You are on page 1of 33

IR Vacuum M.

Sullivan

IR Vacuum Update

M. Sullivan for the PEP-II team

Machine Advisory Committee Review October 25-27, 2006

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Outline
Brief recap of last Januarys presentation History General Characteristics NEG heating tests Last January Conclusions Attempts to pin down the source More NEG heating tests Software Hardware The Answer What it was Present fix Future fix

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

History
We started to notice a large number of beam aborts from high radiation levels from the detector about mid December of last year. In retrospect, we have identified events of this type as early as the beginning of Dec. At that time, we were more concerned about the fast dI/dt LER aborts and some of us thought that perhaps these BaBar aborts were a new manifestation of the fast dI/dt aborts.

It wasnt until Monday, the day after New Years, that we discovered we had very fast vacuum spikes somewhere near the detector on the LER upstream side whenever the detector aborted the beam due to high radiation levels.

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Some Characteristics
Very fast high pressure spikes. Difficult to see with 6 min history

buffers. Seen in single ring for each beam but at much higher currents than colliding beams. Conclusion: either close by or inside shared beam pipe. Insensitive to orbit (+/- 2mm in Y and +/-8 mm in X at the ends of the support tube)

Radiation levels from the LER beam are consistently higher than radiation levels from the HER beam
Exhibits more bunch charge dependence than total current dependence
4
MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Interaction Region Layout


Detector
Forward Q2 NEG 8020 pump 2187 gauge

Support tube end bellows

LER
3027 gauge 3044 pump 3027 pump

SIG11 LER sensitive

HER

7039 gauge

7043 pump

Backward Q2 NEG LER frangible link

NEG pump

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

NEG heating test


In order to try to localize the source of the vacuum spikes we tried heating up some of the NEG pumps and recording the vacuum readings from the various gauges and pumps We decided to heat up the two NEG pumps closest to the IP. These are the two NEGs just outboard of the ends of the support tube We did this without beam and we did not try to regenerate the NEG pumps
6
MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

List of Vacuum spikes


The list of vacuum aborts that we had started in January grew to over 200 entries by the 3rd week of March.

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Pressure and Background Ratios

Forward Q2 NEG

LER radiation event

Backward Q2 NEG

HER radiation event

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Conclusions of Last January


In December we started encountering, with increasing frequency, beam aborts associated with high radiation levels in the detector
It took us a while to understand that these aborts were a new problem and not an alternate manifestation of the instabilities we were already trying to identify We have identified the cause of these beam aborts to be due to fast vacuum spikes in the IR.

All present information points to a region on the forward side of the detector and probably in the LER beam pipe or in the shared beam pipe.
The most likely location is the forward side support tube end bellows The most likely initiation for the event is an arc
9
MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

The Story Continued.


Throughout Jan.-Mar. we made several attempts to try to locate the source of these vacuum spikes More NEG heating tests with and without beam (the IR vacuum model has been greatly improved) We first took out a NEG pump and then later replaced a chamber in the incoming LER beam pipe RGA readings indicated a large burst of nitrogen when we had a vacuum spike We installed the ability to remotely make a gas burst into the beam pipe. This told us we did not have an air leak. The BaBar detector collaboration used the events taken by the detector when these vacuum spikes occurred to try to locate the source. Many different analysis techniques were used: from timing differences to track reconstruction to neutron counting rates We also analyzed timing differences between gas signals from the various gauges and pumps in the area There was an analysis of the shape of the gas pulse from the gauges and pumps Im sure I have forgotten a few more

10

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Average of 8 events seen in March


normalized to 2187 gauge
Detector
Forward Q2 NEG
10.7 Support tube end bellows

100

LER
939

HER
10.6

0.61

0.95 LER frangible link

Backward Q2 NEG

NEG pump

11

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Side view of BaBar


Backward Q1/Q2 bellows
Forward Q1/Q2 bellows

Forward Q2 chamber

12

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Heating up the forward Q2 NEG


Luminosity went down when we added gas. The decrease is noticeable at a pressure of about 30 nTorr

Traced to the HER vertical spot size increasing.


