AGUSAN POWER CORPORATION

LAKE MAINIT HYDRO ELECTRIC POWER PROJECT

PROJECT DEVELOPMENT TIMELINE


YEAR 1991 MILESTONES Full Development of Lake Mainit Arrest Flooding Problem of 60,000 has Agri, Residential & Commercial Land Construction of an open channel through the mountain ridge and into the ocean Energy Resources Development, Inc. (ERDI) Executive Order 215 Develop 22MW Hydroelectric Power Generation Facility NAPOCOR made Pre-Feasibility Study Public Hearing for Project Acceptance

1994

1995

Development of the project awarded to Agusan Power Corp. NAPOCOR instructed APC to undertake Project Feasibility Study Cummins Cockburn LTD undertook Project Feasibility and Engg Studies
Presented to Pres. FVR as Flagship proj of the province Hawaiian Electric Industries (HEI) of Honolulu

1996

1997 2007-2010

Failed transactions to develop the b/w HEI and NAPOCOR APC partnered with Tranzen Updated Statutory Compliance, permits, Licenses Updated conceptual designs into Detailed Engineering Designs (DED)

Key Project Objective


Flood Mitigation Power Generation

25 MW Small Hydro Project


3

CONFIGURATION

31m asl limit

T E C H N I C A L H I G H L I G H T S

ITEM Lake Mainit Catchment Area Lake Levels

DESCRIPTION 723 sq. km. Design Level = 36.0m Average Level = 34 m Min. Level = 31 m Flood Level = 39 m

Gross Head Net Head / Rated Head Design Discharge Intake

34.70 to 35.2 m 27.80 to 28.70 m 98 to 102 cms 15.00m Internal Diameter Concrete Shell with 3 -3.60m x 4.50 m Intake Gates Height = 19.30m Deck Elevation= 40.00m 3.055 km long, 5.80m wide x 5.80m high modified horeshoe 25 MW 3 x 8.6 MW Vertical Francis Turbine

Tunnel

Plant Capacity

Sustainability
The project will use over 34 m of natural gross head that exist between Lake Mainit and the Bohol Sea. Effectively the project uses Lake Mainit as a huge natural reservoir and will have the capacity of lowering the lake water level from 34masl to 31masl The project will not utilize the entire outflow of the lake. A portion will be diverted to generate power and would still allow natural outflow through Kalinawan river for other downstream uses such as transportation, irrigation and fishing.

2011 - 2013
APC partnered with Berkeley Energy LMHGC was created Updated Environmental and Social Impact Study, Biodiversity and Fish Migration Studies DED docs to Good for Construction Plans, Drawings and Specification Grid Impact Study/System Impact Study Power Purchase Agreement with ANECO Energy Regulatory Commission approved provisional rate Bank Financial Closure Construction time : 32 months