Premier Oil
James Blanchard November 18th and 19th 2009
Contents
1. Introductions 1 I t d ti 2. Cost estimation methodology and setting up a QUE$TOR gy g p $
project
3. 3 Capital cost component overviews the operating and capital overviews,
cost reports
4. Modifying QUE$TOR projects using the project editor and
viewer
5. Accessing, reviewing and modifying cost and technical
databases
6. QUE$TOR future developments and wrap-up
Copyright 2009 IHS Inc. All Rights Reserved. 2
support_questor@ihs.com support_international@ihs.com
3
IHS Introduction
The source for critical information and insight
companies and technical professionals In over 100 countries Over 75,000 customers worldwide
and gathered information, obtained through relationships with content providers worldwide Helps to facilitate decision making support key processes and making, processes, improve productivity History of serving customers for over 75 years
Copyright 2009 IHS Inc. All Rights Reserved. 6
PRODUCT LIFECYCLE
ENVIRONMENT
SECURITY
ENERGY
Provides technical standards, codes, government/military specifications &related documentation: Specifications and Standards information Parts Databases
Copyright 2009 IHS Inc. All Rights Reserved.
Addresses concerns related to environmental & sustainability issues: Hazardous & material waste management Supply chain greening, MSDS & chemical management (dolphin)
Specialist in the field of defense, security, transport & law enforcement: p Security Editorial Security Research Security Consulting Lloyds Register Fairplay (50%)
Provides information, decision support tools & gy related services to energy industry: Research & Consulting Energy Editorial Geologic & Exploration Data Services
7
M&A Activity
$$
EVALUATE OPTIONS
QUE$TOR Introduction
Overview
QUE$TOR is a front end cost estimation tool
CAPEX / OPEX / Production Forecast
analysis
11
Project economics
OPEX Forecast
Fiscal Model M d l
Time
Estimation basis
T Targeting Middle of th R d EPC contract cost ti Middl f the Road t t t
Pre-sanction costs excluded (FEED study, Environmental studies etc.) Owners project management costs excluded p j g
14
15
QUE$TOR workflow
Create a project
Schedule S h d l CAPEX
16
17
Cost Databases
Cost databases
R i Regional cost and t h i l d t b l t d technical databases
17 offshore 11 onshore Separate databases for each component, bulk factors and operating costs
19
Database update
May release Q1 costs November release Q3 costs
Software update
Bug fixes g Enhancements New features / components
Release process
20
Tel: (+1) 713 995 1764 Fax: (+1) 713 995 8593 Jonathan Stephens (North, Central & South America) e-mail: jonathan.stephens@ihs.com
Asia Pacific (Singapore)
Tel: (+65) 6225 4166 Fax: (+65) 6225 9694 James Blanchard (Asia, Australia) e-mail: james.blanchard@ihs.com
21
QUE$TOR
Premier Oil
James Blanchard November 18th and 19th 2009
QUE$TOR Methodology
Prime Input Data
Development tollgates
Exploration Tollgates
Appraisal
Pre-FEED FEED Design, Construct & Commission Operate O t Asset Project Delivery Exit E it Asset
Strategic Screening
Country Entry Opportunity Identification
Feasibility
Opportunity Capture, Finance & Market
Concept Tollgate
Feasibility Tollgate
Access
Appraisal
Select
Many Fields/Prospects
24
25
Processing
Gas
Export Flare?
Wells
Wellhead / Manifolding
Separation
Oil Water Export
Processing Treatment
Storage
Re-injection
Disposal
Control Systems
Utilities
Power
Quarters
Drilling
Define project
Select units set, Imperial, Metric, Oilfield or users own
Select main product Select field location to obtain default typical field data extracted from the extensive IHS IRIS21 E&P database Create procurement strategy or select from list of p previously defined ones y Select technical database, default is set by the field location
27
28
29
calculated automatically
All values can be edited l b dit d Automatically generates
costs
Plateau rate used to size
facilities
Production rates can be
edited
30
Concept selector
14 predefined concepts Suggests concept based
can revised at the Field development schematic by adding or removing components and links
31
QUE$TOR Methodology
Field Development Schematic - FDS
Automatically calculates all component costs and p p y p populates the cost tree using QUE$TOR defaults in seconds
Copyright 2009 IHS Inc. All Rights Reserved. 33
34
35
QUE$TOR Methodology
Detailed Costing
of:
Equipment q p Materials Fabrication Installation Hook-Up and Commissioning (Offshore) Insurance Design and Project Management Contingency
37
system This is multiplied by a unit cost to g p y give a cost QUE$TOR then applies bulk material factors (te/te) to calculate weights for piping, electrical etc Steel weights calculated using algorithms specific to substructure type Steel and bulk material costs multiplied by fabrication unit rates Installation durations multiplied by vessel day rates Atshore, Inshore, Offshore HUC calculated D i Design, PM, Certification and C ti PM C tifi ti d Contingency applied t complete li d to l t cost estimate
38
39
CAPEX Methodology
Capital Cost Scheduling
from project analysis Start date and duration of each activity can b adjusted h ti it be dj t d and locked Uniform, triangular, down payment & delivery and user t d li d defined cost distribution profiles available User can adjust the duration and start date of each activity via the Gantt chart Shows 1st oil date Option to show schedule in project or calendar months
41
OPEX Methodology
Operating Expenses
OPEX methodology
QUE$TOR does not simply generate OPEX as % age of CAPEX d t i l t f
per year as this is not field specific or accurate QUE$TOR splits OPEX into the following categories
Operating Personnel (incorporates regional shift patterns) Inspection and Maintenance (labour/spares/surveys/pigging) Logistics and Consumables (helicopters/boats/chemicals) Well Costs (routine/non-routine) Field and Project OPEX ( j (onshore admin/supply base/support) pp y pp ) Tariffs (paid and received)
43
44
QUE$TOR Methodology
Investment and Production Profile
46