Case background
Establishment
Started by Jeff Styles in his two-car garage Business function : transferring hard copy of documents, such as invoices, bills, or mailing list, onto CDs
Operations function
First, unpacking and sorting mails received ( usually 10,000 to 30,000 pieces of mail per day are received) Next, scanning item to transfer content to disk Then, making accuracy check to ensure information is transferred correctly Finally, packaging disks and documents and sending back to the costumers
Data Tech needs to move to a larger facility that could accommodate the larger size of business
Q 1 Part a
Help Jeff Decide whether he should give greater priority
to a smaller facility with possibility for expansion, or move into a large facility immediately.
Decision Tree
Decision
1,000,000
600,000
800,000
500,000
500,000
Probability
The probability of high demand: 0.70 The probability of low demand: 0.30
Large Facility
Q 1 Part b
Choose weights for the two capacity factors based on
your findings.
Proximity to Airport
Proximity to postal service Facility with excess capacity Facility with potential for future expansion Close to business community
20
30 ? ? 10
3
4 4 0 5
4
2 5 1 4
4
5 0 5 4
Pleasant environment
10
100
Missing Data
Total Expected Profit :
= 880,000+710,000 = $1,590,000
Facility with excess capacity Facility with potential for future expansion
Factor Weight for Facility with Excess Capacity should be more than weight for Facility with potential for future expansion
Question 2
Once you have selected the factors for the two capacity
alternatives, use factor rating to select a new location for Data Tech.
Proximity to Airport Proximity to postal service Facility with excess capacity Facility with potential for future expansion Close to business community Pleasant environment
3 4 4 0 5 3
4 2 5 1 4 4
4 5 0 5 4 4
60 120 66.4 0
80 60 83 13.4
80 150 0 67
Finding: best new location for Data Tech Inc is the location with the highest weighted score, and that is location #3 with a weighted score of 377.
Question 3
How would your factor analysis be different if you had
selected a different capacity alternative?
High Demand
Low Demand
High Demand
Low Demand
1,000,000
600,000
800,000
500,000
500,000
EV (Excess capacity) = 0.30($600,000) EV (Potential for expansion) = + 0.70($1,000,000) $800,000 + $150,000 = = $880,000 $950,000
EV =0.3*$500000= 150,000
Factor Weight
Factor weight for excess capacity
= ($880,000 / 1,830,000) * 30 = 14.4
15.6
10 10 100
0
5 3
1
4 4
5
4 4
15.6
78