fabrication, erection, painting of structure for pipe rack of approx 2440 M.T. Preparation of detailed fabrication drawing from engineering drawings.

Preparation of bill of quantities Preparation of procurement schedule as per site requirement. Fabrication of structure in sequence as per site condition /requirement. Conduction necessary NDT clearance and approval prior to paint apply. Carry out shop blasting/ painting and taking approval. Erection and alignment of structural column, tie beam, truss, bracing and taking acceptance from client. Carry out final paint Taking final acceptance from client Preparation of final documents. Preparation of monthly bill and taking certification from client.

5.0 Name of Company : BRIDGE AND ROOF COMPANY (INDIA) LIMITED ( A Government of India Enterprise,), MUMBAI, INDIA. 5.1 Period : 26.02.2002 to 25.11.2002 5.2 Position : Construction Engineer 5.3 Project Title : Construction of 5 Nos Tank 5.4 Client : Reliance Industrial Limited ( RIL) , Hazira, Surat, India. 5.5 Responsibilities : Executing the construction of 2 Nos. 36M Dia. X 20 M ht. Diesel storage tank (Double deck floating

roof) as per API 650 and all associated foam/ cooling system piping inside the tanks farm . Understanding the drawings I.e., bottom plates, shell plates, Roof Plate and all appurtenances. Fabrication, erection of bottom plates, shell plates, Roof Plate etc in sequence as per API 650. Preparation of daily, weekly schedule, meeting with client and review the progress and accordingly allocation of resources to obtain the required progress. Carry out necessary NDT as per the requirement of API 650. Mechanical clearance of tanks. Lifting or floating of tank up to working height. Draining of water and installation of roof drain and completion of all other works. Installation of all accessories and completion the tanks in all respect. Hydro testing of Tank as per API 650 sequence.
Page 6 of 8 Rev.2 -01.03.2012

CV of Masud Hasan

Handover the tank to client. Preparation of As built and final dossiers. Fabrication, installation , testing & commissioning of foam piping and sprinkler piping around the tanks , Laying, testing of Header line up to Tank Dyke wall.

6.0 Name of Company 6.1 Period 6.2 Position 6.3 Project Title 6.4 Client 6.5 Responsibilities

: BRIDGE AND ROOF COMPANY (INDIA) LIMITED ( A Government of Enterprise,), MUMBAI, INDIA : 28.02.2000 to 25.02.2002 : Construction Engineer : Composite mechanical work i.e. piping, painting, insulation and associated civil Work for offsite piping job. : Gas Authority of India Limited (GAIL), Bharuch, Gujrat,India

Executing the piping works i.e. fabrication, erection, testing, and pre commission of offsite piping different services of approx. 30 K.M. (3000 inch. Dia.) Fabrication, erection, testing of steam tracing (0.5) and associated works for steam line, fuel gas line, Preparation of test pack, mechanical clearance of piping loop. Preparation of as built drawings of piping and approval from client/ consultancy. Preparation of WPS/PQR with coordination of QA/QC department and client. Preparation of daily, weekly, monthly schedule for piping, painting, insulation works and execution the works as per schedule in coordination with sub contractor, Daily co ordination with client/ consultant regarding progress, material availability and work front availability and discuss according in case of non availability of material / work front. Co ordination with QA/QC department to conduct the NDT works / completion of the loops. Preparation of reconciliation statement piping materials, final dossiers and final billing,

7.0 Name of Company : BRIDGE AND ROOF COMPANY (INDIA) LIMITED ( A Government of India Enterprise,), MUMBAI, INDIA 7.1 Period : 26.08.1999 to 27.02.2000. 7.2 Position : Construction Engineer. 7.3 Project Title : Shut Down Work for Revamping of FCU/FPU 7.4 Client : Indian Oil Corporation Limited (IOCL) , Baroda, Gujrat, India. 7.5 Responsibilities Identify the piping spool, valves and other items from the drawings which are to be replaced during shut

down. Taking field measurement of spool pieces and approval from client prior to fabrication. Updating the necessary change in the drawings. Fabrication of spool pieces as per approved drawings. Carry out necessary NDT at shop and blasting/priming. Shifting of piping spool , valve near to existing location which is to be replace during shut down Marking of existing piping spool, valve and other items by red color which is to be replaced during shut down and confirmation from client. Erection of new piping wherever possible before shutdown. Scaffolding the area wherever required during shutdown. Preparation off shutdown schedule. Mobilization of resources for each activity prior to shutdown. Dismantling of all spool pieces, valves and others items during shutdown. Installation of new items and carry out NDT. Preparation of test packs, mechanical clearance from client. Carry out hydro test and pre commissioning of the system. Installation of online instrument i.e. control valve, temperature gauge , pressure gauge, orifice plate etc. Handover the system to client.
Page 7 of 8 Rev.2 -01.03.2012

CV of Masud Hasan

House keeping the area. Preparation of as built document/ dossiers & final bill. Certification of sub contractor bill and certification of final bill from client.
8.0 Name of Company 8.1 Period 8.2 Position 8.3 Project Title : BRIDGE AND ROOF COMPANY (INDIA) LIMITED ( A Government of India Enterprise Enterprise,), MUMBAI, INDIA. : 10.07.1997 to 25.08.199 : Assistant Engineer : Construction off 81 Nos tanks and associated piping works for new

8.4 Client 8.5 Responsibilities


Refinery in Jamnagar. : Reliance Petroleum Limited (RPL), Jamnagar, Gujarat, India

Executing the construction of 2 Nos. 72M Dia. X 20 M Ht. crude oil storage tank (Double deck floating roof) as per API 650 and all associated foam/ cooling system piping inside the tanks farm. Executing the construction of 4 Nos 17.5 Dia X 20 M ht. Kerosene storage tank (Cone roof) and all associated foam/ cooling system piping inside the tanks farm. Executing the construction of 4 Nos 10M Dia X 100 M ht. Benzene storage tank (internal floating roof) and all associated foam/ cooling system piping inside the tanks farm. Understanding the drawings bottom plates, shell plates, Roof Plate and all appurtenances. Fabrication, erection of bottom plates, shell plates, Roof Plate etc in sequence as per API 650. Preparation of daily, weekly schedule, meeting with client and review the progress and accordingly allocation of resources to obtain the required progress. Carry out necessary NDT as per the requirement of API 650. Mechanical clearance of tanks. Hydro testing of Tank as per API 650 sequence. Installation of all accessories and completion the tanks in all respect. Handover the tank to client. Preparation of As built and final dossiers. Fabrication, installation , testing & commissioning of foam piping and sprinkler piping around the tanks Laying, testing of Header line up to Tank Dyke wall. Handover the system to client. House keeping the area. Preparation of as built document/ dossiers & final bill. Certification of sub contractor bill and certification of final bill from client

Personal Profile Male, Married, Indian National, 37+ years age. Current Address DAHA, QATAR, MOBILE -(00974) 66148434

Permanent Address S/o Abdul Hai Siddique, Vill-Polta, P.O. Sarapul, Dist: 24 Parganas(N) Pin- 743286.(West Bengal).,INDIA, Ph.-00913217253111

Email ID: 1) masud_hasan2004@yahoo.com Passport Details: Passport No.: G4046520 Date of issue: 28 / 09 / 2007 Valid up to: 27 / 09 / 2017 Place of issue: Regional Passport Office, Kolkata, West Bengal. , INDIA
Yours Faithfully

Masud Hasan END Page 8 of 8 Rev.2 -01.03.2012

You might also like