Professional Documents
Culture Documents
Abstract
Hydro-turbines are rotary machines which convert the mechanical energy of the rotating element into electrical energy. The mechanical energy is imparted to the rotating element by a high speed jet of water stored at a height in a reservoir which is brought through a pipe; known as a penstock, to the machine. The rotating element of the machine is connected through a shaft to the generator, which in turn produces electricity. More the flow through the machine, more the power generated. A turbine is designed for a specific output at the rated net head and flow. A turbine must meet these guarantee conditions in order to deliver the rated output. This paper deals in discussing the actual field performance data of a Francis turbine of 10 MW capacity tested using thermodynamic method.
Guide vane opening, the guarantee point for the said condition have been deduced from the hill chart of the turbine. Table : A Runner Output At Turbine Shaft (kW) Turbine Efficiency (%) 91.79 1000 Designed Net Head (m) Guide Vane Opening (%)
326.43 324.84
Temperature Probes
Power measurement was done using two wattmeter method on the generator side. The generator was producing power at 11KV and 1000 RPM.
Manufacturer provided generator efficiency curve was used to evaluate the generator efficiency in order to calculate the turbine shaft output.
Results
The table 1 below shows the results obtained from the turbine test using thermodynamic method. The calculated data was corrected to the net head; 324.84m, corresponding to the 88% guide vane opening. Simultaneously, the flow was also measured using an ultrasonic flow meter. The results of which are shown in Table 2. Table 1 Test Results from Thermodynamic Test Net Head (m) 329.14 328.53 327.73 326.19 324.84 Turbine Generator Generator Efficiency Efficiency Power (kW) (%) (%) 87.60 88.21 88.94 90.66 91.43 7284.73 7498.37 7773.54 8251.55 8653.55 97.43 97.47 97.52 97.58 97.63 Turbine Shaft Power (kW) 7476.88 7693.03 7971.55 8455.82 8863.65 Turbine Discharge (m3/s) 2.643 2.705 2.787 2.914 3.041 GV Opening (%) 72.20 77.30 79.90 84.00 88.00 Corrected to 324.84m Turbine Shaft Power (kW) 7625.78 7824.36 8077.99 8508.52 8863.59 Turbine Discharge (m3/s) 2.660 2.720 2.799 2.920 3.041
Uncertainty in Efficiency %
Turbine No: 1 Tester: AW/MAY/SP Test date: 01-Feb-2011 AEMS TEST DATA
3.8 3.55
DUTY POINT
Sr. No
95 93 91 89 87 85 83 81 79 77 75
The uncertainty in flow measurement (thermodynamic) is between 1.15 to 1.16% only, which is quite acceptable. Efficiency evaluation using conventional method has a tendency to make an efficient unit appear inefficient and vice versa. The uncertainty in efficiency evaluation was found to be only 0.45% at 88% guide vane opening condition. This is acceptable. The turbine satisfies the guarantee condition.
58 | Pumps Valves and Systems | July-Aug 2011
6500
7100
7700
8300
8900
9500
10100
10700
11300
Conclusion
1. The turbine satisfies the guarantee condition at 88% Guide Vane Opening. The turbine is operating at 91.43% efficiency generating 8863 kW. 2. The turbine was found to be producing slightly more power (63kW) under present condition than expected from the guarantee condition. 3. It is important to keep a watch on the turbine performance as silt/scale deposition on the turbine blades drastically affects the operational efficiency. This also unnecessarily affects the life of bearings, seals, rotor etc besides requiring more water to produce same amount of electricity. 4. It is recommended to get the hydro turbines tested. They are a green source of energy. Testing reveals any extra generation potential lying with the turbine by suitable modification in operating schedule. Subscribe to Pumps Valves and Systems now! Subscription Form available on Page No. 68