Luminosity restored as the pressure goes down.
This told us that the HER was sensitive to relatively small gas bursts

13

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

BaBar Analyses from Brians Talk

14

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

The Answer
In late February we were looking at the Q1/Q2 bellows with a bore scope and trying to see if any of the tiles had come loose when it suddenly became clear that we had incorrectly designed the RF seals that are next to the tiles. The seals were touching the tiles instead of touching the Cu under the tiles. With this knowledge we made new RF seals and prepared for a ten day access starting on March 19
15
MAC Review Oct. 25-27, 2006

Forward Q1/Q2 bellows section

IR Vacuum M. Sullivan

Q1 side of bellows

16

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Close up of damage to the tiles

17

MAC Review Oct. 25-27, 2006

RF seal note the bolt head

IR Vacuum M. Sullivan

RF finger seen in borescope videos


18
MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Close up of RF seal

19

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Another dark spot on another finger

20

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Dark spot corresponds to a pit on the tile

21

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Why was the failure located here?


No real answers Something to do with the corners of the tiles? Something to do with the edges of the RF fingers?

Perhaps a weak point in the tile? A crack?

22

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Picture of bellows before installation in 2002

This picture is a miracle!! The correct bellows section in the correct orientation!!! Thank you Scott!!
23
MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

RF seal repositioned onto bellows

Tile damage is here

24

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Cu posts not brazed to the tile

25

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Present Fix
We designed and built a set new RF seals so that they engage the Cu underneath the tiles
We took out the bellows section from the other side of the detector and placed it in the location of the damaged bellows section

We then reinstalled one of the Mk I bellows on the backward side of the detector. This side collects about half as much power as the forward side All locations had new RF seals in stalled
26
MAC Review Oct. 25-27, 2006

New Q1/Q2 Bellows RF Seal

IR Vacuum M. Sullivan

3/6 - New RF Seal Plate submitted to MFD

3/3 - Prototype RF Seal made using existing SPEAR3 RF seal die and another existing die.

27

MAC Review Oct. 25-27, 2006

New RF seal Compound J seal

IR Vacuum M. Sullivan

28

MAC Review Oct. 25-27, 2006

New RF seal Side away from Tiles

IR Vacuum M. Sullivan

29

MAC Review Oct. 25-27, 2006

New RF seal Close up of tile side

IR Vacuum M. Sullivan

30

MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Improved Design
Current bellows in the forward side (MkII) can absorb 5-10 kW and is currently absorbing about 7 kW When we go to higher currents and shorter bunches we will absorb even more power Presently building a new design bellows (MkIII) that will absorb less direct power from the beam Plan to install the new design this down time
MAC Review Oct. 25-27, 2006

31

Q1/Q2 Blws New Design MkIII


New concept developed based on best information available. Maximum Tile/slot length ~2.4

IR Vacuum M. Sullivan

Possibly

reduce further the travel and offset requirements to increase length.


32

Absorbing tiles are open to the convolutions No additional tile sets needed in bellows cavity. HER Arc Style Bellows Spring Stub RF shield
MAC Review Oct. 25-27, 2006

IR Vacuum M. Sullivan

Summary
We finally tracked down the problem to a design flaw in how the RF seal was engaged at the edge of the absorber tiles in the Q1/Q2 bellows section
An arc track had developed on the surface of the tile. This explains why the beam current threshold came down initially and then stabilized. Once the problem was figured out, new RF seals were made and installed Since the repair, we have had NO unusual abort causing vacuum activity in this area We would like to thank all of the people who helped us with this tough problem BaBar collaborators, engineers, technicians, machine shops, experts from other groups, etc.
MAC Review Oct. 25-27, 2006

33

You might also like