Operation Procedures

1. General requirements before proceeding for line up 2. General procedure for lining up and taking into service a pressure filter/ suction strainer 3. General procedure for line up and taking into service heat exchanger 4. General procedure for lining up pumps 5. General procedure for line up, charging and taking into service of forced lubricating system 6. General line up procedure for oil receipt 7. Line up, charging and taking into service 220/110KV main bus and station transformers 8. Line up, charging and taking into service 6.6KV station bus system 9. Line up, charging and taking into service Unit auxiliary buses 10. Line up and taking sea water filtration system in service

Operation Procedures
11.Line up of circulating water system 12.Charging and taking circulating water system in to service. 13.Line up and taking water box priming system in service. 14. Line up and taking chlorination system in service. 15. Line up for washing travelling water screens. 16. Line up and taking auxiliary cooling water system into service. 17.Line up and taking compressed air system in service. 18. Line up and filling of hot well 19. Line up, priming and starting of condensate extraction pump. 20. Filling of dearator. 21. Line up of Boiler Feed Pumps 22. Procedure for initial filling and venting of steam generator water circulating pump (SGWCP) 23. Line up, charging and taking SGWCP in service

Operation Procedures
24. Line up and filling of steam generator 25. Line up charging and taking RAPH lube oil system in service. 26.Line up and taking RAPH into service. 27. Lining up of flue gas path. 28.Line up of secondary air path. 29. Taking air and flue gas system into service. 30.Line up, charging and taking SCAPH into service. 31. Line up and taking Igniter Air system into service. 32. Line up and taking into service scanner air system. 33. Line up and taking into service Gas Recirculation path. 34. Taking furnace probe into service. 35. General line up procedure for oil receipt. 36. Line up and taking Fuel Tank Heating system in service. 37. Line up and taking Condensate Recovery System into service.

Operation Procedures
38. General procedure for line up, charging and taking into service fuel oil system. 39. Taking fuel oil heater in service. 40. Line up and taking turbine lube oil system in service. 41. Line up and taking jacking oil system in service. 42. Place turbine on Turning Gear (TG). 43. Line up and taking Control Fluid(CF) system in service. 44. Line up and taking Primary Water system in service. 45.Line up and taking generator seal oil system in service. 46. Filling generator with air, carbon dioxide and finally with hydrogen. 47. Line up and taking turbine gland steam in service. 48. Line up and taking vacuum pump/air evacuation system in service. 49. Taking turbine generator on Turning Gear (TG). 50.Preparation for Boiler Purge.

Operation Procedures
51. Boiler Purge 52. Opening Main Trip Valve. 53. Lighting up of boiler with start up oil. 54. Bringing up steam conditions. 55. Silica purging 56. Turbine rolling, synchronizing and loading the machine. 57.Putting the unit controls on auto. 58. Charging and taking feed water heaters in service. 59.Starting and taking STBFP in service. 60. Load pick to 300 MW. 61. Load pick to 500 MW. 62.Taking coal mills in service.